    Agenda SAP MRP Overview

    1

    MRP Terminology Material Master MRP Views

    Other Master Data

    MRP Flow

    MRP Run Steps

    Step 1: Calculate net requirements

    Step 2: Determine quantities

    Step 3: Determine dates

    Step 4: BOM explosion

    Useful Transactions

  • 8/3/2019 MRP Overview Scribd

    2/50

    2

    Horizons relevant for production planning

    Planning horizon: Part of the planning area, where aplanning file entry is made for the net change planning inthe planning horizon. The planning horizon is calculated inworkdays. When a material has an entry in the planningfile, it becomes relevant for MRP

    Scheduling horizon: Once a planned order (for in-house

    production) is in the scheduling horizon, the exactproduction dates are calculated and the capacityrequirements are created.

    Rescheduling horizon: Once a planned order is in therescheduling horizon, exception messages can be created

    Dispatch horizon: If a planned order or process order is inthe dispatch horizon, it becomes visible in the planningboard for sequencing on a production line.

  • 8/3/2019 MRP Overview Scribd

    3/50

    3

    Horizons relevant for production planning

    Planning horizon => 182 days

    Scheduling horizon => 120 days

    Rescheduling horizon => 100 days

    Dispatch horizon => 30 days

    Time fence => 14 days

  • 8/3/2019 MRP Overview Scribd

    4/50

    4

    Creation of exception messages

    Exception messages depend on the transaction being carried outand are meant to inform you of an important or critical event.

    By means of the exception messages, you can easily sort out anymaterials that you need to reprocess manually. Special search andselection functions are available for this in the evaluations for MRP.

    During the planning run, the system recognizes exceptionalsituations where you usually have to manually reprocess theplanning result and it records these situations as exceptionmessages. The system displays the exception messages in theevaluations for MRP.

    Exception messages refer to an individual MRP element. If several

    exception messages occur for one MRP element, the mostimportant ones are stored.

  • 8/3/2019 MRP Overview Scribd

    5/50

    5

    Creation of exception messages

    Rescheduling proposals

    If a material shortage exists, the system usually creates a newprocurement proposal. The rescheduling check is used to changethe dates of already existing firmed receipts not planned on thesame day as the requirement to suit the requirement date. For thispurpose, the system displays the appropriate exception messages

    with rescheduling proposals for these firmed receipts to beprocessed by the MRP controller.

    The rescheduling horizon (defined on MRP group) defines the timeperiods in which exception message are to be created.

    There are also tolerance values which allow rescheduling ofa firm procurement proposal by MRP (defined on MRP group)

    Rescheduling messages:

    Bring process forward

    Postpone/cancel process

  • 8/3/2019 MRP Overview Scribd

    6/50

    6

    Lists for evaluation

    Stock/requirements list: The stock/requirements list is amethod of evaluation that gives an overview of the stock,requirements and receipt elements. This list is continuouslyupdated (except when you keep the transaction open)

    MRP list: The MRP list is the same list as the stock/requirementslist, with the difference that the MRP list is not continuouslyupdated. It gives an overview of the situation as it was at themoment of the last MRP run.

  • 8/3/2019 MRP Overview Scribd

    7/50

    7

    Internal and external procurement

    Material can be purchased externally and internally(Procurement type X)

    Quota arrangements can be used to divide the procuredquantity over time in different sources of supply (internaland external)

    If there are no quota arrangements, the systemautomatically switches to in-house production. MRPtherefore firstly creates planned orders, which you can thenconvert into production orders or purchase requisitions.

  • 8/3/2019 MRP Overview Scribd

    8/50

    8

    Procurement proposals

    Procurement proposals by MRP => planned orders & purchase

    requisitions Proposal determination

    Procurement type:

    E In house production => always planned orders

    F External procurement => planned orders and purchaserequisitions

    X Both types => planned orders and purchaserequisitions

    MRP groups:

    Z001 Finished materials => always planned orders

    Z002 Raw materials => purchase requisitions in theopening period, planned orders outside opening period

    Z003 Semi-finished materials => purchase requisitions inthe opening period, planned orders outside opening period

    Z004 Precious metal materials => purchase requisitionsin the opening period, planned orders outside openingperiod

  • 8/3/2019 MRP Overview Scribd

    9/50

    9

    Planning file

    The point of start for MRP is the planning file. The planning

    run and scope of the planning run (which materials areplanned in which planning run) are controlled by theplanning file.

