Mexico unitization guideline Claudio de la Cerda E&P Director Mexico City | June | 2018 1
Transcript
Page 1: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

Mexico unitization guideline

Claudio de la CerdaE&P Director

Mexico City | June | 2018

1

Page 2: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

1. Unitization Guidelines Purpose and Regulatory Framework

2. Shared fields and reservoirs

3. Key concepts on Unitization Guidelines

4. Pre-Unitization Agreement

5. Unitization Agreement

6. Implementation Procedure

Agenda

Page 3: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

1. Unitization Guidelines Purpose and Regulatory Framework

2. Shared fields and reservoirs

3. Key concepts on Unitization Guidelines

4. Pre-Unitization Agreement

5. Unitization Agreement

6. Implementation Procedure

Agenda

Page 4: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

Establish the procedure for the Unitization of National Shared Reservoirs, throughthe following activities:

I. Approve the Pre-Unitization Agreement;

II. Instruct the Unitization of National Shared Reservoirs;

III. Approve the terms and conditions of the Unitization Agreement, and

IV. Determine the terms and conditions of the Unitization Agreement when the parties do not reach an agreement.

Unitization Guidelines

Regulatory

FrameworkArt. 1Art. 2Art. 3Art. 42

Art. 2Art. 62Art. 63Art. 64

Energy Reform

Dec-2013

Hydrocarbons Law

Aug-2014

Regulation of Hydrocarbons Law

Oct-2014

SENER Unitization Procedure

Mar-2017

Unitization Guidelines

Mar-2018

Page 5: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

Agenda

1. Unitization Guidelines Purpose and Regulatory Framework

2. Shared fields and reservoirs

3. Key concepts on Unitization Guidelines

4. Pre-Unitization Agreement

5. Unitization Agreement

6. Implementation Procedure

Page 6: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

Shared fields and reservoirs

What is a shared field/reservoir?

Those fields/reservoirs that extends beyond contract or assignment areas.

Contractual areas designed to minimize shared reservoirs

Blocks that fully covers explorationopportunities

Contract(B)Contract

(A)

Shared reservoir

Page 7: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

1. Unitization Guidelines Purpose and Regulatory Framework

2. Shared fields and reservoirs

3. Key concepts on Unitization Guidelines

4. Pre-Unitization Agreement

5. Unitization Agreement

6. Implementation Procedure

Agenda

Page 8: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

Key concepts on Unitization Guidelines

Pre-Unitization Agreement

• Describes the coordinated activities that will be carried out in a “Possible Shared Reservoir”

• Not yet determined if there is or not hydraulic connection

• For projects in exploration and evaluation periods

• Each operator must comply its own Minimum Work Commitments

Unitization Agreement

• Establish terms and conditions to develop Unit Operations in the Unit Area

• Shared reservoir confirmed

• Designed operator

• For projects in development period

srot

cart

no R

C E

r NEo S/

d y

n b

a

d

s e

e z

e irn ogi h

s t

s u

A A n

ee

wte

B

For the Unitized Area in surface and depth

instructed by SENER

Main purpose:

Share information and carry out coordinated

activities to determine if the reservoir is shared or

not

Page 9: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

1. Unitization Guidelines Purpose and Regulatory Framework

2. Shared fields and reservoirs

3. Key concepts on Unitization Guidelines

4. Pre-Unitization Agreement

5. Unitization Agreement

6. Implementation Procedure

Agenda

Page 10: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

Pre-Unitization Agreement, what for?

