Agenda SAP MRP Overview
1
MRP Terminology Material Master MRP Views
Other Master Data
MRP Flow
MRP Run Steps
Step 1: Calculate net requirements
Step 2: Determine quantities
Step 3: Determine dates
Step 4: BOM explosion
Useful Transactions
8/3/2019 MRP Overview Scribd
2/50
2
Horizons relevant for production planning
Planning horizon: Part of the planning area, where aplanning file entry is made for the net change planning inthe planning horizon. The planning horizon is calculated inworkdays. When a material has an entry in the planningfile, it becomes relevant for MRP
Scheduling horizon: Once a planned order (for in-house
production) is in the scheduling horizon, the exactproduction dates are calculated and the capacityrequirements are created.
Rescheduling horizon: Once a planned order is in therescheduling horizon, exception messages can be created
Dispatch horizon: If a planned order or process order is inthe dispatch horizon, it becomes visible in the planningboard for sequencing on a production line.
8/3/2019 MRP Overview Scribd
3/50
3
Horizons relevant for production planning
Planning horizon => 182 days
Scheduling horizon => 120 days
Rescheduling horizon => 100 days
Dispatch horizon => 30 days
Time fence => 14 days
8/3/2019 MRP Overview Scribd
4/50
4
Creation of exception messages
Exception messages depend on the transaction being carried outand are meant to inform you of an important or critical event.
By means of the exception messages, you can easily sort out anymaterials that you need to reprocess manually. Special search andselection functions are available for this in the evaluations for MRP.
During the planning run, the system recognizes exceptionalsituations where you usually have to manually reprocess theplanning result and it records these situations as exceptionmessages. The system displays the exception messages in theevaluations for MRP.
Exception messages refer to an individual MRP element. If several
exception messages occur for one MRP element, the mostimportant ones are stored.
8/3/2019 MRP Overview Scribd
5/50
5
Creation of exception messages
Rescheduling proposals
If a material shortage exists, the system usually creates a newprocurement proposal. The rescheduling check is used to changethe dates of already existing firmed receipts not planned on thesame day as the requirement to suit the requirement date. For thispurpose, the system displays the appropriate exception messages
with rescheduling proposals for these firmed receipts to beprocessed by the MRP controller.
The rescheduling horizon (defined on MRP group) defines the timeperiods in which exception message are to be created.
There are also tolerance values which allow rescheduling ofa firm procurement proposal by MRP (defined on MRP group)
Rescheduling messages:
Bring process forward
Postpone/cancel process
8/3/2019 MRP Overview Scribd
6/50
6
Lists for evaluation
Stock/requirements list: The stock/requirements list is amethod of evaluation that gives an overview of the stock,requirements and receipt elements. This list is continuouslyupdated (except when you keep the transaction open)
MRP list: The MRP list is the same list as the stock/requirementslist, with the difference that the MRP list is not continuouslyupdated. It gives an overview of the situation as it was at themoment of the last MRP run.
8/3/2019 MRP Overview Scribd
7/50
7
Internal and external procurement
Material can be purchased externally and internally(Procurement type X)
Quota arrangements can be used to divide the procuredquantity over time in different sources of supply (internaland external)
If there are no quota arrangements, the systemautomatically switches to in-house production. MRPtherefore firstly creates planned orders, which you can thenconvert into production orders or purchase requisitions.
8/3/2019 MRP Overview Scribd
8/50
8
Procurement proposals
Procurement proposals by MRP => planned orders & purchase
requisitions Proposal determination
Procurement type:
E In house production => always planned orders
F External procurement => planned orders and purchaserequisitions
X Both types => planned orders and purchaserequisitions
MRP groups:
Z001 Finished materials => always planned orders
Z002 Raw materials => purchase requisitions in theopening period, planned orders outside opening period
Z003 Semi-finished materials => purchase requisitions inthe opening period, planned orders outside opening period
Z004 Precious metal materials => purchase requisitionsin the opening period, planned orders outside openingperiod
8/3/2019 MRP Overview Scribd
9/50
9
Planning file
The point of start for MRP is the planning file. The planning
run and scope of the planning run (which materials areplanned in which planning run) are controlled by theplanning file.
