Mailing list for 16th WRPC meeting (agenda): List of members of Western Regional Power Committee
List of members of Technical Co-ordination Committee
1 CMD, MPPTCL & Chairman, WRPC 1 Managing Director, GSECL, Vadodara. 2 Member (GO&D), CEA, New Delhi 2 Chief Engineer (GM), CEA, New Delhi. 3 Managing Director, CSPTCL, Raipur. 3 Chief Engineer (Trans.), CSPTCL, Raipur. 4 Managing Director, CSPDCL, Raipur. 4 Executive Director (O & M), CSPDCL, Raipur. 5 Managing Director, CSPGCL, Raipur. 5 Executive Director, CSPGCL, Raipur 6 Chief Engineer (LD), SLDC, Bhilai. 6 Chief Engineer (R & C), GETCO, Vadodara. 7 Chairman, GSECL, Vadodara 7 Addl General Manager (RA&C), MGVCL, Vadodara8 Managing Director, GETCO, Vadodara. 8 Executive Director (O&M-Gen), MPPGCL, Jabalpur.9 Chairman & Managing Director, MGVCL, Vadodara. 9 Asst. General Manager, MPMKVVNL, Bhopal 10 Chief Engineer (LD), SLDC, GETCO, Vadodara. 10 Director (Operation), MSETCL, Mumbai. 11 Chairman & Managing Director, MPPGCL, Jabalpur. 11 Director (Operation), MSEGCL, Mumbai. 12 Chairman & Managing Director, MP MKVVCL, Bhopal.
12 Director (Operation), MSEDCL, Mumbai.
13 CE(LD), SLDC, MPPTCL, Jabalpur. 13 Superintending Engineer (Comml), ED, Goa 14 Managing Director, MSETCL, Mumbai. 14 Executive Engineer, DD, Nani Daman 15 Managing Director, MSEGCL, Mumbai. 15 Executive Engineer, DNH, Silvassa 16 Managing Director, MSEDCL, Mumbai. 16 Regional Executive Director, NTPC Ltd., WRHQ,
Mumbai. 17 Chief Engineer (LD), SLDC, MSETCL, Kalwa. 17 Chief Engineer (Trans), NPCIL, Mumbai. 18 Chief Electrical Engineer, ED, Goa 18 Executive Director, WRTS-I, PGCIL, Nagpur. 19 Secretary(P), UT of Daman & Diu, Moti Daman. 19 Executive Director, WRTS-II, PGCIL, Vadodara. 20 Secretary(P), UT of DNH, Silvassa. 20 General Manager, Tata Power Company, Mumbai 21 Director (Comml.), NTPC Ltd., New Delhi. 21 General Manager (Power), RGPPL, Ratnagiri 22 Director (Operation), NPCIL, Mumbai. 22 General Manager, ISP, NHDC Ltd, Madhya Pradesh23 Director (Operation), PGCIL, Gurgaon. 23 Executive Director (O&M), Torrent Power,
Surat 24 Chief Executive Officer, NLDC, New Delhi. 24 Chief General Manager (Baroda Operations),
GIPCL, Vadodara 25 Executive Director, WRLDC, Mumbai. 25 Vice President, Reliance Energy Ltd., Mumbai. 26 Executive Director, Tata Power Company, Mumbai. Special Invitees 27 Managing Director, RGPPL, Noida 1 Member (Power System), CEA, New Delhi. 28 Chief Executive Director, NHDC Ltd, Bhopal. 2 Chairman & Managing Director, MP Tradeco,
Jabalpur. 29 Member (Power), NCA, Indore. 3 Managing Director, GUVNL, Vadodara. 30 Executive Director, Torrent Power, Surat 31 Managing Director, GIPCL, Vadodara Copy to 32 CEO, RETL, New Delhi 1 Chief Engineer (PP), MSEDCL, Mumbai 33 CEO & Director, Reliance Energy Ltd., Mumbai. 2 Executive Director (Comml), PGCIL, Gurgaon. 34 Member Secretary, WRPC, Mumbai 3 Member Secretary, ERPC, Kolkata 4 Member Secretary, SRPC, Bangalore 5 Member Secretary, NERPC, Shillong 6 Member Secretary, NRPC, New Delhi
Baart sarkar
Government of India kond`Iya ivaVut p`aiQakrNa
Central Electricity Authority
piScama xao~Iya ivaVut saimait WESTERN REGIONAL POWER COMMITTEE
p xao iva sa kI idnaaMk 12 frvarI 2011 kao gaaovaa maoM Aayaaoijat kI jaanaovaalaI 16 vaI baOzk kI kaya-saUcaI
AGENDA NOTES OF 16TH MEETING OF WRPC TO BE HELD ON 12TH FEBRUARY 2011 AT GOA
mauMba[- MUMBAI
C O N T E N T S
ITEM NO. PARTICULARS Page No.
ITEM No.1 CONFIRMATION OF THE MINUTES OF THE 15th MEETING OF WRP COMMITTEE 1
ITEM No.2 SIGNING OF PPA WITH RGPPL (FOR 5% ALLOCATED CAPACITY) AND ITS SCHEDULING 1
ITEM No.3 MODALITIES FOR SHARING THE COST OF ENSURING HEALTHINESS OF NAPHTHA OPERATION AT KAWAS GPS OF NTPC.
2
ITEM No.4 ALLOCATION OF POWER FROM KORBA STPS-III. 3
ITEM No.5
DECISIONS TAKEN DURING 30th MEETING OF STANDING COMMITTEE ON POWER SYSTEM PLANNING IN WR HELD ON 27.12.2010 AND SPECIAL WRPC COMMITTEE MEETING OF STATE TRANSMISSION UTILITIES AND BENEFICIARIES OF WR HELD ON 05.01.2011
5
ITEM No.6 RECOMMENDATIONS OF PSDF GROUP ON PROPOSAL FOR PROCUREMENT OF ERS SUBSTATIONS 9
ITEM No.7 BACKUP COMMUNICATION LINK BETWEEN SLDC GOTRI AND WRLDC BY LAYING OPGW ON 132KV D/C JAMBUVA-GOTRI LINE AND 220KV D/C JAMBUVA-ASOJ LINE
10
ITEM No.8 TRANSMISSION CHARGES FOR USE OF MSETCL TRANSMISSION SYSTEM FOR CONVEYANCE OF CENTRAL SECTOR POWER TO GOA
10
ITEM No.9 REPLACEMENT OF INSULATORS AND EARTH WIRE DETERIORATED DUE TO EXCESSIVE POLLUTION IN TRANSMISSION LINES IN SOUTH GUJARAT
11
ITEM No.10 PLANNING AND REPLACEMENT OF SCADA/EMS SYSTEM IN WR 12
ITEM No.11 ESTABLISHEMNT OF 128Kbps LEASED CIRCUIT 14
ITEM No.12 OPGW BASED COMMUNICATION LINK TO S/S OF PGCIL IN WR 14
ITEM No.13 TELEMETRY TO SLDC FROM CENTRAL SECTOR STATIONS 15
ITEM No.14 ONGOING TRANSMISSION SCHEMES IN WESTERN REGION 16
ITEM No.15 ONGOING GENERATION SCHEMES IN WESTERN REGION 19
ITEM No.16 INCLUSION OF NON-ISTS ASSETS FOR IMPLEMENTATION OF POINT CONNECTION METHOD FOR POINT OF CONNECTION CHARGES
20
ITEM No.17 EXTENSION OF THE DATE OF OPERATION OF CERC (SHARING OF INTER-STATE TRANSMISSION CHARGES AND LOSSES) REGULATIONS, 2010.
21
ITEM No.18 PERFORMANCE OF WR GRID DURING NOVEMBER 2010 TO DECEMBER 2010 22
ITEM No.19 RESPONSE OF GENERATING UNITS UNDER RGMO IN WESTERN REGION 26
ITEM No.20 ANTICIPATED POWER SUPPLY POSITION IN WESTERN REGION FOR THE PERIOD FROM JANUARY 2011 TO MARCH 2011
26
ITEM No.21 MECHANISM FOR COMPENSATION OF LOSSES ON TRANSFER OF POWER TO NR OVER MPPTCL & GUVNL NETWORK 27
ITEM No.22 PAYMENTS OF UI AND REACTIVE ENERGY CHARGES 28
ITEM No.23 WIDE AREA MEASUREMENT SYSTEM (WAMS) IN WR 29
ITEM No.24 PSDF MANAGEMENT COMMITTEE 30
ITEM No.25 GRANT OF LTA FOR GENERATION DEVELOPERS IN SR. 31
ITEM No.26 SHARING OF ESTABLISHMENT EXPENDITURE OF WRPC BY NCA 32
ITEM No.27 RENOVATION AND MODERNISATION OF WRPC OFFICE BUILDING 33
ITEM No.28 MEMBERSHIP OF WRPC 34
ITEM No.29 ANY OTHER ITEM 35
ITEM No.30 DATE AND VENUE OF NEXT WRPC MEETING 35
ANNEXURES
Annexure Particulars
Annexure-1 WRLDC letter No. WRLDC/OS/1517/11/2437 dated 18.01.2011
Annexure-3.1 NTPC letter dated 07.01.2011 Annexure-3.2 GUVNL their letter dated 21.1.2011 Annexure-4 MOP letter No.5/51/2010-Th.II dated 9.12.2010 Annexure-10 MPPTCL letter No. 07-05/E&T/65 dated 24.01.2011
Annexure-11 Estimate from Reliance obtained by WRTS-I with the scheme details
Annexure-14 Details of ongoing transmission schemes in WR
Annexure-15 Details of on going generation schemes in WR both under State as well as Central Sector
Annexure-18.1(a) The details of frequency profile during the period from November 2010 to December 2010
Annexure-18.1(b) Power supply position in WR for the period from November 2010 to December 2010
Annexure- 18.2 The month wise detail of voltages at 400 kV and 765 kV sub-stations during the month of November 2010 to December 2010
Annexure-18.3 Month-wise details of UFR operation in Western Region during the period November 2010 to December 2010
Annexure-19 Details of units under RGMO
Annexure-20 Anticipated power supply position in the region for the period from November 2010 to December 2010
Annexure-26 NCA vide letter No. 2/8/Power/EMC/164 dated 28.01.2011
AGENDA NOTES OF 16 TH MEETING OF WESTERN REGIONAL POWER COMMITTEE TO BE HELD ON 12TH FEBRUARY 2011 AT GOA
ITEM No.1: CONFIRMATION OF THE MINUTES OF THE 15th MEETING OF WRP
COMMITTEE
Minutes of 15th meeting of WRP Committee held on 12th November 2010 at Udaipur
were sent to the members vide letter No. WRPC/Minutes/AS/2010/11030 dated
20.12.2010. WRLDC vide letter No. WRLDC/OS/1517/11/2437 dated 18.01.2011
(enclosed at Annexure-1) have requested to drop the last line of para of Item No. 2 of
the minutes as below.
Quote
“GUVNL requested WRLDC to examine how much of GETCO system is being used for
evacuation of ISGS generation to other beneficiaries. “
Unquote
WRP Committee may like to discuss and confirm the minutes. ITEM No 2: SIGNING OF PPA WITH RGPPL (FOR 5% ALLOCATED CAPACITY)
AND ITS SCHEDULING
2.1 As per MoP order, the scheduling of 5% capacity of RGPPL power i.e. 2% each to
DD & DNH and 1% each to Goa to DD & DNH and Goa could commence only after
completion of all formalities viz., signing of PPA, completion of the process for obtaining
necessary open access, opening of Letter of Credit by the beneficiaries of the
generating station commensurate with the allocated power etc. The issue was also
discussed in 9th WRPC meetings held on 16th January 2009 subsequent WRPC and
commercial meetings of WRPC. In the meetings RGPPL were requested for expediting
the signing of PPAs with beneficiaries. RGPPL had been stating that the matter was
under consideration and awaited their Board’s approval. RGPPL had been assuring that
same would be signed soon. The RGPPL beneficiaries of unallocated power had been
repeatedly requesting that their due share needs to be availed by them in view of
inadequate quantum of allocated power to them compared to their demand. Despite
above, the prolonged pending of expediting the PPA had been causing undue hardship
to them as arrangement to meet their demand from alternative costlier sources of power
had to be made by them pending receiving of approval of PPA document from RGPPL
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
1
Board. In the recent CCM held on 11th January 2011 RGPPL representative stated that
PPA is under final stage of approval by RGPPL Board. RGPPL board meeting was
scheduled to be held within a week’s time.
WRP Committee may like to discuss.
2.2 IEGC-2010 gives criteria for demarcation of control under scheduling and dispatch
code under which, Central generating station with multiple beneficiaries the scheduling
function is to be coordinated by the RLDC, ED, WRLDC, POSOCO vide letter no
WRLDC/OS/1664/2010/2312 dated 24.12.2010 addressed to Secretary, CERC have
sought direction of the Commission on transfer of jurisdiction of RGPPL from SLDC to
WRLDC with reference to the para 98 of the Commission’s order dated 18.08.2009 in
petition No. 283/2009.The allocations made by MOP to beneficiaries mentioned above
could not get implemented for want of signing of PPAs between RGPPL and the
beneficiaries and completion of the process for obtaining necessary open access,
opening of Letter of Credit by the beneficiaries of the generating station commensurate
with the allocated power etc., as at present coordination with respect to RGPPL is being
done by Maharashtra SLDC.
Committee may like to note.
ITEM NO 3.: MODALITIES FOR SHARING THE COST OF ENSURING HEALTHINESS OF NAPHTHA OPERATION AT KAWAS GPS OF NTPC.
In the 413th OCC meeting the operation and coordination committee of WRPC, had
agreed to technical requirement to run Gas Turbine of Kawas on Naphtha fuel for at
least half an hour at 70% load once in 15 days to ensure healthiness of naphtha circuit.
During 56th CCM, NTPC expressed that cost of ensuring the healthiness of Naphtha
circuit cannot be covered under O&M charges as this facility was introduced at later
stage and was not included in the original O&M cost of plant.
The issue was deliberated in 56th CCM and it was agreed that NTPC will give modalities
for sharing the cost to this account. NTPC vide letter dated 07.01.2011 (copy enclosed
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
2
at Annexure-3.1) had submitted the proposal for payment of additional cost of
generation of Naphtha fuel used during the healthiness check as above.
NTPC proposal suggests billing the difference in cost of generation on Naphtha used
and RLNG used during the healthiness check period to all the beneficiaries in proportion
to the allocation from the station.
Proposal of NTPC was discussed in 57th CCM wherein beneficiaries expressed that
details submitted shall be discussed with the their management and would convey their
comments within 10-15 days and the issue may be discussed in the TCC and WRPC to
be held in Feb. 2011 at Goa.
Comments were received from GUVNL vide their letter dated 21.1.2011 (copy at
Annexure -3.2) which suggests payment of variable cost of Naphtha when the Naphtha
based generation is requisitioned by the beneficiary and generator requires to ensure
that Naphtha circuit is healthy when it declares availability on Naphtha and as O&M
charges would adequately cover such cost the Naphtha charge proposed for above
check-period is thus not to be payable.
Committee may like to discuss. ITEM NO 4. : ALLOCATION OF POWER FROM KORBA STPS-III. MOP vide letter No.5/51/2010-Th.II dated 9.12.2010 has allocated power to the Western
Regional beneficiaries with effect from the date of commercial operation (copy enclosed
at Annexure-4). It is seen from the allocation order that 85 % power has been allocated
to WR beneficiaries while 15% of power is to be sold out side PPA. Considering this
aspect, for working out methodology of energy accounting for the same, following points
were outlined in 57th Commercial Committee meeting of WRPC held on 11.2.2010:
Long Term Open Access for Korba-III (500 MW) at Korba in Chhattisgarh was
granted to NTPC Ltd. by CTU in the meeting of WR constituents regarding LTOA
held on 23.02.2007 at Mumbai.
In the 27th Standing Committee Meeting and it was agreed to plan Korba III
STPS switchyard-Raipur 400 kV D/C line as transmission strengthening scheme.
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
3
In 9th WRPC meeting the Korba-III-Raipur D/c line was agreed as ATS of Korba-
III and PGCIL to construct the line on behalf of NTPC and NTPC bear full
transmission cost/charges of the same.
Actual date of commencement of LTOA for Korba-III is from the date of
commissioning of above system strengthening scheme and Signing of BPTA with
PGCIL for sharing of WR transmission charges corresponding to entire 500 MW
generation capacities. It was intimated by NTPC Ltd. and PGCIL that the BPTA
in this respect has already been signed. NTPC may have to apply for short term
open access till the time transmission system planned for Korba-III is completed.
Infirm power from Korba-III w.e.f. 25.11.10 was accounted in UI treating Korba-III
as separate entity under definition as a seller.
After declaration of COD of the Korba-III and till commissioning of Korba-Raipur
D/c line (under ATS) power from Korba-III may be scheduled under STOA and
Korba-III firm/unallocated/power sold outside long-term PPA to be treated as one
combined entity for UI calculation purpose (both infirm/STOA). Capping for
injection more than schedule and more than Installed capacity will be done as
applicable to seller category in accordance with UI regulations, 2010.
