Date post: | 16-Dec-2015 |
Category: |
Documents |
Upload: | emerald-boone |
View: | 235 times |
Download: | 5 times |
MOPANI DISTRICT MUNICIPALITY (LIMPOPO)
1
Project description
• Lepelle Northern Water appointed as implementing agent for the following: – Accelerate the completion of the Giyani water
treatment works (WTW) upgrade and
refurbishment
– Repair of non functional boreholes (inclusive of
Nkhensani Hospital) and
– Refurbishment of Giyani Waste water treatment
works. 2
3
Progress to date
• 32 villages receive bulk water supply • 22 villages receive water from boreholes • One (1) village (Siyandani) receive
tankering service as a temporary measure , while permanent solution to provide water is in progress.
• Though there is water supply in these villages, there are various challenges on the bulk and reticulation that affect the total coverage
4
List of 32 villages supplied from bulk pipeline
1. Makosha2. Mapayeni3. Mapuve4. Maswanganyi5. Mavalani6. Mbatlo7. Mhlava8. Mningisi Block 39. Ndidani10. Nghalalume11. Ngove12. Nkomo A13. Nwadzekudzeku14. Bode15. Dzingidzingi16. Bon’wane
1. Gaula2. Giyani CBD3. Hlomela4. Homu A5. Homu B6. Khakhala7. Krematart8. Mahlathi9. Makhuva10. Shawela11. Thomo12. Vuhehli13. Vuhehli North14. Xibulane15. Xikhumba16. Xikukwani
5
List of 22 villages supplied by boreholes
1. Mbhetle2. Mninginisi Block 23. Mphagani4. Munghonghoma5. Mushiane6. Mzilela7. Nkomo B8. Xitlakati9. Phalaubeni10. Muyexe11. Thomson
1. Bambeni2. Daniel3. Dzumeri4. Guwela5. Khaxani6. Kheyi7. Loloka8. Mageva9. Maphata10. Matsotsosela11. Mayephu
6
Challenges in Siyandani
Supply Challenges Remedial action Responsibility Completion
Date
Giyani Water
Treatment
Works
The Kanyisa Booster is out
of operation due to the
cavitation of pumps
Planned shutdown for the
surveillance of the line from
the Low Lift reservoir to the
Kanyisa Booster station
LNW April 2015
Siyandani pump station Refurbishment of the pumps
station.
LNW June 2015
Illegal connections and
other internal reticulation
challenges
Once the water
Implementation of Water
Conservation and demand
management
LNW June 2015
Mapuve
Scheme
The Mapuve bulk supply to
Siyandanhi project is not
commissioned due to the
blockages on the line
Support the MDM in resolving
the challenges on the Phase
1 of the project. (i.e.
attending to blockages on
the line ,etc. )
LNW February 2015
Groundwater
Augmentation
Boreholes are vandalized
and transformers were
stolen
Refurbishment of boreholes
and application of
transformers.
LNW June 2015
7
Challenges affecting supply
Challenges Remedial Action
• Vandalism of Infrastructure
• Water Conservation and Demand Management
• LNW is providing Security Service to safeguard the Infrastructure
• Unauthorised connection
• Aging Infrastructure • Replacement of asbestos cement pipelines and associated infrastructure
• Lack of operation and Maintenance of Infrastructure
• LNW has deployed personnel to assist with the Operations and Maintenance of the Infrastructure.
• Continuous support is required
• Lack of Reticulation • Installation of reticulation network 8
Giyani water treatment works
The intervention had the following impacts:
• The 6Ml/day expansion project is functionally
complete – snagging in progress
• The refurbishment project is complete
• Total daily yield is now on average greater than
34Ml/day, a capacity which is sufficient to supply
the Giyani town and all its 55 villages that are
within the scheme’s footprint
9
Giyani water reticulation
• Main booster pump station completed and
commissioned
• Material for replacement of asbestos cement pipelines
A, B, D, E has been procured and delivered
• Boreholes to 16 priority villages have been refurbished
and commissioned
• Village reticulation designs in progress
• Leaks and emergency are attended to timeously and
promptly
• More villages now have water supply and consistent
supply is maintained. 10
Nkhensani hospital• The hospital now has a
secure water supply
• The 6 boreholes have been
refurbished and re-
commissioned
• Installation of water
purification plant is in
progress and at an advanced
state.
