Date post: | 24-May-2015 |
Category: |
Real Estate |
Upload: | manjumyhome |
View: | 1,008 times |
Download: | 0 times |
Project Progress – 09thDec,2013
STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 09.12.13
1.1st To 12th Floor Slabs: Completed2.13th Floor Slab : Flat No 1 & 2 flats Slab completed, 4&5 flats Slab planning Today,3rd flats Shuttering work In progress
3.Brick Work: 7th Floor Floor External walls in Progress
STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 09.12.13
1.1st To 12th Floor Slabs : Completed2.13th Floor Slab : Except 3rd flat Slab Remain all flats Slabs completed , 3rd flat shuttering work in progress
3.Brick Work: 8th Floor External walls in Progress
STATUS REPORT OF MY HOME ABHRA Tower-”C” As On 09.12.13
1.1st To 10th Floor Slabs : Completed
2. Brick Work: 6th Floor External walls in Progress
STATUS REPORT OF MY HOME ABHRA Tower-”D” As On 09.12.13
1.1st To 13th Floor Slabs : Completed2.14th Floor Slab : Flat No 1 and 2 slabs Complete Today ,4 and 5 flat Slabs Shuttering Work Progress,3rd Flat Columns work
In Progress3.Brick Work: 8th Floor External walls in Progress
STATUS REPORT OF MY HOME ABHRA Tower-”E” As On 09.12.13
1.1st To 13th Floor Slabs : Completed2.14th Floor Slab : Flat No 1&2 Slab Completed ,4 & 5 flats Bar bending work Progress, 3rd Flat Columns work in
Progress .3. Brick Work: 8th Floor External walls in Progress