+ All Categories
Home > Documents > Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Date post: 16-Dec-2015
Category:
Upload: derek-anderson
View: 213 times
Download: 0 times
Share this document with a friend
Popular Tags:
17
Master Plan
Transcript
Page 1: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Master Plan

Page 2: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Citizens’ Health Care Working Group

Master PlanNovember 2005

Page 3: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Master Plan—November 2005

• Schedule• Budget• Community Meetings• Questions for America• Recommendations• External Communications

Page 4: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Schedule

Page 5: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Master Schedule

Working Group appointed February 28, 2005

Hearings conducted May 11 – August 17, 2005

Health Report to the American People issued October 6, 2005

Hold Community Meetings December 10, 2005 – April 2006

Develop interim recommendations December 14 – May 15, 2006

Issue interim recommendations May 15, 2006

Public comment period on interim recommendations

May 15 – August 14, 2006

Issue final recommendations to the President and Congress

September 29, 2006

President submits recommendations to Congress

October 13, 2006

Congress conducts hearings Early 2007

Page 6: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Working Group Appointed

Hearings

Report

Questions forAmerica

Community Meetings

Interim Recommendations

Public Comment Period

FinalRecommendations

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

2005 2006

2/28

5/11 8/17

10/6

10/6 4/14

12/10 4/14

12/14 5/15

5/15 8/14

6/1

9/29

Page 7: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Scheduling IssuesCommunity meetings—crammed into short timeframe

• December-January: 6 meetings• February-mid April: 30 meetings

Development of recommendations--overlaps period of citizen input

Schedule for development of recommendations involves extremely short turnarounds for decision making and report writing

Final recommendations—developmental work must begin before all public comments are in

Page 8: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Scheduling Options

• Extend the Life of the Working Group

• Move Date of Issuance of Preliminary Recommendations

• Conduct Community Meetings After Preliminary Recommendations Are Issued

Page 9: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Extend Life of Working Group

Authorization of appropriations ends September 30, 2006

Legislation would be needed to continue beyond this dateObtaining an extension would be difficult::

• Few legislative vehicles available—probably only the upcoming appropriations bill• Budget and legislative culture not generally amenable to such requests.

A budget increase is unlikely; the best that could be hoped for probably is a no cost extension

The outcome is uncertain, so we would still need to work under current deadlines while requesting an extension

Page 10: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

PROS and Cons of Seeking an Extension

PROS:• An extension would provide a more orderly execution of the program• It would rationalize the relationship of the schedules for community meetings,

interim recommendations, and final recommendations by allowing more time for meetings and analysis of results.

CONS• A no cost extension would require a budget/schedule adjustment—e.g., spreading

out Working Group meetings rather than having more of them• Making the case for an extension will consume staff resources, detracting from

current work

Page 11: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Specific ProposalShould the Working Group wish to request an extension, staff would recommend a 3 month extension

• One month would be added to the periods available for each of the 3 major future activities (community meetings, and interim and final recommendations), thereby providing more time to complete each one and reducing the overlap between them.

• Community meetings end May 15• Interim recommendations issued July 15• Public comment period ends October 15• Final recommendations issued December 31

• The ending date would be December 31, 2005• This would result in final recommendations being issued right before the new

Congress convenes

Page 12: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Report

Questions forAmerica

Community Meetings

InterimRecommendations

Public Comment Period

FinalRecommendations

Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

2005 2006 2007

10/6

10/6 5/15

12/10 5/15

12/14 7/15

7/15 10/15

9/15 12/31

Page 13: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Other Scheduling Options

Move Date of Issuance of Preliminary Recommendations• The schedule presented here incorporates such a change. Based on staff analysis

of the process needed for developing recommendations, we recommend moving the date of issuance of preliminary recommendations from May 1 to May 15, 2006.

• This will be discussed more thoroughly at the meeting on that subject

Conduct Community Meetings After Preliminary Recommendations Are Issued

• The idea of conducting community meetings after preliminary recommendations are issued will be discussed at the meeting on community meetings

Page 14: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Budget

Page 15: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Budget Status

FY 2005 FY 2006

Authorization: $3,000,000 $3,000,000

Appropriated: 2,976,000 386,880

Status: For FY 2006 we are operating under a continuing resolution which ends November 16.

We are awaiting word on next stage—another continuing resolution, or appropriation

Restrictions apply to procurements during continuing resolutions

However, we are authorized to use unspent FY 2005 funds in 2006 and to procure contractor assistance on an incremental basis.

Page 16: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

Budget Review and Adjustments

It is likely that our budget will need to be adjusted to reflect a number of evolving factors:

• More recent cost estimates• Reconciliation of actual versus planned expenditures• Congressional action on the FY 2006 budget• Decisions from the Working Group based on discussions at this November Working Group

meeting, including such matters as• Overall schedule for completing the Working Group’s program• Additional community meetings• Budget set-aside for Member meetings• Budget set-aside for Member presentations

Staff will present a revised budget at the December Working Group meeting.

Page 17: Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.

The following components of the Master Plan will be completed based on decisions of the Working Group at this meeting

• Community Meetings• Questions for America• Recommendations• External Communications


Recommended