Cost Management
PAN-AFRICAN INSTITUTE OF PROFESSIONAL STUDIES. Email: [email protected] Page 1
Section 9Managing Project Costs.
8/10/2019 msproject 9
2/14
Cost Management
PAN-AFRICAN INSTITUTE OF PROFESSIONAL STUDIES. Email: [email protected] Page 2
Section Objectives
Upon completion of section 9, you will be able to:
Define the types of costs Understand Cost Calculations
Apply Overtime using the Overtime Rate
View the Cost Table
Input Fixed Costs
Apply Rate increases and decreases
Setup new Rate Tables
Obtain a general understanding of budget resources
8/10/2019 msproject 9
3/14
Cost Management
PAN-AFRICAN INSTITUTE OF PROFESSIONAL STUDIES. Email: [email protected] Page 3
Cost Categories
The types of costs you are most likely to encounter for Project Management are listed in the
table below. Although most field in Microsoft Project can be entered in many different ways,
the most often used table or view if provided in the Usually defined in column, and only servesas a quick guide.
Type of Cost Usually defined In
Standard Resource sheet
Overtime Resource sheet
Cost per Use Resource sheet
Fixed Costs Cost Table
Variable Costs Resource Information Form
Standard, Overtime and cost per Use have all been discussed in the Resource Management
Section. This Section will cover Fixed cost, and Variable Costs.
Fixed Costs
The fixed cost field displays any task expense that is non-labour (non-labour) related. This field
is manually entered.
Fixed Cost Accrual
You can accrue fixed costs
At the start of a task, once a task has commenced (any amount of progress has been
entered)
At the end of a task, once the task if 100% complete
Or pro-rated as the task progresses the cost will be calculated accordingly
To Access the Fixed Cost Field
8/10/2019 msproject 9
4/14
Cost Management
PAN-AFRICAN INSTITUTE OF PROFESSIONAL STUDIES. Email: [email protected] Page 4
Click on View, and Table
Choose the Cost Table
The cost table appears
Entering Fixed Cost Information
8/10/2019 msproject 9
5/14
Cost Management
PAN-AFRICAN INSTITUTE OF PROFESSIONAL STUDIES. Email: [email protected] Page 5
Click in the Fixed cost cell for the appropriate task, and type in the costs (this is a
currency field therefore you do not need to enter the dollar sign, or there decimal)
Click in the Accrue column, and choose the appropriate accrual method.
Exercise:
1. Enter the amount of $20,000 in the fixed cost cell for reinforcing site, and leave theaccrual as Pro-rated.
Note: how the Total cost, the Reinforcing summary phase, and the project summary task line
are also recalculated as a result of this fixed cost being added into the cost table.
Cost Rate Tables
There two components to the Cost Rate Tables Form
a) Establish pay increase at specific dates throughout the project
A resource will receive rate increases (or decreases) at specific dates, and this rate
needs to be accounted for, to accurately track the project costs. If a task crosses through
the line where the new rate takes effect, then the part of the task prior to the effective
date will be costed at the current rate, and the task after the effective date of the
increase or decrease would be costed at the new rate. Once entered the program takes
care of the calculations automatically.
b) Establish Different rates for one resource
A resource assigned to more than one task, and different types of work, may charge a
different rate dependent on the task. A task may require more technical knowledge,
may be dependent on the task. A task may require more technical knowledge, may be
more dangerous to perform, or may require working in very challenging environment
circumstances. To handle the various costs for one resource, Microsoft Project provides
5 different rate tables (Rate table A (default), B, C,D,E).
To set up a rate increase or Decrease
Double clickon the resources name in the resource sheet view
Choosethe Cost Tab
8/10/2019 msproject 9
6/14
Cost Management
PAN-AFRICAN INSTITUTE OF PROFESSIONAL STUDIES. Email: [email protected] Page 6
Cost Rate Table A is the default, and is cross referencing the resource sheet to pick up the
standard and overtime rates, and Per Use Cost, where applicable.
To input a new rate, click in the second row, pick an effective date (if no date is chosen
the rate will be commence at the beginning of the project)
You can enter the actual new amount, or a percentage (i.e +/- 10%) if you enter a
percent, when you hit enter or click in another cell, MS Project will calculate the actual
value of the increase or decrease.
Click on the Ok button
8/10/2019 msproject 9
7/14
Cost Management
PAN-AFRICAN INSTITUTE OF PROFESSIONAL STUDIES. Email: [email protected] Page 7
Note: Rate increase and decreases can be entered in any rate table
To establish a New Rate Table
Double clickon the resources name in the resource sheet
Choose a different rate table(B to E). Notice there is no cross-reference to the resource
sheet.
Type in the new rate (standard, overtime, and/or per Use Cost ), and the appropriate
effective date
Click on the Ok button
Exercise:
a) Setup a rate increase of 10% for project engineer (no effective date is required)
b) Set Up a new rate table (B), and input project engineer new salary as $100,000 per
year.