The Committee discussed the same as under:
WRLDC representative had stated that NTPC Ltd. shall require to apply for STOA for
power to be scheduled from the above Unit till commissioning of Korba-Raipur D/c line
(under ATS) and power under STOA would be allowed as per prevalent STOA
regulations. The Infirm power from the station would be allowed subject to grid security
and other operational constraints.
NTPC representative had stated that in view of unit no 7 of Korba STPS, under Stage-
III, now being retained as a regional station by MOP, Govt. of India vide letter dated
9.12.2010, and long term PPAs having been signed by all the constituents, evacuation
of unit no 7 of Korba STPS power needs to be ensured, on first priority basis, in utilizing
transmission capacity from the ATS of Korba STPS (2100MW) as the ATS of Korba
(2100 MW) was developed on n-I redundancy basis. He further added that, the
beneficiaries of WR have all these years serviced the investment made in the ATS of
Korba (2100MW). Therefore, power scheduled to them from unit no 7 of Korba STPS,
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
4
for which they also have long term PPAs, should get priority over any other short term
customer in this corridor.
GUVNL vide letter 21.1.2011 have expressed that as beneficiaries of WR are serving
cost of transmission evacuation associated with Korba STPS (2100 MW) including for
redundancy & have opined that as LTOA has higher priority over STOA which is
granted by RLDC on margins available after meeting LTOA requirement. Therefore the
beneficiaries have first right for STOA of transmission capacity utilization. GUVNL have
requested to discuss methodology and modalities by the Commercial Committee
considering the above aspects. NTPC have also requested that the modalities may be
discussed in detail.
As the LTOA is to get effected after commissioning of the associated system of Korba –
III, the power scheduling after COD is to take place under STOA on the basis of system
margins available. In view of the same and the suggestions made by the constituents as
above, the detailed methodology of energy scheduling and accounting under
LTOA/STOA conditions is to be worked out, as also with reference to treatment of
portions of allocated power under ISGS and power sold outside long-term PPA,
payment for ISTS charges by NTPC Ltd. etc.
TCC/WR Power Committee may like to discuss so that Commercial Committee would work out detailed methodology for accounting accordingly.
ITEM No.5: DECISIONS TAKEN DURING 30th MEETING OF STANDING COMMITTEE ON POWER SYSTEM PLANNING IN WR HELD ON 27.12.2010 AND SPECIAL WRPC COMMITTEE MEETING OF STATE TRANSMISSION UTILITIES AND BENEFICIARIES OF WR HELD ON 05.01.2011
5.1 PGCIL vide letter No.C/OS/WRPC-16th/Agenda dated 25.01.2011 have submitted following items to be discussed in the meeting: 5.1.1. ESTABLISHMENT OF PROPOSED HVDC SUB-STATION (PG) DHULE
UNDER TRANSMISSION SYSTEM WITHIN WR ASSOCIATED WITH NEW IPPS IN CHHATTISGARH
PGCIL have intimated that during 15th WRPC Meeting, MSETCL indicated that
MSPGCL had planned 3000 MW generation near Dhule at Dondaicha and 1350 MW
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
5
generation of M/s India Bulls at Sinnar in Nasik District. In view of the same they have
planned parallel additional corridors in Dhule-Nashik-Malegaon area and therefore had
suggested POWERGRID to review the decision of establishing HVDC s/s at Dhule with
+/- 600 kV Raigarh (Kotra) – Dhule (PG) HVDC Bipolar link and 400 kV interconnecting
lines with Malegaon, Nashik, Dhule(MSETCL) which POWERGRID had agreed .
GETCO had indicated that in case the HVDC Station was not required at Dhule the
same may be shifted to Vadodara.
In the 31st meeting of Standing Committee on Power System planning in WR held on
27.12.2010, modifications requested by MSTECL in the Transmission System
associated with IPP projects in Chhattisgarh taking into account 3300MW generation
project proposed near Dhule was deliberated.
In the meeting it was concluded that at present no additions/deletions to the already
planned transmission system is to be done. It was decided that 400 kV interconnections
from Dhule (PG) to Malegaon and Nasik could be reviewed in a year’s time frame, if
required.
WRP Committee may concur recommendation of Standing Committee on Power System Planning in WR. 5.1.2 ESTABLISHMENT OF 765/400KV GIS S/S AT PUNE UNDER
KRISHNAPATNAM UMPP
PGCIL have intimated that during 15th WRPC Meeting, while expressing difficulties by
POWERGRID in acquiring land at Pune for establishing AIS at Pune, MSETCL had
opined that POWERGRID should go in for AIS instead of proposed GIS at Pune and for
difficulties in availability of land MSETCL shall assist for taking up at Government level if
POWERGRID required so.
Regarding establishment of GIS 765/400 kV s/s at Pune, MSETCL was requested to
resolve the issue regarding land availability for AIS by 30th November 2010 else
POWERGRID may go in for GIS s/s.
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
6
In the 31st meeting of Standing Committee on Power System planning in WR held on
27.12.2010, the proposal of 765/400 kV GIS substation at Pune was agreed. WRP Committee may concur recommendation of Standing Committee on Power System Planning in WR. 5.1.3 LAND REQUIREMENT FOR 400/220 KV GIS SUBSTATION AT DAMAN PGCIL have intimated that during 15th WRPC meeting, the matter regarding acquisition
of 8-12 acres of Land for establishing 400/220kV GIS station at Daman by PGCIL, had
been deliberated. PGCIL has intimated that as on date no land has been allocated
which is causing delay in preparation of Feasibility Report and tying up the funding
agency. However, DD representative stated that they have identified the land for
substation and the necessary formalities for acquisition are in advanced stage. WRPC
noted the same. Demand Note for 72,200 Sq Mtrs of land is yet to be received from
Daman Administration.
WRP Committee may like to note.
5.1.4 LAND REQUIREMENT FOR ESTABLISHMENT OF 765/400 kV GIS S/S AT VADODARA
PGCIL have intimated that during 15th WRPC meeting, it was decided that the
availability of 125-130 acres of land is very difficult in the vicinity of Vadodara and GIS
s/s may be installed instead of AIS s/s for which land requirement is to be tune of 50-60
acres. PGCIL intimated that to avoid further delay they are going ahead in initiating the
process of acquisition of land. WRP Committee endorsed the above recommendation
of TCC. POWERGRID have intimated that it has put up application for acquisition of 69.8 acres
of land on 20.12.2010 and have requested GETCO to please assist in identifying
suitable land for acquisition.
WRP Committee may like to note.
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
7
5.2 ASSOCIATED TRANSMISSION SYSTEM OF 4000 MW UMPPs IN CHHATTISGARH (IN DISTT. SURGUJA) AND ORISSA (IN DISTT. SUNDERGARH) GENERATION BY STANDING COMMITTEE PROJECTS AND THE OTHER TRANSMISSION SYSTEMS RECOMMENDED IN 31ST STANDING COMMITTEE MEETING ON PSP OF WR
Special meeting of State transmission utilities and beneficiaries of WR of 4000 MW
UMPPs in Chhattisgarh (in Distt. Surguja) and Orissa (in Distt. Sundergarh) was held
on 5.1.2011 at WRPC, Mumbai to discuss the associated transmission system with
these projects and the other transmission systems recommended by standing
committee in 31st meeting of Standing Committee on Power System Planning for
Western Region held at Nagpur. The transmission systems agreed in the 31st Standing
Committee Meeting were concurred by the WRPC Committee members/
representatives from the WR states mentioned above. The minutes of the meeting were
sent vide letter No. WRPC/Spl. WRPC Mtg/AS/2011/734 dated 25.1.2011. WR Power Committee may like to note. 5.3 OTHER TRANSMISSION SYSTEMS AGREED IN THE 31st STANDING
COMMITTEE MEETING:
Other transmission systems were also discussed and agreed in the 31st Standing
Committee meeting held on 27.12.2010. The minutes of the standing Committee
meeting were sent to WR constituents vide CEA letter No. 26/10/2011-SP&PA dated
20.1.2011. These are are listed as follows:-
i) Transmission system associated with 1400 MW (2X700 MW) Kakrapar Atomic Power Project Unit 3 & 4 (2x700MW).
ii) Transmission system associated with 4000 MW (6X660) Chhattisgarh UMPP Transmission system of Mauda Stage-II (1320 MW) and Bus Splitting arrangement at 400kV Wardha(PG) S/S
iii) Transmission System Associated with the Orissa UMPP (5x800MW) and Phase-II IPPs in Orissa.
iv) Connectivity and Long Term Open Access Applications pertaining to new IPP Generation Projects in Nagapattinam / Cuddalore and Vemagiri area of Southern Region with target beneficiaries in Western/Northern/Southern Region.
v) Transmission System for Tilaiyya (4000 MW) UMPP vi) Review of 765kV Aurangabad - Padghe transmission corridor as a part of IPPs
generation projects in Chhattisgarh. vii) Evacuation of power from generation projects coming up in Sikkim and Bhutan.
viii) Proposals of GETCO for interconnection of STU and CTU network in Gujarat ix) LILO of Wanakbori TPS – Soja (GETCO) 400 kV S/C line at Dehgam (PG) substation x) Koasamba (GETCO) – Vapi (PG) 400 kV D/C line.
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
8
xi) LlLO of 400 KV D/C Vadavi (Ranchhodpura) - Zerda (Kansari) line at proposed 400/220 KV Sankhari (GETCO) substation
xii) Provision of 2 nos. 220 kV feeder bays at Pirana (PG) 400 kV substation. xiii) Proposal of MPPTCL for interconnection of Pithampur (MPPTCL) 400 kV substation with Indore (PG) 765/400 kV substation. xiv) Termination of Aurangabad – Khargar 400 kV line at Boisar in place of Khargar. xv) Interconnection between Aurangabad(PG) – Aurangabad (MSETCL) 400 kV D/C
(quad) line under System Strengthening in WR for Mundra UMPP. xvi) Implementation of 400 kV bays at Bhopal (MPPTCL) 400 kV substation by
MPPTCL and Dhule (MSETCL) 400 kV substation by MSETCL for termination of 400 kV D/C quad line from Bhopal 765/400 kV and Dhule (IPTC) 765/400 kV substation respectively.
WRP Committee may like to note. ITEM No.6: RECOMMENDATIONS OF PSDF GROUP ON PROPOSAL FOR
PROCUREMENT OF ERS SUBSTATIONS PGCIL vide above letter dated 25.1.2011 have intimated that the PSDF Group
consisting of members from MSETCL, GETCO, MPPTCL, CSPTCL, NTPC, WRLDC,
POWERGRID and WRPC felt that it was difficult to accommodate the ERS equipment
at the existing Substations considering overall dimensions of the trailer-equipment and
its weight. As such, Committee had not recommended for procurement of ERS
substations at 400 kV level in this phase. The Committee had suggested that the
procurement for ERS for lower kV level i.e. 220 kV could, however, be explored by
PGCIL. WRPC agreed to the recommendation of PSDF group and did not recommend
the procurement of ERS-substations at 400 kV level in this phase and suggested that
the procurement for ERS of lower kV level i.e. 220 kV, 110 kV / 132 kV could, however,
be explored by the constituent states.
PGCIL has submitted that this kind of equipment is meant not only for installation in a
Substation, these can be installed anywhere as and when required below the EHV
Lines even, where there is no space constraint. Further the Unit can cater load at 33kV
level upto 33% of the rated capacity of the Transformer besides establishing
connectivity over 400 /220 kV level. The unit is ideally suited for emergency
requirement during any natural calamity and can also be used for providing reliable
power supply at important load centre at short notice. Powergrid has requested to
reconsider the procurement of two (2) Sets of ERS- Substations at 400kV level for WR.
WRP Committee may discuss.
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
9
ITEM NO 7: BACKUP COMMUNICATION LINK BETWEEN SLDC GOTRI AND WRLDC BY LAYING OPGW ON 132KV D/C JAMBUVA-GOTRI LINE AND 220KV D/C JAMBUVA-ASOJ LINE
In 7th WRPC meeting the work of Backup Communication link between SLDC Gotri and
WRLDC by laying OPGW on 132kV D/C Jambuva-Gotri line and 220 kV D/c Jambuva-
Asoj line was approved. OPGW has been installed on 35.427 kms long lines. The link
has been commissioned and is under operation since January’ 2011.
The link shall be handed over to GETCO for O&M of OPGW as the line belongs to
GETCO.
Members may please note.
ITEM NO 8 :TRANSMISSION CHARGES FOR USE OF MSETCL TRANSMISSION SYSTEM FOR CONVEYANCE OF CENTRAL SECTOR POWER TO GOA
POWERGRID has intimated that in 13th WRPC meeting on 9th April’ 2010 at Mumbai,
the issue of billing & payment of wheeling charges was discussed and it was agreed
therein that no deduction on account of service tax and TDS will be done for payment to
POWERGRID. PGCIL have intimated the status as on date as below:
i) GUVNL has not yet refunded the differential wheeling charges for previous block (2004-09) since over a year (about Rs. 30Crs)
ii) LTA customers M/s Jindal & Torrent Power have not paid the arrears of wheeling charges from Aug’09 till Jul’10.
iii) M/s MPTRADECO, CSPDCL, D&D, DNH, Jindal & Torrent Power are deducting TDS from amount payable to POWERGRID, despite the decision in 13th WRPC meeting as above.
PGCIL intimated that in the 110th WREB meeting, the issue was first discussed & it was
agreed that, the pooling of wheeling charges payable to Maharashtra & Gujarat with
POWERGRID charges would be reviewed, in case POWERGRID faces payment
problems. As some of the beneficiaries viz. MPTRADECO, CSPDCL, D&D, DNH,
Jindal & Torrent Power are deducting TDS from amount payable to POWERGRID,
despite the decision in 13th WRPC meeting as above, POWERGRID have urged that
due to the same, they are not in a position to continue billing the wheeling charges in
their Bills for GUVNL & MSEDCL and that from Jan’11 concerned Licensees may raise
the bill at their end & collect money from the concerned directly.
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
10
In this context, it is required that as agreed in 13th WRPC meeting PGCIL will continue
to include billing of transmission charges payable to MSETCL and GETCO for wheeling
of Central sector power in their bill which they had stopped billing the same from Aug.
2009 onwards as the constituent State were deducting TDS and Service tax at their end
while making transmission charges payment to PGCIL. However PGCIL had agreed
with the condition that no deduction on account of Service Tax and TDS will be done by
the beneficiaries at their end and it should not be implicated on PGCIL. As all the
beneficiaries had then agreed to the same.
In 15th WRPC meeting, it was intimated by MSETCL that monthly wheeling charges
payable to Maharashtra have not been credited by POWERGRID w.e.f. Aug-2009.
POWERGRID had intimated that the credit is being passed on to all the constituents as
per the REA details on monthly basis. POWERGRID intimated that the accumulation
arising out on revising the REA is paid immediately upon receiving the same from other
paying utilities. It had further intimated that credit could not be passed on to MSETCL
due to non-receipt of the same from GUVNL on account of arrears due for the years
2004-05-2008-09. However, they had started billing and passing the credit to MSETCL
on monthly basis w.e.f. September 2010 and the previous dues w.e.f. Aug-2009 will be
cleared in due course. POWERGRID were requested for continuing to release amount
every month to Maharashtra and Gujarat the amount received from all paying utilities
corresponding to each month as per the REA details issued.
In line with the above decisions of the Committee, it is requested that the utilities may
release the payments to PGCIL on account of the wheeling charges so that payments to
the receiving utilities may be cleared by PGCIL early so that the existing mechanism is
can be followed smoothly and the difficulties expressed by PGCIL are overcome.
WRP Committee may like to discuss.
ITEM NO. 9: REPLACEMENT OF INSULATORS AND EARTH WIRE DETERIORATED DUE TO EXCESSIVE POLLUTION IN TRANSMISSION LINES IN SOUTH GUJARAT
POWERGRID has intimated that due to excessive pollution in south Gujarat,
transmission lines of POWERGRID around Surat are severely affected. Insulator
flashover, failure of insulators and earth wire due to corrosion is very frequent. To
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
11
ensure uninterrupted service, POWERGRID has taken up replacement of Insulators
besides their cleaning twice in a year and replacement of Earth wire in the polluted
stretches. POWERGRID have intimated that it has already incurred an expenditure of
approx Rs. 3.85 Crs. and another Rs. 4 Crs is estimated in procurement and
replacement of balance insulators and earth wire to eliminate vulnerability of
transmission system for reasons beyond the control of POWERGRID. In view of the
circumstances outlined above, POWERGRID has proposed following :
1) Reimbursement of cost of Insulator and Earth wire replacement to POWERGRID.
2) The outages required for Insulator replacement & cleaning process and earth wire replacement may be treated as deemed available.