I. Share information;

II. Coordinate activities to evaluate a possible shared reservoir;

III. Minimize capital expenditure;

IV. Save evaluation time/resources;

V. Up to two (2) years period to carry out coordinatedactivities (period extension possible);

VI. The agreement allows activities in both sides of theborder to comply contractual obligations;

VII. Ease controversy resolution

Possibly shared reservoirs

Contract(B)

Contract(A)

Page 11: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

Pre-Unitization Agreement implementation

Notification of a possible shared reservoir

Either presented jointly or individually by operators

Content as established in guidelines

Verification of a possible shared reservoir

SENER verifies information and request the Pre-Unitization Agreement

Presentation of a Pre-Unitization Agreement

SENER will request parties to present the Pre-Unitization Agreement

SENER will have a 20 business days period to solve

Pre-Unitization Agreement

Up to 2 years and extensible

Information sharing

Hydraulic connectivity confirmation

Gather information to notify Shared Reservoir Discovery

Coordinated activities

Exploration

Evaluation

Delimitation

Characterization

develop a Unitization

Page 12: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

1. Unitization Guidelines Purpose and Regulatory Framework

2. Shared fields and reservoirs

3. Key concepts on Unitization Guidelines

4. Pre-Unitization Agreement

5. Unitization Agreement

6. Implementation Procedure

Agenda

Page 13: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

Unitization Agreement

Operators notify about shared

reservoir discovery

SENER determines a

shared reservoir

SHCP opinion regarding reservoir

unitization

SENER instructs unitization

SENER requests Unitization Agreement

SENER approves Unitization Agreement

Incorporation of the Unitization Agreement into

Planswill

60Business

days

45Business

days

30Business

days

30Business

days

120Business

days

95-115Business

days

✓ SENER will be assisted by CNH;

✓ For Unitization Agreement approval:

▪ CNH will solve operator designation within 45 business days

▪ SENER will solve UA within 40 business days once operator is approved

▪ SENER may adapt UA within 60 business days once operator is approved

Page 14: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

Approaches for Unitization Agreement

14

Up to 1 year

Pre-Unitization Agreement

Shared reservoir

confirmed

Operators for contracts (A) & (B)

Missing operators for contract (A) or (B)

Unitization Agreement

SENER Unitization Resolution

If no Unitization Agreement reached

If no UA reached, SENER may consult an independentthird party. Both operators may jointly propose thatexpert.

Page 15: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

• Existence of a shared reservoir to SENER & CNH

• Within 60 business days

• Technical support

• G&G Studies

• Work program proposal

Notification

• From CNH to SENER within 45 business days

• Opinion from SHCP requiredTechnical opinion

• Within 30 business days

• Guidelines applicable to request information

• SENER will determinate terms and conditions if no information is received

SENER instructs

unitization

B)

Un

itiz

ati

on

wit

ho

ut

co

nti

gu

ou

s

Co

ntr

ac

tor

/ A

ss

ign

ee

•Existence of a shared reservoir to CNH

•Technical support

•G&G StudiesNotification

•As approved Plans

•SENER will determinate how to proceed in non contractual/assigned areas

Continuity of E&P

activities

Unitization in E&P Contracts

15

s

uo

u egi et n

n go i

sc sh At i /

w r on toi ct a

a rz ti nti o

n C U)

A

Page 16: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

1. Unitization Guidelines Purpose and Regulatory Framework

2. Shared fields and reservoirs

3. Key concepts on Unitization Guidelines

4. Pre-Unitization Agreement

5. Unitization Agreement

6. Implementation Procedure

Agenda

Page 17: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

Procedimiento del Acuerdo Preliminar de Unificación

1. The Assignees and/or Contractorsjointly send to SENER, the requestto sign an APU.

2. SENER receives the request andevaluates it within a period of 20business days

3. SENER notifies by resolution theassignees and / or contractors, iftheir request to present the APUis authorized. Otherwise theprocedure will be terminated.

4. The Assignees and/or Contractorssubmit to SENER their APUproposal within 20 business days.

5. SENER approves the proposal andthe assignees and/or contractorscarry out coordinated operations.

Page 18: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization
Page 19: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization
Page 20: Mexico unitization guideline - gob.mx · 2019. 4. 18. · reservoir discovery SENER determines a shared reservoir SHCP opinion regarding reservoir unitization SENER instructs unitization

Thank You