Incremental Scenario Testing: Beyond Exploratory Testing 2
Background
Teleca is a world-leading supplier of software services and solutions to the mobile industry
Global capability to deliver packaged software solutions,systems design, integration and testing
Teleca was developing a complex internet service fora top 5 mobile OEM
500kLOC, large number of handsets, operators, target markets complex multi-backend with e-commerce, operator integration
High functional compliancy reached ... but due to the complexity the quality was poor
Incremental Scenario Testing: Beyond Exploratory Testing 3
SW functionality to
be tested
Software complexitySW function range
Cross-functionalit
yHW / SW
configuration
Memory situation
Data in- & outputEnvironme
nt variations
Network
User interactio
nHW
variations
SW customizati
on
SW re-usage
Distributed developme
nt
Distributed systems
Incremental Scenario Testing: Beyond Exploratory Testing 4
Test cases
Errors
Regression TestingSW function range
Error fixes
Existing errors...to be exposed
Regression Tests need complementation
Incremental Scenario Testing: Beyond Exploratory Testing 5
Be part of the overall test strategy
Find as many errors as possible
Generate test cases within the test session
Challenge the tester Work without detailed test case descriptions Allow creativity, force own ideas and motivate to be pro-
active Own judgment of the test result (no expected behavior)
Utilize the feedback from previous test sessions
Exploratory Testing was not successful for us:Difficult to come up with new and creative test ideasToo many areas remained untested
Exploratory Testing
Incremental Scenario Testing: Beyond Exploratory Testing 6
Incremental Scenario Testing (IST)
IST controls the complexity
IST guides & inspires the tester with Scenarios Encourage the tester to explore new functionality
IST automates the test planning Optimize the utilization of the available testers and test time Indentify SW areas not tested ever before
IST focuses the testing on new, modified & weak SW areas Provide an interface for collaboration between Test and SW
Team
IST increases the visibility of all activities
IST provides a web-based tool to offer the features above The Incremental Scenario Testing Tool (ISTT)
Incremental Scenario Testing: Beyond Exploratory Testing 7
Test Scenario
High level test case description built out ofthree test items:
1. Precondition
2. State
3. Event
How to reach each test itemis up to the tester This assures additional variation
for usage, input data, timing etc.
To be understood as a guideline The tester is free to experiment and
to do additional things
State
Precondition
Event
Incremental Scenario Testing: Beyond Exploratory Testing 8
Test items forming a Scenario
Precondition: Everything influencing the SW to be tested Dependent or independent of the functionality to be
tested The amount of preconditions is flexible from 0 – 5
State: All states and functionalities to be tested May be linked to requirements or specifications
Event: An action with internal or external influence Dependent or independent of the functionality to be
tested
Execu
tion fl
ow
Test items are grouped by test categories
NOTE: Testing can only be as complete as its test data
Incremental Scenario Testing: Beyond Exploratory Testing 9
Test environment and setup for one tester
Hardware, Operating System, Configuration, Language, ...
Test Scope
The Test Scope won‘t be changed within the test session
All testers might get the same Test Scope
...or each tester might get a different Test Scope
Incremental Scenario Testing: Beyond Exploratory Testing 10
SW complexity example: Voice calls
Outgoing calls (MO)
Incoming calls (MT)
States
Scopes, Preconditions & Events
User interactio
n
New MO / MT
callsOS /
Phone / Language
Battery / Headset
Call settings / Contacts /Call listsRAM / C:
status
Network coverage
Operator2G / 3G
Incremental Scenario Testing: Beyond Exploratory Testing 11
Voice call complexity in numbers
How to ensure that the important Scenarios are selected?
Scopes cannot be
counted easily,
e.g. number of
devices supported.
Preconditions >50
States >40
Events >50
Incremental Scenario Testing: Beyond Exploratory Testing 12
Test Scenario generation
Test itemhistory
Failed ShowstopperFailed Critical
Failed MajorFailed MinorNot tested(Passed)
Scenariohistory
Test itemfocus
Selectedto be
tested?