WRP Committee may like to discuss. ITEM No. 10: PLANNING AND REPLACEMENT OF SCADA/EMS SYSTEM IN WR The above item was discussed in 12th WRPC meeting held on 16.01.2010 and it was
decided in the meeting that WR constituents would implement their SCADA/EMS
systems as per their plan but common specifications would be prepared, discussed in
SCADA committee meeting for further action. POWERGRID had earlier suggested
three approaches to this issue and had requested the constituents to choose one that
best fitted their requirement.
a) PGCIL may provide consultancy services on turnkey basis from concept to commissioning. Funds have to be arranged by constituents and PGCIL’s overhead charges shall be applicable
b) PGCIL may arrange funds & execute project on turnkey basis with appropriate administrative charges. Constituents may repay the project cost over the life span of the system. However such proposal can be considered by PGCIL only if such investment proposal is accepted by CERC.
c) Constituents may implement their system as per their plan. In such case common time frame and data interchange strategy have to be firmed up.
During 8th SCADA –O&M Committee meeting held at WRLDC on 7.01.2011, AGM
(LD&C), POWERGRID informed that recently, NR constituents in NRPC meeting had
agreed for a unified approach of control centre SCADA/EMS hardware / software up
gradation to be carried out by POWERGRID and recovery by way of tariff similar to the
model adopted in ULDC schemes. Based on the NRPC decision, POWERGRID would
approach Central Regulatory Commission for approval of the unified approach of
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
12
SCADA/EMS up gradation and tariff proposal. AGM, WRLDC stated that in view of the
latest development in NR, the decision taken in WR earlier may be reviewed. However,
depending on the decision to be taken by WR constituents, the final approach to
replacement issue would be frozen in consultation with LD&C, POWERGRID. He also
informed that considering the time line of around two years required for replacement
activity, it would be prudent to arrive at the final approach as early as possible. He
informed that the the Present LTSA time line is fixed for five years from 14th Oct 2009
and there is an exit option at the end of 3 years by payment of additional demobilisation
charge of 10% of the balance charges of two years.
ED, WRLDC suggested that the future system should be planned with the two year
clock starting from 1st April 2011 and the new system should be commissioned by 1st
April 2013. Both the new system and the old ULDC would operate in parallel for a year
so that the new system could be evaluated for its stability and reliability and the ULDC
system could be phased out at the end of 5 year LTSA.
The matter was further deliberated in 8th SCADA –O&M Committee meeting and
outcome is recorded as under:
• MSETCL representative stated that the up gradation of SCADA/EMS
systems of MSETCL had recently been awarded on Siemens and the work was in advanced stage.
• GETCO representative informed that unified approach of SCADA/EMS up gradation is suitable to them however the final decision could be taken at WRPC forum.
• CSPTCL representative informed that unified approach of SCADA/EMS up gradation is suitable to them however the final decision could be taken at WRPC forum.
• MPPTCL representative informed that the matter needs further deliberation in MPPTCL forum and they would communicate MPPTCL opinion tentatively in a week’s time. MPPTCL vide letter No. 07-05/E&T/65 dated 24.01.2011 (copy enclosed at Annexure-10) have confirmed that MPPTCL may also like to replace their SCADA/EMS system through unified approach through PGCIL.
WRP Committee may like to discuss.
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
13
ITEM No. 11: ESTABLISHEMNT OF 128Kbps LEASED CIRCUIT As discussed during 7th SCADA meeting, 128Kbps leased circuit have been
commissioned between SLDC Jabalpur - WRLDC Mumbai and SLDC Gotri – WRLDC
Mumbai. The other circuit between SLDC Bhilai and WRLDC Mumbai and Tarapur-I
and WRLDC Mumbai are under progress. The leased circuit have been very helpful
during communication failure in the recent past and vital ICCP data has continued to
flow between SLDCs and WRLDC. ED, WRLDC opined that considering the critical
nature of grid operation and possible failure of only one communication path, it would be
proper to make a back up leased line with MSETCL Kalwa and WRLDC Mumbai also,
though both are in same city. It was discussed and decided that WRLDC would check
with MSETCL for proper port availability and initiate the process of taking 128Kbps
leased line between SLDC Kalwa and WRLDC Mumbai.
In this context, during 8th SCADA meeting DGM, WRTS-I informed that the scheme that
included the OFC links on Maharashtra and Reliance lines and was proposed in last
meeting would serve dual purpose of providing alternate path for central sector RTU
data as well as the redundancy to existing ICCP links between SLDC, Kalwa and
WRLDC. The part of the link would involve hiring of fibers from Reliance. An estimate
from Reliance obtained by WRTS-I and the same along with the scheme details is
enclosed at Annexure-11. After detailed deliberation on subject matter, the Committee
agreed for the scheme which would now be put up in next WRPC for approval.
WRP Committee may discuss and approve.
ITEM No. 12: OPGW BASED COMMUNICATION LINK TO S/S OF PGCIL IN WR The matter was discussed and the Master Communication Plan for WR was approved
by WRPC in their 14th meeting held on 19th August 2010 at a cost of Rs 144.35cr. In the
same meeting, MPPTCL requested for inclusion of their communication requirements in
the master communication plan. The cost estimate for wide band equipments & node
proposed in MP state were required to be worked out. It was suggested by
POWERGRID that the terminal equipment for the MPPTCL requirements could be
included in the Master Communication Plan but OFC laying on MPPTCL lines would be
taken care of by MPPTCL. Alternately, if MPPTCL choose to procure the terminal
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
14
equipments as well, the technical interface details of the same would be made available
to MPPTCL.
In the finalized master communication network, following two lines being constructed by
IPTC were decided to be included in the network.
(i) Parli (PG) – Sholapur (PG) – 225Km.
(ii) Sholapur (PG) – Kolhapur (PG) – 167Km
The matter was discussed in 8th SCADA O&M Committee on 7.01.2011 and it was
proposed to include the following MSETCL lines in the proposed network :
(i) Parli (PG) – Parli (MSETCL).
(ii) Parli (MSETCL) – Sholapur (Lamboti) MSETCL
(iii) Sholapur (MSETCL) – Sholapur (PG)
(iv) Sholapur (MSETCL) – Kolhapur (MSETCL)
MSETCL representative agreed for the proposal. AGM, WRLDC stated that with this
modification in master communication plan, the respective MSETCL stations would as
will be covered for telemetry requirements of WR SCADA systems. Further, MSETCL
agreed to permit the laying of fibres wherever MSETCL fibres were not being planned.
For lines where MSETCL had initiated process for laying fibre, the fibres could be
spared for the master communication plan. It was informed that the Master
Communication Plan for WR as approved by WRPC and indicated above is under
process by POWERGRID and the NIT would be floated by March 2011 with a
commissioning time line of 30 months, to be taken up in a phased manner.
WRP Committee may like to note. ITEM No. 13: TELEMETRY TO SLDC FROM CENTRAL SECTOR STATIONS The matter was discussed in the 12th WRPC meeting and it was decided that PGCIL will
address the issues concerning frequent failure of communication between RLDC and
SLDC resulting in interruption of real time data communication to SLDC. Also, PGCIL
will discuss the matter with the supplier to check the feasibility of providing an additional
port in the gateway for data communication to SLDC in respect of substation with
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
15
automation. The above matter will be discussed by the SCADA O&M Committee of WR
and the outcome will be put up to TCC/WRP Committee for further directions, if any.
During 8th SCADA O&M Committee meeting held on 7.01.2011, LD&C, POWERGRID
informed that these locations were equipped with SAS/GAS with interface converters for
real time data reporting. He further informed that most of the locations were housing
SAS schemes that had dual ports for reporting to RLDC and no spare port was
available for reporting to SLDCs.
ED WRLDC informed that as per IEGC clause 6.4, all players are governed by control
area concept including real time data flow and thus real time data from the stations
coming under RLDC control area should be made available to RLDC. He further
informed that backup MTNL/BSNL leased circuits have been taken by WRLDC for ICCP
data continuity, as such central sector data to SLDCs is assured on the prevailing
communication network. Hence, same data reporting to SLDC through wide band
communication would be redundant. Therefore, it was concluded that direct reporting of
central sector station to SLDC would not be taken up.
Committee may discuss and approve. ITEM No.14: ONGOING TRANSMISSION SCHEMES IN WESTERN REGION
It is intimated that in accordance with the decision taken in the 12th WRPC meetings
held on 16th January 2010 at Vadodara, 4th meeting to review ongoing transmission
projects in Western Region was held on 16th December 2010 at WRPC, Mumbai
14.1 The status of the construction of transmission schemes under execution by
Gujarat Electricity Transmission Company Ltd., Madhya Pradesh Power Transmission
Company Ltd., Chhattisgarh State Power Transmission Company Ltd., Maharashtra
State Transmission Company Ltd, and PGCIL & Reliance Power Transmission Ltd. was
reviewed and discussed in detail under various heads separately as given below:
a) Progress of transmission schemes associated with evacuation and system
strengthening scheme for own Generating Station.
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
16
b) Progress of transmission schemes associated with evacuation and system strengthening scheme for Generating Station set up by IPP.
c) Progress of interconnected transmission schemes associated with PGCIL Sub-station.
d) Progress of transmission schemes and system strengthening schemes set up through IPTC route.
e) Progress of Intra-state transmission schemes The status of lines identified for completion on priority is as below:-
S.No. Line Implementing Agency
Anticipated target
1 400 kV D/C Mundra (Adani) - Varsana D/C line
Gujarat Dec-10
2 400 kV Tappar( Varsana)-Hadala line Gujarat Charged on 02.11.10
3 220 kV V D/C Varsana (Tappa)-Morbi Gujarat Charged on 31.3.2010
4 400 kV D/C line from Bhusawal II to Aurangabad (Loc. No. 1 to 270)
Maharashtra Jan-11
5 400 kV D/C Birsighpur(MPGENCO)-Damoh(PG)
PGCIL Syncd in Dec-10
6 400 kV Vapi(PG)-Navi Mumbai D/C line
PGCIL Oct-12
7 400 kV D/C Mundra-Bachchau- Ranchodpur line (Triple snowbard)
PGCIL March-11
8 400 kV D/C Gandhar-Navsari line PGCIL Oct-12 9 400 kV D/C Navsari- Mumbai line(Boisar) PGCIL Oct-12 10 400 kV D/C Ranchi – Rourkela PGCIL Charged on
30.11.10 11 400 kV D/C Rourkela – Raigarh PGCIL Feb-11 12 400 kV D/C Raigarh – Raipur PGCIL charged on
30.09.10 13 LILO of Lonikhand(MSEB)-
Kalwa(MSEB)400 kV D/C at Pune(PG) Reliance (IPTC route)
Mar-11
14 LILO of Solapur(MSEB)-Karad(MSEB)400 kV D/C at Pandharpur/Solapur(PG)
Reliance (IPTC route)
Commissionedin Jan 11
15 400 kV D/C Limbdi(Chorania)(GEB)-Ranchodpura(Vadavi)(GEB)
Reliance (IPTC route)
March-11
16 400 kV D/C Ranchodpura(Vadavi)(GEB)-Zerda(Kansari)(GEB)
Reliance (IPTC route)
March-11
17 400 kV D/C Rajgarh(PG) – Karamsad (GEB)
Reliance (IPTC route)
May- 11
The details of ongoing transmission schemes under construction are enclosed at
Annexure-14.
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
17
14.2 Following transmission lines have been commissioned in Western Region during
2010-11 up to December 2010:-
S.N. State/ Agency
400kV/ 220kV
Length in Ckt. Kms.
Name of Transmission Line Date of Charging
1 Madhya Pradesh.
220kV 54.00 Maheshwar-Nimrani Line 12.04.10
2 Chhattisgarh 220 kV 50.90 220kV DCSS Khedamara-220kV S/S Bematara
18.05.10
3 Gujarat 400 kV 118.00 400 kV D/C Mundra (Adani) - Varsana D/C line
Dec-10
220kV 118.00 220kV Viramgam-Bhat line 29.05.10 4 Gujarat 220kV 71.25 220kV Bhat-Salejada line 01.06.10 400 kV 400 kV D/C Birsighpur
(MPGENCO) - Damoh(PG) Syncd in Dec-10
5 Madhya Pradesh
220kV 266.60 Chhindwara-Betul 220kV DCDS Line
03.06.10
6 Maharashtra 220kV 46.00 220 kV Chandrapur- Warora for 220 kV Wani
10.06.10
7 Maharashtra 400kV 54.75 400 kV D/C Jaigad- New Koyana line (Ckt.-I)
06.04.10
8 Chhattisgarh 220kV 42.94 LILO of 220kV Bhatapara-Raipur (PGCIL) at Doma
10.07.10
9 Maharashtra 400kV 137.43 Dabhol-Nagothane II ckt. 24.08.10 10 Madhya
Pradesh 220kV 7.8 LILO of 220kV Satna-
Bansagar line at Kotar S/S 15.08.10
11 Powergrid 400kV 440.00 400 kV D/C Raigarh – Raipur 30.09.10 Total 1289.67
10.3 Important EHV lines, which are expected to be commissioned during the current year:
S.No. Line Anticipated target 1 400 kV D/C Mundra (Adani) - Varsana D/C line Dec-10 2 400 kV D/C line from Bhusawal II to Aurangabad
(Loc. No. 1 to 270) Jan-11
4 400 kV D/C Ranchi – Rourkela Dec-10 5 400 kV D/C Mundra-Bachchau- Ranchodpur line March-11 6 LILO of Lonikhand(MSEB)-Kalwa(MSEB)400 kV D/C
at Pune(PG) March-11
7 LILO of Solapur(MSEB)-Karad(MSEB)400 kV D/C at Pandharpur/Solapur(PG)
Charged on 21.1.11
8 400 kV D/C Limbdi(Chorania)(GEB)-Ranchodpura(Vadavi)(GEB)
March-11
9 400 kV D/C Ranchodpura(Vadavi)(GEB)-Zerda(Kansari)(GEB)
March-11
WRP Committee may like to note.
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
18
ITEM No. 15: ONGOING GENERATION SCHEMES IN WESTERN REGION The generating units expected to be commissioned during current year are as follows:
Name of the Power Projects Unit No.
Capacity (MW) Schedule Date of Commissioning
GUJARAT (i) Mundra TPP Ph-I, APL 4 330 Dec.2010 (ii) Hazira CCPP (GSEG) GT+ST 350 Sep. 2010 (iii) Mundra STPP APL 1 660 Jan. 2011 MADHYA PRADESH (i) Satputa TPS Ext. 10 250 Nov. 2010 (ii) Satputa TPS Ext. 11 250 March 2011 MAHARASHTRA (i) JSW Energy, Ratnagiri (4x300) 2 300 Sep. 2010 (ii) JSW Energy, Ratnagiri (4x300) 3 300 Dec. 2010 (iii) JSW Energy, Ratnagiri (4x300) 4 300 March 2011 CENTRAL SECTOR – NTPC (i) Sipat-I, TPP 1 660 Nov. 2010 2 660 May 2011 3 660 Nov 2011 (ii) Korba STPP Stage-III 7 500 Oct 2010
The details of ongoing generation schemes in WR both under State as well as Central
Sector are enclosed at Annexure-15. Following Generating units have been commissioned in Western Region during 2010-11
up to December. 2010
S.No. State/Agency Name of Project Unit No. Capacity in MW
Date of Sync./Comml.
1 Gujarat Surat Lignite TPP Extn.
3 125.00 12.04.10
2 Gujarat Surat Lignite TPP Extn.
4 125.00 23.04.10
3 Maharashtra Wardha Warora TPP
1 135.00 05.06.10
4 Gujarat Mundra TPP Ph-2 3 330.00 02.08.10 Mundra TPP Ph-2 4 330.00 20.12.10 Mundra TPP Ph-2 5 660.00 26.12.10 5 Maharashtra JSW Energy TPP 1 300.00 24.08.10 6 Maharashtra Wardha Warora
TPP 2 135.00 10.10.10
Total 1150 WRP Committee may like to note.
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
19
ITEM No.16: INCLUSION OF NON-ISTS ASSETS FOR IMPLEMENTATION OF
POINT CONNECTION METHOD FOR POINT OF CONNECTION CHARGES
16.1 CERC Regulations, 2010 on "Sharing on transmission charges and Losses"
regulation 2010 are to come in force from 1.4.2011. The determination of transmission
charges as per this Regulation is required to be limited to the network owned, operated
and maintained by the ISTS Licensees or those transmission licensees / SEBs whose
assets have been certified by RPCs as being used for inter-state transmission. During
15th WRP Committee meeting The WRP Committee approved the criteria and the list of
state owned Interstate / Inter-regional lines for certification as ISTS lines. It was also
agreed that any other non-ISTS line that comes up and meets the criteria agreed as
above, may be considered for certification as ISTS line. Accordingly list of state owned
Interstate / Inter-regional lines certified as ISTS lines as approved above was forwarded
to implementing agency. Also the list was sent to the concerned non- ISTS Licensees
for furnishing YTC of the respective lines certified as above to NLDC.