Water purification plant on site
Water softener11
Giyani wastewater treatment works
The intervention had the
following impacts:
• 1.5Ml/day expansion project
complete and functional –
test and commissioning
underway
• 1.5Ml/day package plant –
fabrication complete,
construction under way.
• Morogholo Pump station
refurbishment complete
1.5Ml/day expansion project complete and functional – test and
commissioning underway
12
Giyani water reticulation
• Main booster pump station completed and commissioned
• Material for replacement of asbestos cement pipelines A,
B, D, E has been procured and delivered.
• These pipelines are within the diameter distance of not
less than 700 km
13
Action plan Project Brief Scope Time
frame Amount R,000
Giyani Groundwater Augmentation-
Boreholes at Khensani Hospital And Prioritised villages and scheme assessment
March 2015 R65 000
Giyani Water Treatment Works Refurbishment
Refurbishment of electro-mechanical equipment and 16 sand filters
30 September
2014
R10 000
Giyani Water Treatment Works upgrade
Expansion of existing Water Treatment works by 6.7 ML/day
30 September
2014
R10 000
Giyani waste Water Treatment works revitalization
Refurbish and install package plant and construct 20ML/day
March 2017 R333 000
Middle Letaba-Nsami canal repairs
60km engineering assessment and repairs
March 2015 R50 000
Nandoni – Nsami raw water bulk pipeline
52 km pipeline planning and re-designing
March 2017 R450 000
Bambanana Pipeline New 600mm pipeline, planning, approval and design
March 2017 R308 000
New Nwamitwa dam Planning, finalised design and permits
March 2017 R80 00014
Action plan Project Brief Scope Time frame Amount
R,000
Mametja Sekororo New Water treatment works, raw and clear water pipelines and reservoirs
March 2017 R249 000
Water Conservation and demand management
District wide demand and supply measures
March 2019 R340 000
Nandoni- Mhinga water supply
Feasibility, planning , finalised designs and permits
March 2016 R40 000
Namakgale Waste water treatment works upgrade
Refurbish existing and upgrade
March 2016 R249 000
TOTAL PROGRAMME VALUE R1, 992 000
15
NGAKA MODIRI MOLEMA DISTRICT MUNICIPALITY (NORTH WEST)
16
Mahikeng bulk water supply (BWS) action plan
• Phase 1 (Refurbishment of the Mmabatho Water Treatment Works (WTW): – Complete by 30 November 2014, with the last few
adjustments to maximize output to be completed in February 2015.
– This intervention has increased the output of the WTW from an average of 9.5Mℓ/d to 17.5Mℓ/d currently due to reach 20Mℓ/d once fully operational.
• Phase 2 (Upgrading of the Mmabatho WTW from 20Mℓ/d to 30Mℓ/d): – Work is underway and the expected completion date is
October 2016
• Phase 2 (Construction of the Lokaleng reservoir and related bulk pipelines): – Design work has been completed– Envisaged to start with construction from April 2016 and
completion by July 2017 17
Mahikeng BWS financial implications
Funding allocation
Total
Expenditure / Allocation x R1000
Expenditure 12/13-13/14
14/15 projected expenditure 15/16 16/17 17/18
Total project cost
286 648 22 785 33 039 55 716 87 554 87 554
RBIG funding
186 869 22 78533 039 45 000 50 000 36 045
Counter funding
0 0 0 0 0
Shortfall on MTEF *
99 779 0 10 716 37 554 51 509
Cumulative shortfall 0 10 716 48 270 99 779
* In October 2014 the NMMDM indicated their inability to counter fund the project with an amount of R186 869 million. It is expected that counter funding by the NMMDM will not be possible, resulting in the Department having to fund the complete project. The additional funding is expected to be obtained from the RBIG programme in 2018/19 amounting to R99 779 million for project completion in the same year.