Next to the material number the planning file includes anumber of important entries:
Low level code
Net change planning indicator => if this indicator is set,this material has to be planned in the NETCH planningmode
Net change in the planning horizon indicator => if thisindicator is set, this material has to be planned in theNETPL planning mode
Reset procurement proposals => indicates that existingprocurement proposals will be deleted and recreated
Re-explode BOM => Controls the re-explosion of BOMsfor existing procurement proposals that came from thelast planning run. This indicator can be set by changesin the BOM, changes in the sales BOM, changes in thematerial classification, etc.
8/3/2019 MRP Overview Scribd
10/50
10
Low level code
In an MRP run every material is
planned separately. In order to organizethe planning in the most efficient wayevery material in a BOM is assignedwith a low level code. The lowest codematerials are planned first, then thenext level until the last level is reached.
The finished product is given a low level
code 000. The next level in the BOM isgiven a higher number. A raw materialis always the highest code possible(999), because they are planned in theend of the planning run.
If a material is used in several BOMs
so that it has more than one low levelcode, the lowest number is chosen. Inthe examples BBB has low level codes001 and 002. MRP will only startplanning BBB when it starts planningthe materials with low level code 002.
A
AAA BBB
X Y
000
999 001
999 999
B
AA BB
AAA BBB
000
999 001
999 002
X Y999 999
8/3/2019 MRP Overview Scribd
11/50
11
The days supply of a material indicates how long a material willcover requirements if you only take current plant stock intoaccount.
The first/second receipt days' supply indicates how manyworkdays a material will cover the requirements when taking
current plant stock and specific, predefined receipts into account.Days' supply 1st rcpt 2nd rcpt
Process orders + Production orders X X
Purchase orders + shipping notifications +schedule lines + schedule line deliveries X X
QM inspection lots X X
Firmed purchase requisitions XFirmed planned orders X
Assigned planned orders X
Receipt reservations X X
Shipping notifications X X
Days supply determination
8/3/2019 MRP Overview Scribd
12/50
Agenda SAP MRP Overview
12
MRP Terminology Material Master MRP Views
Other Master Data
MRP Flow
MRP Run Steps
Step 1: Calculate net requirements
Step 2: Determine quantities
Step 3: Determine dates
Step 4: BOM explosion
Useful Transactions
8/3/2019 MRP Overview Scribd
13/50
13
Material master data
MRP 1
MRP group: number of settings are defined on MRP group level=> linked to material type
Plant specific material status: Status that can be set to restrictthe usability of a material on plant-level.
MRP type: key that determines whether and how the material
is planned. Current keys that are used Reorder point: stock level that triggers a procurement element
(purchase requisition or planned order) => only used forreorder point planning (V1).
MRP controller: key to group materials in a number of listings
Lot size: key that determines how and when the quantity is tobe procured or produced is calculated
Min./max. lot size: to avoid procurement/production of toobig/small quantities
Rounding value: value to a multiple of which the system roundsup the production/procurement quantity
8/3/2019 MRP Overview Scribd
14/50
8/3/2019 MRP Overview Scribd
15/50
15
Material master data
MRP 3
Total replenishment lead time: total time needed toreplenish the stock of a material => relevant for reorderpoint planning
MRP 4
Production versions: list of all the production versionsmaintained for the material => see next slide
=> Enter storage location at entry screen
Storage location MRP indicator: Indicator to exclude
storage locations from MRP at plant level => storagelocations excluded CA04, CA05 and CA06 excluded forplanning
8/3/2019 MRP Overview Scribd
16/50
Agenda SAP MRP Overview
16
MRP Terminology Material Master MRP Views
Other Master Data
MRP Flow
MRP Run Steps
Step 1: Calculate net requirements
Step 2: Determine quantities
Step 3: Determine dates
Step 4: BOM explosion
Useful Transactions
8/3/2019 MRP Overview Scribd
17/50
17
Other master data (1/2)
Resource: After calculating the basic dates MRP will start a
scheduling process and calculate the capacity requirements,in which MRP will start calculating backwards from the basicfinish date using a scheduling formula which is taken fromthe resource.
Bill of material: A bill of material is a formally structured listof the components that make up a product or assembly.The list contains the object number of each component,together with the quantity and unit of measure.
Production version: It is possible that a material can be
produced on different production lines or productionoperations. A production version determines the variousproduction techniques that can be used to produce amaterial.
8/3/2019 MRP Overview Scribd
18/50
18
Other master data (2/2)
Master recipe: The master recipe in PP-PI describes the
production of a material in the production run. Next to theheader information, it lists the number of operations andthe component materials (BOM).