16.2 GETCO vide letter No.SLDC/MIS/1509 dated 3.12.2010 and MPPTCL vide letter
No.04-02/PSP-386/1408 dated 9.11.10 have requested inclusion of more following lines
for certification as non-ISTS assets of WR for POC charges which were discussed in
57 Commercial Committee meeting. CSPTCL also vide letter No. CE/Trans/PL/4274
dated 10.1.2011 sent list of four 220kV and 132 kV lines for inclusion:
th
Sr. No. Line Status GETCO 1 220 kV S/c Navsari-Chikhali-Vapi For Kawas GPS/ Kakrapar
APS 2 220 kV S/c Navsari-Bhilad -do- 3 220 kV S/c Vav-Sachin-Navsari -do- 4 400 kV S/c Jetpur-Hadala-Chorania For Mundra UMPP 5 400 kV S/c Jetpur-Amreli-Chorania -do- 6 400 kV D/c Asoj-Chorania -do- 7 400 kV S/c Kasor-Chorania -do- 8 400 kV D/c Vadavi-Dehgam -do- 9 220 kV D/c Kansari-Palanpur-Kheralu-Jamla-
Soja Higher voltage line considered for POC along this path.
10 220 kV D/c Vadavi-Mitha-Soja Lower voltage parallel path
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
20
11 220 kV S/c Soja-Mehsana-Radanpur-Deodar-Kansari
-do-
12 400 kV S/c Asoj-SSP Dedicated line for SSP 13 400 kV S/c Kasor-SSP -do- 14 220 kV S/c Tarapur-Bhilad ISGS evacuation line 15 220 kV S/c Tarapur-Vapi -do- MPPTCL 1 400 kV S/c Seoni-Satpura Intrastate line and has
connectivity with CTU exists at Seoni.
2 400 kV D/c Nagda-Rajgarh Part of dedicated line for SSP and connectivity with CTU exists at Rajgarh
3 400 kV D/c Rajgarh-SSP Dedicated line for SSP 4 220 kV D/c Satpura-Pandhurna Intrastate line and has
connectivity with CTU line CSPTCL 1 220 kV Korba(E)-Raigarh Connectivity with CTU at
Raigarh 2 220 KV Raigarh-Budhipadar -do- 3 220 kV Korba(w)-Kotmikala D/c 4 132 kV Dongargarh-Balaghat S/c Intrastate line considered
already During the 57th CCM the consensus opinion on inclusion of such state lines which carry
power that is evacuated from the ISGS through CTU line(s) or through dedicated line(s)
from this generating station to the State points beyond which no direct connectivity to
nearest CTU point exists, could not be arrived at. It was agreed that issue may be
further discussed in next CCM after constituents further examine various aspects in this
context.
Committee may like to note. ITEM NO.17 : EXTENSION OF THE DATE OF OPERATION OF CERC (SHARING OF
INTER-STATE TRANSMISSION CHARGES AND LOSSES) REGULATIONS, 2010.
Central Electricity Regulatory Commission, Regulations, 2010 on Sharing of Inter-State
Transmission Charges and Losses were to take effect from 1.1.2011. NLDC the
implementing agency of the above Regulations have submitted to Commission the,
details of Point of Connection charge worked out based on the data and network details
received from the various DICs. It has sought more time for submitting the modified
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
21
procedure after incorporating comments of stakeholders and decision of CERC on the
issues raised. CERC vide order 30.12.2010 has directed that the Regulations shall
come into force with effect from 1.4.2011.
As the States want to see the implication of the new method of sharing of transmission
charges through calculation of actual transmission charges through both the
methodologies before the same gets implemented, constituents may see the
transmission charges worked out through both methodologies which shall be
maintained on the NLDC website w.e.f 01.02.2011.
Committee may like to note.
ITEM No.18: PERFORMANCE OF WR GRID DURING NOVEMBER 2010 TO DECEMBER 2010
18.1 SYSTEM PERFORMANCE Frequency: During November 2010 and December 2010 system frequency was in the permissible
range of 49.5 Hz to 50.20 for 86.77 % and 88.94 % of time. Frequency remained below
49.50 Hz for 0.49 % of time during November 2010 and for 2.02 % of time during
December 2010. In higher frequency regime, system frequency remained above 50.20
Hz for 12.74 % and 9.04 % of time respectively in November 2010 and December 2010.
The monthly average frequency was 50.00 Hz & 49.92 Hz in November 2010 and
December 2010 respectively.
During months of November and December 2010, the grid operated in the frequency
range of 49.2 Hz to 50.2 Hz for 87.25 % and 90.88% of time respectively. The maximum
period frequency was below 49.2 Hz was 0.01 % of time during November 2010 and
0.08% of time during December, 2010.
The number of occasions when instantaneous frequency touched 48.8 Hz was nil
during November 2010 and December 2010. The detail of frequency profile for the
months of November to December 2010 is placed at Annexure 18.1(a).
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
22
Partial grid disturbances: Partial grid disturbances took place in Mumbai system on 18.11.2010 at 1740 hrs and
21.11.2010at 1705 hrs.
On 18.11.2010 the system frequency was 49.76 Hz and Maharashtra state demand was
13007 MW and Mumbai catered demand was 2599 MW. The disturbance initiated with
the tripping of 220 kV Trombay-Salsette I followed by tripping of 220 kV Trombay-
Salsette II, 220 kV Boisar-Dahanu, 220 kV Boisar – Versova and 220 kV Borivali-Aarey
D/c and 220/100 kV ICTs at Borivali. Both the units at Dahanu tripped. Loads of R-Infra
at Ghodbunder, Versova and Aarey (713 MW total) were affected. The Restoration
commenced at 1748 hrs with the charging of 220 kV Trombay-Salsette II and by 1904
hrs 664 MW loads were restored.
On 21.11.2010 power supply in Dharavi Backbay, Vikroli and Mahalaxmi were affected
with the tripping of 220 kV Trombay-Dharavi ckt V and VI and 220 kV Trombay- Salsette
II. The loss of load was around 450 MW and there was no loss of generation.
Restoration commenced at 1714 hrs by extending power from 110 kV PArel s/s and by
1801 hrs the loads were restored with the charging of above lines.
It has been intimated that MERC has set up a Committee headed by Prof
S.A.Khaperde, IIT Bombay consisting of representatives from SLDC, WRLDC, STU,
TPC and R-Infra and Commission’s Officer to review the existing protection schemes,
Under frequency relay settings, islanding schemes and suggest remedial measures to
avoid such occurrences in future.
OverDrawal Messages: WRLDC issued advisory messages of type A, B and C to WR constituents for curtailing
over drawal as below:
Message type /Constituent A B C Total GETCO November -2010 Nil Nil Nil Nil December-2010 2 2 0 4 MPPTCL
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
23
Message type /Constituent A B C Total November -2010 Nil Nil Nil Nil December-2010 5 3 1 9 CSPTCL November -2010 Nil Nil Nil Nil December-2010 1 2 0 3 MSETCL November -2010 Nil Nil Nil Nil December-2010 0 0 0 0 DNH November -2010 Nil Nil Nil Nil December-2010 Nil Nil Nil Nil GOA November -2010 Nil Nil Nil Nil December-2010 Nil Nil Nil Nil
No regulatory measures were required to be taken.
There were net inter-regional export of 757.74 MUs and 1376.60 MUs by WR against
net export schedule of 362.649 MUs, and 676.371 MUs respectively in November and
December 2010.
The instances of overdrawal and TTC violation by neighbouring regions were taken up
by WRLDC in real time. The messages issued by WRLDC for curtailment of overdrawl/
TTC violation to other regions.
LINK NR ER MPPTCL MSETCL TOTAL
No of O/D Messages
November -2010 6 6 Nil Nil 12
December-2010 33 34 Nil Nil 67
No of TTC Messages
November -2010 Nil Nil Nil Nil Nil
December-2010 8 Nil Nil Nil 8
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
24
The maximum unrestricted demand of Western Region was 39589 MW and 41252 MW
in November 2010 and December 2010 respectively, as compared to 39208 MW and
38755 MW during the same months last year respectively. The region faced capacity
shortage in the range of 5946 MW and 6910 MW (peak deficit of 15.02 % & 16.75 %)
during November 2010 & December 2010 respectively. The per day energy requirement
during November 2010 and December 2010 was 719.81 MUs and 803.13 MUs
respectively. The energy shortage was 75.89 MUs per day and 109.79 MUs per day
during these months The details of unrestricted peak demand, demand met and energy
requirement and availability are as furnished at Annexure-18.1 (b).
Overall voltage profile had been satisfactory during the period under review. However,
instances of low and high voltages beyond the IEGC specified operating range were
observed at some of the EHV sub-stations in the region. Minimum voltage of 372 kV &
374 kV was noted on 2nd November & 4th December 2010 at 400 kV Jetpur substation.
Higher voltages in the range of 421 kV to 435 kV were noted. SSP units run in
synchronous condenser mode for 124 m/c hrs. in the month of December 2010.
18.2 The detail of voltages at important 400 kV and 765 kV sub-stations for the months
November 2010 and December 2010 is placed at Annexure- 18.2. In order to control
incidences of high voltages during low load periods, installation of reactors at following
locations as planned by various utilities is in the process as per following schedule:
S.No. 400 kV Substation
Size (MVAR)
Implementing agency
Expected commissioning date
1. Khandwa 1x125 PGCIL Commissioned on 30th Sep. 2010
2. Dhule 2x50 MSETCL 1x50 MVAr is already commissioned. 2nd reactor is commissioned on 11th December 2010 end.
3. Dehgam 1x125 PGCIL Commissioned on 29th October 2010
4. Kasor 1x125 GETCO Likely to be Commisioned in January 2011
5 Soja 1x80 GETCO Likely to be Commisioned in January 2011
6 Rajgarh 1x125 PGCIL September 2011
The timely commissioning of the above reactors is likely to help in smoothening of high
voltage profile.
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
25
18.3 AUFLS Performance. The month-wise details relating to performance of AUFLS scheme in Western Region
during the period November 2010 to December 2010 in terms of quantum of load relief
obtained and number of occasions the UFR operated is at Annexure-18.3. It may be
noted that there was no occasion when the AUFLS relays was called to operate.
WRP Committee may like to note. ITEM No.19 : RESPONSE OF GENERATING UNITS UNDER RGMO IN WESTERN
REGION WRLDC vide letter dated 27.01.2011 have intimated that as per the clause no. 5.2 of
the IEGC effective from 3.05.2010, WRLDC has commenced monitoring the RGMO
status of generating units in WR and the same has been regularly reviewed/discussed
in regional OCC forum and the position of generating units in WR is as below: -
• The units which are eligible to participate in RGMO are 188 Nos (29701 MW) • WRLDC has developed an analyzing tool to carry out RGMO analysis • WRLDC has carried out detailed analysis of the units that have confirmed
participation (62 units, 11776 MW; 29 hydro units, 1586 MW & 33 thermal units, 10190 MW) in RGMO
• 20 units have applied for exemption to CERC • 104 units(15345 MW) have informed that there are some problems in
implementing RGMO and WRLDC have requested these generators to take up with CERC for exemption under intimation to WRLDC
• Out of 188 eligible units (11776 MW), telemetry is available for 155 units. The details are enclosed at Annexure-19. WRP Committee may like to note. ITEM No.20: ANTICIPATED POWER SUPPLY POSITION IN WESTERN
REGION FOR THE PERIOD FROM JANUARY 2011 TO MARCH 2011
The anticipated power supply position in the region for the period from January 2011 to
March 2011 is at Annexure-20. The demand during the period is likely to remain at a
high plateau. The anticipated regional demand is likely to vary between 40201 MW to
40496 MW and the capacity shortage will vary from 4.38 % to 7.19 %. In terms of
energy, the unrestricted requirement is expected to range from 22582 MUs to 25313
MUs with regional energy deficit of the order of 1.6 % to 3.38 %. The anticipated Peak
demand shortage of 50 to 180 MW in Gujarat, 410 to 560 MW in Chhattisgarh, 4450 to
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
26
4630MW in Maharashtra, 675 to 1555 MW in Madhya Pradesh, 17 to 26 MW in Goa,
130 to 170 MW in DD & 15 MW to 50 MW in DNH is likely to prevail.
WRPC Committee may like to note. ITEM No. 21: MECHANISM FOR COMPENSATION OF LOSSES ON TRANSFER OF
POWER TO NR OVER MPPTCL & GUVNL NETWORK WRLDC vide letter No. WRLDC/OS/1517/11 dated 28.01.2011 have intimated that
during 15th WRPC meeting, the mechanism of compensation of losses for transfer of
power between WR and NR over MPPTCL and GUVNL network was discussed and it
was decided that the compensation of losses shall be done by applying necessary loss
compensation to the actual inter regional power transfer on 220kV Badod-Kota and
220kV Badod-Modak inter-regional links and 400kV Zerda-Kankroli inter-regional link
approved by State Regulatory Commission for State Transmission System in respective
states and this loss may be pooled among the WR constituents and have suggested on
the following:-.
21.1 Mechanism for compensation of losses on transfer of power to NR over GUVNL Network.
(i) In case of GUVNL only one link i.e. 400 kV Zerda- Kankroli is mentioned in the
minutes and have suggested that Power transfer over 400kV Zerda-Bhinmal link is also
required to be considered while giving loss compensation to the actual power transfer.
(ii) Clarification on application of loss compensation to both export and import of power
through this links has been sought by WRLDC and have proposed that compensation of
loss to both export and import shall be applied on power through these lines lines viz.
400 kV Zerda- Kankroli and 400kV Zerda-Bhinmal. 21.2 Mechanism for compensation of losses on transfer of power to NR over
MPPTCL Network. WRLDC have stated that in reality four numbers of STU network is used for power
transfer between WR and NR, i.e. 220kV Auraiya-Malanpur, 220kV Auraiya – Mehgaon,
220kV Kota- Badod, 220kV Modak-Badod.
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
27
WRLDC has proposed that the compensation of loss shall be applied to the net
transaction over these four links between WR and NR in each 15- minute time block.
Also clarification has been sought that whether to apply loss compensation to both
export and import of power through these links and has proposed that, compensation of
loss shall be applied to both import/export of power transfer between WR and NR using
MPPTCL network.
WRP Committee may like to discuss and decide. ITEM No.22: PAYMENTS OF UI AND REACTIVE ENERGY CHARGES
22.1 As per the information received from WRLDC, the status of payment to UI pool
account and Reactive Energy Pool account as on 25.01.2011 i.e. upto week 3.01.11 to
9.01.11 of the current financial year is given below: -
UI Pool Account Reactive Energy Pool Account Constituents Dues (in Rs.) Constituents Dues (in Rs.)CHHATTISGARH -29,947,824 CHHATTISGARH -3,471,705MADHYA PRADESH 63,056,956 MADHYA PRADESH 5,118,050GUJARAT -134,807,433 GUJARAT -272,419MAHARASHTRA -86,720,233 MAHARASHTRA -769,852GOA -3,053,039 GOA 504,607DD 139,071,416 DD 2,554,338DNH 0 DNH 51,018NTPC -42,172,357 NR Exchange 554,459,508 SR Exchange -18,692,053 ER Exchange 257,997,637 Jindal Power 884,698 HVDC Vindhyachal -166,051 HVDC Bhadravati -654,787 Lanco Amarkantak -63,194,101 Diff. due to capping>105% -53,514,818 Diff. due to Addl. UI -379,445,014 Diff. due to capping on o.inj/U.drl -329,816,733 Net Total -126,713,929 3,714,037
WRP Committee may like to note.
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
28
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
29
22.2 WRLDC vide letter dated 27.01.2011 have intimated that the requirement of LC
to be opened by the entities of WR as per the provisions in Central Electricity
Regulatory Commission (Unscheduled Interchange Charges and related matters)
(Amendment) Regulations, 2010 as below :
Sr. No. Entity of WR LC requirement for payment of UI charges
Status of opening of LC, amount, date
1 Chhattisgarh 802 Lacs Not Opened
2 Madhya Pradesh 2221 Lacs Not Opened
3 Gujarat 1238 Lacs Not Opened
4 Maharashtra 928 Lacs Not Opened
5 Goa 79 Lacs Not Opened
6 Daman & Diu 137 Lacs Not Opened
7 Dadra & Nagar Haveli
124 Lacs Opened LC for ` 124 Lacs on 21.12.2010
8 Jindal Power 279 Lacs Opened LC for ` 238 Lacs on 22.09.2010
WRLDC further intimated other constituents are requested to open the LC as above. In
the past meetings this issue is discussed and constituents expressed reservations in
opening LC and WRLDC therein mentioned that WRLDC is only implementing the
CERC regulation which is applicable to all and in case of reservations by the
constituents in opening of LC, they may approach the Hon’ble Commission in
accordance with Clause-12 of CERC Notifications on “Unscheduled Interchange
charges and related matters, Regulations 2009.
Members may indicate the status of opening of LCs.
ITEM No.23: WIDE AREA MEASUREMENT SYSTEM (WAMS) IN WR
23.1 The matter regarding implementation of WAMS in WR was discussed during 11th
meeting of WRPC held on 25th September 2009 at Raipur and also during 13th meeting
of WRPC held on 9th April 2010. A meeting of Task Force on WAMS was proposed by
WRPC on 10th March 2010 to discuss the modalities etc. regarding implementation of
WAMS Project in WR. However, GM (LD & C), PGCIL vide letter dated 5th March 2010
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
30
had intimated that in view of CERC order directing one time expenses from UI Fund
towards the above project, PGCIL had taken up the issue with CSIR and on their
approval they would sign the agreement with CSIR and other consortium partners.
