Date post: | 13-Jan-2016 |
Category: |
Documents |
Upload: | terence-heath |
View: | 212 times |
Download: | 0 times |
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
CONCEPTS FOR ENHANCING THE EFFECTIVENESS OF TRAFFIC CONTROL PLANS
Stuart AndersonGerald Ullman
Making Work Zones Work Better Workshop
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Background
• Maintenance of traffic issues and traffic control plans (TCP)
• Temporal and spatial requirements impact construction– Temporal - time– Spatial - dimensions
• Options available
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Background
Traffic Management Requirements
Options Available
Temporal Daytime off-peak work (i.e., 9 a.m. – 4 p.m.) Nighttime work (i.e., 7 p.m. – 6 a.m.) Weekend work (i.e., 7 p.m. Friday – 6 a.m. Monday) Intermediate-term work (overnight to 3 days duration) Long-term work (longer than 3 days duration)
Spatial Lateral Lane shifts onto a shoulder or to temporary lanes Lane constrictions Lane closures Number of lanes closed
Single lane Multiple lanes
Traffic-handling schemes Crossovers Interior (middle) lane or lanes Reversible express lanes
Total roadway closures Longitudinal Full length closures
Advancing limited closure Leap-frogging limited closure
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Problem
• Lack of early and sufficient input of traffic and construction expertise
• Policy directives, funding and other factors often limit alternatives
• Solution may be sub-optimal
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Preferred Practice
• Prior to detailed PS&E design• During detailed PS&E design
Phase I
Inside Shoulders Widened
Phase II
ConstructionArea
Traffic on Widened Inside Shoulder
ConstructionArea
Phase III
Traffic on New Pavement
Construction Area
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Consider
• Pavement related processes – What is done– Pavement treatments and
materials
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Consider
• Non-pavement related processes– How is pavement treatment
accomplished– Traffic and construction related
issues
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Process Approach• Integrate pavement and non-
pavement related processes• Process developed under NCHRP
Project 10-50A• Fundementals
– Start early in project development– Use multidisciplinary team approach– Analyze Traffic approaches to minimize
impacts– Promote construction input on
continuous basis
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Process Approach• Four main steps
– Identify candidate sections– Identify pavement condition– Screen potential strategies– Evaluate feasible strategies
• Content of steps– Objectives– Key activities– Issues to consider– Resources– Practical illustrations
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Process Approach• Validated by industry• Case studies demonstrated
applicability• Documented in final report
– A Process for Selecting Strategies for Rehabilitation of Rigid Pavements, Final Report, NCHRP Project 10-50A, February 2002
– Contact NCHRP Program for Copy
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Preferred Strategy
RequireAdditionalInformation?
1. Select Possible Treatments2. Identify Traffic and Construction Issues3. Estimate Preliminary Cost4. Identify Feasible Strategies5. Identify Feasible Strategies
STEP 1 Identify Candidate Sections
STEP 2 Identify Pavement Condition
1. Conduct Survey2. Conduct Field & Laboratory Tests3. Identify Distress Mechanisms
STEP 3 Screen Potential Strategies
STEP 4 Evaluate Feasible Strategies
1. Determine Level of Traffic and Construction Analysis2. Analyze Traffic Alternatives3. Perform Constructibility Analysis4. Determine Contracting Approach5. Perform Life Cycle Cost Analysis (LCCA)6. Recommend Most Appropriate MRR Strategy
No
YesSelectionProcess
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Screen Potential Strategies
STEP 4 Evaluate Feasible Strategies
Yes
Output:
Required Design Information Feasible Strategies
RequireAdditionalInformation?
1. Select Possible Treatments2. Identify Traffic and Construction
Issues3. Estimate Preliminary Cost4. Identify Feasible Strategies
STEP 3 Screen Potential Strategies
STEP 2 Identify Pavement Condition
No
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Resource
• Description of resource• Relevance to analysis• References for more information• Examples
– Work zone analysis tool - QUICKZONE– Workshop approach - Get In, Get Out,
Stay Application– Constructibility Review Process
Workbook - NCHRP Report 391
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Traffic and Construction Issues
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Traffic and Construction Issues:Caltrans I-710 Alternative• Traffic
– Segmental full closure (3 to 5 miles) in one direction
– All lanes available to traffic weekdays
– Install ITS during construction– Recommend use of alternate
routes (I-110, I-605, Lakewood Blvd. and other local streets)
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Traffic and Construction Issues:Caltrans I-710 Alternative• Construction
– Two concrete plants– Concrete plants produce about 1800
CY per hour– Back-up equipment and extra
sources of materials– Recycle existing PCC pavement– Ten-hour shifts– Three stage operation– 16 weekends
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Evaluate Potential Strategies
STEP 4 Evaluate Feasible Strategies
1. Determine Level of Traffic andConstruction Analysis
2. Analyze Traffic Alternatives3. Perform Constructibility Analysis4. Determine Contract Approach5. Perform LCCA6. Recommend Preferred Strategy
Preferred StrategyOutput :
STEP 3 Screen Potential Strategies
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Level of Analysis
• DOT standard traffic and construction approach
• DOT standard traffic and construction approach but with some enhanced techniques to address special issues
• A corridor wide project-oriented traffic and construction approach
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Traffic Analysis:Michigan I-496 Project
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
TCP Development for PS&E• Traffic • Constructibility reviews• Contract methods• Materials and equipment
See NCHRP Synthesis 293
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Benefits
• Efficient and cost effective construction
• Minimize impact on road users, local businesses
• Safer work zones• Special needs identified early
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Application
• Most projects types and sizes• May have higher impact on
projects with high traffic volumes• Concepts currently being tested
– TRB Task Force A5T60, “Accelerating Innovation in the Highway Industry”
– IPRF research project, “Traffic Management Studies for Reconstruction of High Volume Roadways”
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Application - TF A5T60• Accelerated Construction Technology
Team (ACTT)• Corridor review• “Outside” experts visit state experts• Share, learn, and promote new ideas
• Two-day workshop with Indiana and Penn DOTs
• Proposed use of innovation in twelve areas
• Ultimately - DOT decides what is best for their project
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Application - Twelve Areas• Corridor
improvements• Contracting and
procurement techniques
• Work zone traffic management
• Stay out techniques
• Constructibility• Geotechnology
• Utility delays• Prefab/modular• High speed QA/QC• Workforce health
and safety• Training and
education• Communications
of best practices
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Application - IPRF Project• Task 6 Conceptual Study• Workshops with DOT• Late in programming/early in design• Brainstorm traffic and construction
issues• Recommend feasible alternatives• Current studies
– Mississippi DOT - I-55 South of Memphis
– Washington DOT - I-5 through Seattle
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Lessons Learned
• Do not “set” design basis too early
• Team approach enhances TCP development
• Early involvement of traffic and construction expertise helps identify possible problems and solutions
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Conclusions
• DOTs should be encouraged to follow concepts throughout TCP development
• Constructibility reviews integral to TCP development
• Team approach essential especially on larger projects
Materials, Pavements & Transportation OperationsTransportation
Institute
Texas
Thank you!
Discussion?