18
Ratlou BWS action plan
• Phase 1A (Provision of water to Setlagole): site establishment is underway, together with earthworks at the reservoir and procuring of the necessary materials, i.e. reinforcement steel, shuttering and the like. The expected completion date of the works is June 2016.
• Phase 1B(Provision of water to Madibogo) and Phase 2 (Provision of water to the balance of Ratlou): Implementation Readiness Studies are to be completed by July 2015, followed by the approval process and implementation.
19
Ratlou BWS financial implications
Funding allocation
Total
Expenditure / Allocation x R1000
Expenditure 12/13-13/14
14/15 projected expenditure 15/16 16/17 17/18
Total project cost
78 690 8 557 51 501 18 632 Total project cost
RBIG funding *
203 180 8 557 45 000 51 000 98 622 RBIG funding *
Counter funding
0 0 0 0 0 Counter funding
Shortfall on MTEF **
-124 490 0 6 501 -32 368 -98 622 Shortfall on MTEF **
Cumulative shortfall 0 6 501 -25 867 -124 490
Cumulative shortfall
** Although counter funding is reflected as zero, the amount of R7.079 million to be provided by NMMDM as counter funding will be included in the counter funding requirement for the balance of the project
20
WATER CONSERVATION THROUGH WAR ON LEAKS PROGRAMME
Part C
Background
• All Municipalities in the country experience high water losses. The majority are above the National Average of 36.8% and are therefore vulnerable.
• Examples of some Vulnerable Municipalities per province in terms of non-revenue water (in excess of the National Average):
No. Municipality Province
1 Makana Local Municipality Eastern Cape
2 Ndwedwe Local Municipality KwaZulu-Natal
3 Letsemeng Local Municipality Free State
4 Knysna Local Municipality Western Cape
5 Nama Khoi Local Municipality Northern Cape
6 Moses Kotane Local Municipality North West
7 Polokwane Local Municipality Limpopo
8 Emfuleni Local Municipality Gauteng
9 Emalahleni Local Municipality Mpumalanga22
Background (cont...)
23
Background (cont...)• Losses categorized as:
• Water leaks Physical leakage (Real losses)
• Non-revenue water Unbilled authorized consumption
• Unauthorized consumption
• Technical inaccuracies Commercial losses (Apparent losses)
• Administrative inaccuracies
• High water loss areas:• “Rural municipalities have a non-revenue water rate of 72.5%, while
metropolitan municipalities are averaging around 34.3% water loss. Rural municipalities have such a high water loss, despite servicing less citizens, due to poorer infrastructure.”
– Source: http://www.sablog.kpmg.co.za/2014/04/sa-needs-curb-water-wastage
–Non_revenue water levels:• Metro Municipalities - 34,3% (on average)• Mid-sized Municipalities - 30,5% - 41,3% (on average).• Small Municipalities – 72.5% (on average)– Source:
http://www.wrp.co.za/sites/default/files/event_attachments/WaterWheel_2013_1_Jan.pdf 24
Proposal on War on Leaks
15000UNEMPLOYE
DYOUTH
RECRUITMENTTRAINING
PLACEMENTS
PLUMBERS
SCIENTISTS
WAR ON LEAKS
INITIATIVES
LEAKAGE WATERCONTROL BALANCE
UNLAWFUL MAINTENANCECONNECTIONS
IDENTIFICATION
INTERVENTION
EVALUATION
Area of SupplySouth Africa
STEP 1(Recruitment and project Infrastructure setup).
STEP 2
(Initiate various initiatives national)
STEP 3(Rollout and deploy national)
25
Proposal on War on Leaks (cont...)
Real Losses (Training Programmes)
Plumbers, Graduate engineers, Asset management, Water Quality, Water
Conservation and demand Management
Real Losses (Infrastructure assessment)
Specialized Services:Infrastructure Conditional
assessment for infrastructure priorities
This will then input into Municipal IDP processes
for MIG allocation
Unbilled authorized consumption and Commercial losses
Training:Administrative on accounting- Water Balance Apprenticeship
26
Proposal on War on Leaks (cont...)