During 13th WRPC meeting PGCIL were requested to expedite issues concerning
approval/ signing of the agreement etc. with CSIR and other consortium partners so that
a meeting of Task Force on WAMS could be called at the earliest for further needful
action. POWERGRID vide communication dated 21.10.2010 and also in the 15th
TCC/WRPC meeting intimated that their Board have approved the Project with certain
conditions like availability of software for all RLDCs and NLDC. The acceptance of the
conditions by the consortium members had not been received by them thereby resulting
delay in signing of necessary agreement with CSIR for moving ahead with the Project
Implementation. POWERGRID further intimated that they have requested consortium
partners to send their response within two weeks' time. Subsequently no communication
has been received from POWERGRID on the above matter.
POWERGRID may inform the current status on the above.
23.2 During the 15th TCC/ WRPC meeting, Chairman WRPC suggested that in the
presentations/ exposures on WAMS systems made by eminent experts like Shri
A.G.Phadke may be attended by the regional utilities for the benefit of all constituents.
It is hereby informed that on 22.12.2010, presentation for the benefit of WR
Constituents was arranged by POWERGRID at WRLDC, Mumbai which was attended
by the constituents of WR. Dr A.G.Phadke and Mr Ken Martin gave presentation that
covered the various aspects of WAMS.
ITEM No.24: PSDF MANAGEMENT COMMITTEE CERC vide order dated 4th June 2010 have issued regulation called the Central
Electricity Regulatory Commission (Power System Development Fund) Regulations
2010. As per the provision under the above regulations, a fund to be called the “Power
System Development Fund” shall be constituted and there shall be credited thereto.-
a) Congestion charges standing to the credit of the “Congestion Charge Account”
b) Congestion amount arising from the difference in the market prices of different
regions
c) Unscheduled Interchange charges standing to the credit of the “Unscheduled
Interchange Pool Account Fund”
d) RLDC reactive energy charges standing to the credit of Reactive Energy
Charges Account;
e) Such other charges as may be notified by the Commission from time to time;
f) Provided that amounts representing the sources as specified in sub-clauses (a)
to (d) and lying in the custody of Central Transmission Utility together with
interest earned thereon upto 30th of April, 2010 shall be credited to the Fund.
Regulation 7 of the Power System Development Fund, Regulation 2010 specifies that
an officer of the level of General Manager or above is to be nominated by each of the
five Regional Power Committees as member of Management Committee. As discussed
in 15th WPC meeting, nomination of one member from WRPC i.e. Member Secretary,
WRPC as a member of the Management Committee of PSDF from WRPC was sent to
NLDC.
The matter of representation of RPC in PSDF management Committee was also
discussed in other RPCs. ERPC had suggested that as handling fund of the above
nature by Regulator is unique, the Region should have ultimate say in the utilization of
the fund contributed to PSDF and utilization of PSDF & functioning of the PSDF
Management Committee monitored closely by the RPC. The Committee further
recommended that broader representation should be made to the Management
Committee. ERPC have since forwarded the recommendations of the Committee to
Secretary, CERC for information.
Committee may like to discuss. ITEM No. 25: GRANT OF LTA FOR GENERATION DEVELOPERS IN SR. PGCIL granted LTA to following generator developers of SR as per the following details:
Quantum allocated to
Sr. No.
Generation Developer
Installed Capacity
LTA granted
SR WR NRPGCIL letter no. C/ENG/SEF/TA/L/S/10/008 dated 10.12.2010 : Vemagiri Area in Andhra Pradesh 1 Thermal Powertech
Corporation India Ltd. 1320 1320 1125 115 0
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
31
Quantum allocated to
Sr. No.
Generation Developer
Installed Capacity
LTA granted
SR WR NR2 Meenakshi Energy Pvt.
Ltd. 300 273 273 0 0
3 Nelcast Energy Corporation Ltd.
1320 1240 840 400 0
PGCIL letter no. C/ENG/SEF/TA/L/S/10/009 dated 10.12.2010 : Nagapattinam/Cuddalore Area in Tamil Nadu 4 NSL Power Pvt. Ltd. 1320 800 267 267 2665 PEL Power Ltd. 1050 987 700 0 2876 IL&FS Tamil Nadu Power
Co. Ltd. 1200 1150 575 575 0
PGCIL letter no. C/ENG/SEF/TA/L/S/09/001(R3) dated 10.12.2010 : Krishnapatnam Area in Andhra Pradesh 7 Simhapuri Energy Pvt. Ltd. 600 491 356 135 0 8 Meenakshi Energy Pvt.
Ltd. 600 546 186 177 183
9 Krishnapatnam Power Corporation Ltd. (Navayuga)
1320 925 725 200 0
10 Kineta Power Pvt. Ltd. 1320 925 625 300 0 11 Thermal Powertech
Corporation India Ltd. 1320 1240 1125 115 0
12 Nelcast Energy Corporation Ltd.
1320 1240 840 400 0
13 Meenakshi Energy Pvt. Ltd.
300 273 273 0 0
14 Andhra Pradesh Power Development Co. Ltd.
1600 175 0 0 175
PGCIL letter no. C/ENG/SEF/TA/L/S/10/007 dated 10.12.2010 : Vemagiri Area in Andhra Pradesh 15 Spectrum Power
Generation Ltd. 1400 1350 1120 330 0
16 Reliance Infrastracture Ltd. 2400 2200 1500 700 0 17 GVK Gautami Power Ltd. 800 800 433 100 26718 GVK Power (Jegurupadu)
Pvt. Ltd. 800 800 520 100 180
Details of above LTA are available as additional Annexure on WRPC website. WRP Committee may like to note. ITEM No.26: SHARING OF ESTABLISHMENT EXPENDITURE OF WRPC BY NCA Member (Power), NCA vide letter No. 2/8/Power/EMC/164 dated 28.01.2011 (copy
enclosed at Annexure-26) have intimated that NCA have been granted the membership
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
32
of WRPC. He further intimated that NCA is an organization working directly under
MOWR and its all expenditure is provided and shared by beneficiary States and
beneficiary States are of the view that as they are already funding WRPC so sharing of
expenditure of WRPC membership by NCA is not justified.
In view of above, NCA have requested to discuss this issue in WRPC and exempt NCA
from payment towards expenses of WRPC Secretariat at par with
WRLDC/CEA/NLDC/WRPC.
WRP Committee may like to discuss. ITEM No.27: RENOVATION AND MODERNISATION OF WRPC OFFICE BUILDING 27.1 During 15th WRPC meeting the matter regarding sharing of expenditure for
renovation & Modernisation of WRPC Office Building was deliberated and it was agreed
therein to exclude NCA, NHDC and SLDCs from contributing for the this particular R&M
work and distribute sharing of the remaining amount amongst the rest of the members
in the manner as approved by the WR Power Committee in the 13th WRPC meeting and
as per the payment schedule decided in 14th WRPC meeting held on 19th August 2010.
Accordingly, WRPC Secretariat vide letter no. WRPC/AS/Contribution/2010/1690 dated
3.01.2011 have requested members to release the payment as per Annexure-I of the
letter by 15th December 2010. Contribution from DNH is received so far. Draft MOU
document discussed in the implementation committee to be signed with PGCIL in
respect of R&M work was prepared and sent to PGCIL. PGCIL had subsequently
requested to include clause relating to TDS/Sales tax deduction etc. PGCIL were
intimated to retain clause as suggested by WRPC. Further as the 50% of the estimated
expenditure is to be passed on to PGCIL the payments requested to the members are
to be expedited, which are to be released immediately before commencement of the
R&M activity and upon signing of the MOU with PGCIL, from when the zero date of the
activity will start.
27.2 Reliance Energy Trading Ltd. vide letter no. RETL/WRPC/2010-11 dated
10.01.2011 have requested for clarification regarding sharing of the expenditure
towards R&M of WRPC office building to be shared equally by the electricity traders
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
33
having trading volume of more than 500 MUs during the previous financial year i.e.
2009-10.
WRP Committee may like to discuss and members may expedite the respective payments to ensure timely payment to PGCIL. ITEM No. 28: MEMBERSHIP OF WRPC
28.1 Government of India, Ministry of Power under the provision of Section 2,
Subsection 55 of the Electricity Act 2003 vide its resolution F.No.23/1/2004-R&R dated
25.05.2005 and subsequent amendments dated 29.11.2005 and 9th May 2008
published in the Gazette of India established the Western Regional Power Committee in
place of erstwhile Western Regional Electricity Board.
28.2 Accordingly, membership of State DICOM having more than one Distribution
Companies, representation of Private DISCOM, representation of IPPs having installed
capacity of 1000 MW and below and representation of Electricity Traders is due for
rotation and for the year 2011-2012 it will be as given below:
(i) Gujarat Dakshin Gujarat Vitaran Co. Ltd, Surat
(ii) Madhya Pradesh Poorva Kshetra Vidyut Vitaran Co. Ltd., Jabalpur
(iii) Representative of GENCO having IC 1000 MW and less.
Gujarat Paguthan Energy corporation Pvt. Ltd.
(iv) One DISCOM out of private DISCOs in WR
Tata power Company(Distribution), Mumbai
(v) One member representing Electricity Traders
Tata Power Trading (P) Ltd.
28.3 M/s Adani Power Ltd., Ahmedabad vide letter No. APL/WRPC/070111 dated
7.01.2011 have intimated that with Commissioning of Unit-4 (330 MW) of APL the
installed capacity of the plant has been increased to 1320 MW. As such Adani Power
Ltd. is having installed Capacity of above 1000 MW is eligible for membership of WRP
Committee. Adani Power Ltd. have requested for membership of WRP Committee.
Accordingly, Adani Power Ltd. may be considered as member w.e.f 1st April 2011.
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
34
28.4 Chairmanship of WRPC is due for rotation w.e.f. 1.04.2011 and CMD/MD of
Chhattisgarh State Power Companies would be Chairman of WRPC for the next year.
Members of Chhattisgarh State may intimate the name for the Chairman, WRPC among
different power companies of Chhattisgarh State.
WRP Committee may discuss and approve as above. ITEM No. 29: ANY OTHER ITEM ITEM No. 30: DATE AND VENUE OF NEXT WRPC MEETING It is proposed to hold next meeting of WRP Committee i.e. 17th meeting in the month of
May 2011.
*****
Agenda Notes of 16th WRPC meeting to be held on 12th February 2011 at Goa
35
Annexure-14.1(1/3)
(A) Transmission Schemes associated with State Generating Stations
1 Utran CCPP (2009-10) (370 MW) June 091.1 220kV Utran-Kosamba D/C line No.1 86.00 143 143 143 86 May-10 Line work completed
1.2 220kV Utran-Kosamba D/C line No.2 86.00 144 3 Mar-11 Work under progress. Severe ROW problems
1.3 220kV Kosamba-Mobha line 176.80 275 27 16 May-11 Work in progress.
2 Sikka Unit 3&4 (2x250 MW) C.O.D.- Dec'12
2.1 220kV D/C Sikka-Moti Paneli line with Moose cond.
156.00 248 - - - Tender under approval
2.2 LILO to Sikka from 220kV Jamnagar-Jetpur ckt. 1 116 178 - - - Tender under scrutiny
2.3 LILO to Sikka from 220kV Jamnagar-Jetpur ckt. 2 120 187 - - - Tender under scrutiny
3 Ukai Extension (2010-11) (500 MW) C.O. D.- Jul'11
3.1 400kV D/C Ukai-Kosamba line 136.2 189 24 - - Aug-11 Work in progress.
3.2 400 kV D/C Kosamba-Chorania line (Package I)(From Chorania S/S to AP-54)
222.4 308 78 28 - Jul-11Work in progress.
3.3 400 kV D/C Kosamba-Chorania line (Package II)(From Kosamba S/S to AP-54)
234.6 328 36 - - Jul-11Work in progress.
3.4 LILO to Kosamba from 400kV Asoj-Ukai line 64 95 89 75 - Feb-11 Work in progress. Severe ROW problems
3.5 220kV D/C Kosamba-Zagadia line 48.4 78 74 64 - Jan-11 Work in progress. 4 Dhuvaran CCPP-III (360 MW) July'13
4.1 LILO of 220kV Kasor-Vartej S/C at Dhuvaran CCPP-III 60 - - - - - Yet to be awarded.
4.2 LILO of 220kV Karamsad-Vartej S/C at Dhuvaran CCPP-III
60 - - - - - Yet to be awarded.
Remark Stub
setting Tower
erectedStringing complete
Status of Ongoing Transmission Progress in Gujarat (Dec.-10)
Sr. No. Name of Transmission lineLength in Ckt
Km
Total Location
Present Status as on 01.01.2011 Anticipated
completion Target
Annexure-14.1(2/3)
(B) Transmission Schemes associated with IPP 5 Adani Power, Mundra (Bid-I) (1000 MW)
5.1 220 kV D/C Mundra(Adani)-Varsana line 164.00 256 256 256 164.00 Jan-10 Line charged on 26.01.105.2 400 kV D/C Mundra(Adani)-Varsana line 168.20 277 277 277 147.76 Jan-11 Work in progress.Severe ROW
problem5.3 400kV D/C Varsana-Hadala line 318.00 490 490 490 316.35 Oct-10 Line charged on 02.11.105.4 220 kV D/C Varsana-Morbi line 214.00 353 353 353 214 Mar-10 Line Charged on 31.03.105.5 400kV D/C Hadala-Halvad line 161.56 244 111 68 - Apr-11 Work in progress
6 Adani Power, Mundra (Bid-II)(2011-12) (1000 MW) Feb'12
6.1 400 kV D/C Mundra-Zerda line No. 1 660.12 921 - - - - Tender under scrutiny6.2 400 kV D/C Mundra-Zerda line No. 2 660.12 921 384 160 - Oct-11 Work in Progress
7 Essar Power, Vadinar (Bid-3) (2011-12)(1000 MW) Feb'11
7.1 400 kV D/C Vadinar-Hadala line 226.00 353 343 305 44.7 Feb-11 Work in progress7.2 400 kV D/C Vadinar-Amreli line 360.00 506 25 - - - Work in progress
8 GSPC Pipavav Power Co. Ltd.(2010-11) (2x350 MW) Mar'11
8.1 220 kV D/C GPPCL-Dhokadva line 100.00 167 54 34 - Mar-11 Work in progress.Severe ROW problem
8.2 LILO to GPPCL from 220 kV Savarkundla-Otha Ckt. No. 1
93.00 151 94 87 25.80 Jan-11 Work in progress.Severe ROW problem
8.3 LILO to GPPCL from 220 kV Savarkundla-Otha Ckt. No. 2
82.60 131 61 47 - Mar-11 Work in progress
8.4 220 kV D/C Otha-Sagapara line 95.60 163 - - - - Tender under approval9 GSEG Extension Phase-I (350 MW) Jan'11
9.1 220 kV D/C GSEG-Kosamba line 124.00 197 151 103 8.08 Jan-11 Work in progress9.2 220 kV D/C GSEG-Mota line with AL-59 conductor 111.06 182 20 - - Mar-11 Work in progress10 Bhavnagar Energy Co. Ltd.(BECL)(2011-12) (2x300
MW)10.1 220 kV D/C BECL-Botad line 188.52 292 - - - - Estimate prepared & to be taken up10.2 220 kV D/C BECL-Sagapara line 82.40 135 - - - - Estimate prepared & to be taken up10.3 LILO of 220kV Savarkundla-Vartej at BECL 56.20 97 - - - - Estimate prepared & to be taken up
Present Status as on 01.01.2011Sr. No. Name of Transmission line
Length in Ckt
Km
Total Location
Anticipated completion
TargetRemark Stub
setting Tower
erectedStringing complete
Annexure-14.1(3/3)
(C) Transmission Schemes associated with PGCIL Substation
1 LILO OF 220 kV to Bhimasar from Morbi -Halvad ckt.no.1 215.00 331 192 111 - Mar-11 Work in progress.
2 LILO OF 220 kV to Bhimasar from Morbi -Halvad ckt.no.2 210.00 329 213 120 14.84 Mar-11 Work in progress.
3 220kV D/C Bhat-Pirana line with AL-59 Cond. 28.94 55 37 34 3.40 Jan-11 Work in progress.
(D) Transmission Schemes through IPTC route NIL
(E) Intrastate transmission schemes1 400kV Mundra-Hadala LILO to Halvad 89.40 124 - - - Work in progress.
2 220kV LILO to Kapadvanj from Wanakbori-Ranasan ckt.No. 2
30.31 49 49 48 30.31 Nov-10 Line charged on 18.11.10.
3 220 kV D/C Nakhatrana-Varsana line with AL-59 Cond. 213.76 334 268 194 11.58 Mar-11 Work in progress.
