315_11-HerbWeedControl.xlsx CRP-Riparian-Wetland
Payment Schedule Results
315
Payment Schedule Development Methodology
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$118.17$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$1.17$0.00$0.00
Scenario Code
3151
PracticeCost Share Program
Practice Code
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $58.50Herbaceous Weed Control CRP-Riparian or Wetland Areas
CRP
Equipment/InstallationMaterials
Forgone Income
$0.00$45.00$13.50
0%0%0%50%
$90.00$27.00
50%50%
$58.50$0.00$0.00$0.00$0.00$0.00$0.00
50%
0%0%
1 of 200
315_11-HerbWeedControl.xlsx CRP-Riparian-Wetland
Practice Cost Data
Materials per Acre
Equipment/Installation per AcreEquipment/Installation costs included with the cost of Materials
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
$0.00
$1.17
Units Price/Unit Total Cost
$0.00
$90.00
Source: FY10 USDA-NRCS Program Payment Database
$1,350.00
Notes
1%
Total CostUnits
Price/Unit$27.00
0%
15 $90.00
Cost Summary:
Equipment/Labor/Mobilization
Cost Summary:
15 $405.00
15 $1,350.00Units Total Cost
MCM 1/
$117.00
$118.17
$0.00
None.
None
$0.00
$0.00
$0.00
None.
None.
Notes
5%1
Acre
Herbaceous Weed Control includes the use of appropriate treatment sequence/measures as defined in Range and Pasture Tech Note 20 "Quick Guide to Invasive Plant Treatment" as appropriate to control invasive herbaceous plants. The typical scenario for appropriate control measures is implemented on approximately 15 acres of riparian land in the riparian corridor in order to control herbaceous invasive species (i.e. Reeds canary grass, phragmites, and purple loosestrife). An operation and maintenance plan (including scouting, follow-up treatments and other IPM strategies after initial treatment measures such as grazing, spot treatments and other appropriate techniques) will also be developed.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
$27.00Total Cost$405.00
Unit for Cost Estimate
UnitsChemical 15
Source: FY10 USDA-NRCS Program Payment Database
2 of 200
315_11-HerbWeedControl.xlsx CRP-Grass Seedings
Payment Schedule Results
315
Payment Schedule Development Methodology
$9.79$0.00$0.00$0.00$0.00$0.00
Forgone Income
$0.00$0.00
0%0%
Total CostAdministration & Permit CostsRisk
$19.57$0.00$0.00
$9.50
0%0%0%50%
$0.00$19.00
Acre $9.79Herbaceous Weed Control CRP-Grass Seedings
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$0.57$0.00
$0.2950%
50%
$0.00$0.00$0.00
Scenario Code
3152
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
MobilizationLabor
50%
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & Maintenance
3 of 200
315_11-HerbWeedControl.xlsx CRP-Grass Seedings
Practice Cost Data
Materials per Acre
Equipment/Installation per AcreEquipment/Installation costs included with the cost of Materials
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
$19.00Total Cost$2,470.00 Source: FY10 USDA-NRCS
Program Payment Database
5%1
Acre
Herbaceous Weed Control includes the use of appropriate post emergent weed control measures on newly seeded herbaceous/grass seedings including between tree or shrub rows within 12 months of plantings. The typical scenario is used for controlling herbaceous weeds threatening a stand of grass on 130 acres. An appropriate operation and maintenance plan (including scouting, follow-up treatments and other IPM strategies) will be developed after initial treatment measures for ongoing weed control needs.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
6/
$19.00
$19.57
$0.00
None.
None
$0.00
$0.00
$0.00
None.
0%
Total CostUnits
Price/Unit$19.00
3%
None.
130 $2,470.00
$0.57
$0.00
$0.00
$0.00
Cost Summary:
UnitsWeed Control in Grass Seedings 130
Notes
4 of 200
315_11-HerbWeedControl.xlsx CRP-Upland (Non-Cropland)
Payment Schedule Results
315
Payment Schedule Development Methodology
0%0%
$9.79$0.00$0.00
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$19.57$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.00$0.57$0.00
Scenario Code
3153
PracticeCost Share Program
Practice Code
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $9.79Herbaceous Weed Control CRP-Upland (Non-Cropland)
Equipment/InstallationMaterials
Forgone Income
$0.00$0.00$9.50
0%0%0%50%
$0.00$19.00
$0.00$0.00$0.00$0.29
50%50%50%
5 of 200
315_11-HerbWeedControl.xlsx CRP-Upland (Non-Cropland)
Practice Cost Data
Materials per Acre
Equipment/Installation per AcreEquipment/Installation costs included with the cost of Materials
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
$0.00
$0.00
Cost Summary: Notes
None.
160 $3,040.00
$0.57
$0.00
Total CostUnits
3%
6/
$19.00
$19.57
$0.00
None.
None
$0.00
$0.00
$0.00
None.
0%
$19.00Total Cost$3,040.00
Unit for Cost Estimate
UnitsChemical Application 160
5%1
Acre
Price/Unit$19.00
Source: FY10 USDA-NRCS Program Payment Database
Herbaceous Weed Control includes the use of appropriate burn-down herbicide treatments targeting control of undesirable herbaceous plants such as bromegrass, bluegrass or other undesirable species threatening native plant communities as appropriate. Herbaceous weed control will be implemented in a fashion that will maintain and enhance desirable plants such as Big bluestem, Indiangrass, Sideoats grama and other native plants on range, pasturelands, and permanent hayland where the composition of the undesirable plants is excessive and is compromising grassland health and where grazing, forage harvest or mechanical treatments alone will not attain the desired plant community. An operation and maintenance plan (including scouting, spot treatments, early grazing/haying, and other treatment strategies) will be developed after initial treatment measures for ongoing weed control needs. Prescribed Grazing, Forage Harvest Management or Upland Wildlife Habitat Management is a required component with this practice and must be designed to control/manage the invasive plant and improve native plant communities. Typical size is 160 acres. Requires record keeping.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
6 of 200
332_11-ContourBuffers.xlsx CRP-Contour Buffer
Payment Schedule Results
332
Payment Schedule Development Methodology
Nebraska
0%0%
50%
0%0%0%50%
Risk
$0.00
$237.79$0.00$0.00
$108.54Forgone Income
Total CostAdministration & Permit Costs
Payment Rate
Unit TypeScenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$1.22$6.10$0.00
Scenario Code3321
PracticeCost Share Program
Practice Code
CRP
Cost Category
Acre
$3.0550% $0.00
Cost/Unit
$64.02Contour Buffer CRP-Contour Buffers
CRP Program Payment Rate
$0.00
$64.02$0.00$0.00$0.00$0.00
CRP Producer Payment Rate
Equipment/InstallationMaterials $52.7250%
$16.50$105.44
$8.25
7 of 200
332_11-ContourBuffers.xlsx CRP-Contour Buffer
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per AcreMobilization
Total Materials, Equipment/Installation and Labor Costs. per AcreOperation & Maintenance
Total Materials, Equipment/Installation and Labor Costs. per AcreAcquisition of Technical Knowledge
per AcreForgone Income
Unit per AcreBefore (Corn-Soybeans)
BuBu $108.54
After (Buffer)Bu $0.00
Source: University of Nebraska Crop BudgetsRisk
per AcreAdministration & Permit Costs
per AcreTotal Cost Estimate: per Acre
Associated Practices:CP15 A/B
$121.94
$237.79$0.00
None.
None
$0.00
$108.54
$0.00None.
Crop Rotation Production C
Crop Crop Gross Net
Corn (following S )
$346.72
Units
Total Cost NotesGrass Seeding (G13)
Cost Summary: Notes
5%
1 $105.44
$6.10
$0.00
$16.50
$1.22
Units Price/Unit Total Cost1 $16.50 $16.50
1%
Cost Summary:1 $16.50
Units
Source: FY10 USDA-NRCS Program Payment Database
Acre
The typical application of this practice is applying buffer strips to 20% of the field's hillslope. On an 80-acre field with 40 acres within the field with an acceptable slope for this practice will result in removing 8 acres from cropland and converting it to grass/herbaceous cover. In most cases the converted cropland will be suitible for haying or incidental grazing. This practice includes all seedbed preparation, seed and seeding. The seed mixture used to establish the price is shown below under materials, however, any mixture that is appropriate for the geopgraphic location and meets NRCS practice standards is acceptable.