Resource Categories
Target Area Objective Value Proposition Numbers
1. Water Agents Communities Water Wise Knowledge Water ConservationPollution ReductionWater Wise GardeningSchool learning
7000
2. Plumbers Communities / Municipalities
Water Loss reductionInstallation of water-efficient devicesWater Leakage Repairswater audits; identify and repair water leaks; retrofit water fixtures, fittings and devices and undertake water conservation advocacy.
Water losses reductionSavings from reduction of physical losses
3000
3. Technicians Municipalities / Industry
Water system management ,Retrofitting, Pressure management
Water system management 1000
4. Process Controllers
Municipalities / WATSAN Sector
Water treatment and waste management Water and waste water treatment management
500
5. Scientists Municipalities / WATSAN Sector
Water / Waste management Water and waste water controls and verifications
500
6. Engineers Municipalities / WATSAN Sector
Water / waste Water Systems Design and maintenance
Water and waste water system design and maintenance, Assets Management
500
7. Post Graduates MSc
Municipalities / WATSAN Sector
Water / waste research and development Research and development in water risks
250
8. Post Graduates PhD
Municipalities / WATSAN Sector
Water / waste research and development Research and development in water risk management and solutions
250
9. Water Managers
Municipalities Develop and promote WC/WDM strategies and BPs
Management of water balance more accuratelyImproved management through sectorisation, water balance calculations and response time
2000
27
Implementation plan
28
Budget: real losses (training programme)
DESCRIPTION
Total YR-1 YR-2 YR-3 YR-4 YR-6 YR-6
Contract Staff
R94,500,000.00
R15,750,000.00 R15,750,000.00 R15,750,000.00 R15,750,000.00
R15,750,000.00
R15,750,000.00
Graduate Learner Requirement (including stipend)
R16,011,811,111.11
R5,993,572,222.22
R3,403,572,222.22
R3,403,572,222.22
R1,570,322,222.22
R1,570,322,222.22
R70,450,000.00
Overheads / Capex - RWA
R424,305,300.00
R168,479,300.00
R50,815,200.00 R50,815,200.00 R52,565,200.00
R50,815,200.00
R50,815,200.00
Total (Excluding project fees, contingences and CPI adjustment)
R16,530,616,411.11
R6,177,801,522.22
R3,470,137,422.22
R3,470,137,422.22
R1,638,637,422.22
R1,636,887,422.22
R137,015,200.00
Project management fees - 8.5% of Total
R1,405,102,394.94
R491,785,838.23
R281,020,478.99
R210,765,359.24
R140,510,239.49
R140,510,239.49
R140,510,239.49
Contingencies - 5% of Total
R896,785,940.30
R149,464,323.38
R149,464,323.38
R149,464,323.38
R149,464,323.38
R149,464,323.38
R149,464,323.38
Overall cost (excluding CPI)
R18,832,504,746.36
R6,819,051,683.84
R3,900,622,224.59
R3,830,367,104.85
R1,928,611,985.10
R1,926,861,985.10
R426,989,762.88
29
Budget: real losses (infrastructure)
• Real Losses (Infrastructure)
– This Budget should be a revolving loan, there is a
positive business plan in fixing all the leaks
• Example: Emfuleni has an estimated 37% non-
revenue water
– Roughly 15% of this is infrastructure losses
– If they buy R500,000,000 worth of water they loose
R75,000,000 on Municipal leaking infrastructure30
Funding / investment required
• Real Losses (Training Programme)
– Budget rolled over 5 - 8 years is approximately
(R18 Billion)
– Bulk of budget (Stipends, Training Costs)
• Real Losses (Infrastructure)
– Revolving loan that all municipalities will pay back
with water savings revenues (R5 Billion)
– The 1% fund can contribute to the revolving
loan fund31
Decisions under consideration
• National roll out approach
• Stakeholder identification
• Budget provisions
32