4 220 kV D/C Tappar - Varsana line 8.00 15 15 15 7.8 Oct-10 Line charged on 23.10.10.5 220kV D/C Bhutiya - Kheralu line 98.63 163 141 124 - Feb-11 Work in progress. 6 220kV LILO to Kangasiyali from Gondal - Rajkot line 28.00 52 41 35 10.87 Mar-11 Work in progress. 7 220 kV LILO to Shapur from Jetpur - Kesod line 3.22 7 7 7 - Jan-10 Work in progress. 8 220 kV LILO at Mota S/S from 2nd Ckt.of Ukai(T)-Vav
line9.60 16 16 16 9.60 Jan-11 Line Work Completed.LILO work
pending.9 220 kV D/C Viramgam-Salejada 118.00 183 183 183 118.00 May-10 Viramgam-Bhat commissioned on
29.05.10 10 220 kV M/C LILO to Bhat from Viramgam-Salejada line 71.25 60 60 60 71.25 May-10 Bhat-Salejada commissioned on
01.06.10 11 220 kV LILO at Kukma s/s from one ckt. Of Shivlakha-
Nanikhakhar line. 34.00 54 40 40 17.74 Jan-11 Work in progress.
12 220kV D/C Tharad - Thavar line 97.09 152 57 5 - Mar-11 Work in progress. 13 220kV D/C Tharad - Deodar line 77.46 124 55 1 - Mar-11 Work in progress. 14 220kV D/C Sankhari - Jangral line 64.00 107 58 28 - Mar-11 Work in progress.
Sr. No. Name of Transmission lineLength in Ckt
Km
Total Location
Present Status as on 01.01.2011
Anticipated completion
TargetRemark Stub
setting Tower
erectedStringing complete
Annexure-14.2(1/2)
A.Transmission Schemes associated with evacuation and system strengthening scheme foown Generating Station.
1 Malwa-TPH-Pithampur 400KV DCDS Line 300 - - - - September/12 In principal forest approval received on 10.12.10
2 Malwa TPH-Chhegaon 400 KV DCDS Line 130 - - - - June/12 Survey Under progress
3 Chhegaon-Julwania 400 KV DCDS Line 230 - - - - September/12 Survey to be taken up4 Satpura TPH-Ashta 400KV DCDS Line 470 - - - - December/12 Forest proposal submitted.5 Malwa TPH-Chhegaon 220KV DCDS Line 130 - - - - June/12 Survey under progress
BTransmission Schemes associated with evacuation and system strengthening scheme foGenerating Station set up by IPP.
1 400KV Bina S/s to BPSCL's Bina TPS 400KV DCDS Line 40 - - - - September/12 Complete work including survey
being carried out by BPSCL
2 Maheshwar-Nimrani 220KV DCDS Line 52.10 90 90 90 52.10 2010-11 Line charged on 12.04.2010
3 Maheshwar-Pithampur 220KV DCDS Line 108.00 195 185 181 89.26 March/11 Work is in progress
C Transmission Schemes associated with PGCIL Substation.
1 Pithampur-Indore (PGCIL) - 400 kV DCDS Line 130 - - - - June/12 Survey Under Progress.
2 LILO of 220 kV Amarkantak-Birsinghpur Line at 400 kV S/S Sukha (PGCIL) 331.80 547 547 547 331.80 December/10
Work completed. Charging arrangement is being done.
3 LILO of one circuit of 220KV Bina-Shivpuri at 765KV S/s PGCIL, Bina 1.66 5 5 3 - March/11 Work is in progress
4 Indore 765 KV (PGCIL) -Indore-II (Jaitpura) 220KV DCDS Line 20 - - - - June/12 Survey to be taken up
Status of Ongoing Transmission Progress in Madhya Pradesh (Dec.-10)
Sr. No. Name of Transmission line Length inCkt Km
Total Location
Present Status as on 31.12.2010 Anticipated completion
TargetRemark
Stub setting
Tower erected
Stringing completed
Annexure-14.2(2/2)
DTransmission Schemes and system strengthening schemes set up through IPTC Route.
NIL
NIL
E Intra-State Transmission Schemes
1 Chhindwara-Betul 220KV DCDS Line 266.60 458 458 458 266.6 2010-11 Line charged on 03.06.2010
2 LILO of 220KV Satna-Bansagar line at Kotar S/s 7.8 16 16 16 7.8 September/10 Line charged on 15.08.2010
3 Satna-Chhatarpur 220 kV DCDS Line 159.541 538 538 538 154.87 December/10 Work is in progress
4 LILO of one circuit of 220 kV Bhopal-Bina for Vidisha S/S 42.32 71 68 62 13.512 March/11 Work is in progress
5 Dewas-Ashta 220 kV DCDS Line 144.00 239 239 239 73.48 March/11 Work is in progress
6 LILO of 220KV Khandwa-Nepanagar Line at Chhegaon S/s 35.03 66 66 65 34.00 December/10 Work almost calculated.
7 Pithampur 400-Pithampur 220KV Interconnector (D/C) 20 - - - - March/12 Survey to be taken up
8 LILO of both CKT. OF Nimrani-Julwania 220KV Line at Julwania 400KV 40 - - - - March/12 Survey to be taken up
9 Ashta 400-Indore-II(Jetpura) 220 kV DCDS line 200 - - - - June/12 Survey Under progress.
10 Ratlam-Daloda 220 KV DCSS Line 60 - - - - March/12 Survey to be taken up
11 LILO of 220 KV DCDS Nagda-Neemuch line at Daloda S/S 16 - - - - March/12 Survey Under progress.
12 LILO of 220 KV Itarsi-Narsinghpur Line at Chichli S/s. 16 - - - - March/12 Survey Under progress.
Sr. No. Name of Transmission lineLength in Ckt
Km
Total Location
Present Status as on 31.12.2010 Anticipated
completion Target
Remark Stub setting
complet
Tower erected
Stringing completed
Annexure-14.3
(A) Transmission Schemes associated with State Generating Stations
1 1x500 MW Korba West TPP Power Evacuation Scheme
1.1 LILO of 400 kV Korba (West)-Bhilai at Raipur DCDS 50.00 69 36 19 1.41 Dec.11 Work under progress.
1.2 400 kV Korba(West)- Khedamara DCDS Ckt. I &II 448.00 648+8G 380 158 - Mar.12 Work under progress.
1.3 220kV DCSS line between Khedamara and 220 kV S/S Bemetara
50.34 157 157 157 50.8 Mar.10 Charged on 18.05.10
2 2x500 MW Marwa TPP Power Evacuation Scheme
2.1 400 DCDS Marwa-Raipur(Raita) 300.00 458 13 - - Jun.12 Work under progress.
2.2 LILOof 400kV K(W)-Khedamara line at Marwa (one ckt.)
120.00 - - - - Mar.12 Tender in Process.
2.3 220kV line Marwa to Banari DCDS 28.26 47 - - - Mar.12 Work started shortly.
(B) Transmission Schemes associated with IPP NIL
(C) Transmission Schemes associated with PGCIL Substation NIL
(D) Transmission Schemes through IPTC route NIL
(E) Intrastate transmission schemes
2.1 220 kV Korba -Bishrampur DCSS 153.00 509 349 305 37.67 Jan'12 Final approval received from AIG(FC) New Delhi
2.2 LILO of 220 kV Bhatapara-Raipur (PGCIL) at Doma 42.38 76 76 76 42.35 Apr.-10 Work completed & Charged on 10.07.10.
2.3 LILO of 200 kV Korba(E)-Siltara at Mopka DCDS 24.28 47 47 47 22.4 Mar.-11 Work under Progress.2.4 220 kV DCDS lines Chhuri-Mopka(Bilaspur) 180.00 270.0 104 52 - Mar'12 Work under Progress.
2.5220 kV line from existing 220 kV S/S Raigarh to Proposed 220 kV S/S Saraipali
200 325 127 59 Mar.-12 Work under Progress.
2.6 220 kV DCSS line Bemetara to Mungeli 38.34 - - - - Apr-11 Tender in Process.
Tower erected
Stringing completed
Status of Ongoing Transmission Progress in Chhattisgarh (Dec.-10)
Sr. No. Name of Transmission lineLength in Ckt
Km
Total Location
Present Status as on 30.11.2010 Anticipated
completion Target
Remark Stub setting
complete
Annexure-14.4(1/3)
(A) Transmission Schemes associated with State Generating StationsI. 400 KV Lines
1 400 kv Dabhol-Nagothane IInd ckt. 137.431 342 342 342 137.431 Aug.10 Line charged on 24.08.10
2 400 KV D/C from 400 KV Bhusaval II - existing 400 KV Khadka.
7.373 26 26 26 7.373 June.10 Line charged on 31.03.10 (Ckt-I). Second Ckt. of line test charged on 31.10.2010.
3 400 KV D/C line from Bhusaval-II to A'bad. (Loc. No. 1 to 270)
96.83 283 282 276 76.940 Jan.11 Work in progress.
4 400 KV D/C line from New Bhusaval - Aurangabad (Loc. No. 271 to Waluj S/S)
89.6 251 251 251 89.400 Jan.11 Work in progress.
5 400 KV S/C line from 400 KV New Khaperkheda - 400 KV Koradi
4.05 13 12 12 3.5 Mar.11
Major ROW problem at Loc. No. 1. An Appeal in Appellate Tribunal, Delhi is filed by MSETCL regarding Order no. 41/2009 received from MERC.
6 400 KV D/C line from Koradi-TPS to Wardha S/S 120 329 208 47 0 April 11 Work in progress.
7 LILO on 400 KV koradi- Chandrapur S/S line for 400KV khaparkheda II S/S.
2.88 8 8 8 2.882 Mar.10 Line charged on 12.10.09
II. 220KV Lines
1 LILO on 220 KV Tarapur-Borivali line for Boisar II S/S 8 15 15 12 4.350 Dec.10Loc. No. 11(Court case). Forest proposal submitted to CCF Thane on 17.01.09. Work held up due to Court case.
2220 KV Koradi II to Butibori II D/C line on M/C tower at 400 KV Koradi II S/S 53 176 64 23 0 Sept.11 Work in progress.
3220KV Parli TPS-Nanded M/C line( Waghala) 90.3 299 272 220 0 Mar.11
Work in progress. ( M/s. Bajaj )
4 220 kV D/C on D/C from 400 kV new Bhusaval - 220 kV Amalner S/S
182.2 326 309 301 72.79 Mar.11 Work in progress. ( M/s. ATSL )
5220 kV line D/C line on M/C tower from 400/220 kV new Bhusaval -II S/S - existing 400 kV Khadka
20 53 39 34 3.154 Mar.11 Work in progress.( Court case for Loc.No.20 ) ( M/s. ATSL )
6 220 kV Paras-Balapur MIDC M/C -M/C 5.61 30 14 10 0 Jan.11 Work in progress. ( M/s. Bajaj )
7 220 kV D/C on D/C by LILO on 220 KV Chandrapur-Warora for 220 KV Wani
47.2 84 84 84 47.2 JUNE.10 Line Charged on 10.06.10
8 220KV M/C- M/C from 400 New K'Kheda to 220KV Existing K'Kheda
3.5 19 15 15 2 SEPT.10 Work in progress. ( M/s.Shirke )
(B) EVACUATION (LINES & S/S) FOR IPPs
Mauda Transmission System1
400 KV D/C Jaigad - New Koyana line. 109.5 151 151 151 109.500 May 10Ckt.I charged on 06.04.10. Ckt.II charged on 07.07.10. Works by JPTL.
2400 KV D/C Jaigad - Karad line. 222 300 273 181 27.11 Mar. 11
Work in progress. Works by JPTL.
Remark Stub setting completed
Status of Ongoing Transmission Progress in Maharashtra (Nov-10)
Sr. No. Name of Transmission lineLength in Ckt Km
Total Location
Present Status as on 30.11.2010Anticipated completion
TargetTower
erectedStringing
completed
Annexure-14.4(2/3)
I. 400KV Lines
1 400KV Chandrapur-II Wardha PGCIL Via Warora D/C 122.8 335 171 113 - Dec.11 Work in progress. ( Quad conductor)( M/s. Cobra-KCL )
2 400KV D/C line from Koradi-II to Wardha S/S(PG) 119.5 329 222 98 - Dec.11 Work in progress.( M/s. Cobra-KCL )
II. 220KV Lines
1 220KV D/c on M/C tower from 400KV PGCIL Talegaon to 220KV Urse 20.54 40 40 40 10.9 MAR.11
2 LILO on Apta-Kalwa & Kandalgaon-Kharghar for Navi Mumbai S/S 8 19 - - - Sep.11 Work awarded to M/S KPTL. ROW problem.
4 220kV D/C line from Pune(PG) to Talegaon 8 12 2 - - MAR.11
5 220kV D/C line from Chincholi(PG) to South Solapur 10.64 18 - - - MAR.11 Check survey partially completed.
6 220kV D/C line from Wardha(PG) to Ghatodi 322 510 - - - MAR.12 Check survey started & completed.
7 LILO on 220kV Bhugaon-Pusad SC at Wardha(PG) 15 - - - - Dec.11
(D) LINES & S/S LINKING WITH PROJECTS- IPTC Routes NIL
(E) SYSTEM STRENGTHENING LINES (INTRA STATE)
I. 220KV Lines
1 LILO of 220 kV Nashik -Kalwa ckt 3&4 ( Padghe - Kalwa) for Airoli 3 9 - - - March.10 Line is charged on 21.03.10 (Ckt -3) & S/s
chared on 22.03.10
2 220KV D/C Nagothane Wadkhal. 30 93 56 44 -Severe ROW problem. The contract is being closed. Estimate is under preparation for balance work for fresh tenderisation.
3 LILO on 220 KV Padghe - Kalwa for Temghar S/S. 1.5 8 7 6 1
Court case at Location No.3 &4 .Work in progress. Work obstructed by local land owners.( M/s. IVRCL )
4 LILO on 220 KV Mulund - Borivali by U/G cable for BhandupGIS S/S. 2 2 - - - Mar. 11 U/G cable is supplied by the agency. Work
for cable trench in progress. (M/s EPIL)
5 220 KV D/C from Phursungi - 400 KV Jejuri S/S. 62 104 81 78 19.82 Mar.11 Work in progress. ( M/s. Bajaj )
Present Status as on 30.11.2010 Anticipated completion
TargetRemark Stub setting
completedSr. No. Name of Transmission line
Length in Ckt
Km
Total Location Tower
erectedStringing
completed
(C.)- EVACUATION (LINES) LINKED WITH PGCIL
Annexure-14.4(3/3)
I. 220KV Lines
6 shifting of 220KV Telco-Bhosari interconnecting bay at chinchwad S/s. 0.5 6 6 5 0.133 Sep.11
The order is short closureat Dn office & estimate for balance work is sanctioned by C.A. This work can be done after completion of Chinchwad phase-II S/S. (M/s Power Engg., Navi Mumbai)
7 220KV D/C line on M/c tower LILO on 220KV Bhosari-Chinchwad D/C on M/C. for 400KV Chakan S/s. 18 31 16 2 Mar.11
New design for 4.5 m narrow base Tower is being given as MIDC has given 5 mtr. Corridor. ( M/s.Shirke )
8 220 kV D/C on D/C LILO on 2nd ckt Kolhapur Phonda line 220 kV Halkarni 19.93 33 33 33 19.93 JUNE.10 Line ready. Work completed
9 220 KV D/C on D/C by LILO on Pusad- Parbhani line for Hingoli. 43.74 75 75 75 43.74 Jan.11 Work in progress.
( M/s. Jyoti )
10 220 kV Chitegaon - Shendra D/C Line. 86.2 154 97 61 14.2 Mar.11 Partly line charged on 14.06.10 for Shendra S/S. Work in Progress.
11 Reorientation of 220 KV Padegaon I & II, Babhaleshwar I&II, Chetegaon I&II and Jalna I&II at Aurangabad 8.84 14 14 14 7.5 Oct.10 Line charged on 27.09.10
12 220 kV D/C line Jeur - Paranda 73.74 94 7 Sep.11 Alternate line LILO on 220kv Usmanabad -Barshi for paranda is given to M/s. Kalpataru
13 220 kV D/C Beed- Patoda line 86.338 151 129 120 3.8 Mar.11 Work in progress. ( M/s. Bajaj )
14 220KV D/C-D/C Jalna - Chikli 150 248 194 175 41 Mar.11 Work in progress. ( M/s. Bajaj )
15220 KV Line from PGCIL to 220 KV Wada S/S Section - 1 to 80
22 90 85 82 15.73 Dec 10
16220 KV Line from PGCIL to 220 KV Wada S/S , Section - 81 to Wada
31 121 88 84 12.19 Dec 10
Work held up due to ROW problems. ROW problems & 3 Nos. Court Cases. Forest proposal yet to be approved.
Sr. No. Name of Transmission lineLength in Ckt Km
Total Location
Present Status as on 30.11.2010 Anticipated completion
TargetRemark Stub setting
completedTower
erectedStringing
completed
Annexure-14.5(1/2)PROGRESS OF TRANSMISSION LINES UNDER CONSTRUCTION BY PGCIL (Dec. 10)
Sr.No.
