MRP Systems. MRP – Material Requirements Planning Commonly used method in industry to coordinate the production scheduling of end items and their associated sub components. Ford’s MRP systems is known as CMMS, c ommon m anufacturing m anagement s ystem. MRP Systems. - PowerPoint PPT Presentation
Popular Tags:
23
MRP Systems MRP – Material Requirements Planning Commonly used method in industry to coordinate the production scheduling of end items and their associated sub components. Ford’s MRP systems is known as CMMS, c ommon m anufacturing m anagement s ystem.
Transcript
Page 1: MRP Systems

MRP Systems

MRP – Material Requirements Planning

Commonly used method in industry to coordinate the production scheduling of end items and their associated sub components.

Ford’s MRP systems is known as CMMS, common manufacturing management system.

Page 2: MRP Systems

MRP Systems

End Item – final product that is to be shipped from the manufacturing facility (engine by engine code, replacement engine blocks, replacement crankshafts, etc…)

General Idea: A desired production date for end-items is known, the inventory level of all components and sub-assemblies required by the end-item is known, the lead time to produce the subcomponents or delivery time of supplied parts is known, therefore scheduled the production of any shortfall of parts and subcomponents at a point in time to support the desired production date of the end-item.

Page 3: MRP Systems

MRP Systems

Required information to support an MRP system:

• Master Production Schedule (MPS)

• Bill of Material (BOM)

• Inventory Status Records by each part or component

• Lead times

• Item master data

Page 4: MRP Systems

MRP Systems

Master Production Schedule (MPS): Planned production quantities for end-items in each time period of the planning horizon.

Planning horizon – length of time over which to plan the production schedule. This length of time must exceed the cumulative lead time to replenish an end-item through all production stages.

Time period (or time bucket) – smallest unit of time in which end-item production is schedule. In practice, time buckets of one week are typical used.

Page 5: MRP Systems

MRP Systems

Master Production Schedule (MPS):

Example

Production of 1000 no. 12468 staplers is planned for weeks 1, 2, and 3, followed by no more stapler production until week 6 in which 1500 staplers will be produced.

Product: personal stapler no. 124681 2 3 4 5 6

Planned order releases 1000 1000 1000 0 0 1500

Week

Page 6: MRP Systems

MRP Systems

Bill of Material (BOM): A listing of all components required for each end-item.

Example – personal stapler no. 12468. This stapler is assembled from 3 sub-assemblies.

Insert Figure

Page 7: MRP Systems

MRP Systems

Inventory Status Records: Dynamic information about the current level of inventory for all components designated in the BOM of each end item. In practice, accurate inventory levels are difficult to maintain.

Example Component Inventory StatusTop Assembly 1212Spring Assembly 1150Locator Plate 146Slide Pin 558

Page 8: MRP Systems

MRP Systems

Lead Times: the time from when an order to replenish a part is initiated until the part becomes available for use.Lead times in practice are variable, but for the MPS, a fixed value is applied, usually the mean plus some safety factor.

Example Component Lead Time (weeks)Top Assembly 1Spring Assembly 1Locator Plate 2Slide Pin 1

Page 9: MRP Systems

MRP Systems

Item Master Data - unique data for each part or component. This data includes:

• unique part number• annual demand• nominal order quantity• cost• scrap rate• production lead time• resource requirements• pointers to engineering drawings (if produced internally)• vendor information (if purchased)• etc…

Page 10: MRP Systems

MRP Systems

Requirements explosion and order release plan:

Example – order release plan for personal stapler no. 12468

Level One Planning – Top Assembly

0 1 2 3 4 5 6Top Assembly: Lead time = 1Gross Requirements 1000 1000 1000 1500Scheduled Receipts(Projected) On-hand 1212 212Net Requirements 788 1000 1500Planned Order Releases 788 1000 1500

Week

Page 11: MRP Systems

MRP Systems

Requirements explosion and order release plan:

Example – order release plan for personal stapler no. 12468

Level One Planning – Spring Assembly

0 1 2 3 4 5 6Spring Assembly: Lead time = 1Gross Requirements 1000 1000 1000 1500Scheduled Receipts(Projected) On-hand 1150 150Net Requirements 850 1000 1500Planned Order Releases 850 1000 1500

Week

Page 12: MRP Systems

MRP SystemsRequirements explosion and order release plan:

Ex. – order release plan for personal stapler no. 12468, an order for 750 locator plates is expected to arrive early in week 1

* The 892 units released in week 1 will not arrive till week 3 unless some expedited actions occur

Level Two Planning – Spring Assembly

0 1 2 3 4 5 6Locator Plate: Lead time = 2Gross Requirements 788 1000 1500 Scheduled Receipts 750(Projected) On-hand 146 108Net Requirements 892 1500 Planned Order Releases 892* 1500

Week

Page 13: MRP Systems

MRP SystemsRequirements explosion and order release plan:

Ex. – order release plan for personal stapler no. 12468, a batch of 650 slide pins is just about complete.

