Project Progress – 21st Feb,2014
STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 21.02.14
1.1St Floor To 17th Floor Slabs Completed
STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 21.02.14
1.1st Floor To 17th Floor Slabs Completed
STATUS REPORT OF MY HOME ABHRA Tower-”C” As On 21.02.14
1.1St Floor To 15th Floor Slabs Completed
STATUS REPORT OF MY HOME ABHRA Tower-”D” As On 21.02.14
1.1St Floor To 17th Floor Slabs Completed
STATUS REPORT OF MY HOME ABHRA Tower-”E” As On 21.02.14
1.1St Floor To 17th Floor Slabs Completed