    Next to the material number the planning file includes anumber of important entries:

    Low level code

    Net change planning indicator => if this indicator is set,this material has to be planned in the NETCH planningmode

    Net change in the planning horizon indicator => if thisindicator is set, this material has to be planned in theNETPL planning mode

    Reset procurement proposals => indicates that existingprocurement proposals will be deleted and recreated

    Re-explode BOM => Controls the re-explosion of BOMsfor existing procurement proposals that came from thelast planning run. This indicator can be set by changesin the BOM, changes in the sales BOM, changes in thematerial classification, etc.

  • 8/3/2019 MRP Overview Scribd

    10/50

    10

    Low level code

    In an MRP run every material is

    planned separately. In order to organizethe planning in the most efficient wayevery material in a BOM is assignedwith a low level code. The lowest codematerials are planned first, then thenext level until the last level is reached.

    The finished product is given a low level

    code 000. The next level in the BOM isgiven a higher number. A raw materialis always the highest code possible(999), because they are planned in theend of the planning run.

    If a material is used in several BOMs

    so that it has more than one low levelcode, the lowest number is chosen. Inthe examples BBB has low level codes001 and 002. MRP will only startplanning BBB when it starts planningthe materials with low level code 002.

    A

    AAA BBB

    X Y

    000

    999 001

    999 999

    B

    AA BB

    AAA BBB

    000

    999 001

    999 002

    X Y999 999

  • 8/3/2019 MRP Overview Scribd

    11/50

    11

    The days supply of a material indicates how long a material willcover requirements if you only take current plant stock intoaccount.

    The first/second receipt days' supply indicates how manyworkdays a material will cover the requirements when taking

    current plant stock and specific, predefined receipts into account.Days' supply 1st rcpt 2nd rcpt

    Process orders + Production orders X X

    Purchase orders + shipping notifications +schedule lines + schedule line deliveries X X

    QM inspection lots X X

    Firmed purchase requisitions XFirmed planned orders X

    Assigned planned orders X

    Receipt reservations X X

    Shipping notifications X X

    Days supply determination

  • 8/3/2019 MRP Overview Scribd

    12/50

    Agenda SAP MRP Overview

    12

    MRP Terminology Material Master MRP Views

    Other Master Data

    MRP Flow

    MRP Run Steps

    Step 1: Calculate net requirements

    Step 2: Determine quantities

    Step 3: Determine dates

    Step 4: BOM explosion

    Useful Transactions

  • 8/3/2019 MRP Overview Scribd

    13/50

    13

    Material master data

    MRP 1

    MRP group: number of settings are defined on MRP group level=> linked to material type

    Plant specific material status: Status that can be set to restrictthe usability of a material on plant-level.

    MRP type: key that determines whether and how the material

    is planned. Current keys that are used Reorder point: stock level that triggers a procurement element

    (purchase requisition or planned order) => only used forreorder point planning (V1).

    MRP controller: key to group materials in a number of listings

    Lot size: key that determines how and when the quantity is tobe procured or produced is calculated

    Min./max. lot size: to avoid procurement/production of toobig/small quantities

    Rounding value: value to a multiple of which the system roundsup the production/procurement quantity

  • 8/3/2019 MRP Overview Scribd

    14/50

  • 8/3/2019 MRP Overview Scribd

    15/50

    15

    Material master data

    MRP 3

    Total replenishment lead time: total time needed toreplenish the stock of a material => relevant for reorderpoint planning

    MRP 4

    Production versions: list of all the production versionsmaintained for the material => see next slide