Scenario calculation based the Test Session Configuration
Test itemweight
OftenRegularlySporadicRarely
(Unusual)
Prefer the newor changed functionality
Test Scenario to be tested
Prefer the common
functionality (items)
Prefer the riskyand not tested functionality
(items)
Prefer the riskyand not tested
Scenarios
Incremental Scenario Testing: Beyond Exploratory Testing 13
Scope: Nokia N96, OS 3.1,
English, T-Mobile
Scope: iPhone, OS 3.0, German, Vodafone
Voice call Scenario examples
P1: Headset connectedP2: Sceensaver = ON
P3: Profile = Silent
S: MT call ringing
E: Lose GSM network
P: Battery almost empty
S: MO call via address
book
E: Plug in charger
P1: RAM almost fullP2: UMTS active
S: MO call via speed dial
E: MT call ringing
P1: Sending of caller ID = ON
P2: Summary after call = ON
S: MO call via SMS is
ringing
E: Calendar alarm expires
Incremental Scenario Testing: Beyond Exploratory Testing 14
Test sessions
Test sessions are individual Every tester can start at any time independent of each other Every tester can pause or stop at any time Everybody is able to see the progress and results at any time
Test sessions are flexible Test as much as possible within a given time box Test as long as testers are available (without a deadline)
Test sessions can be distributed globally
Test sessions are stopped by the Test Manager Updating the SW will stop the test session and start a new
one The testers are notified after finishing the current Scenario
Incremental Scenario Testing: Beyond Exploratory Testing 15
Further add-ons
Ranking system (Junior Tester, Tester, Senior Tester)The rank depends on the experience within the IST projectShall motivate the tester and gives the Test Manager confidence when analyzing the test results
Re-Testing: Momentous test results, especially „Failed“ & „Impossible“, need evidence in the same sessionPreferable done by a tester with a higher rankSupports the Test Manager within the test result analysis
Developer Role: Everyone can influence the testingAdding of new test itemsMarking test items as „To be tested“
Incremental Scenario Testing: Beyond Exploratory Testing 16
Possible scenario (here 40)
Possible scenario
Test focus: „To be tested“
Test Scenario spectrum 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
Test session kick-off
Test session
Possible scenario
Test focus: „To be tested“
Scenario to be tested
First scenarios
are selected by
test focus
and weights
Incremental Scenario Testing: Beyond Exploratory Testing 17
Test Scenario spectrum 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
Test Scenario results
Test session ?
?
PASS
Failed
Impossible
Skipped
Not clear
Possible scenario
Test focus: „To be tested“
Scenario (to be) tested
Scenario (to be) re-tested
Impossible scenario
Incremental Scenario Testing: Beyond Exploratory Testing 18
Test session evolutionTest Scenario spectrum
Test session 1
(Increment 1)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
?
Test session 2
(Increment 2)
?
41 42 43 44 45
PASS
Failed
Impossible
Skipped
Not clear?
46
Test session 6
(Increment 6)
47 48 49 50
Test session 5
(Increment 5)
?
Test session 4
(Increment 4)
?
Test session 3
(Increment 3)
Incremental Scenario Testing: Beyond Exploratory Testing 19
Case study
Project period Mar/06 – Mar/09
IST usage period Nov/07 – Mar/09 (17 months)
Performed test sessions 27
Duration of test sessions in days1 – 38 (average: 4,8 days)
Possible Test Scenarios (1 precondition) 1.274.400Possible Test Scenarios (2 preconditions)
50.976.000
Executed Test Scenarios 10.219
New severe error reports 476
Incremental Scenario Testing: Beyond Exploratory Testing 20
Our main achievement
Time
Internal errors found
Err
ors
Release to
customer
Internal + customer errors found
Internal + customererrors found
Release to
customer
Time
Internal errors found
plus IST
Err
ors
Incremental Scenario Testing: Beyond Exploratory Testing 21
The football trainer
Scopes:TeamLeague /TournamentRules
Preconditions:Position/rankTeam conditionOpponentVenueWeather
Events:Goal InjuryYellow cardRed card
States:ScoreTime left
IST is suitable for any complex system
Matthias RatertTeleca GermanyRensingstr. 1544807 [email protected]
Thank you for your attention!
Please visit us at our stand no. 52
for a demo session & further discussions