Quota arrangements: If a material can be obtained fromvarious sources of supply, each individual source of supplycan be allocated a quota arrangement. The quotaarrangement is valid for a certain period of time andspecifies exactly how the receipts are to be distributedamongst each source of supply.
Source list: List that links a material to a vendor to makeautomatic vendor determination possible.
8/3/2019 MRP Overview Scribd
19/50
Agenda SAP MRP Overview
19
MRP Terminology Material Master MRP Views
Other Master Data
MRP Flow
MRP Run Steps
Step 1: Calculate net requirements
Step 2: Determine quantities
Step 3: Determine dates
Step 4: BOM explosion
Useful Transactions
8/3/2019 MRP Overview Scribd
20/50
20
MRP Flow - Overview
In-house production
Capacityevaluation
Capacityleveling
External procurement
MRP run
Conversion of MRP proposals
MRPevaluation
8/3/2019 MRP Overview Scribd
21/50
21
MRP Flow - Parameters
MRP
External requirements:Sales orders, schedulingagreements, deliveries
Order reservations Dependent requirements Safety stock
Fixed receipts: Purchase orders Shipping notifications Process orders Firmed planned orders Firmed purchaserequisitions
Stock level
Procurement proposals Planned orders Assigned purchaserequisitions
Dependent requirementsException messages
Planningfile
8/3/2019 MRP Overview Scribd
22/50
22
MRP Flow - In-house production vs. External Procurement
Dispatch in
planning board
Planned order
MRP
Firm planned order
Collective
conversion
Process order
Firmingproposals *
Planned order
MRP
Firm purchase req.
Purchase order
Purchase requisition
Collectiveconversion
* Exceptional
In-house External Procurement
8/3/2019 MRP Overview Scribd
23/50
Agenda SAP MRP Overview
23
MRP Terminology Material Master MRP Views
Other Master Data
MRP Flow
MRP Run Steps
Step 1: Calculate net requirements
Step 2: Determine quantities
Step 3: Determine dates
Step 4: BOM explosion
Useful Transactions
8/3/2019 MRP Overview Scribd
24/50
24
MRP
Creation of proposal consists of 4 stages / steps
Calculate net requirements
Calculate quantity needed
Calculate dates: Determination of basic dates For in-house produced goods => calculation ofexact production dates and capacity requirements
Explode BOM Vendor assignment
MRP Run Steps
Result: Procurement proposals
8/3/2019 MRP Overview Scribd
25/50
25
Result: Procurement proposals
Planned orders: A planned order is sent to a plant and is an MRPrequest for the procurement of a particular material at adetermined time. It specifies when the inward material movementshould be made and the quantity of material that is expected.Planned orders can be created for in-house produced materials as
well as for externally purchased materials. Purchase requisitions: Purchase requisitions are used to give
notification of requirements of materials and/or external servicesand keep track of such requirements.
Determination of which procurement proposal to create = definedin procurement type on MRP 1 view
E: always produced in house => planned order F: always externally purchased => purchase requisition in opening
period and planned order outside opening period
8/3/2019 MRP Overview Scribd
26/50
Agenda SAP MRP Overview
26
MRP Terminology Material Master MRP Views
Other Master Data
MRP Flow
MRP Run Steps
Step 1: Calculate net requirements
Step 2: Determine quantities
Step 3: Determine dates
Step 4: BOM explosion
Useful Transactions
8/3/2019 MRP Overview Scribd
27/50
27
MRP types:
PD: standard MRP run
P3: standard MRP runwith the use of a planningtime fence
V1: ( Reorder pointplanning): a newprocurement proposal will
be created by MRP as soonas plant stock falls below aspecified stock level(reorder point).