Nebraska
Typical Practice Scenario
Unit for Cost EstimateGeographic Area
$16.52$5.98$8.99$6.84$7.73
Discount Rate (%/Year) 5%
$105.44Total Cost$22.21 Source: Vendor Quotes,
September 2010
$23.95
$13.68$8.50
$9.57
Practice Life (Years) 10
$14.94
$12.59
Price/Unit
25.76
$6.94
Illinois bundleflower
Indiangrass
1.45
UnitsBig bluestem 3.20
Western wheatgrassSideoats grama
1.601.402.001.10Switchgrass
Maximillian sunflower 0.58Total Cost
$3.45 125 $431.25 $84.53Soybeans (following
C )$233.86 $9.16 40 $366.40 $132.54
Buffer $0.00 $0.00 0 $0.00 $0.00
8 of 200
340_11-CoverCrop.xlsx CRP-Cover Crop
Payment Schedule Results
340
Payment Schedule Development Methodology
$12.0050%$34.50$24.00
$30.71$0.00$0.00
Acre $30.71Cover Crop CRP-Cover Crop
$1.46
$0.00
$0.00$17.25
$0.00$0.00
CRP Producer Payment RateCost Category
Materials
0%0%
50%
0%
CRP Program Payment RateCost/Unit
0%0%
50%50%$0.00
Equipment/Installation
$2.93
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$62.01$0.00$0.00$0.00Forgone Income
CRP
Payment Rate
Unit TypeScenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.59
Scenario Code3401
PracticeCost Share Program
Practice Code
9 of 200
340_11-CoverCrop.xlsx CRP-Cover Crop
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
Source: FY109 USDA-NRCS Program Payment Database
Total Cost
Grass SeedingCost Summary:
$660.00Mechanical Site Preparation 40 $18.00 $720.00
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost EstimateGeographic Area
5%1
Acre
This practice includes the seed, seed bed preparation, and the seeding of a summer annual cover crop to protect the soil during critical erosion periods, and provide desired cover according to the 340-Cover Crop Standard and the 550DP-Herbaceous Seeding Design Procedures in preparation for a grass planting. The typical application is 40 acres of cropland.
Nebraska
Total Cost Notes
$24.00Total Cost$960.00 Source: Vendor Quotes,
September 2010
UnitsSorghum-Sudan seed mixture 800
Price/Unit$1.20
2/
$58.50
$62.01
$0.00
None.
$0.00
$34.50
Cost Summary: Notes
40 $16.50
40 $1,380.00Units
None
$0.00
$0.00
$0.00
Total CostUnits
Price/Unit
None.
None.
40 $960.00
$2.93
$0.59
Units
5%
1%
10 of 200
342_11-CriticalAreaPlanting.xlsx CRP-Native-Introduced Mix
Payment Schedule Results
342
Payment Schedule Development Methodology
Equipment/InstallationMaterials $22.3850%
$1.9850%
$0.00$200.00Forgone Income
$34.50$44.75
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.79$3.96$0.00
$41.61$0.00$0.00$0.00
$0.00$17.25
$0.00$0.00
Payment Rate
Unit Type
ScenarioScenario Code
3421
PracticeCost Share Program
Practice Code
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $41.61Critical Area Planting CRP-Native-Introduced Mix
Nebraska
0%0%
50%
0%0%0%50%
Total CostAdministration & Permit CostsRisk
$0.00
$284.01$0.00
11 of 200
342_11-CriticalAreaPlanting.xlsx CRP-Native-Introduced Mix
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
5%15
Acre
Critical Area Planting of 3 acres on environmentally sensitive land using a mixture of Smooth bromegrass and Switchgrass.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost Estimate
CP8A; 3/
$79.25
$284.01
$0.00
None.
None
$0.00
Geographic Area
$0.00
$34.50
Cost Summary:
UnitsSmooth bromegrass 11
Notes
$44.75Total Cost
Site Preparation 1 $18.00 $18.00
$7.73 $23.19Switchgrass
$200.00
$0.00
1%
Total CostUnits
Total Cost
Grass Seeding 1 $16.50 $16.50
5%
Cost Summary:1 $34.50
Units Total Cost Notes
Source: FY10 USDA-NRCS Program Payment Database
One acre taken out of production, assuming a corn-soybean crop rotation minus the value of an occassional hay/forage crop from the cover crop.
Price/Unit$1.96
None.
1 $44.75
$3.96
$0.79
Units Price/Unit
$21.56 Source: FY10 USDA-NRCS Program Payment Database3
12 of 200
342_11-CriticalAreaPlanting.xlsx CRP-Native Mix
Payment Schedule Results
342
Payment Schedule Development Methodology
Nebraska
Scenario Code
3422
PracticeCost Share Program
Practice Code
CRP
Payment Rate
Unit Type
Scenario
Acre $68.93Critical Area Planting CRP-Native Mix
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$34.50$96.80
$68.93$0.00
$0.00$17.25
$1.31$6.56$0.00
$0.00$0.00
Risk
$0.00
$339.18$0.00$0.00
$200.00Forgone Income $0.00$0.00
Equipment/InstallationMaterials $48.4050%
$3.2850%
0%0%
50%
0%0%0%50%
Total CostAdministration & Permit Costs
13 of 200
342_11-CriticalAreaPlanting.xlsx CRP-Native Mix
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
Cost Summary:
Total Cost
Grass Seeding 1 $16.50 $16.50
5%
CP8A; 3/
$131.30
$339.18
$0.00
None.
None
$0.00
$200.00
$0.00
One acre taken out of production, assuming a corn-soybean crop rotation minus the value of an occassional hay/forage crop from the cover crop.
1%
None.
$6.56
$1.31
UnitsWestern wheatgrass 9.50
Notes
$96.80Total Cost$56.81
Source: FY10 USDA-NRCS Program Payment Database
Total CostUnits
Price/Unit$5.98
1.703.20
1 $96.80
Units
$0.00
$34.50
5%15
Acre
Critical Area Planting of 3 acres on environmentally sensitive land using a mixture of Western wheatgrass, Switchgrass, Big bluestem, and Sideoats grama.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost EstimateGeographic Area
Cost Summary: Units Total Cost Notes
$2.32 $4.64Red clover 2.00
Site Preparation 1 $18.00 $18.00
1 $34.50
Source: FY10 USDA-NRCS Program Payment Database
Price/Unit
$7.73$6.94
$13.14$22.21
SwitchgrassBig bluestem
14 of 200
356_11-Dike.xlsx CRP-Wetland Dike
Payment Schedule Results
356
Payment Schedule Development Methodology
$3.12$0.00$0.00$0.00$0.00$0.00$0.15
50%Equipment/Installation
0%0%
Materials
Forgone Income
$0.00$0.00$2.98
0%0%0%50%
$0.00$5.95
50%50%
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
LF $3.12Dike CRP-Wetland Dike
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$6.55$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.30$0.30$0.00
Scenario Code
3561
PracticeCost Share Program
Practice Code
15 of 200
356_11-Dike.xlsx CRP-Wetland Dike
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
5%20LF
This practice includes construction of a 800-feet long dike for water level control which is less than 6-foot in height above ground. This practice does not apply to dikes for flood protection.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost EstimateGeographic Area
$5.95Total Cost$4,760.00 Source: FY10 USDA-NRCS
Program Payment Database
5%
$0.00
$0.00
Cost Summary:
UnitsEarthfill, Class C Compaction (E02) CY 2800
Notes
CP9; CP23/A; CP27; CP30; 3/
$5.95
$6.55
$0.00
None.
None
$0.00
$0.00
$0.00
None. Minimal land taken out of production.
$0.305%
Total CostUnits
Price/Unit$1.70
None.
800 $4,760.00
$0.30
16 of 200
362_11-Diversion.xlsx CRP-Crop-Range Applications
Payment Schedule Results
362
Payment Schedule Development Methodology
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
Scenario Code
3621
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
$0.03
50%$1.70
0%0%0%50%
$0.00$3.40
LF $1.75Diversion CRP-Crop-Range Application
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$0.10$0.00
$0.0550%
50%
$0.00$0.00
$1.75$0.00$0.00$0.00$0.00$0.00
Forgone Income
$0.00$0.00
0%0%
Total CostAdministration & Permit CostsRisk
$3.54$0.00$0.00
17 of 200
362_11-Diversion.xlsx CRP-Crop-Range Applications
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:CP9; CP21; CP23/A; CP27; CP29; CP30; 3/
$3.40
$3.54
$0.00
None.
None.
1,200 $4,080.00
$0.10
$0.03
None
$0.00
$0.00
$0.00
None.
Total Cost$4,080.00 Source: FY09 USDA-NRCS
Program Payment Database
1%
Total CostUnits
Price/Unit$1.20
$0.00
$0.00
Cost Summary:
UnitsEarthfill-Class C Compaction (E02) 3400
Notes
$3.40
3%
LF
An embankment constructed to divert water away from farmsteads, gullies, critical erosion areas or constuction areas. Can also be used to collect and direct runoff and protect terrace systems. The typical application of this practice scenario is 1,200 linear foot of embankment.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
18 of 200
380_11-WindbreakEstablishment.xlsx CRP-Trees with Mulch-Limited SP
Payment Schedule Results
380
Payment Schedule Development Methodology
Nebraska
0%0%
50%
0%0%0%50%
Total CostAdministration & Permit CostsRisk
$0.00
$1.04$0.00$0.00$0.01
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.09$0.02$0.00
Scenario Code
3801
PracticeCost Share Program
Practice Code
CRP
50%
50%
LF
Equipment/InstallationMaterials
Forgone Income
$0.46
$0.47Windbreak/Shelterbelt Establishment
CRP-Trees with Mulch or APDs-Limited Site Prep
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$0.00$0.92
$0.47$0.00$0.00$0.00$0.00$0.00$0.01$0.00$0.00
19 of 200
380_11-WindbreakEstablishment.xlsx CRP-Trees with Mulch-Limited SP
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:CP5A; CP16A; CP17A; 4/
$0.92
$1.04
$0.00
None.