    => Enter storage location at entry screen

    Storage location MRP indicator: Indicator to exclude

    storage locations from MRP at plant level => storagelocations excluded CA04, CA05 and CA06 excluded forplanning

  • 8/3/2019 MRP Overview Scribd

    16/50

    Agenda SAP MRP Overview

    16

    MRP Terminology Material Master MRP Views

    Other Master Data

    MRP Flow

    MRP Run Steps

    Step 1: Calculate net requirements

    Step 2: Determine quantities

    Step 3: Determine dates

    Step 4: BOM explosion

    Useful Transactions

  • 8/3/2019 MRP Overview Scribd

    17/50

    17

    Other master data (1/2)

    Resource: After calculating the basic dates MRP will start a

    scheduling process and calculate the capacity requirements,in which MRP will start calculating backwards from the basicfinish date using a scheduling formula which is taken fromthe resource.

    Bill of material: A bill of material is a formally structured listof the components that make up a product or assembly.The list contains the object number of each component,together with the quantity and unit of measure.

    Production version: It is possible that a material can be

    produced on different production lines or productionoperations. A production version determines the variousproduction techniques that can be used to produce amaterial.

  • 8/3/2019 MRP Overview Scribd

    18/50

    18

    Other master data (2/2)

    Master recipe: The master recipe in PP-PI describes the

    production of a material in the production run. Next to theheader information, it lists the number of operations andthe component materials (BOM).

    Quota arrangements: If a material can be obtained fromvarious sources of supply, each individual source of supplycan be allocated a quota arrangement. The quotaarrangement is valid for a certain period of time andspecifies exactly how the receipts are to be distributedamongst each source of supply.

    Source list: List that links a material to a vendor to makeautomatic vendor determination possible.

  • 8/3/2019 MRP Overview Scribd

    19/50

    Agenda SAP MRP Overview

    19

    MRP Terminology Material Master MRP Views

    Other Master Data

    MRP Flow

    MRP Run Steps

    Step 1: Calculate net requirements

    Step 2: Determine quantities

    Step 3: Determine dates

    Step 4: BOM explosion

    Useful Transactions

  • 8/3/2019 MRP Overview Scribd

    20/50

    20

    MRP Flow - Overview

    In-house production

    Capacityevaluation

    Capacityleveling

    External procurement

    MRP run

    Conversion of MRP proposals

    MRPevaluation

  • 8/3/2019 MRP Overview Scribd

    21/50

    21

    MRP Flow - Parameters

    MRP

    External requirements:Sales orders, schedulingagreements, deliveries

    Order reservations Dependent requirements Safety stock

    Fixed receipts: Purchase orders Shipping notifications Process orders Firmed planned orders Firmed purchaserequisitions

    Stock level

    Procurement proposals Planned orders Assigned purchaserequisitions

    Dependent requirementsException messages

    Planningfile

  • 8/3/2019 MRP Overview Scribd

    22/50

    22

    MRP Flow - In-house production vs. External Procurement

    Dispatch in

    planning board

    Planned order

    MRP

    Firm planned order

    Collective

    conversion

    Process order

    Firmingproposals *

    Planned order

    MRP

    Firm purchase req.

    Purchase order

    Purchase requisition

    Collectiveconversion

    * Exceptional

    In-house External Procurement

  • 8/3/2019 MRP Overview Scribd

    23/50

    Agenda SAP MRP Overview

    23

    MRP Terminology Material Master MRP Views

    Other Master Data

    MRP Flow

    MRP Run Steps

    Step 1: Calculate net requirements

    Step 2: Determine quantities

    Step 3: Determine dates

    Step 4: BOM explosion

    Useful Transactions

  • 8/3/2019 MRP Overview Scribd

    24/50

    24

    MRP

    Creation of proposal consists of 4 stages / steps

    Calculate net requirements

    Calculate quantity needed

    Calculate dates: Determination of basic dates For in-house produced goods => calculation ofexact production dates and capacity requirements

    Explode BOM Vendor assignment

    MRP Run Steps

    Result: Procurement proposals

  • 8/3/2019 MRP Overview Scribd

    25/50

    25

    Result: Procurement proposals

    Planned orders: A planned order is sent to a plant and is an MRPrequest for the procurement of a particular material at adetermined time. It specifies when the inward material movementshould be made and the quantity of material that is expected.Planned orders can be created for in-house produced materials as

    well as for externally purchased materials. Purchase requisitions: Purchase requisitions are used to give

    notification of requirements of materials and/or external servicesand keep track of such requirements.

