Date post: | 28-Nov-2014 |
Category: |
Business |
Upload: | paul-oconnor |
View: | 454 times |
Download: | 1 times |
Major projects in Victoria: challenges, issues and where to from here?
Paul O’Connor
Sessional Lecturer & Doctoral CandidateSchool of Property, Construction and Project Management
Paul O'Connor 2RMIT University © 2013
Scope of this presentation
1. State of play for major projects in Victoria
2. Recent reviews and enquiries - how can major projects be better procured and implemented?
3. The alphabet soup of procurement options for major public sector infrastructure: traditional, alliance or PPP?
4. Addressing infrastructure project challenges and trends in times of fiscal austerity
5. PPPs: key drivers in Victoria and the story so far
6. Case studies - success stories and some areas for improvement…
Paul O'Connor 3
State of play for major projects in Victoria
Perceptions:
•Projects have been stalled through inaction
•Not enough focus on economic productivity
•Lack of holistic infrastructure vision
•Too much political focus on “debt” as BAD
• ‘Penny pinching’ at expense of future capacity
•Rising construction costs due to mining boom and resurgent union militancy
RMIT University © 2013
Paul O'Connor 4
Recent reviews and enquiries
Public Accounts and Estimates Committee inquiry into significant infrastructure projects (Dec 2012) found a number of key issues:
•Optimism bias (underestimating of costs and over estimating of benefits) was too prevalent
•Poor scoping & planning work = poor delivery
•Lack of suitable and available skillsets in PS
•Role confusion as ‘owner’, ‘investor’ & ‘deliverer’
•But more central scrutiny is positive development
RMIT University © 2013
Paul O'Connor 5
Context: infrastructure & development (1)
•Wide range of public infrastructure demand is forecast for many sectors:–Transport–Education–Health–Government accommodation/facilities–Utilities (water, sewerage, telecoms, power)
• Infrastructure ‘deficits’ are making larger calls upon scarce (shrinking?) government capital
RMIT University © 2013
Paul O'Connor 6
Context: infrastructure & development (2)
•Recurrent demands also increasing to fund essential citizen services
•Large and lumpy disbursements
•Debt/surplus funding raises fiscal issues:–Sovereign credit ratings linked to debt–‘Lazy’ balance sheets/inefficient allocations–Inter-generational equity of debt liabilities–Ongoing operations and maintenance liability plus depreciation and replacement funding
RMIT University © 2013
Paul O'Connor 7
Alphabet soup of procurement options
•Many options to procure infrastructure available:–Build to design (B)–Design and build (D and B)–Managing contractor (D and B)–Alliance (D and B)–JV (D, B and O) (and maybe F)–PPP/PFI (D,B, F, M) (and maybe O)
•Analysis of the profile of the infrastructure should drive the procurement strategy
RMIT University © 2013
Paul O'Connor 8
Funding projects in austere times
• Just as water always finds its course, a ‘good’ project will always find a sponsor and funding
•Austerity is a chance to get back to basics:–More work on cost-benefit analysis not just back of the envelope calculations and spin
–More scoping, planning and community engagement to de-risk and build buy-in
–More market engagement to find deliverer–More appropriate risk and cost sharing
RMIT University © 2013
Paul O'Connor 9
Benefits of a long term funding modelSmooth and predictable budget outlays
Promotes inter-generational equity
Embeds whole-of-life asset costing
Technology obsolescence better managed
Maintenance funding no longer discretionary
Operations can be kept contestable via regular market benchmarking or resets
Funding profile matches long-term institutional investors like pension or sovereign funds
RMIT University © 2013
Paul O'Connor 10
PPPs: Where did they come from?
• PPPs have been around for hundreds of years–Perrier Brothers had a drinking water concession in 1700s
• Modern PPPs started with the UK’s Private Financing Initiative launched in 1992:–Policy to extend Thatcher’s near-complete privatisation push–Kept and embraced by ‘New Labour’ when elected in 1997
• Seen as a way to smooth out demands upon the capital account for developed economies with high deficits
• Seen as one of Tony Blair’s “third way” vehicles to engage with the private sector and achieve public goals
• Seen as a way to speed up social and economic infrastructure renewal & promote delivery effectiveness
RMIT University © 2013
Paul O'Connor 11
What were the key drivers in Victoria?
•Two distinct periods–Pre-2000 – emerging PPP guidelines–Post-2000 – current PPP guidelines
•Pre-2000–Post recession period looking to kick start economy and
find “non-debt” capital methods
•Post-2000–Iconic and one-off complex projects–User pays (i.e. toll roads) and water treatment plants–Social infrastructure replacement and augmentation
RMIT University © 2013
Paul O'Connor 12
Why choose PPPs for infrastructure?
Value and size of the project
Technical complexity/novelty
Risk allocation profile (especially demand risk)
Scope for design/technical innovation
Maturity of the public sector project owner
Private sector interest/public sector need
Complementary projects to go with the PPP?