None
$0.00
$0.01
$0.00
Loss of production on approximately 1 acre of cropland (1 acre x $130/acr
2%
Total CostUnits
Price/Unit$0.27$0.65 $1,950.00
None.
3,000 $2,760.00
$0.02
$0.09Includes the costs to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
10%
Geographic Area
$0.00
$0.00
Cost Summary:
UnitsTrees (bare root & machine plant) TS03 3000
Notes
$0.92
Fabric mulch or Animal Protection Device 3000
Total Cost$810.00 Source: FY10 USDA-NRCS
Program Payment Database
5%25LF
This practice includes limited site preparation, planting, grass and seeding (if required), trees and fabric mulch or animal protection devices for a 3,000-feet windbreak, which includes five rows of trees, each row 600-feet long. Limited site preparation is defined as planting directly into cover crop, crop stubble or tilled crop stubble (includes fields that have residue tilled or shredded prior to planting.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost Estimate
20 of 200
380_11-WindbreakEstablishment.xlsx CRP-Trees with Mulch-Complex SP
Payment Schedule Results
380
Payment Schedule Development Methodology
$0.53$0.00$0.00$0.00$0.00$0.00
50%
Forgone Income 0%0%
$0.02$0.00
Total CostAdministration & Permit CostsRisk
$0.00
$1.16$0.00$0.00$0.01
0%
Cost Category
$0.0150%
Equipment/InstallationMaterials
LF
$0.00$0.06$0.46
$0.53
$0.11$0.92
0%
50%
0%50%
Nebraska
Scenario Code
3802
PracticeCost Share Program
Practice Code
CRP Windbreak/Shelterbelt Establishment
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.10
CRP-Trees with Mulch or APDs-Complex Site Prep
CRP Producer Payment RateCRP Program Payment RateCost/Unit
21 of 200
380_11-WindbreakEstablishment.xlsx CRP-Trees with Mulch-Complex SP
Practice Cost Data
Materials per LF
Equipment/Installation per LF
Labor per LFLabor costs included with the cost of Equipment/Installation.
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & Maintenanceper LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
10%
$330.00
Cost Summary: Units Total Cost Notes3,000 $330.00
2%
Source: FY10 USDA-NRCS Program Payment Database
3000 $0.11
Fabric mulch or Animal Protection Device 3000
5%25LF
This practice includes complex site preparation, planting, grass and seeding (if required), trees and fabric mulch or animal protection devices for a 3,000-feet windbreak, which includes five rows of trees, each row 600-feet long. Complex site preparation includes residue management measures such as residue removal, shredding, raking, etc. and the application of burn down herbicides to kill sod, alfalfa or other perennial vegetation.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost EstimateGeographic Area
UnitsTrees (bare root & machine plant) TS03 3000
Notes
$0.92Total Cost
Source: FY10 USDA-NRCS Program Payment Database
Price/Unit$0.27 $810.00
Total CostUnits
$1,950.00$0.65
Cost Summary:3,000 $2,760.00
Units Price/Unit Total CostSite Preparation for Trees (TS02)
$0.00
$0.11
CP5A; CP16A; CP17A; 4/
$1.03
$1.16
$0.00
None.
None
$0.00
$0.01
$0.00
Loss of production on approximately 1 acre of cropland (1 acre x $130/acr
None.
$0.02
$0.10Total Materials, Equipment/Installation & Labor Costs. Includes the cost to controlcompetitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
22 of 200
380_11-WindbreakEstablishment.xlsx CRP-Trees wo Mulch-Limited SP
Payment Schedule Results
380
Payment Schedule Development Methodology
$0.27
$0.14$0.00$0.00$0.00$0.00$0.00$0.00
50%50%
50%
$0.00$0.01
0%0%
50%
0%0%0%
$0.00
LF
Equipment/InstallationMaterials
Forgone Income
$0.00$0.00$0.14
Scenario Code
3803
PracticeCost Share Program
Practice Code
CRP
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.03$0.01$0.00
Nebraska
$0.14Windbreak/Shelterbelt Establishment
CRP-Trees with Mulch or APDs-Limited Site Prep
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Total CostAdministration & Permit CostsRisk
$0.00
$0.31$0.00
23 of 200
380_11-WindbreakEstablishment.xlsx CRP-Trees wo Mulch-Limited SP
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LF
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
10%
5%25LF
This practice includes limited site preparation, planting, grass and seeding (if required), and trees for a 3,000-feet windbreak, which includes five rows of trees, each row 600-feet long. Limited site preparation is defined as planting directly into cover crop, crop stubble or tilled crop stubble (includes fields that have residue tilled or shredded prior to planting.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost EstimateGeographic Area
$0.00
$0.00
Cost Summary:
UnitsTrees (bare root & machine plant) TS03 3000
Notes
$0.27Total Cost$810.00 Source: FY10 USDA-NRCS
Program Payment Database
2%
Total CostUnits
Price/Unit$0.27
CP5A; CP16A; CP17A; 4/
$0.27
$0.31
$0.00
None.
None
$0.00
$0.01
$0.00
Loss of production on approximately 1 acre of cropland (1 acre x $130/acr
None.
3,000 $810.00
$0.01
$0.03Includes the costs to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
24 of 200
380_11-WindbreakEstablishment.xlsx CRP-Trees wo Mulch-Complex SP
Payment Schedule Results
380
Payment Schedule Development Methodology
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$0.44$0.00$0.00$0.01
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.04$0.01
Forgone Income
0%0%
50%50%
Scenario Code
3804
PracticeCost Share Program
Practice Code
CRP
$0.06$0.14
$0.11$0.27
CRP Producer Payment RateCRP Program Payment RateCost/Unit
$0.00
Cost Category
LF $0.19Windbreak/Shelterbelt Establishment
CRP-Trees with Mulch or APDs-Complex Site Prep
Equipment/InstallationMaterials
$0.19$0.00$0.00$0.00$0.00$0.00$0.00
50% $0.00
0%0%0%50%
25 of 200
380_11-WindbreakEstablishment.xlsx CRP-Trees wo Mulch-Complex SP
Practice Cost Data
Materials per LF
Equipment/Installation per LF
Labor per LFLabor costs are included with the cost of Equipment/Installation.
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:CP5A; CP16A; CP17A; 4/
$0.38
$0.44
$0.00
None.
None
$0.00
$0.01
$0.00
Loss of production on approximately 1 acre of cropland (1 acre x $130/acr
Includes the costs to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
None.
$0.01
$0.04
2%
Total CostUnits
Price/Unit$0.27
3000
$0.00
$0.11
Cost Summary:
UnitsTrees (bare root & machine plant) TS03 3000
Notes
$0.11 Source: FY10 USDA-NRCS Program Payment Database
Notes3,000
Price/Unit Total CostSite Preparation for Trees (TS02)
5%25LF
This practice includes complex site preparation, planting, grass and seeding (if required), and trees for a 3,000-feet windbreak, which includes five rows of trees, each row 600-feet long. Complex site preparation includes residue management measures such as residue removal, shredding, raking, etc. and the application of burn down herbicides to kill sod, alfalfa or other perennial vegetation.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost EstimateGeographic Area
$0.27Total Cost$810.00 Source: FY10 USDA-NRCS
Program Payment Database
10%
$330.00
Cost Summary: Units Total Cost$330.00
3,000 $810.00
Units
26 of 200
380_11-WindbreakEstablishment.xlsx CRP-Replants
Payment Schedule Results
380
Payment Schedule Development Methodology
Nebraska
0%0%
50%
0%0%0%50%
Total CostAdministration & Permit CostsRisk
$0.00
$2.26$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.20$0.06$0.00
Scenario Code
3805
PracticeCost Share Program
Practice Code
CRP
50%
50%
Each
Equipment/InstallationMaterials
Forgone Income
$1.00
$1.03Windbreak/Shelterbelt Establishment
CRP-Replants
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$0.00$2.00
$1.03$0.00$0.00$0.00$0.00$0.00$0.03$0.00$0.00
27 of 200
380_11-WindbreakEstablishment.xlsx CRP-Replants
Practice Cost Data
Materials per Each
Equipment/Installation per EachEquipment/Installation costs included with the cost of Materials
Labor per Each
Total Materials, Equipment/Installation and Labor Costs: per Each
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Each
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Each
Acquisition of Technical Knowledgeper Each
Forgone Incomeper Each
Riskper Each
Administration & Permit Costsper Each
Total Cost Estimate: per Each
Associated Practices:CP5A; CP16A; CP17A;
$2.00
$2.26
$0.00
None.