    Determination of which procurement proposal to create = definedin procurement type on MRP 1 view

    E: always produced in house => planned order F: always externally purchased => purchase requisition in opening

    period and planned order outside opening period

  • 8/3/2019 MRP Overview Scribd

    26/50

    Agenda SAP MRP Overview

    26

    MRP Terminology Material Master MRP Views

    Other Master Data

    MRP Flow

    MRP Run Steps

    Step 1: Calculate net requirements

    Step 2: Determine quantities

    Step 3: Determine dates

    Step 4: BOM explosion

    Useful Transactions

  • 8/3/2019 MRP Overview Scribd

    27/50

    27

    MRP types:

    PD: standard MRP run

    P3: standard MRP runwith the use of a planningtime fence

    V1: ( Reorder pointplanning): a newprocurement proposal will

    be created by MRP as soonas plant stock falls below aspecified stock level(reorder point).

    Plant stock

    + Open order quantity (purchase orders, firmed plannedorders, firmed purchase requisitions)

    - External sales quantities in replenishment lead time

    = Available stock

    Step 1: Calculate net requirements

  • 8/3/2019 MRP Overview Scribd

    28/50

    28

    Step 1: Calculate net requirements

    MRP type PD

    MRP calculates untill it finds a first net requirement =>completes all the next steps

    First netrequirement

  • 8/3/2019 MRP Overview Scribd

    29/50

    29

    Step 1: Calculate net requirements

    MRP type PD MRP applies the next steps to calculate the dates and

    quantity of the first procurement element

    MRP moves to next net requirement and applies the samesteps

    First net

    requirement isno longerrequirement

    New first net

    requirement

  • 8/3/2019 MRP Overview Scribd

    30/50

    30

    Step 1: Calculate net requirements

    MRP type PD MRP applies the next steps to calculate the dates and

    quantity of the first procurement element

    MRP keeps iterating until are net requirements are handled

    Second netrequirement is

    no longerrequirement

  • 8/3/2019 MRP Overview Scribd

    31/50

    31

    Step 1: Calculate net requirements

    MRP type P3

    P3 uses the same logic as PD

    Use of planning time fence:

    MRP will not schedule planned orders inside the planningtime fence

    A requirement in the planning time fence will trigger thecreation of a planned order

    MRP will schedule a planned order at the end of theplanning time fence

    Planned orders which are not firm, will keep gettingpushed outside of the planning time fence => fixplanned orders to avoid this

  • 8/3/2019 MRP Overview Scribd

    32/50

    32

    Step 1: Calculate net requirements

    MRP type P3

    Planned order is pushed out by MRP to end of planningtime fence

    MRP RUN

  • 8/3/2019 MRP Overview Scribd

    33/50

    33

    Step 1: Calculate net requirements

    MRP type V1

    V1 only takes into account only external requirements thatlie in the replenishment lead time of the material

    The otherrequirements

    are not takeninto account

    by MRP

  • 8/3/2019 MRP Overview Scribd

    34/50

    Agenda SAP MRP Overview

    34

    MRP Terminology Material Master MRP Views

    Other Master Data

    MRP Flow

    MRP Run Steps

    Step 1: Calculate net requirements

    Step 2: Determine quantities

    Step 3: Determine dates

    Step 4: BOM explosion

    Useful Transactions

  • 8/3/2019 MRP Overview Scribd

    35/50

    35

    Step 2: Determine quantities

    Lot size procedures:

    EX Lot for lot order quantity: Planned orders or purchaserequisitions are planned with the same quantities as therequirements. The procurement elements are planned to beavailable on the day that they are required. This procedure can beused in combination with rounding values, maximum and minimumlot sizes.

