+ All Categories
Home > Documents > MISO: An Intro - michigan.gov€¦ · MISO Intro UP Task Force June 9 Presentation Author: Cole,...

MISO: An Intro - michigan.gov€¦ · MISO Intro UP Task Force June 9 Presentation Author: Cole,...

Date post: 27-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
13
MISO: An Intro June 9, 2020
Transcript
Page 1: MISO: An Intro - michigan.gov€¦ · MISO Intro UP Task Force June 9 Presentation Author: Cole, Cathy \(LARA\) Subject: MISO Intro UP Task Force June 9 Presentation Keywords: MISo,

MISO: An IntroJune 9, 2020

Page 2: MISO: An Intro - michigan.gov€¦ · MISO Intro UP Task Force June 9 Presentation Author: Cole, Cathy \(LARA\) Subject: MISO Intro UP Task Force June 9 Presentation Keywords: MISo,

MISO is an independent, non-profit organization in 15 US States and one Canadian Province

2

MISO by-the-numbers

High Voltage Transmission 65,800 miles

Generation Capacity 174,000 MW

Peak System Demand 127,125 MW

Customers Served 42 million

Page 3: MISO: An Intro - michigan.gov€¦ · MISO Intro UP Task Force June 9 Presentation Author: Cole, Cathy \(LARA\) Subject: MISO Intro UP Task Force June 9 Presentation Keywords: MISo,

MISO’s Key Functions

3

Page 4: MISO: An Intro - michigan.gov€¦ · MISO Intro UP Task Force June 9 Presentation Author: Cole, Cathy \(LARA\) Subject: MISO Intro UP Task Force June 9 Presentation Keywords: MISo,

Generation Dispatch

4

In accordance with MISO’s FERC-approved Tariff: https://www.misoenergy.org/legal/tariff/

Page 5: MISO: An Intro - michigan.gov€¦ · MISO Intro UP Task Force June 9 Presentation Author: Cole, Cathy \(LARA\) Subject: MISO Intro UP Task Force June 9 Presentation Keywords: MISo,

MISO’s Transmission Planning Principles

5

Page 6: MISO: An Intro - michigan.gov€¦ · MISO Intro UP Task Force June 9 Presentation Author: Cole, Cathy \(LARA\) Subject: MISO Intro UP Task Force June 9 Presentation Keywords: MISo,

MISO Transmission Planning

6

Project types: reliability, economic, other (typically asset replacement), MVP

Page 7: MISO: An Intro - michigan.gov€¦ · MISO Intro UP Task Force June 9 Presentation Author: Cole, Cathy \(LARA\) Subject: MISO Intro UP Task Force June 9 Presentation Keywords: MISo,

MTEP Projects

7

Page 8: MISO: An Intro - michigan.gov€¦ · MISO Intro UP Task Force June 9 Presentation Author: Cole, Cathy \(LARA\) Subject: MISO Intro UP Task Force June 9 Presentation Keywords: MISo,

MISO Transmission Expansion Plan

8https://www.misoenergy.org/planning/planning/mtep-2019-/

Page 9: MISO: An Intro - michigan.gov€¦ · MISO Intro UP Task Force June 9 Presentation Author: Cole, Cathy \(LARA\) Subject: MISO Intro UP Task Force June 9 Presentation Keywords: MISo,

MISO Tariff: Modules

9

Page 10: MISO: An Intro - michigan.gov€¦ · MISO Intro UP Task Force June 9 Presentation Author: Cole, Cathy \(LARA\) Subject: MISO Intro UP Task Force June 9 Presentation Keywords: MISo,

MISO Stakeholder Governance Structure

10

***This is where stakeholder involvement happens***

Page 11: MISO: An Intro - michigan.gov€¦ · MISO Intro UP Task Force June 9 Presentation Author: Cole, Cathy \(LARA\) Subject: MISO Intro UP Task Force June 9 Presentation Keywords: MISo,

MISO Stakeholders

11

Page 12: MISO: An Intro - michigan.gov€¦ · MISO Intro UP Task Force June 9 Presentation Author: Cole, Cathy \(LARA\) Subject: MISO Intro UP Task Force June 9 Presentation Keywords: MISo,

Eastern UP Transmission Expansion StudyRequest

• On August 17, 2016, Governor Snyder and the Michigan Agency for Energy (MAE) requested MISO to conduct an informational study to help Michigan understand the potential cost savings, reliability, and resource adequacy benefits of transmission and generation expansion in Michigan.

• The specific request was for MISO conduct an exploratory study to evaluate transmission expansion between the Upper Peninsula of Michigan and Ontario, as well as to Lower Michigan. MISO also received a request from MAE and the Michigan Public Service Commission to study two generation scenarios one in Kalkaska (Lower Peninsula) and one in Pine River (Upper Peninsula).

12

Results• Currently there’s no transmission

connection between Ontario and the UP. The study indicated that with a new intertie, 125 MW can be transferred between Ontario and the UP. Significant reliability upgrades would be needed on both systems to increase that transfer capability.

• With limited transfer capability and relatively high construction cost, none of the transmission ideas provided enough benefit to cover costs. A generator sited in the UP provides comparable benefit to transmission ideas but still not provide high enough benefit to outweigh its cost.

• Additionally, the intertie between Ontario and the UP did not have any impact to the Local Reliability Requirement or the Capacity Import Limit for Zones 2 and 7.

Page 13: MISO: An Intro - michigan.gov€¦ · MISO Intro UP Task Force June 9 Presentation Author: Cole, Cathy \(LARA\) Subject: MISO Intro UP Task Force June 9 Presentation Keywords: MISo,

Questions?

Cathy [email protected]

13


Recommended