None
$0.00
$0.00
$0.00
None
3%
Total CostUnits
Price/Unit$2.00
None.
1 $2.00
$0.06
$0.20Includes the costs to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
10%
Geographic Area
$0.00
$0.00
Cost Summary:
UnitsTrees & Hand Planting (weight avg TS11 & TS 1
Notes
$2.00Total Cost
$2.00 Source: FY10 USDA-NRCS Program Payment Database
5%25
Each
This practice includes the replanting of select trees due to death or damage of the seedlings following an initial windbreak/shelterbelt establishment.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost Estimate
28 of 200
382_11-Fence.xlsx CRP-Electric
Payment Schedule Results
382
Payment Schedule Development Methodology
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
Scenario Code
3821
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
$0.01
50%$0.50
0%0%0%50%
$0.00$1.00
LF $0.53Fence CRP-Electric Fence
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$0.05$0.00
$0.0350%
50%
$0.00$0.00
$0.53$0.00$0.00$0.00$0.00$0.00
Forgone Income
$0.00$0.00
0%0%
Total CostAdministration & Permit CostsRisk
$1.06$0.00$0.00
29 of 200
382_11-Fence.xlsx CRP-Electric
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:CP9; CP22; CP23/A; CP25; CP27; CP29; CP30
$1.00
$1.06
$0.00
Reduced risk, better livestock control
None.
5,280 $5,280.00
$0.05
$0.01
None
$0.00
$0.00
$0.00
None.
Total Cost$5,280.00 Source: FY10 USDA-NRCS
Program Payment Database
1%
Total CostUnits
Price/Unit$1.00
$0.00
$0.00
Cost Summary:
UnitsFence-Permanent Electric 5280
Notes
$1.00
5%
5%20LF
One mile of high-tensiel electric fence. Used in conjunction with a rotational grazing system.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
30 of 200
382_11-Fence.xlsx CRP-Barbed Wire
Payment Schedule Results
382
Payment Schedule Development Methodology
$0.74$0.00$0.00$0.00$0.00$0.00$0.04
50%Equipment/Installation
0%0%
Materials
Forgone Income
$0.00$0.00$0.70
0%0%0%50%
$0.00$1.40
50%50%
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
LF $0.74Fence CRP-Barbed Wire
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$1.48$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.01$0.07$0.00
Scenario Code
3822
PracticeCost Share Program
Practice Code
31 of 200
382_11-Fence.xlsx CRP-Barbed Wire
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
5%20LF
One mile of barbed wire fence. Used in conjunction with a rotational grazing system.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost EstimateGeographic Area
$1.40Total Cost$7,392.00 Source: FY10 USDA-NRCS
Program Payment Database
5%
$0.00
$0.00
Cost Summary:
UnitsFence-Standard, suspension (F01) 5280
Notes
CP9; CP22; CP23/A; CP25; CP27; CP29; CP30
$1.40
$1.48
$0.00
Reduced risk, better livestock control
None
$0.00
$0.00
$0.00
None.
$0.011%
Total CostUnits
Price/Unit$1.40
None.
5,280 $7,392.00
$0.07
32 of 200
382_11-Fence.xlsx CRP-Woven Wire
Payment Schedule Results
382
Payment Schedule Development Methodology
PracticeCost Share Program
Practice Code
$1.20$0.00$0.00
Nebraska
LF $1.20Fence CRP-Woven Wire
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Scenario Code
3823
Risk
$0.00
$0.45$0.00$0.70
0%0%0%50%
50%
50%
$0.00Acquisition of Tech. KnowledgeOperation & MaintenanceMobilization
$0.00$0.06
$0.00
CRP
Payment Rate
Unit Type
Scenario
Equipment/InstallationMaterials
Forgone Income
0%0%
50%
$2.43$0.00$0.00$0.00
Labor
$0.02$0.11$0.90$0.00$1.39
Total CostAdministration & Permit Costs
33 of 200
382_11-Fence.xlsx CRP-Woven Wire
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LF
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
1%
Total CostUnits
Fence Installation 5280 $0.90
None.
5,280 $7,339.20
$0.11
$0.02
Total Cost$4,752.00 Source: FY10 USDA-NRCS
Program Payment Database
$0.90
$0.00
Notes
CP9; CP22; CP23/A; CP25; CP27; CP29; CP30
$2.29
$2.43
$0.00
Reduced risk, better livestock control
None
$0.00
$0.00
$0.00
None.
5%
Units Price/Unit
Cost Summary:
$1.39Total Cost$7,339.20 Source: FY10 USDA-NRCS
Program Payment Database
Price/Unit$1.39
UnitsFence-Woven Wire 5280
5%20LF
One mile of barbed wire fence. Used in conjunction with a rotational grazing system.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost EstimateGeographic Area
34 of 200
386_11-FieldBorder.xlsx CRP-High Diversity Mixture
Payment Schedule Results
386
Payment Schedule Development Methodology
Nebraska
0%0%
50%
Risk
$0.00
$278.34$0.00$0.00
$175.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
Scenario Code
3862
PracticeCost Share Program
Practice Code
CRP
Total CostAdministration & Permit Costs
$16.50$82.87 50%
50%
0%0%0%
50%
Acre
Equipment/InstallationMaterials
Forgone Income
$0.00$8.25
$41.44
$51.18Field Border CRP-High Diversity for Wildlife
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$1.49$2.98$0.00
$0.99
$51.18$0.00$0.00$0.00$0.00$0.00
35 of 200
386_11-FieldBorder.xlsx CRP-High Diversity Mixture
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
$175.00
$0.00
1%
Total CostUnits
$0.99
Units Price/Unit
One acre of cropland taken out of production. Assuming a corn-soybean rotation minus the value of an occasional hay/forage crop from herbaceous cover crop.
None.
1 $82.87
$2.98
Total Cost
3%
Grass Seeding (G13) 1
CP33
$99.37
$278.34
$0.00
None.
Geographic Area
$0.00
$16.50
Cost Summary:
UnitsLittle bluestem 0.9
Notes
$82.87Total Cost
16.520.12
Illinois bundleflower 1.21
$16.50 $16.50
Grayhead coneflower
Big bluestem
None
$0.00
Acre
This practice includes a 30-foot wide field border consisting of a high diversity mixture of grass and forb species planted around a 160 acre field to protect water quality. This scenario is aimed at those seedings in which a high diversity of species is seeded to attract certain wildlife species. It is used as part of a conservation system to capture sediment and agricultural nutrients/chemicals. This includes all seedbed preparation, seeding, and seed to implement this practice. The seed mixture used to establish the cost is shown below under materials, however, any mixture that is appropriate for the geographic location and meets NRCS practice standards can be used.
Nebraska
Typical Practice Scenario
Unit for Cost Estimate
23.85White prairieclover 0.19 $4.53
Source: FY10 USDA-NRCS Program Payment Database
$1.55
Practice Life (Years)Discount Rate (%/Year)
$10.93 $9.84Price/Unit
Western wheatgrass
$19.99
105%
Showy partridgepea 1.45 11.68 $16.94
$3.43$28.62
Sideoats grama0.81.2
Indiangrass 0.8$6.94$8.99 Source: Vendor Quotes,
September 2010
Switchgrass0.8 $5.98 $4.780.2
$5.55$10.79
$6.84 $5.477.73
36 of 200
386_11-FieldBorder.xlsx CRP-Low Density Mixture
Payment Schedule Results
386
Payment Schedule Development Methodology
$23.11
$0.000%0%
Risk 0%Forgone Income
$221.67$0.00$0.00
$175.00
Total CostAdministration & Permit Costs
Labor
Scenario Code
3863
Practice
$0.00
$0.00
Materials $28.38
50%
50%$16.50
$0.45
Nebraska
0%
Acre $23.11Field Border CRP-Low Density for Wildlife Mixture
CRP Producer Payment RateCRP Program Payment RateCost/Unit
Cost Share Program
Practice Code
$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
CRP
Cost Category
$0.00$8.25
$14.19
0%
$1.35
Equipment/Installation50%
$0.6750%
$0.00Acquisition of Tech. KnowledgeOperation & MaintenanceMobilization
37 of 200
386_11-FieldBorder.xlsx CRP-Low Density Mixture
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
$6.61Notes
2.32Red clover
Units
Showy partridgepea 0.40
Crimson clover
$16.5211.68
Cost Summary:
Grass Seeding (G13) $16.50
Total Cost
0.100.20
Illinois bundleflower 0.40
$0.640.200.60
0.20$10.93$6.73
$0.46
White prairieclover 0.17 23.85
10Discount Rate (%/Year) 5%
$16.50Units Price/Unit Total Cost
$28.381
$28.38
Source: Vendor Quotes, September 2010
$2.19$4.04
$3.19
$3.21
$4.67
$5.39
$4.05$0.32
UnitsSideoats grama 0.60
Price/Unit$8.99
Acre
This practice includes a 30-foot wide field border planted around a 160 acre field to protect water quality and provide habitat to bobwhite quail. It is used as part of a conservation system to capture sediment and agricultural nutrients/chemicals. This system will be seeded at 10 PLS in order to provide brood-rearing habitat preferred by bobwhite quail. This includes all seedbed preparation, seeding, and seed. The seed mixture used to establish the cost is shown below under Materials, however, any mixture that is appropriate for the geographic location and meets NRCS practice standards can be used.
