MICE RF TEST STAND
• Major Milestones (2006)– Testing of BURLE 4616 circuit
• September 2006
– Testing of 4616 circuit with full amplitude and phase control
• November 2006
– Work beginning on refurbishment of TH116 circuit
• September 2006
Current progress
• 4616HT Power supply – Power supply is being constructed by DL power
supply group, and is progressing well.– All major components are on order, or have been
delivered.
• 4616 Auxiliary Rack– Heater control system has been purchased– Screen pulser is currently being designed.– PLC control system has been procured ready for
programming
HT power supply Rack
• 4616HT Power supply rack– Construction
almost finished
Low level RF
• Low level components are under investigation– Oscillator on the basis of DDS (Direct digital
synthesis) has been procured– RF detector prototypes have been produced– Basic low level system components are
available (no phase and gain control)– Full Low level system to be produced by NOV
2006 (with phase and gain control)
High Power Coaxial Components• Directional coupler and water load are now on
site. –Ready for installation
4616 circuit refurbishment
• Circuit is in surprisingly good condition!– Flexible water pipes to be replaced– Rubber o-rings to be replaced– Redundant ancillary equipment has been
removed.– Minor repairs to finger stock in progress.– Cleaning of RF surfaces in progress.
Tubes• 2 x BURLE 4616
Tubes Have been delivered, and are ready for installation
Test Area• Area is still being prepared for MICE equipment
Test area
• Water panel is now in place.
• Electrical services will be installed in the next few weeks