    FX: Procurement elements are only created with one fixed lot size.

    If the requirement is larger than lot size, a second order/requisitionis created. The procurement elements are planned to be availableon the day of the first requirement.

    MB: All requirements for 1 month are bundled into one procurementelement. The elements are planned to be ready at the 1st day ofthe month. This procedure can be used in combination with

    rounding values, maximum and minimum lot sizes. WB: All requirements for 1 week are bundled into one procurementelement. The elements are planned to be ready at the 1st day ofthe month. This procedure can be used in combination withrounding values, maximum and minimum lot sizes.

  • 8/3/2019 MRP Overview Scribd

    36/50

    36

    Step 2: Determine quantities

    Lot size procedures:

    Z3 Two months lot size: All requirements for twomonths are bundled into one procurement element. Theelements are planned to be ready at the 1st day of themonth. This procedure can be used in combination withrounding values, maximum and minimum lot sizes.

    Z4 Three months lot size: All requirements for threemonths are bundled into one procurement element. The

    elements are planned to be ready at the 1st day of themonth. This procedure can be used in combination withrounding values, maximum and minimum lot sizes.

    ZM All requirements for 1 month are bundled into oneprocurement element. The procurement elements areplanned to be available on the day of the first

    requirement. This procedure can be used in combinationwith rounding values, maximum and minimum lot sizes.

    ZW All requirements for 1 week are bundled into oneprocurement element. The procurement elements areplanned to be available on the day of the firstrequirement. This procedure can be used in combinationwith rounding values, maximum and minimum lot sizes.

  • 8/3/2019 MRP Overview Scribd

    37/50

    37

    Step 2: Determine quantities

    Other elements:

    Rounding value

    Maximum lot size

    Minimum lot size

    Assembly Assembly scrap: No examples at AC

  • 8/3/2019 MRP Overview Scribd

    38/50

    Agenda SAP MRP Overview

    38

    MRP Terminology Material Master MRP Views

    Other Master Data

    MRP Flow

    MRP Run Steps

    Step 1: Calculate net requirements

    Step 2: Determine quantities

    Step 3: Determine dates

    Step 4: BOM explosion

    Useful Transactions

  • 8/3/2019 MRP Overview Scribd

    39/50

    39

    Calculation of basic dates

    If backwards scheduling is not possible (Start date in thepast)=> switch to today scheduling

    Step 3: Determine dates In-house Production

  • 8/3/2019 MRP Overview Scribd

    40/50

    40

    Release date (only for process orders):

    Scheduled startRelease date

    Release period

    Step 3: Determine dates In-house Production

  • 8/3/2019 MRP Overview Scribd

    41/50

    41

    Step 3: Determine dates In-house Production

    Calculation of scheduled dates using resource calendar. The production version of a material can be assigned

    automatically to a planned order

    The production version determines which master recipe,which BOM and which resource will be used

    Production time is calculated based on data maintained

    in the master recipe and resource

    If the basic start date is different from the scheduledstart date, the basic start date will be adjusted.

  • 8/3/2019 MRP Overview Scribd

    42/50

    42

    Select production version

    Material master=> quota arrang.

    usage indicator

    Quotaarrangements

    (MEQ1)

    Productionversions (C223)

    1/2 (no QA for MRP)

    3/4 (QA relevant for MRP)

    Productionversion X

    Check quantities &validity dates

    No quotaarrangements found

    Check quantities &validity dates

    Step 3: Determine In-house Production

    In-house produced goods

  • 8/3/2019 MRP Overview Scribd

    43/50

    43

    Step 3: Determine External Procurement

    External procurement Calculation of basic dates

    Opening period: time buffer for converting planned orders into purchaserequisitions. The opening horizon is calculated from the planned start date of thepurchase requisition into the past, determining the opening date. (defined in thescheduling margin key)