Nebraska
Typical Practice Scenario
Geographic AreaUnit for Cost Estimate
Practice Life (Years)
Total Cost
1% $0.45
$1.353%
Canada wildryeLittle bluestemAlfalfa
CP33
$16.50
$16.50
$0.00
$44.88
$221.67
$0.00
None.
None
$0.00
$175.00One acre of cropland taken out of production. Assuming a corn-soybean rotation minus the value of an occassional hay/forage crop from herbaceous cover crop.
$0.00None.
Cost Summary:
Source: FY10 USDA-NRCS Program Payment Database
1Units Total Cost Notes
1
38 of 200
390_11-RiparianHerbCover.xlsx CRP-Native Seed Mixture
Payment Schedule Results
390
Payment Schedule Development Methodology
$52.72
0%0%0%50%
$52.50$105.44
Acre $81.34Riparian Herbaceous Cover CRP-Native Seed Mixture
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$4.74$0.00
$2.3750%
$0.00$0.00$0.00
Forgone Income
$0.00$26.25
$81.34$0.00$0.00
Administration & Permit CostsRisk
$0.00
$242.42$0.00$0.00$75.00
50%
Scenario Code
3901
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$4.74
0%0%
50%
Total Cost
39 of 200
390_11-RiparianHerbCover.xlsx CRP-Native Seed Mixture
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per AcreMobilization
Total Materials, Equipment/Installation and Labor Costs. per AcreOperation & Maintenance
Total Materials, Equipment/Installation and Labor Costs. per AcreAcquisition of Technical Knowledge
per AcreForgone Income
per AcreRisk
per AcreAdministration & Permit Costs
per AcreTotal Cost Estimate: per Acre
Associated Practices:
Units Total Cost NotesGrass Seeding 1 $16.50 $16.50
Cost Summary:
UnitsBig bluestem 3.20
Notes
5%10
Acre
This practice is intended to convert an existing, undesirable vegetation community adjacent to a stream or waterbody to a diverse vegetation community which will provide the function of a filter strip. It includes the seedbed preparation, seeding and seed for seeding a riparian area to native herbaceous species. The seed mixture used to establish the cost is shown under Materials below, however, any mixture which is appropriate for the geopgraphic area and meets NRCS practice standards may be used. Complex site preparation includes residue management measures such as residue removal, shredding, raking, etc. and the application of burn down herbicides to kill sod, alfalfa or other perennial vegetation.The typical application of this practice is three acres.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Unit for Cost EstimateGeographic Area
Switchgrass
1.45
2.00
Total Cost$22.21
$14.94
Source: Vendor Quotes, September 2010
$6.84
Western wheatgrass 1.60
$7.73
$23.95
$13.68$8.50
$16.52
$8.99 $12.595.98 $9.57
$105.44
1.10
Sideoats grama 1.40
3%
CP29; CP30
$157.94
$242.42$0.00
None.
None
$0.00
$75.00
$0.00
3%
Total CostUnits
Price/Unit
25.76
$6.94
Illinois bundleflower
Indiangrass
Maximillian sunflower 0.58
3 acres of riparian grazing taken out of production.
None.
1 $105.44
$4.74
$4.74
Units Price/Unit Total Cost
$0.00
$52.50
Source: FY10 USDA-NRCS Program Payment
Database
Mechanical Seedbed Prep 1 $18.00 $18.00Chemical Seedbed Prep 1 $18.00 $18.00
Cost Summary:1 $52.50
40 of 200
Payment Schedule Results
391
Payment Schedule Development Methodology
Acre $663.29Riparian Forest Buffer CRP-Trees with Mulch or Animal Protection Devices
Equipment/InstallationMaterials
Forgone Income
$0.00$17.25$633.03
0%0%0%50%
$34.50$1,266.06
$0.00$0.00$0.00
Cost Category
$663.29$0.00$0.00
Labor
$65.03$26.01$0.00
$13.0150%
Scenario Code
3911
PracticeCost Share Program
Practice Code
CRP
50%
CRP Producer Payment RateCRP Program Payment RateCost/Unit
Nebraska
0%0%
50%
Total CostAdministration & Permit CostsRisk
$0.00
$1,391.60$0.00$0.00$0.00
Payment Rate
Unit TypeScenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilization
41 of 200
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
Grass Seeding 1 $16.50 $16.50Source: FY10 USDA-NRCS Program Payment Database
Trees & Machine PlantingWeed Control for trees or APD 640 $544.00
$672.00$1.05
Practice Life (Years)
$25.19 $2.52
1.80
Blackeyed Susan 0.05Upright coneflower
Big bluestem
$0.85
23.85 $4.05White prairieclover 0.17
Source: FY10 USDA-NRCS Program Payment
Database and Vendor Quotes, September 2010
0.10
$6.94$10.93
$1.39$19.67
Price/Unit$8.99
Total Cost$21.58
$17.02 $0.85
15Discount Rate (%/Year)Acre
This practice includes the planting of trees with simple site preparation, with fabric mulch or animal protection devices. Site preparation includes chemical application to kill undesirable plant species. The planting would include approximately 320 small shrubs, 220 large trees and small shrubs, and 100 large trees each per acre. The grass mixture used to establish this price is listed below, however, any mixture that is appropriate for the geographic area and meets NRCS practice standards can be used.The typical application of this practice is 3 acres.
Nebraska
Typical Practice Scenario
5%
CP22; 4/
$1,300.56
$1,391.60
$0.00
None.
Unit for Cost EstimateGeographic Area
$0.00
$34.50
Cost Summary:
UnitsSideoats grama 2.40
Notes
$1,266.06
Little bluestem
640
0.20
None
$0.00
$0.00
$0.00
5%
Total CostUnits
Variable, land may or may not be taken out of production.
None.
1
2%
Includes the cost to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
Cost Summary:1 $34.50
Units Total Cost
$1,266.06
$26.01
$65.03
Units Price/Unit Total Cost
Notes
Seedbed Preparation-Chemical 1 $18.00 $18.00
42 of 200
Payment Schedule Results
391
Payment Schedule Development Methodology
Nebraska
0%0%
Scenario Code
3912
PracticeCost Share Program
Practice Code
CRP
Payment Rate
Unit Type
Scenario
Acre $385.85Riparian Forest Buffer CRP-Trees without Mulch or Animal Protection Devices
CRP Producer Payment RateCRP Program Payment Rate
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$37.83$15.13$0.00
50%
Total CostAdministration & Permit CostsRisk
Cost/UnitCost Category
Forgone Income
Equipment/InstallationMaterials
$0.00$17.25
$361.03
0%0%0%
50%
50%
$0.00$0.00
50%$34.50
$722.06
$7.57
$385.85$0.00
$809.52$0.00$0.00
$0.00$0.00
$0.00$0.00
43 of 200
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
2%
640
Blackeyed Susan
None.
1 $722.06
$15.13
$37.83
Units Price/Unit Total Cost
$0.00
Total Cost NotesCost Summary:1 $34.50
5%
Total CostUnits
Seedbed Preparation-Chemical 1
CP22
$756.56
$809.52
$0.00
None.
None
$0.00
$0.00
$0.00
Variable, land may or may not be taken out of production.
Includes the cost to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
Acre
This practice includes the planting of trees with complex site preparation. Complex site preparation includes chemical application to kill undesirable plant species. The tree planting would include approximately 320 small shrubs, 220 large shrubs and small trees, and 100 large trees each per acre. The grass mixture used to establish this price is listed below, however, any mixture that is appropriate for the geographic area and meets NRCS practice standards can be used. The typical application of this practice is 3 acres.