Plant stock
+ Open order quantity (purchase orders, firmed plannedorders, firmed purchase requisitions)
- External sales quantities in replenishment lead time
= Available stock
Step 1: Calculate net requirements
8/3/2019 MRP Overview Scribd
28/50
28
Step 1: Calculate net requirements
MRP type PD
MRP calculates untill it finds a first net requirement =>completes all the next steps
First netrequirement
8/3/2019 MRP Overview Scribd
29/50
29
Step 1: Calculate net requirements
MRP type PD MRP applies the next steps to calculate the dates and
quantity of the first procurement element
MRP moves to next net requirement and applies the samesteps
First net
requirement isno longerrequirement
New first net
requirement
8/3/2019 MRP Overview Scribd
30/50
30
Step 1: Calculate net requirements
MRP type PD MRP applies the next steps to calculate the dates and
quantity of the first procurement element
MRP keeps iterating until are net requirements are handled
Second netrequirement is
no longerrequirement
8/3/2019 MRP Overview Scribd
31/50
31
Step 1: Calculate net requirements
MRP type P3
P3 uses the same logic as PD
Use of planning time fence:
MRP will not schedule planned orders inside the planningtime fence
A requirement in the planning time fence will trigger thecreation of a planned order
MRP will schedule a planned order at the end of theplanning time fence
Planned orders which are not firm, will keep gettingpushed outside of the planning time fence => fixplanned orders to avoid this
8/3/2019 MRP Overview Scribd
32/50
32
Step 1: Calculate net requirements
MRP type P3
Planned order is pushed out by MRP to end of planningtime fence
MRP RUN
8/3/2019 MRP Overview Scribd
33/50
33
Step 1: Calculate net requirements
MRP type V1
V1 only takes into account only external requirements thatlie in the replenishment lead time of the material
The otherrequirements
are not takeninto account
by MRP
8/3/2019 MRP Overview Scribd
34/50
Agenda SAP MRP Overview
34
MRP Terminology Material Master MRP Views
Other Master Data
MRP Flow
MRP Run Steps
Step 1: Calculate net requirements
Step 2: Determine quantities
Step 3: Determine dates
Step 4: BOM explosion
Useful Transactions
8/3/2019 MRP Overview Scribd
35/50
35
Step 2: Determine quantities
Lot size procedures:
EX Lot for lot order quantity: Planned orders or purchaserequisitions are planned with the same quantities as therequirements. The procurement elements are planned to beavailable on the day that they are required. This procedure can beused in combination with rounding values, maximum and minimumlot sizes.
FX: Procurement elements are only created with one fixed lot size.
If the requirement is larger than lot size, a second order/requisitionis created. The procurement elements are planned to be availableon the day of the first requirement.
MB: All requirements for 1 month are bundled into one procurementelement. The elements are planned to be ready at the 1st day ofthe month. This procedure can be used in combination with
rounding values, maximum and minimum lot sizes. WB: All requirements for 1 week are bundled into one procurementelement. The elements are planned to be ready at the 1st day ofthe month. This procedure can be used in combination withrounding values, maximum and minimum lot sizes.
8/3/2019 MRP Overview Scribd
36/50
36
Step 2: Determine quantities
Lot size procedures:
Z3 Two months lot size: All requirements for twomonths are bundled into one procurement element. Theelements are planned to be ready at the 1st day of themonth. This procedure can be used in combination withrounding values, maximum and minimum lot sizes.
Z4 Three months lot size: All requirements for threemonths are bundled into one procurement element. The
elements are planned to be ready at the 1st day of themonth. This procedure can be used in combination withrounding values, maximum and minimum lot sizes.
ZM All requirements for 1 month are bundled into oneprocurement element. The procurement elements areplanned to be available on the day of the first
requirement. This procedure can be used in combinationwith rounding values, maximum and minimum lot sizes.
ZW All requirements for 1 week are bundled into oneprocurement element. The procurement elements areplanned to be available on the day of the firstrequirement. This procedure can be used in combinationwith rounding values, maximum and minimum lot sizes.
8/3/2019 MRP Overview Scribd
37/50
37
Step 2: Determine quantities
Other elements:
Rounding value
Maximum lot size
Minimum lot size
Assembly Assembly scrap: No examples at AC
8/3/2019 MRP Overview Scribd
38/50
Agenda SAP MRP Overview
38
MRP Terminology Material Master MRP Views
Other Master Data
MRP Flow
MRP Run Steps
Step 1: Calculate net requirements
Step 2: Determine quantities
Step 3: Determine dates
Step 4: BOM explosion
Useful Transactions
8/3/2019 MRP Overview Scribd
39/50
39
Calculation of basic dates
If backwards scheduling is not possible (Start date in thepast)=> switch to today scheduling
Step 3: Determine dates In-house Production
8/3/2019 MRP Overview Scribd
40/50
40
Release date (only for process orders):
Scheduled startRelease date
Release period
Step 3: Determine dates In-house Production
8/3/2019 MRP Overview Scribd
41/50
41
Step 3: Determine dates In-house Production
Calculation of scheduled dates using resource calendar. The production version of a material can be assigned
automatically to a planned order
The production version determines which master recipe,which BOM and which resource will be used
Production time is calculated based on data maintained
in the master recipe and resource
If the basic start date is different from the scheduledstart date, the basic start date will be adjusted.