RMIT University © 2013
Paul O'Connor 13
Practical considerations for PPPs
For…
–Fixed capital payments over life of the asset
–Asset will return to public ownership
–Contract ‘locks in’ O and M funding
–Output specification drives service and asset quality
–Value for money
Against…
–Finding a good partner
–Funding availability (esp. due to GFC)
–Transparency of risk transfer premiums
–Up-front and high transaction costs
–Long term monitoring regime to maintain expected standards
RMIT University © 2013
Paul O'Connor 14
What has been achieved in a decade?
•UK has 500+ PFI projects with a capital value in excess of £28 billion
•Victoria has A$10.5 billion contracted in 21 projects (www.partnerships.vic.gov.au)
•Detailed policy and guidance suites have been developed in UK and Australia
•World Bank and ADB promoting PPPs
•PPPs being adopted in emerging economies
RMIT University © 2013
Paul O'Connor 15
SECTOR CASE STUDIES
Major PPP Projects:
RMIT University © 2013
Paul O'Connor 16RMIT University © 2013
PPPs in Action – Sector case studies
•Health
•Transport
•Education
Paul O'Connor 17
Health PPPs – some typical models
• DBFM – design, build, finance, maintain–Positive (refer to RWH
report and the RCH project summary)
–Negative (refer to PAC report on Paddington)
• DBFOM – design, build, finance, operate, maintain–(similar to privatisation?)
RMIT University © 2013
Paul O'Connor 18RMIT University © 2013
Paul O'Connor
RMIT University © 2013 19
Health PPPs – lessons & observations
•Transfer of design risk to private sector is only effective if State has clearly specified:–Present and future clinical models
–Present and future demand
–Expected functionality of the facility
–Non-negotiable building standards
•UK issues – quality of build in some facilities and fair profit share for refinancing gains
Paul O'Connor
RMIT University © 2013 20
Transport PPPs
RMIT University © 2013 Paul O'Connor 21
Road PPPs
Variety of models to consider
• ‘Toll road’ concession model–Successes: CityLink and EastLink in Melbourne –Failures: Sydney and Brisbane tunnels (over optimistic demand
forecasts and upfront payments to Government)
• HOT lane model–Augment existing corridor with express toll lane
• ‘Availability’ model–Used in UK with ‘shadow tolls’ –New PPP in Victoria – KPI not volume based
Paul O'Connor 22
Rail PPPs
• Infrastructure–London Underground
(refer to NAO reports)
•Rolling stock–(NSW)
•Facilities/interchange–Southern Cross Station
(refer to VAGO report)
RMIT University © 2013
Paul O'Connor 23
RMIT University © 2013
Transport PPPs - observations
•For roads –don’t be greedy and demand upfront payments, as this is
passed on via higher tolls to the public who may then boycott the route. (Refer to NSW AG report on tunnels)
•For rail–Understand the value drivers of the business and focus on
using private sector expertise to increase operational efficiency and reliability, as well as contain costs over the long-term. (Refer NAO reports on the underground)
Paul O'Connor 24
Education PPPs - Variety of models
• New build–Single site schools–Multiple site schools (refer PV
schools summary)
• Tertiary research precinct–LaTrobe University (refer
Biosciences summary)
• Refurbishment–UK building schools for the
future (refer NAO report)–Southbank TAFE (Brisbane)
RMIT University © 2013
Paul O'Connor
RMIT University © 2013 25
Education PPPs – some observations…
•Specify demand corridors and let private sector take site risk (PV schools)
•Multi-site deal is effective way to achieve quick build-out of many sites over a wide area
•Some risks of a “two class” system, due to poor asset maintenance in the State build sector
•Lock in of service payments reduces future flexibility (c.f. declining revenue base in Scotland)
Paul O'Connor 26
Other sectors?
• Prisons–Facilities only (DBFM)–Integrated correctional
services (DBFOM)
• Electricity–Independent power
producers
• Water–Town supply or desalination
plants
RMIT University © 2013
Paul O'Connor 27
PPPs: the future or a passing fad?• In Australia:
–Still only account for about 10% of total public sector asset investments (approx. $10.5 billion in Victoria across 10 years)
–Most are on balance sheet, no accounting advantage–User pays model (i.e. toll roads) becoming difficult due to problems with accuracy of traffic demand forecasting
–Some states pursuing Alliances more aggressively–Marginal cost of capital issue – cost and availability of private finance versus public sector debt raisings?
–Low hanging fruit exhausted? Iconic/innovative facilities likely to be overtaken by more ‘boring’ facilities (such as schools, water and sewerage)
RMIT University © 2013
Paul O'Connor 28RMIT University © 2013
Any questions?
• My contact details:
Paul O’Connor DipPer&OpsMgt, DipGovMgt, BA(AsianStudies), GradCertPPPs (Melb.), MPubInfra (Melb.)
School of Property, Construction and Project Management
RMIT University
E: <[email protected]>
M: +61 437 587 396