Nebraska
Typical Practice Scenario
Geographic AreaUnit for Cost Estimate
$1.05
$17.02 $0.85
23.85 $4.05$25.19 $2.52
Grass Seeding 1 $16.50 $16.50
$34.50
Cost Summary:
UnitsSideoats grama 2.40
Notes
0.05
White prairieclover
Practice Life (Years) 15Discount Rate (%/Year) 5%
0.17Upright coneflower
$722.06
Trees & Machine Planting
Big bluestem
Units
$18.00 $18.00 Source: FY10 USDA-NRCS Program Payment Database
$672.00
Price/Unit$8.99
Little bluestem
Total Cost$21.58
Source: FY10 USDA-NRCS Program Payment
Database and Vendor Qutoes, September 2010
0.10
0.201.80
$6.94$10.93
$1.39$19.67
44 of 200
Payment Schedule Results
391
Payment Schedule Development Methodology
$147.29$0.00$0.00$0.00Forgone Income
$125.00
0%0%0%50%$8.58
$0.00
$0.00$0.00
$36.00$250.00
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$5.72
Payment Rate
Unit TypeAcre $147.29Riparian Forest Buffer CRP-Direct Seeding3913
$4.2950%
Equipment/InstallationMaterials 50%
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$0.00$18.00
Nebraska
0%0%
50%
Scenario Code
Total CostAdministration & Permit CostsRisk
$0.00
$300.30$0.00$0.00$0.00
PracticeCost Share Program
Practice Code
CRP
45 of 200
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
15Discount Rate (%/Year) 5%Unit for Cost Estimate
$250.00
Acre
This practice includes the seed, seed collection, and site preparation for trees or shrubs which are direct seeded. This scenario is typically used to direct seed large seeded species such as Oaks or Walnuts using a tree seed planter. Site preparation could include residue management measures such as residue removal, shredding, raking, etc., and the application of burn down herbicides to kill sod, alfalfa, or other perennial vegetation. This practice meets the requirements listed in the 380 Windbreak/Shelterbelt Establishment Tree Planting Procedures. Typical application of this scenario is 5 acres.
Nebraska
Typical Practice Scenario
Geographic Area Practice Life (Years)
Price/Unit$250.00
3%
1 $36.00
CP22
$286.00
$300.30
$0.00
None.
None
$0.00
$0.00
$0.00
Includes the cost to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
Source: Vendor Quotes, Sept. 2010
Total Cost$250.00
$18.00 $18.00
Units Total Cost Notes
$0.00
2%
Total CostUnits
$36.00
Cost Summary:
UnitsSeed and Seed Collection 1.00
Notes
Source: FY10 USDA-NRCS Program Payment Database
None
None.
1 $250.00
$8.58
$5.72
Units Price/Unit Total Cost
Cost Summary:Seedbed Prepparation-Chemical 1 $18.00 $18.00Seedbed Preparation-Mechanical 1
46 of 200
Payment Schedule Results
391
Payment Schedule Development Methodology
Nebraska
Scenario Code
3914
PracticeCost Share Program
Practice Code
CRP Riparian Forest Buffer CRP-Replants
CRP Producer Payment Rate
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$2.26$0.00$0.00
50%
$0.00Forgone Income
0%0%
Total CostAdministration & Permit CostsRisk
$1.03$0.00$0.00$0.00
Materials$0.00$2.00
$0.00$1.00
50%
Payment Rate
Unit Type
Each $1.03
Cost/UnitCost Category
50%
CRP Program Payment Rate
$0.00
0%0%0%50%
$0.00$0.00$0.03
Equipment/Installation
$0.20$0.06$0.00
$0.00
47 of 200
Practice Cost Data
Materials per Each
Equipment/Installation per EachEquipment/Installation costs included with the cost of Materials
Labor per EachLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Each
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Each
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Each
Acquisition of Technical Knowledgeper Each
Forgone Incomeper Each
Riskper Each
Administration & Permit Costsper Each
Total Cost Estimate: per Each
Associated Practices:
10%
Total CostUnits
Price/Unit$2.00
3%
Cost Summary:
1.00
None
None.
1 $2.00
$0.06
$0.20
$0.00
$0.00
Notes
Source: USDA-NRCS FY10 Average Cost Database
CP22
$2.00
$2.26
$0.00
None.
None
$0.00
$0.00
$0.00
Includes the cost to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
5%15
Each
This practice includes the replanting of select trees due to death or damage of the seedlings following an initial riparian forest buffer establishment.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost Estimate
$2.00
(weighted avg TS11 & TS13)
Total Cost$2.00
UnitsTrees & Hand Planting
Geographic Area
48 of 200
Payment Schedule Results
393
Payment Schedule Development Methodology
Equipment/InstallationMaterials $31.9950%
$34.50$63.98
Cost Category
Acre $51.70Filter Strip CRP-Standard Mixture
CRP Producer Payment RateCRP Program Payment Rate
$2.4650% $0.00
Cost/Unit
$17.25
$51.70$0.00$0.00
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.98$4.92$0.00
Scenario Code
3931
PracticeCost Share Program
Practice Code
CRP
Total CostAdministration & Permit Costs
$0.00$0.00$0.00
Nebraska
0%0%
50%
0%0%0%50%
Risk
$0.00
$304.39$0.00$0.00
$200.00Forgone Income
Payment Rate
Unit Type
49 of 200
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
Units Total Cost Notes
Indiangrass
Red clover 0.8
$34.50
Grass Seeding 1 $16.50
Cost Summary:1 $34.50
Units Price/Unit Total CostSource: FY10 USDA-NRCS Program Payment Database
$16.50
$6.84$7.73
$3.51$17.10
Price/Unit
2.32
$6.94
Alfalfa
$12.37
Practice Life (Years) 10Discount Rate (%/Year) 5%Acre
A filter strip approximately 20 feet wide consisting of a native grass mix of Big bluestem, Switchgrass, Indiangrass, Alfalfa, and Red clover, however, any seed mixture which is appropriate to the geographic location and meets NRCS practice standards may be used seeded at a rate of 40 PLS. Operations include 2 tillage operations (light disking) and seeding operation using a special grass drill.
Nebraska
Typical Practice Scenario
Unit for Cost EstimateGeographic Area
CP21; CP22; CP23A; CP28; CP29; CP30
$98.48
$304.39
$0.00
None.
$63.98Total Cost$29.15
$1.86
Source: Vendor Quotes, September 2010
1 $63.98
$4.92
Cost Summary:
UnitsBig bluestem 4.2
2.51.6
Notes
Switchgrass
1.1 $3.19
Seedbed Preparation 1 $18.00 $18.00
Total CostUnits
None
$0.00
$200.00
$0.00None.
1%
One acre of cropland taken out of production. Assuming a corn-soybean rotation minus the value of an occassional hay/forage crop from herbaceous cover crop.
$0.98
$0.00
5%
50 of 200
Payment Schedule Results
393
Payment Schedule Development Methodology
Nebraska
0%0%
50%
Payment Rate
Unit TypeScenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
0%0%0%50%
$0.00
Scenario Code
$7.00$0.00
Total CostAdministration & Permit Costs
$348.34$0.00
Equipment/Installation
3932
PracticeCost Share Program
Practice Code
CRP
$0.00$200.00Forgone Income
Risk
Filter Strip
Materials 50%
50%$34.50
$105.44
$1.40
Acre
$0.00$17.25
$0.00
CRP Producer Payment Rate
$73.47$0.00$0.00$0.00
$73.47
$0.00
$52.72
$3.50
CRP-High Diversity for Wildlife Mixture
CRP Program Payment RateCost/UnitCost Category
51 of 200
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
1%
Total CostUnits
Practice Life (Years) 10Discount Rate (%/Year) 5%
$1.40
Units Price/Unit Total CostSource: FY10 USDA-NRCS Program Payment Database$18.00
5%
1 $105.44
$7.00
Sideoats grama 1.40
$25.76Illinois bundleflower
$18.00
1
CP21; CP22; CP23A; CP28; CP29; CP30
$139.94
$348.34
$0.00
None.
None
$0.00
$200.00
$0.00None.
One acre of cropland taken out of production. Assuming a corn-soybean rotation minus the value of an occassional hay/forage crop from herbaceous cover crop.
UnitsBig bluestem 3.20
Notes
Cost Summary:
Grass Seeding 1 $16.50Seedbed Preparation 1
Units Total Cost Notes
IndiangrassSwitchgrass
2.00
Maximillian sunflower 0.581.451.60
$34.50
$105.44Total Cost$22.21
$14.94
Source: Vendor Quotes, September 2010
Price/Unit$6.94
$13.68$7.73 $8.50
$16.52
$8.99 $12.59$5.98 $9.57
$6.84
Acre
A filter strip approximately 20 feet wide consisting of a native grass mix of Big bluestem, Switchgrass, Indiangrass, Sideoats grama, Western wheatgrass, Illinois bundleflower, and Maximillian sunflower (although any seed mixture which is appropriate to the geographic location and meets NRCS practice standards may be used) seeded at a rate of 40 PLS. Operations include 2 tillage operations (light disking) and seeding operation using a special grass drill.