Name of transmission line Length in Ckt. Km
Total Locations
Anticipated Completion
REMARKS
Stub Setting completed
Tower erected
Stringing completed
Target
(Nos.) (Nos) (Ckm)
765 kV & 400 kV Lines 1 Western Region Stregthening Scheme-II1.1 SET-A: For absorbing import in eastern¢ral part of WR1.1.1 765 kV 2nd S/C Seoni(PG)-Wardha(PG) line (initially to be operated at
400kV)261 704 590 398 44 Jun-11
1.1.2 400 kV D/C Wardha (PG)-Parli (PG)(Quad.) 674 897 879 820 490 Mar-111.1.3 400 kV D/C Raipur(PG)-Wardha(PG) line 741 989 953 884 480 Jun-11 Work affected due to ROW problem in line. &
delayed forest clearence.1.1.4 400 kV D/C Bhadravati (PG)-Parli(PG) line 768 1032 1031 995 552 Mar-11 Work affected due to ROW problem in line.
Forest strech of 5-8 hectare. 1st stage forest clearence received.
1.1.5 400 kV D/C Parli(MSEB)-Parli(PG) line 10 15 15 13 2 Mar-11 Stringing commenced from Dec'101.2 SET-B: For Regional strengthening in Southern Maharashtra
Implemented through IPTC route by Western Region Transmission (Mah) Pvt.Ltd. Progress indicated saperately
1.3 SET-C: For Regional strengthening in Gujarat Implemented through IPTC route by Western Region Transmission (Guj) Pvt.Ltd. Progress indicated saperately
1.4 SET-D: For Regional strengthening in Northern Madhaya Pradesh
1.4.1 Bina(PG)-Gwalior(PG) 765kV 2nd S/C line (initially to be operated at 400kV)
233 624 624 624 233 Feb-10 Line commissioned on 27.02.10
1.4.2 400 kV D/C Korba(NTPC)-Birsighpur(MPGENCO) line 453 644 553 522 230 Mar-11 Forest strech of 157 hectare.1st stage forest clearence delayed.
1.4.3 400 kV D/C Birsighpur(MPGENCO)-Damoh(PG) line 457 637 637 637 457 Jan-11 Line alongwith associated bays completed & ready for charging.
1.4.4 400 kV D/C Damoh(PG)-Bhopal(MPSEB) 432 577 577 577 432 Mar-10 Line Test charged & commissioned1.5 Trans. Sy. Associated with Gandhar-II (GBPP) *33 months from investment approval or from
date of tying up of FSA by NTPC whichever is later.
2 Western Region Stregthening Scheme-V2.1 400 kV Vapi(PG)-Navi Mumbai D/C line 258 385 105 58 - Jun-11 Severe Row problem being faced in
Maharashtra & DNH on allmost all locations. Compltion likely to be delayed.
2.2 220 kV Vapi-Khadoli (UT of DNH) D/C line 56 103 103 103 56 Sep-10 Line test charged on 15.09.102.3 LILO of Lonikhand(MSEB)-Kalwa(MSEB) 400 kV S/C line at Navi
Mumbai 10 27 1 - - Jun-11 Engg. & survey in progress. Severe ROW
problem in Maharashtra on allmost all locations.
PRESENT STATUS
Annexure-14.5(2/2)Sr.No.
Name of transmission line Length in Ckt. Km
Total Locations
(Nos)
Anticipated Completion
REMARKS
Stub Setting completed
Tower erected
Stringing completed
Target
(Nos.) (Nos) (Ckm)3 Western Region Stregthening Scheme-VI3.1 400 kV D/C Dehgam - Pirana line 94 139 139 139 94.00 Dec-10 Line test charged in Dec'104 Western Region Stregthening Scheme-IX4.1 LILO of 400 kV D/C Bina-Nagda line at Sujalpur 44 61 54 47 Jan-00 Mar-11 Stringing commenced from Dec'105 Western Region Stregthening Scheme-X5.1 LILO of 765 kV S/C Sipat-Seoni line at WR Pooling station near Sipat 14 Feb. 12 Tendering under progress.
6 Western Region Stregthening Scheme-XI6.1 LILO of 765 kV S/C 2nd Sipat-Seoni line at WR Pooling station near
Sipat at Bilaspur (Pooling Stn.)24 Feb. 12 Tendering under progress.
7 Transmission System associated with Korba-III7.1 400 kV D/C Korba STPS-Raipur line 428 596 491 350 70.00 Jun. 11
8 Mauda Transmission System 8.1 400kV D/C Mauda STPS - Wardha line (Quad) 250 342 125 12 Oct. 12 Tower erection commenced from Dec'108.2 400kV D/C Mauda STPS - Khaperkheda line (Quad) 120 Oct. 12 Tendering under process9 Transmission System Associated with Mundra UMPP9.1 Part-A Transmission System of Mundra UMPP9.1.1 400 kV D/C Mundra-Limbdi line (Tripal snowbard) 626 838 356 235 52.00 Dec. 119.1.2 400 kV D/C Mundra-Bachchau- Ranchodpur line (Tripal snowbard) 764 1040 916 799 321.00 Mar' 11 Efforts being made to prepone the line matching
with Generating Projects.9.1.3 400 kV D/C Mundra-Bachchau- Jetpur line (Tripal snowbard) 666 900 404 145 Mar. 129.2 Part-B Regional System Strengthening in WR for Mundra UMPP9.2.1 400 kV D/C Gandhar-Navsari line 212 299 214 146 8.00 Oct. 12 Stringing commenced from Dec'109.2.2 400 kV D/C Navsari- Boisor line 408 1020 98 48 Oct. 12 01 out of 02 pkgs awarded. Line is now
proposed to be terminated at Boiser S/stn in place of Mumbai new loc.
9.2.3 400 kV D/C Wardha- Aurangabad line 700 980 66 Oct-12 Foundation commenced from Nov'10. 1200 kV towers.
9.2.4 400 kV D/C Aurangabad - Aurangabad (MSETCL)line 60 Oct. 12 Award placed in July'10. Engg. In process.9.2.5 LILO of both Ckt of Kawas-Navsari 220 kV D/c at Navsari 68 130 16 Oct. 12
10 Transmission System Associated with Sasan UMPP10.1 Part-A Transmission System of Sasan UMPP10.1.1 765 kV S/C Sasan-Satna line-I 246 689 581 410 45.00 Dec. 1210.1.2 765 kV S/C Sasan-Satna line-II 243 676 293 95 Dec. 1210.1.3 765 kV S/C Satna-Bina line-I 274 735 687 485 84.00 Dec. 1210.1.4 765 kV S/C Satna-Bina line-II 276 737 560 310 60.00 Dec. 1210.1.5 765 kV S/C Sasaram-Fatehpur line-II 356 950 82 Dec. 1210.1.6 765 kV S/C Fatehpur-Agra line 303 889 99 20 Dec. 1210.1.7 400 kV D/C Bina-Bina (MPPTCL) line 10 25 Dec. 12 Engg. in progress.10.1.8 LILO of both Ckt Vindhyachal-Jablapur 400 kV D/c at Sasan 13 26 6 Dec. 1210.2 Part-B Regional System Strengthening in WR for Sasan UMPP10.2.1 765 kV S/C Bina-Indore line 311 827 600 320 62.00 Dec. 1210.2.2 400 kV D/C Indore-Indore(MPPTCL) (quad) line 99 140 128 92 Dec. 1211 Inter-regional lines11.1 East-West Transmission corridor strengthening scheme11.1.1 400 kV D/C Ranchi - Rourkela 290 401 401 401 290 Nov-10 Line commissioned on 30.11.10
11.1.2 400 kV D/C Rourkela - Raigarh 420 589 579 562 280 Feb-11 1st stage forest clearence accorded in Oct.09(100 kms. Stretch involved). Pending final clearence MOEF has given permission to work in the forest stretch. All efforts being made to complete the line at the earliest. Critical.
11.1.3 400 kV D/C Raigarh - Raipur 440 584 584 584 440 Sep-10 Line commissioned in Sep'10
PRESENT STATUS
Annexure-14.6
PROGRESS OF TRANSMISSION LINES UNDER CONSTRUCTION TROUGH IPTC ROUTE (Dec. 2010)
Sr.No.
Name of transmission line Length in Ckt. Km
Total Locations
(Nos)
Anticipated Completion
REMARKS
Stub Setting completed
Tower erected
Stringing completed
Target
(Nos.) (Nos) (Ckm)WRSSS-II (Set-B)
2.2 SET-B: For Regional strengthening in southern Maharashtra implemented through IPTC route by Western Region Transmission (Mah) Pvt.Ltd.
2.2.1 400 kV D/C Parli(PG)-Pune 646 886 509 188 6 Sep-11 Forest NOC obtained. For PTCC joint inspection completed.
2.2.2 400 kV D/C Pune(PG)-Aurangabad(MSEB) 472 623 349 82 - Apr-11 All cases submitted clearance received. GIB new alignment from 91/5 to 104/0 is completed.For PTCC joint inspection completed.
2.2.3 400 kV D/C Parli(PG)-Solapur 272 355 171 88 - May-11 Forest clearence received.Power line Xing proposal submitted for all cases.
2.2.4 400 kV D/C Solapur(PG)-Kolhapur(MSEB) 438 575 254 69 - Sep-11 For forest clearence all cases submitted & clearence received.For PTCC final report sent to Director PTCC. Power line Xing proposal submitted for all cases.
2.2.5 LILO of Lonikhand(MSEB)-Kalwa(MSEB)400 kV D/C at Pune(PG) 2.4 8 6 2 - Jan-11 Forest clearence not required. PTCC clearance received.
2.2.6 LILO of Solapur(MSEB)-Karad(MSEB)400 kV D/C at Pandharpur/Solapur(PG)
232 298 298 298 115 Nov-10 Line ready for commissing
WRSSS-II (Set-C)2.3 SET-C: For Regional strengthening in Gujarat implemented through
IPTC route by Western Region Transmission (Guj) Pvt.Ltd.
2.3.1 400 kV D/C Rajgarh(PG)-Karamsad(GEB) 468 652 561 354 - May-11 Forest proposal for Gujarat portion submitted to DFO. Tree enumeration permission granted for Gujarat portion.Forest proposal submitted for Jhabua range of MP portion. Dhar range inspection completed. Processed from Jhabua DFO office.
2.3.2 400 kV D/C Limbdi(Chorania)(GEB)-Ranchodpura(Vadavi)(GEB) 206 270 268 268 87 Jan-11 Forest clearence not required. For PTCC proposal submitted. Processed from Mumbai. File sent to Delhi.
2.3.3 400 kV D/C Ranchodpura(Vadavi)(GEB)-Zerda(Kansari)(GEB) 280 375 366 306 29 Jan-11 For social Forest Proposal submitted, Inspection under progress. For PTCC proposal submitted. Processed from Mumbai. File sent to Delhi.
PRESENT STATUS
Annexure-15 (1/2)piScama xao~ maoM 11 vaIM yaaojanaa mao inamaa-MNaaiQana na[- ]%padk yauinaTaoM kI p`gait GENERATION SCHEMES UNDER CONSTRUCTION DURING 11th PLAN IN WESTERN REGION
Sr. No. Name of the Power Projects Unit No. Capacity (MW)
Schedule Date of Commissioning
A GUJARATGeneration Schemes included in 11th Plan
1 Kutch Lignite TPS 4 75 Commissioned on 01.10.20092 Sugen CCPP (Torrent Power Gen. Ltd.) Block -1 382.5 Commissioned on 20.11.2008
Block-2 382.5 commissioned on 07.05.09Block-3 382.5 commissioned on 08.06.09
3 Surat Lignite expansion- GIPCL 3 125 commissioned on 12.04.104 125 commissioned on 23.04.10
4 Utran GPP GT+ST 374 Commissioned on 10.10.20095 Sikka TPP Extn. 3 250 Jan. 2010
4 250 May. 20106 Ukkai TPS Extn. 6 490 Feb. 20117 Pipavav CCPP- GPCL & GSPC joint venture Block-1 350 Sep. 2010
Block-2 350 Mar. 20118 Mundra TPP Ph-1 (Adani Power Ltd.) 1 330 Commissioned on 04.08.2009
2 330 Commissioned on 17.03.109 Mundra TPP Ph-2 (Adani Power Ltd.) 3 330 Commissioned on 02.08.10
4 330 Commissioned on 20.12.1010 Mundra Ultra Mega TPP (Tata Power Ltd.) 1 800 Sep. 2011
2 800 Mar. 201211 Hazira CCPP Expansion GSEG GT+ST 350 Sep. 2010
Other Projects1 Gujarat Lignite-NLC & GPCL joint venture Stage-I 1500 2011-12
Stage-II 500 2012-132 Dhuvaran CCPP GSECL Stage-III 360 Mar. 20103 Pipavav TPP- Torrent Power 1000 2011-124 Bhavnagar Lignite TPP-joint venture 500 Apr. 20115 Mundra STPP (Adani Power Ltd.) 1 660 Commissioned on 26.12.2010
2 660 June. 2011
B MADHYA PRADESHGeneration Schemes included in 11th Plan
1 Amarkantak TPS 5 210 Commissioned on 15.06.20082 500 Apr. 2011
2 Satpura TPS Extn. 10 250 Nov. 201011 250 Mar.2011
Other Projects1 Maheshwar HEP - 400 2010-112 Malwa TPP 1 500 Dec. 2010
Annexure-15 (2/2)
Sr. No. Name of the Power Projects Unit No. Capacity (MW)
Schedule Date of Commissioning
C CHHATTISGARHGeneration Schemes included in 11th Plan
1 Jindal PL 1 250 Commissioned on 08.12.072 250 Commissioned on 16.04.083 250 Commissioned on 15.06.084 250 Commissioned on 17.06.08
2 LANCO Amarkantak PL 1 300 Commissioned on 04.06.092 300 Commissioned on 25.03.10
3 Marwa TPP 1 500 Sept. 20122 500 Nov. 2012
4 Korba West-III TPP 1 500 Jun. 2012Other Projects
1 Bhaiyathan TPP Phase-I 1 500 Dec. 20122 500 Aug. 2013
2 IFFCO 1 660 Aug. 2012660 Dec. 2012
D MAHARASHTRAGeneration Schemes included in 11th Plan
1 New Parli TPS Extn. 2 250 Commissioned on 10.02.20102 Paras TPS Extn. 2 250 Commissioned on 27.03.103 Khaperkheda TPP Extn. 1 500 Mar. 20104 Bhusawal Extn. TPP 1 500 May. 2010
2 500 Sep. 20105 Trombay TPS Extn. (Tata Power Co.) 8 250 Commissioned on 14.01.20096 Ghatghar HPS (Hydro) 1 125 Commissioned on 13.05.08
2 125 Commissioned on 01.07.087 JSW Ratnagiri TPP (JSW Energy (Ratnagiri) Ltd.) 1 300 Commissioned on 24.08.10
2 300 Commissioned on 09.12.103 300 Dec. 20104 300 Mar. 2011
Other Projects1 Koradi TPS Extn. 1 800 Oct. 20122 Dhopawe TPP 1 800 Nov. 2011
2 800 May 20123 Uran CCPP Block-1 700 Feb. 2010
Block-2 340 May. 20104 Koradi TPS Extn. (Replacemet of 4 x 120) 1 800 Apr 20125 Parli TPS (Replacement of 2x30) 1 250 May. 20106 Paras TPS (Replacement of 1x62.5) 1 250 May. 20107 Bhusawal TPS (Replacement of 1x62.5) 1 250 May. 20108 Chandrapur TPS Extn. 1 500 Dec. 2011
2 500 May. 20129 Wardha Warora TPP(M/S Wardha Power Co. Ltd.) 1 135 Commissioned on 05.06.10
10 Wardha Warora TPP(M/S Wardha Power Co. Ltd.) 2 135 Commissioned on 10.10.10
E CENTRAL SECTOR - NTPCGeneration Schemes included in 11th Plan
1 Sipat-II TPP 5 500 Commissioned on 27.12.08
2 Sipat-I TPP 1 660 Nov. 20102 660 May. 20113 660 Nov. 2011
3 Bhilai TPP (Joint venture with SAIL) 1 250 Commissioned on 22.04.09
2 250 Commissioned on 12.07.09
4 Korba STPS-III 7 500 Commissioned on 26.12.10
5 Mauda TPP 1 500 2011-122 500 2012-13
Sr.No. PARTICULARS Nov-10 Dec-10 Jan-111 MAXIMUM FREQUENCY (Hz)
1.1 Integrated over an hour 50.52 50.42
1.2 Instantaneous 50.73 50.68
2 MINIMUM FREQUENCY (Hz)
2.1 Integrated over an hour 49.64 49.49
2.2 Instantaneous 49.12 48.94
3 AVERAGE FREQUENCY (Hz) 50.00 49.92
4.1 48.6 Hz 0 0
4.2 48.8 Hz 0 0
4.3 51.0 Hz 0 0
5.1 Above 50.2 Hz 12.74 9.04
5.2 Above 50.3 Hz 4.07 3.32
5.3 Between 50.2 Hz & 49.5 Hz 86.77 88.94
5.4 Between 50.2 Hz & 49.2 Hz 87.25 90.88
5.5 Below 49.2 Hz 0.01 0.08
5.6 Below 49.5 Hz 0.49 2.02
5.7 Between 50.3 Hz & 48.5 Hz 95.93 96.68
Annexure-18.1(a)FREQUENCY PARTICULARS OF WESTERN REGION FOR THE PERIOD
NOVEMBER 2010 TO JANUARY 2011
5PERCENTAGE TIME WHEN FREQUENCY WAS
4
NUMBER OF TIMES FREQUENCY TOUCHED
Nov-10 Dec-10 Jan-11 Nov-10 Dec-10 Jan-11 Nov-10 Dec-10 Jan-11 Nov-10 Dec-10 Jan-11Availability (MW) 2429 2651 9751 9518 7866 7414 14918 15753Unrestricted demand (MW) 2439 2672 10730 10373 8029 8928 18378 19488Deficit(-)/Surplus(+) in MW -10 -21 0 -979 -855 0 -163 -1514 0 -3460 -3735 0Deficit(-)/Surplus(+) in % -0.41 -0.79 #DIV/0! -9.12 -8.24 #DIV/0! -2.03 -16.96 #DIV/0! -18.83 -19.17 #DIV/0!