Level Two Planning – Spring Assembly

0 1 2 3 4 5 6Slide Pins: Lead time = 1Gross Requirements 850 1000 1500 Scheduled Receipts 650(Projected) On-hand 558 358Net Requirements 642 1500 Planned Order Releases 642 1500

Week

Page 14: MRP Systems

MRP Systems

Recall the requirements explosion and order release plan from Ex. – order release plan for personal stapler no. 12468

How might you allow for quality losses and or demand variability and lead-time variability?

0 1 2 3 4 5 6Top Assembly: Lead time = 1Gross Requirements 1000 1000 1000 1500Scheduled Receipts(Projected) On-hand 1212 212Net Requirements 788 1000 1500Planned Order Releases 788 1000 1500

Week

Page 15: MRP Systems

MRP SystemsScrap losses – recall on the item master data record, quality yield is a field which has been populated using historical data or a “guess”. If yield for the stapler top assembly is say 90%, then more units should be planned for release than are required for the planned end-items according to:

Ex. If there is a 90% yield for for top assembly then:

0 1 2 3 4 5 6Top Assembly: Lead time = 1Gross Requirements 1000 1000 1000 1500Scheduled Receipts(Projected) On-hand 1212 212Net Requirements 788 1000 1500Planned Order Releases 876 1111 1667Yeild = 90%

yield

reqnetreleaseorder

.

Page 16: MRP Systems

MRP SystemsSafety Stock and Safety Lead Time – to protect against demand variability and lead time variablity, a safety factor may be applied. Numerous application a safety factors exist, the simplest may be multiply by some percentage. Ex. If a 15% safety factor has been identified for top assembly then:

0 1 2 3 4 5 6Top Assembly: Lead time = 1Gross Requirements 1000 1000 1000 1500Scheduled Receipts(Projected) On-hand 1212 212Net Requirements 788 1000 1500Planned Order Releases 906 1150 1725Safety facotr = 15%

Page 17: MRP Systems

MRP Systems

Rough-Cut Capacity Planning:

When developing an MPS, one must consider if the schedule is feasible based on the capacity of workcenters within the plant.

This is performed by determining the number of hours impact on all workcenters required to produce the end item, and identified by “time bucket”.

Page 18: MRP Systems

MRP Systems

Rough-Cut Capacity Planning:

For example, suppose for every unit of end item “A” that is planned for production, the following workcenters are impacted:

Insert figure

Part C has a 2-week lead time, and uses both workcenter 200 and 300. Part D consists of part E which requires WC 300 and part F (a purchased component).

Page 19: MRP Systems

MRP SystemsRough-Cut Capacity Planning:

An aggregated, time phased profile for end item A and another end item B is shown below.

Insert fig

Page 20: MRP Systems

MRP SystemsRough-Cut Capacity Planning:

Given a master production schedule for the facility: 

And the time-phased load profile, results in the total resource requirements

End Item 1 2 3 4 5 6A 50 75 25 50 200B 75 125 100 150

Period

Workcenter -1 0 1 2 3 4 5 6100 6.25 3.75 7.5 7.5 10 7.5200 20 32.5 42.5 55 50 70 30300 18.75 41.25 33.75 63.75 67.5 52.5 45

Period

Page 21: MRP Systems

MRP SystemsRough-Cut Capacity Planning:

Given this rough cut capacity plan, and the knowledge that you operate a single shift 10 hours a day, and 6 days a week, do you foresee a problem? If so, how might you adjust?

Workcenter -1 0 1 2 3 4 5 6100 6.25 3.75 7.5 7.5 10 7.5200 20 32.5 42.5 55 50 70 30300 18.75 41.25 33.75 63.75 67.5 52.5 45

Period

Page 22: MRP Systems

MRP SystemsCapacity Requirements Planning (CRP):

Similar to rough cut capacity planning, but includes details such as current inventory levels and the impact of lot-sizing decisions.

Ex. Assume initial inventory levels:

Then net MPS becomes:

On-Hand InventoryA 100B 125

End Item 1 2 3 4 5 6A 25 25 50 200B 75 100 150

Period

Page 23: MRP Systems

MRP SystemsCapacity Requirements Planning:

From the net MPS, the workstation loading levels by part:

Therefore capacity plan is:

Are there any concerns?

0 1 2 3 4 5 6WC100-A 1.25 1.25 2.5 3 12 10 0WC200-A 0 5 7.5 22.5 0 0 0WC300-A 0 3.75 7.5 11.25 45 20 0WC100-B 0 3.75 5 0 37.5 30 0WC200-B 0 0 15 35 7.5 0 30WC300-B 0 0 22.5 41.25 20 30 22.5

Period

0 1 2 3 4 5 6WC100 1.25 5 7.5 3 49.5 40 0WC200 0 5 22.5 57.5 7.5 0 30WC300 0 3.75 30 52.5 65 50 22.5

Period


Recommended