Nebraska
Typical Practice Scenario
Unit for Cost EstimateGeographic Area
$0.00
$34.50
Cost Summary:
$16.50
$23.95
1.10
Western wheatgrass
52 of 200
394_11-Firebreak.xlsx CRP-Vegetative
Payment Schedule Results
394
Payment Schedule Development Methodology
$42.50$26.90
$36.43$0.00$0.00$0.00
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $36.43Firebreak CRP-Vegetative
Forgone Income
$0.00$21.25$13.45
0%0%0%50%
$0.00$3.47
$0.00$0.00$1.73
50%Equipment/InstallationMaterials
MobilizationLabor
Scenario Code
3941
PracticeCost Share Program
Practice Code
CRP
$0.00
50%
Nebraska
0%Administration & Permit CostsRisk
$0.00
$72.87$0.00$0.00$0.00
0%
50%
Total Cost
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & Maintenance
53 of 200
394_11-Firebreak.xlsx CRP-Vegetative
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
10Discount Rate (%/Year) 5%
Seedbed Preparation 7.2 $18.00
$2.32$3.19
Practice Life (Years)Acre
This scenario includes the construction of a 30-feet wide vegetative firebreak around a 160 acre field, including seedbed preparation, temporary cover crop, grass seeding, seed, and weed control in the seeding. The mixture of seed used to establish the price is a mixture of Western wheatgrass, Orchardgrass, Alfalfa, and Red Clover, however, any mixture that is appropriate for the geographic location and meets NRCS practice standards can be used. The typical application of this practice is 7.2 acres of firebreak in a CRP field.
Nebraska
Typical Practice Scenario
Unit for Cost EstimateGeographic Area
MCM 1/
$69.40
$72.87
$0.00
Reduced risk, less risk of fire damage.
None
$0.00
$0.00
$26.90Total Cost$17.94 Source: FY10 USDA-
NRCS Program Payment Database
$1.07Orchardgrass
1.21.60.5
$0.00
$42.50
Cost Summary:
UnitsWestern wheatgrass 3.0
Notes
One acre of lost production due to deferrment. Assume pasture/forage use.
0%
Total CostUnits
Price/Unit$5.98
Red cloverAlfalfa
Grass SeedingCost Summary:
7.2
5%
$2.14
$2.78$5.10
$129.60Weed control in grass seeding 7.2 $16.25 $117.00
$306.00Units Total Cost
None.
1 $26.90
$3.47
$0.00
Units Price/Unit Total CostSource: FY10 USDA-
NRCS Program Payment Database
$0.00
Notes$59.403.6 $16.50
54 of 200
394_11-Firebreak.xlsx CRP-Mowed or Tilled
Payment Schedule Results
394
Payment Schedule Development Methodology
50%
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.00
0%
Scenario Code
3942
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
$0.00$0.00
$0.00
0%0%0%50%
$14.00$0.00
Acre $7.70Firebreak CRP-Mowed/Tilled Firebreak
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$1.40$0.00
$0.7050%50%
$0.00
$7.70$0.00$0.00$0.00$0.00$0.00
Forgone Income
$0.00$7.00
0%
Total CostAdministration & Permit CostsRisk
$15.40$0.00
55 of 200
394_11-Firebreak.xlsx CRP-Mowed or Tilled
Practice Cost Data
Materials per AcreMaterials costs included with the cost of Equipment/Installation
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:MCM 1/
$14.00
$15.40
$0.00
Reduced risk, less risk of fire damage.
None
$0.00
$0.00
$0.00None.
$1.40
$0.00
One acre of lost production due to deferrment. Assume pasture/forage use.
10%
Unit for Cost EstimateGeographic Area
Discount Rate (%/Year)Practice Life (Years)
Mowing $100.80
Cost Summary:7.2 $100.80
Units Total Cost Notes
Source: FY10 USDA-NRCS Program Payment Database
$0.00
7.2 $14.00
0%
Units Price/Unit Total Cost$14.00
$0.00
5%10
Acre
This scenario includes the construction of a 30-feet wide mowed or tilled firebreak around a 160 acre field. This would result in 7.2 acres of firebreak. This scenario is used in conjunction with a prescribed burn.
Nebraska
Typical Practice Scenario
56 of 200
410_11-GradeStabStructure.xlsx CRP-CMP with Riser
Payment Schedule Results
410
Payment Schedule Development Methodology
Equipment/InstallationMaterials
Forgone Income
$0.00$0.00$2.00
0%0%0%50%
$0.00$4.00
$0.00$0.00$0.00$0.10
50%50%50%
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Cu Yd $2.10Grade Stabilization Structure CRP-CMP with Riser
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$4.32$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.12$0.20$0.00
Scenario Code4101
PracticeCost Share Program
Practice Code
0%0%
$2.10$0.00$0.00
57 of 200
410_11-GradeStabStructure.xlsx CRP-CMP with Riser
Practice Cost Data
Materials per Cu Yd
Equipment/Installation per Cu YdEquipment/Installation costs included with the cost of Materials
Labor per Cu YdLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Cu Yd
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Cu Yd
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Cu Yd
Acquisition of Technical Knowledgeper Cu Yd
Forgone Incomeper Cu Yd
Riskper Cu Yd
Administration & Permit Costsper Cu Yd
Total Cost Estimate: per Cu Yd
Associated Practices:
This practice consists of earthen structures which include a Corrugated Metal Pipe (CMP) with a riser. Also included in the total cost are stripping, all gravel drains and rock rip rap. The typical application of this practice is 2,500 cubic yards of fill which includes backfill of all required excavations with 90 feet of 18" CMP and 8 foot of 30" CMP for the riser.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
$4.00
12" CMP Pipe (P05)
Total Cost$4,250.00 Source: FY10 USDA-
NRCS Program Payment Database
Unit for Cost Estimate
890
$70.50$57.50
UnitsEarthfill-Class C Compaction (E02) 2500
$564.00$5,175.00
5%25
Cu Yd
Price/Unit$1.70
30" CMP Pipe (P10)
5%
CP8A; CP9; CP21; CP23; CP27; CP29; CP30; 3/
$4.00
$4.32
$0.00
None.
None
$0.00
$0.00
$0.00
None, minimal land taken out of production
3%
$0.00
$0.00
Cost Summary: Notes
None.
2,500 $9,989.00
$0.20
$0.12
Total CostUnits
58 of 200
410_11-GradeStabStructure.xlsx CRP-CMP without Riser
Payment Schedule Results
410
Payment Schedule Development Methodology
Nebraska
4102
PracticeCost Share Program
Practice Code
CRP
$0.00$0.00$0.00
Cu Yd $1.98Grade Stabilization Structure CRP-CMP without Riser
50%
Acquisition of Tech. Knowledge
Payment Rate
Unit Type
Scenario
$0.11$0.19$0.00
Cost/Unit
Equipment/Installation
0%0%
Total CostAdministration & Permit CostsRisk
$0.00
$4.07
Scenario Code
Operation & MaintenanceMobilizationLabor
Materials
Forgone Income
50%
$0.00
CRP Producer Payment RateCRP Program Payment Rate
50%$0.00$0.00$1.89
$0.09
Cost Category
$0.00$3.77
$1.98$0.00$0.00$0.00$0.00
0%0%0%50%
59 of 200
410_11-GradeStabStructure.xlsx CRP-CMP without Riser
Practice Cost Data
Materials per Cu Yd
Equipment/Installation per Cu YdEquipment/Installation costs included with the cost of Materials
Labor per Cu YdLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Cu Yd
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Cu Yd
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Cu Yd
Acquisition of Technical Knowledgeper Cu Yd
Forgone Incomeper Cu Yd
Riskper Cu Yd
Administration & Permit Costsper Cu Yd
Total Cost Estimate: per Cu Yd
Associated Practices:
3%
Total CostUnits
Price/Unit$1.70
5%
Cost Summary:
2500
None.
2,500 $9,425.00
$0.19
$0.11
$0.00
$0.00
Notes
90 $57.50 $5,175.00Source: FY10 USDA-NRCS Program Payment Database
CP8A; CP9; CP21; CP23; CP27; CP29; CP30; 3/
$3.77
$4.07
$0.00
None.