8/3/2019 MRP Overview Scribd
42/50
42
Select production version
Material master=> quota arrang.
usage indicator
Quotaarrangements
(MEQ1)
Productionversions (C223)
1/2 (no QA for MRP)
3/4 (QA relevant for MRP)
Productionversion X
Check quantities &validity dates
No quotaarrangements found
Check quantities &validity dates
Step 3: Determine In-house Production
In-house produced goods
8/3/2019 MRP Overview Scribd
43/50
43
Step 3: Determine External Procurement
External procurement Calculation of basic dates
Opening period: time buffer for converting planned orders into purchaserequisitions. The opening horizon is calculated from the planned start date of thepurchase requisition into the past, determining the opening date. (defined in thescheduling margin key)
Processing time for purchasing: average time needed by purchasing to converta purchase requisition into a purchase order (2 days for AC)
Planned delivery time: If source list exists, the entry in the material master isoverruled by the purchasing info record
Release date: Latest date to convert purchase requisition to purchase orders
8/3/2019 MRP Overview Scribd
44/50
44
Selection of source of supply
Material master=> quota arrang.usage indicator
Quotaarrangements
(MEQ1)
Source list
1/2 (no QA for MRP)
3/4 (QA relevant for MRP)
No quotaarrangements found
Vendor X
Check MRP indicatorin source list
Check MRP indicatorin source list
Step 3: Determine External Procurement
External procurement
8/3/2019 MRP Overview Scribd
45/50
45
Step 3: Determine Factory Calendar
Factory calendar
Times defined on the material master can be defined in twoways:
Calendar days => 365/366 days per year
Work days => depending on factory calendar
Factory calendar AC Burlington: Work days => 7 days per week, except public holidays
Planning calendar => not used
Resource calendar => calendar with available days of a certainresource
8/3/2019 MRP Overview Scribd
46/50
Agenda SAP MRP Overview
46
MRP Terminology
Material Master MRP Views
Other Master Data
MRP Flow
MRP Run Steps
Step 1: Calculate net requirements
Step 2: Determine quantities
Step 3: Determine dates
Step 4: BOM explosion
Useful Transactions
8/3/2019 MRP Overview Scribd
47/50
47
Step 4: BOM explosion
Select production version:
The production version of a material can be assigned automatically to aplanned order
The system will search in the quota arrangements which is the preferredproduction version. This can be based on:
Lot sizes
Quotas or percentages
Priorities If none of these are maintained, the system will take the first production
version using the alphanumeric name
Explode BOM
If a material is produced in-house, the system also calculates thedependent requirements, that is, the required quantity of componentsrequired to produce the finished product or the assembly and required
date. This is done by exploding the BOM which is defined in thepreferred production version. If a material shortage exists, plannedorders are created at every BOM level to cover requirements.
Component scrap is applied to calculate the required quantity
8/3/2019 MRP Overview Scribd
48/50
Agenda SAP MRP Overview
48
MRP Terminology
Material Master MRP Views
Other Master Data
MRP Flow
MRP Run Steps
Step 1: Calculate net requirements
Step 2: Determine quantities
Step 3: Determine dates
Step 4: BOM explosion
Useful Transactions
8/3/2019 MRP Overview Scribd
49/50
49
Useful Transactions (1/2)
MD01: Plant MRP run
MD02: Single item, multi-level MRP run
MD03: Single item, single-level MRP run
MDBT: MRP run in background*
MD20: Create planning file entries
MD21: Display planning file entries
MDAB: Setup planning file in background
MDRE: Consistency check planning file
MD04: Individual stock/requirements list
MD07: Collective stock/requirements list
MD05: Individual MRP list
MD06: Collective MRP list
MD44: Planning situation material
8/3/2019 MRP Overview Scribd
50/50
50
Useful Transactions (2/2)
MD14: Individual conversion of planned orders to purchase
requisitions MD15: Collective conversion of planned orders to purchase
requisitions
MD04/MD07: Firming of procurement proposals (exceptional case)
ME57: Collective conversion of purchase requisitions to purchase
orders CM01 Capacity load per resource
CM25 Capacity planning table (graphical)
CM29 Capacity planning table (graphical) => profile defined inparameters
COR7: Individual conversion of planned order to process order COR8: Collective conversion of planned orders to process orders
MD06/MD07: Firming of procurement proposals