8/10/2019 msproject 9
8/14
Cost Management
PAN-AFRICAN INSTITUTE OF PROFESSIONAL STUDIES. Email: [email protected] Page 8
Budget Resources
A new function in Microsoft Project 2007 is the ability to create a budget for your project.
As this function requires considerable customization and application of fields in the database,exercise would be applied in an advanced training program. However as this is new, a general
overview of the function is provided in this two day class, to assist you in understanding if
budgets resources could be helpful to you for future projects.
At the end of this section, the author has provided their comments on using the function.
Create A Budget for Your Project
Five steps are required to create a project budget
1. Create a budget resource
A budget resource defines the maximum capacity for the project to consume
money work or the material units. Budget must be applied at the project level
(assigning a budget resource to the project summery task). The project summary
task represents the overall project budget (including resources costs, work and
materials that have been defined in the project)/
2. Assign the Budget Resource to Summary Task Line
This assign the budget resources to the entire project
3. Enter a value amount for the budget resources
Input the data(values) for the budget resources
4. Categorize the costs according to the budget type
Identify the other resources to track and monitor against the overall budget
resources (group them by budget type)
5. Group the resources, and compare them against the budget amounts.
Step 1- Create a Budget Resources
We will create two budget resources
Budget Travel
Budget Accommodation
Note: The names you provide for budget resources helps to distinguish them from other type ofresources when you do step 4 (categorized them)
Exercise:
Step 1Create the budget resources
8/10/2019 msproject 9
9/14
Cost Management
PAN-AFRICAN INSTITUTE OF PROFESSIONAL STUDIES. Email: [email protected] Page 9
Choose the Resource Sheet View
Create the budget resource (travel and Accommodation)
Choose the type of cost (the following information is now defined)
Double click on the travel resource (you will see the Resource Information dialogue box)
Activate the Budget selection box
Do the same for Accommodation.
Step 2Assign the budget resources to the Project Summary Task
Select the Gantt Chart view
8/10/2019 msproject 9
10/14
Cost Management
PAN-AFRICAN INSTITUTE OF PROFESSIONAL STUDIES. Email: [email protected] Page 10
Make sure theproject summary taskline is showing at the top of the task name column
if it is not, choose tools, option and the View Tab. In the outline option section, activate
the show project summary task box and then click Ok
Assign the two budget resource to the project summary task line (by using the AssignDialogue shortcut button on the standard toolbar)
Note: If you have a long list of resources in the assignment dialogue box, you can filter the
resources for budget resources only.
8/10/2019 msproject 9
11/14
Cost Management
PAN-AFRICAN INSTITUTE OF PROFESSIONAL STUDIES. Email: [email protected] Page 11
Step 3Enter values for the budget resources
Choose the Resource Usage view
Insert two new columns Budget Cost, and Budget Work fields (if appropriate) right
click on the resource name row.
You must now enter the budget values for each appropriate resource.
8/10/2019 msproject 9
12/14
Cost Management
PAN-AFRICAN INSTITUTE OF PROFESSIONAL STUDIES. Email: [email protected] Page 12
Enter the value of the travel ($4000, 00) and accommodation ($1500, 00), in the line for the
project summary task field (see below).
.
When you hit enter or click away from the cost cell, the value will rill up to the resource line for
travel and Accommodation.
Step 4- Categorize the Resource Costs according to their budget type
Create a custom text field that identified words or phrase for each of the budget types,
you can then compare them to the overall budget.
Choose the Resource Sheet View
Insert a new customized text column and name it Budget Type
Name the type as Expenses for each budget resource (as you see above)
8/10/2019 msproject 9
13/14
Cost Management
PAN-AFRICAN INSTITUTE OF PROFESSIONAL STUDIES. Email: [email protected] Page 13
Step 5Group the Resources
In the Resource Usage view
Choose the Project menu, and click on Group by, and Customize Group by:
The Customize Group by dialogue box will appear
Choose the custom field name that you created in step 4
8/10/2019 msproject 9
14/14
Cost Management
PAN-AFRICAN INSTITUTE OF PROFESSIONAL STUDIES. Email: [email protected] Page 14
And click Ok
Notice the group Expenses in the resource name column (notice the cell background is
hilited)
Authors comments:
Overall, this function can be helpful for total management of the work and the costs of a
project. It is the authors opinion that it takes considerable effort to set up the fields to
categorize, to group, to baseline and finally to insure that all work and cost are entered and
accounted for. I would have preferred that this function be more intuitive than it is. I am not
sure that for the amount of work in the set up, that enough value is provided that could not be
found in default table and reports already in the program. That being said I did set up a sample
scenario where all costs were identified, and some of you may find that you like the at a
glance view of you project health.