Nov-09 Dec-09 Jan-10 Nov-09 Dec-09 Jan-10 Nov-09 Dec-09 Jan-10 Nov-09 Dec-09 Jan-10Availability (MW) 2557 2559 2612 9264 9025 8997 6153 6198 6334 14456 14212 14071Unrestricted demand (MW) 2643 2610 2673 10156 10032 9723 7098 7217 7663 19095 18499 18535Deficit(-)/Surplus(+) in MW -86 -51 -61 -892 -1007 -726 -945 -1019 -1329 -4639 -4287 -4464Deficit(-)/Surplus(+) in % -3.25 -1.95 -2.28 -8.78 -10.04 -7.47 -13.31 -14.12 -17.34 -24.29 -23.17 -24.08
Nov-10 Dec-10 Jan-11 Nov-10 Dec-10 Jan-11 Nov-10 Dec-10 Jan-11 Nov-10 Dec-10 Jan-11Availability (MW) 443 445 253 249 520 520 33643 34342Unrestricted demand (MW) 473 481 278 274 520 520 39589 41252Deficit(-)/Surplus(+) in MW -30 -36 0 -25 -25 0 0 0 0 -5946 -6910 0Deficit(-)/Surplus(+) in % -6.34 -7.48 #DIV/0! -8.99 -9.12 #DIV/0! 0.00 0.00 #DIV/0! -15.02 -16.75 #DIV/0!
Nov-09 Dec-09 Jan-10 Nov-09 Dec-09 Jan-10 Nov-09 Dec-09 Jan-10 Nov-09 Dec-09 Jan-10Availability (MW) 422 444 453 218 237 232 458 464 494 32290 32277 31842Unrestricted demand (MW) 469 467 453 230 249 232 458 464 529 39208 38755 38504Deficit(-)/Surplus(+) in MW -47 -23 0 -12 -12 0 0 0 -35 -6918 -6478 -6662Deficit(-)/Surplus(+) in % -10.02 -4.93 0.00 -5.22 -4.82 0.00 0.00 0.00 -6.62 -17.64 -16.72 -17.30
Details
Details
Goa Daman & Diu
Annexure -18.1(b)(1/2) POWER SUPPLY POSITION IN WR FOR PERIOD FROM NOVEMBER 2010 TO JANUARY 2011 (IN MW)
POWER SUPPLY POSITION IN WR FOR PERIOD FROM NOVEMBER 2010 TO JANUARY 2011 (IN MW)
POWER SUPPLY POSITION IN WR FOR PERIOD FROM NOVEMBER 2009 TO JANUARY 2010 (IN MW)
Details Chhatisgarh Gujarat
POWER SUPPLY POSITION IN WR FOR PERIOD FROM NOVEMBER 2009 TO JANUARY 2010 (IN MW)
Chhatisgarh Gujarat Madhya Pradesh MaharashtraDetails
Maharashtra
Goa Daman & Diu Dadra & Nagar Haveli Western Region
Madhya Pradesh
Dadra & Nagar Haveli Western Region
Annexure -18.1(b)(2/2)
Nov-10 Dec-10 Jan-11 Nov-10 Dec-10 Jan-11 Nov-10 Dec-10 Jan-11 Nov-10 Dec-10 Jan-11Availability (MUs) 806 875 5299 6073 3564 4154 8871 9580Unrestricted Requirement (MUs) 811 879 5657 6611 4584 5333 9744 11241Deficit(-)/Surplus(+) in MUs -5 -4 0 -358 -538 0 -1020 -1179 0 -873 -1661 0Deficit(-)/Surplus(+) in % -0.62 -0.46 #DIV/0! -6.33 -8.14 #DIV/0! -22.25 -22.10 #DIV/0! -8.96 -14.78 #DIV/0!
Nov-09 Dec-09 Jan-10 Nov-09 Dec-09 Jan-10 Nov-09 Dec-09 Jan-10 Nov-09 Dec-09 Jan-10Availability (MUs) 590 685 838 5989 6009 5793 3199 3666 3733 8351 9071 9109Unrestricted Requirement (MUs) 600 693 852 6494 6555 6334 3669 4446 4692 9948 11371 11392Deficit(-)/Surplus(+) : in MUs -10 -8 -14 -505 -546 -541 -470 -780 -959 -1597 -2300 -2283Deficit(-)/Surplus(+) : in % -1.67 -1.15 -1.64 -7.78 -8.33 -8.54 -12.81 -17.54 -20.44 -16.05 -20.23 -20.04
Details Nov-10 Dec-10 Jan-11 Nov-10 Dec-10 Jan-11 Nov-10 Dec-10 Jan-11 Nov-10 Dec-10 Jan-11
Availability (MUs) 253.48 258.94 160.23 171.46 363.62 380.44 19318 21494Unrestricted Requirement (MUs) 256.16 262.00 178.23 190.06 363.62 380.44 21594 24897Deficit(-)/Surplus(+) : in MUs -2.68 -3.06 0.00 -18.00 -18.60 0.00 0.00 0.00 0.00 -2276 -3403 0Deficit(-)/Surplus(+) : in % -1.05 -1.17 #DIV/0! -10.10 -9.79 #DIV/0! 0.00 0.00 #DIV/0! -10.54 -13.67 #DIV/0!
Nov-09 Dec-09 Jan-10 Nov-09 Dec-09 Jan-10 Nov-09 Dec-09 Jan-10 Nov-09 Dec-09 Jan-10Availability (MUs) 248.73 278.36 280.08 146.71 159.96 158.43 333.92 343.17 350.93 18858 20213 20264Unrestricted demand (MUs) 251.85 280.53 280.08 155.35 168.60 158.43 333.92 343.17 350.93 21452 23858 24059Deficit(-)/Surplus(+) : in MUs -3.12 -2.17 0.00 -8.64 -8.64 0.00 0.00 0.00 0.00 -2594 -3645 -3795Deficit(-)/Surplus(+) : in % -1.24 -0.77 0.00 -5.56 -5.12 0.00 0.00 0.00 0.00 -12.09 -15.28 -15.77
Details Chhatisgarh Gujarat
Details
Details
Chhatisgarh Gujarat Madhya Pradesh Maharashtra
Western RegionGoa Daman & Diu Dadra & Nagar Haveli
Dadra & Nagar Haveli Western Region
POWER SUPPLY POSITION IN WR FOR PERIOD FROM NOVEMBER 2010 TO JANUARY 2011 (IN MUs)
POWER SUPPLY POSITION IN WR FOR PERIOD FROM NOVEMBER 2009 TO JANUARY 2010 (IN MUs)
POWER SUPPLY POSITION IN WR FOR PERIOD FROM NOVEMBER 2010 TO JANUARY 2011 (IN MUs)
POWER SUPPLY POSITION IN WR FOR PERIOD FROM NOVEMBER 2009 TO JANUARY 2010 (IN MUs)Goa Daman & Diu
Madhya Pradesh Maharashtra
400 kV S/SMonth Max Min Max Min Max Min Max Min Max Min Max Min Max Min
Nov-10 425 385 431 390 435 397 434 394 429 405 429 406 425 397
Dec-10 421 384 428 386 430 397 434 396 427 406 430 408 427 399
Jan-11
400 kV S/SMonth Max Min Max Min Max Min Max Min Max Min Max Min Max Min
Nov-10 429 372 432 392 432 384 431 390 434 390 781 725 795 739
Dec-10 424 374 427 372 431 380 430 390 431 393 784 742 798 750
Jan-11
Annexure-18.2
BhilaiIndore Itarsi Karad Dhule
Voltages at the important 400 and 765 kV substations during the period NOVEMBER 2010 to JANUARY 2011
Asoj Kasor
Sipat (765 kV) Seoni (765 kV)Jetpur Bina Gwalior Nagda Khandwa
No. of Occasions
Max Load Relief at 48.8 Hz
No. of Occasions
Max Load Relief at 48.8 Hz
No. of Occasions
Max Load Relief at 48.8 Hz
No. of Occasions
Max Load Relief at 48.8 Hz
1 01-Nov-10 0 0 0 0 0 0 0 0
2 02-Nov-10 0 0 0 0 0 0 0 03 03-Nov-10 0 0 0 0 0 0 0 04 04-Nov-10 0 0 0 0 0 0 0 05 05-Nov-10 0 0 0 0 0 0 0 06 06-Nov-10 0 0 0 0 0 0 0 07 07-Nov-10 0 0 0 0 0 0 0 08 08-Nov-10 0 0 0 0 0 0 0 09 09-Nov-10 0 0 0 0 0 0 0 0
10 10-Nov-10 0 0 0 0 0 0 0 011 11-Nov-10 0 0 0 0 0 0 0 012 12-Nov-10 0 0 0 0 0 0 0 013 13-Nov-10 0 0 0 0 0 0 0 014 14-Nov-10 0 0 0 0 0 0 0 015 15-Nov-10 0 0 0 0 0 0 0 016 16-Nov-10 0 0 0 0 0 0 0 017 17-Nov-10 0 0 0 0 0 0 0 018 18-Nov-10 0 0 0 0 0 0 0 019 19-Nov-10 0 0 0 0 0 0 0 020 20-Nov-10 0 0 0 0 0 0 0 021 21-Nov-10 0 0 0 0 0 0 0 022 22-Nov-10 0 0 0 0 0 0 0 023 23-Nov-10 0 0 0 0 0 0 0 024 24-Nov-10 0 0 0 0 0 0 0 025 25-Nov-10 0 0 0 0 0 0 0 026 26-Nov-10 0 0 0 0 0 0 0 027 27-Nov-10 0 0 0 0 0 0 0 028 28-Nov-10 0 0 0 0 0 0 0 029 29-Nov-10 0 0 0 0 0 0 0 030 30-Nov-10 0 0 0 0 0 0 0 0
220 38 152 550
220 38 152 550
( Compiled from the data received from the constituents)
ANNEX -18.3 (1/2)Under Frequency Operation in various Constituent System of Western Region during the month November 2010
Sl. No Date Gujarat Chhattisgarh Madhya Pradesh Maharashtra
Recommonded Load relief at 48.6 Hz
Recommonded Load relief at 48.8 Hz
No. of Occasions
Max Load Relief at 48.8 Hz
No. of Occasions
Max Load Relief at 48.8 Hz
No. of Occasions Max Load Relief at 48.8 Hz
No. of Occasions
Max Load Relief at 48.8 Hz
1 01-Dec-10 0 0 0 0 0 0 0 02 02-Dec-10 0 0 0 0 0 0 0 03 03-Dec-10 0 0 0 0 0 0 0 04 04-Dec-10 0 0 0 0 0 0 0 05 05-Dec-10 0 0 0 0 0 0 0 06 06-Dec-10 0 0 0 0 0 0 0 07 07-Dec-10 0 0 0 0 0 0 0 08 08-Dec-10 0 0 0 0 0 0 0 09 09-Dec-10 0 0 0 0 0 0 0 0
10 10-Dec-10 0 0 0 0 0 0 0 011 11-Dec-10 0 0 0 0 0 0 0 012 12-Dec-10 0 0 0 0 0 0 0 013 13-Dec-10 0 0 0 0 0 0 0 014 14-Dec-10 0 0 0 0 0 0 0 015 15-Dec-10 0 0 0 0 0 0 0 016 16-Dec-10 0 0 0 0 0 0 0 017 17-Dec-10 0 0 0 0 0 0 0 018 18-Dec-10 0 0 0 0 0 0 0 019 19-Dec-10 0 0 0 0 0 0 0 020 20-Dec-10 0 0 0 0 0 0 0 021 21-Dec-10 0 0 0 0 0 0 0 022 22-Dec-10 0 0 0 0 0 0 0 023 23-Dec-10 0 0 0 0 0 0 0 024 24-Dec-10 0 0 0 0 0 0 0 025 25-Dec-10 0 0 0 0 0 0 0 026 26-Dec-10 0 0 0 0 0 0 0 027 27-Dec-10 0 0 0 0 0 0 0 028 28-Dec-10 0 0 0 0 0 0 0 029 29-Dec-10 0 0 0 0 0 0 0 030 30-Dec-10 0 0 0 0 0 0 0 031 31-Dec-10 0 0 0 0 0 0 0 0
220 38 152 550
220 38 152 550Recommonded
Load relief at 48.6
Maharashtra
Recommonded Load relief at 48.8
Sl. No Date Gujarat Chhattisgarh Madhya Pradesh
Under Frequency Operation in various Constituent System of Western Region during the month December 2010( Compiled from the data received from the constituents)
ANNEX -18.3 (2/2)
Annexure-20
Details Jan-11 Feb-11 Mar-11 Jan-11 Feb-11 Mar-11 Jan-11 Feb-11 Mar-11 Jan-11 Feb-11 Mar-11
Availability (MW) 2578 2492 2722 9555 10044 10186 6685 6858 6560 14829 15116 15529Unrestricted demand (MW) 2987 3049 3218 9734 9849 10235 8239 7955 7235 19457 19626 19975
Deficit(-)/Surplus(+)(i) MW -409 -557 -495 -179 195 -49 -1554 -1097 -675 -4628 -4510 -4447
( ii) % -13.69 -18.26 -15.40 -1.84 1.98 -0.48 -18.86 -13.79 -9.33 -23.79 -22.98 -22.26
Details Jan-11 Feb-11 Mar-11 Jan-11 Feb-11 Mar-11 Jan-11 Feb-11 Mar-11 Jan-11 Feb-11 Mar-11
Availability (MW) 458 465 468 217 224 225 508 550 554 37309 38229 38724Unrestricted demand (MW) 484 482 492 348 370 392 560 566 568 40201 40287 40496
Deficit(-)/Surplus(+)(i) MW -26 -17 -24 -131 -146 -167 -52 -16 -14 -2891 -2058 -1772
(ii) % -5.44 -3.62 -4.82 -37.69 -39.51 -42.72 -9.29 -2.76 -2.50 -7.19 -5.11 -4.38
Details Jan-11 Feb-11 Mar-11 Jan-11 Feb-11 Mar-11 Jan-11 Feb-11 Mar-11 Jan-11 Feb-11 Mar-11
Availability (MUs) 1676 1572 1795 6615 6175 7029 4241 3742 4028 9758 9166 10327Unrestricted Requirement (MUs) 1541 1752 4943 6406 5872 6861 5062 4219 4175 10852 10163 11659
Deficit(-)/Surplus(+)(i) MUs 135 -180 -3149 209 302 167 -821 -477 -148 -1094 -997 -1332
(ii) % 8.75 -10.26 -63.70 3.26 5.15 2.44 -16.22 -11.31 -3.54 -10.08 -9.81 -11.43
Details Jan-11 Feb-11 Mar-11 Jan-11 Feb-11 Mar-11 Jan-11 Feb-11 Mar-11 Jan-11 Feb-11 Mar-11
Availability (MUs) 271 254 278 130 122 136 335 325 368 23952 22220 24886Unrestricted Requirement (MUs) 254 246 272 219 211 247 346 330 346 24790 22582 25313
Deficit(-)/Surplus(+)(i) MUs 17 8 6 -89 -89 -111 -11 -5 22 -838 -362 -426
(ii) % 6.60 3.11 2.35 -40.68 -42.29 -44.87 -3.09 -1.48 6.43 -3.38 -1.60 -1.68
ANTICIPATED POWER SCENARIO IN WR FOR PERIOD FROM JANUARY 2011 TO MARCH 2011 (IN MW)
MaharashtraChhatisgarh Gujarat Madhya Pradesh
Goa Daman & Diu Dadra & nagar Haveli Western Region
ANTICIPATED POWER SCENARIO IN WR FOR PERIOD FROM JANUARY 2011 TO MARCH 2011 (IN MUs)
Chhatisgarh Gujarat Madhya Pradesh Maharashtra
Western RegionGoa Daman & Diu Dadra & nagar Haveli