Site 27 Update
Restoration Advisory Board MeetingFormer Naval Air Station Moffett FieldJuly 12, 2007
Presented by: Scott GromkoNavy Remedial Project Manager
2
Overview
• Site Background• Recently Completed Actions• Upcoming Action• Remedial Action Completion Report• Schedule• Questions
7
Upcoming Actions
• Re-hydroseed areas of the Northern Channel slope with limited growth
– Mixture of salt tolerant grasses (salt grass, alkali sacaton)
– California native species– Water application into the rainy season (October)
10
Remedial Action Completion Report
• Describe activities of Remedial Action– Pre-construction, construction, demobilization
activities– Biological Mitigation– Waste management– Site Restoration– As Builts
• Appendices – Lots of Data
11
Schedule
• Draft Remedial Action Completion Report –September 2007
• Respond to Comments – November 2007
• Draft Final RACR – December 2007
• Final RACR and Site Close Out – January 2008