    Processing time for purchasing: average time needed by purchasing to converta purchase requisition into a purchase order (2 days for AC)

    Planned delivery time: If source list exists, the entry in the material master isoverruled by the purchasing info record

    Release date: Latest date to convert purchase requisition to purchase orders

  • 8/3/2019 MRP Overview Scribd

    44/50

    44

    Selection of source of supply

    Material master=> quota arrang.usage indicator

    Quotaarrangements

    (MEQ1)

    Source list

    1/2 (no QA for MRP)

    3/4 (QA relevant for MRP)

    No quotaarrangements found

    Vendor X

    Check MRP indicatorin source list

    Check MRP indicatorin source list

    Step 3: Determine External Procurement

    External procurement

  • 8/3/2019 MRP Overview Scribd

    45/50

    45

    Step 3: Determine Factory Calendar

    Factory calendar

    Times defined on the material master can be defined in twoways:

    Calendar days => 365/366 days per year

    Work days => depending on factory calendar

    Factory calendar AC Burlington: Work days => 7 days per week, except public holidays

    Planning calendar => not used

    Resource calendar => calendar with available days of a certainresource

  • 8/3/2019 MRP Overview Scribd

    46/50

    Agenda SAP MRP Overview

    46

    MRP Terminology

    Material Master MRP Views

    Other Master Data

    MRP Flow

    MRP Run Steps

    Step 1: Calculate net requirements

    Step 2: Determine quantities

    Step 3: Determine dates

    Step 4: BOM explosion

    Useful Transactions

  • 8/3/2019 MRP Overview Scribd

    47/50

    47

    Step 4: BOM explosion

    Select production version:

    The production version of a material can be assigned automatically to aplanned order

    The system will search in the quota arrangements which is the preferredproduction version. This can be based on:

    Lot sizes

    Quotas or percentages

    Priorities If none of these are maintained, the system will take the first production

    version using the alphanumeric name

    Explode BOM

    If a material is produced in-house, the system also calculates thedependent requirements, that is, the required quantity of componentsrequired to produce the finished product or the assembly and required

    date. This is done by exploding the BOM which is defined in thepreferred production version. If a material shortage exists, plannedorders are created at every BOM level to cover requirements.

    Component scrap is applied to calculate the required quantity

  • 8/3/2019 MRP Overview Scribd

    48/50

    Agenda SAP MRP Overview

    48

    MRP Terminology

    Material Master MRP Views

    Other Master Data

    MRP Flow

    MRP Run Steps

    Step 1: Calculate net requirements

    Step 2: Determine quantities

    Step 3: Determine dates

    Step 4: BOM explosion

    Useful Transactions

  • 8/3/2019 MRP Overview Scribd

    49/50

    49

    Useful Transactions (1/2)

    MD01: Plant MRP run

    MD02: Single item, multi-level MRP run

    MD03: Single item, single-level MRP run

    MDBT: MRP run in background*

    MD20: Create planning file entries

    MD21: Display planning file entries

    MDAB: Setup planning file in background

    MDRE: Consistency check planning file

    MD04: Individual stock/requirements list

    MD07: Collective stock/requirements list

    MD05: Individual MRP list

    MD06: Collective MRP list

    MD44: Planning situation material

  • 8/3/2019 MRP Overview Scribd

    50/50

    50

    Useful Transactions (2/2)

    MD14: Individual conversion of planned orders to purchase

    requisitions MD15: Collective conversion of planned orders to purchase

    requisitions

    MD04/MD07: Firming of procurement proposals (exceptional case)

    ME57: Collective conversion of purchase requisitions to purchase

    orders CM01 Capacity load per resource

    CM25 Capacity planning table (graphical)

    CM29 Capacity planning table (graphical) => profile defined inparameters

    COR7: Individual conversion of planned order to process order COR8: Collective conversion of planned orders to process orders

    MD06/MD07: Firming of procurement proposals