None
$0.00
$0.00
$0.00
None, minimal land taken out of production
5%25
Cu Yd
This practice consists of earthen structures which include a Corrugated Metal Pipe (CMP) without a riser. Also included in the total cost are stripping, all gravel drains and rock rip rap. The typical application of this practice is 2,500 cubic yards of fill which includes backfill of all required excavations with a 90 foot of 18" CMP.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost Estimate
$3.77
12" CMP Pipe (P05)
Total Cost$4,250.00
UnitsEarthfill-Class C Compaction (E02)
Geographic Area
60 of 200
410_11-GradeStabStructure.xlsx CRP-PVC Pipe
Payment Schedule Results
410
Payment Schedule Development Methodology
$1.60$0.00$0.00$0.00$0.00$0.00
CRP Producer Payment RateCRP Program Payment Rate
50%$0.00$0.00$1.53
$0.08
0%0%0%50%
50%
50%
Cu Yd $1.60Grade Stabilization Structure CRP-PVC Pipe
Scenario Code4103
PracticeCost Share Program
Practice Code
CRP
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.00$0.00$0.00
Equipment/Installation
$0.00$0.09$0.15$0.00
Cost Category
Materials
Forgone Income
$0.00$3.05
Nebraska
0%0%
Total CostAdministration & Permit CostsRisk
$3.29
Payment Rate
Unit Type
Cost/Unit
61 of 200
410_11-GradeStabStructure.xlsx CRP-PVC Pipe
Practice Cost Data
Materials per Cu Yd
Equipment/Installation per Cu YdEquipment/Installation costs included with the cost of Materials
Labor per Cu YdLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Cu Yd
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Cu Yd
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Cu Yd
Acquisition of Technical Knowledgeper Cu Yd
Forgone Incomeper Cu Yd
Riskper Cu Yd
Administration & Permit Costsper Cu Yd
Total Cost Estimate: per Cu Yd
Associated Practices:
5%25
Cu Yd
This practice consists of earthen structures which include a PVC Pipe without a riser. Also included in the total cost are stripping all gravel drains and rock rip rap. The typical application of this practice is 1,500 cubic yards of fill which includes backfill of all required excavations with 60 foot of 12" PVC pipe.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
CP8A; CP9; CP21; CP23; CP27; CP29; CP30; 3/
$3.05
$3.29
$0.00
None.
None
$3.05
12" PVC Pipe (P79)
Total Cost$2,550.00
UnitsEarthfill-Class C Compaction (E02) 1500
Price/Unit$1.70
Notes
Source: FY10 USDA-NRCS Program Payment Database
3%
Total CostUnits
5%
Cost Summary:
None.
$0.00
$0.00
$0.00
None, minimal land taken out of production
Unit for Cost Estimate
50 $40.50 $2,025.00
1,500 $4,575.00
$0.15
$0.09
$0.00
$0.00
62 of 200
410_11-GradeStabStructure.xlsx CRP-Non-Earthen Structures
Payment Schedule Results
410
Payment Schedule Development Methodology
Nebraska
4104
PracticeCost Share Program
Practice Code
CRP
$0.00$0.00$0.00
Cu Yd $21.48Grade Stabilization Structure CRP-Non-Earthen Structures
50%
Acquisition of Tech. Knowledge
Payment Rate
Unit Type
Scenario
$0.41$2.05$0.00
Cost/Unit
Equipment/Installation
0%0%
Total CostAdministration & Permit CostsRisk
$0.00
$43.37
Scenario Code
Operation & MaintenanceMobilizationLabor
Materials
Forgone Income
50%
$0.00
CRP Producer Payment RateCRP Program Payment Rate
50%$0.00$0.00$20.46
$1.02
Cost Category
$0.00$40.91
$21.48$0.00$0.00$0.00$0.00
0%0%0%50%
63 of 200
410_11-GradeStabStructure.xlsx CRP-Non-Earthen Structures
Practice Cost Data
Materials per Cu Yd
Equipment/Installation per Cu YdEquipment/Installation costs included with the cost of Materials
Labor per Cu YdLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Cu Yd
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Cu Yd
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Cu Yd
Acquisition of Technical Knowledgeper Cu Yd
Forgone Incomeper Cu Yd
Riskper Cu Yd
Administration & Permit Costsper Cu Yd
Total Cost Estimate: per Cu Yd
Associated Practices:
1%
Total CostUnits
Price/Unit$3.95
5%
Cost Summary:
7070
None.
760 $31,091.90
$2.05
$0.41
$0.00
$0.00
Notes
70 $45.22 $3,165.40Source: FY10 USDA-NRCS Program Payment Database
CP8A; CP9; CP21; CP23; CP27; CP29; CP30; 3/
$40.91
$43.37
$0.00
None.
None
$0.00
$0.00
$0.00
None, minimal land taken out of production
5%25
Cu Yd
Includes construction of a sheet pile weir or fabricated toe wall structure to stabilize channel grade. This includes the cost of the cap steel, whaler supports, and armoring of the outlet channel for a sheet pile weir or a pre-fabricated toe wall structure with concrete apron and footings.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost Estimate
$40.91
Rock Rip Rap (CY)
Total Cost$27,926.50
UnitsSteel Sheet Pile (LB)
Geographic Area
64 of 200
412_11-GrassedWaterway.xlsx CRP-Waterway with Side Dikes
Payment Schedule Results
412
Payment Schedule Development Methodology
Equipment/InstallationMaterials
Forgone Income
$0.00$0.00
$576.50
0%0%0%50%
$0.00$1,153.00
$0.00$0.00$0.00$28.83
50%50%50%
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $605.33Grassed Waterway CRP-Waterway with Side Dikes
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$1,433.71$0.00$0.00
$200.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$23.06$57.65$0.00
Scenario Code
4121
PracticeCost Share Program
Practice Code
0%0%
$605.33$0.00$0.00
65 of 200
412_11-GrassedWaterway.xlsx CRP-Waterway with Side Dikes
Practice Cost Data
Materials per Acre
Equipment/Installation per AcreEquipment/Installation costs included with the cost of Materials
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
The typical application of this scenario includes one acre of constructed waterway channel (35-ft by 1,200-ft) with 2,400-ft of side dikes. This practice includes all earthwork for erosion control.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
$1,153.00
Waterway-Side Dike construction (W11)
Total Cost$985.00 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost Estimate
2400 $0.07 $168.00
UnitsWaterway Earthwork (W10) 1
5%10
Acre
Price/Unit$985.00
5%
CP8A
$1,153.00
$1,433.71
$0.00
Reduced risk, less concentrated flow erosion, less machinery wear & tear
None
$0.00
$200.00
$0.00
One acre taken out of production, assume corn-soybean rotation
2%
$0.00
$0.00
Cost Summary: Notes
None.
1 $1,153.00
$57.65
$23.06
Total CostUnits
66 of 200
412_11-GrassedWaterway.xlsx CRP-Waterway Only
Payment Schedule Results
412
Payment Schedule Development Methodology
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & Maintenance
Scenario Code4122
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
MobilizationLabor
50%$492.50
0%0%0%50%
$0.00$985.00
Acre $517.13Grassed Waterway CRP-Waterway Only
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$49.25$0.00
$24.6350%
50%
$19.70$0.00
$200.00
$517.13$0.00$0.00$0.00$0.00$0.00
Forgone Income
$0.00$0.00
0%0%
Total CostAdministration & Permit CostsRisk
$1,253.95$0.00$0.00
67 of 200
412_11-GrassedWaterway.xlsx CRP-Waterway Only
Practice Cost Data
Materials per Acre
Equipment/Installation per AcreEquipment/Installation costs included with the cost of Materials
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
2%
Total CostUnits
Price/Unit$985.00
5%
None.
1 $985.00
$49.25
$19.70
$0.00
$0.00
Cost Summary:
UnitsWaterway Earthwork (W10) 1
Notes
CP8A
$985.00
$1,253.95
$0.00
Reduced risk, less concentrated flow erosion, less machinery wear & tear
None
$0.00
$200.00
$0.00
One acre taken out of production, assume corn-soybean rotation
$985.00Total Cost$985.00 Source: FY10 USDA-NRCS
Program Payment Database
5%10
Acre
The typical application of this scenario includes one acre of constructed waterway channel (35-ft by 1,200-ft) without side dikes. This practice includes all earthwork for erosion control.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
68 of 200
412_11-GrassedWaterway.xlsx CRP-Waterway with Fabric Checks
Payment Schedule Results
412
Payment Schedule Development Methodology
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & Maintenance
Scenario Code
4123
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
MobilizationLabor
50%$809.00
0%0%0%50%
$0.00$1,618.00
Acre $849.45Grassed Waterway CRP-Waterway with Fabric Checks
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$80.90$0.00
$40.4550%
50%
$32.36$0.00
$200.00
$849.45$0.00$0.00$0.00$0.00$0.00
Forgone Income
$0.00$0.00
0%0%
Total CostAdministration & Permit CostsRisk
$1,931.26$0.00$0.00
69 of 200
412_11-GrassedWaterway.xlsx CRP-Waterway with Fabric Checks
Practice Cost Data
Materials per Acre
Equipment/Installation per AcreEquipment/Installation costs included with the cost of Materials
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
2%
Total CostUnits
Price/Unit$985.00
5%
None.
1 $1,618.00
$80.90
$32.36
$0.00
$0.00
Cost Summary:
UnitsWaterway Earthwork (W10) 1
Notes
CP8A
$1,618.00
$1,931.26
$0.00
Reduced risk, less concentrated flow erosion, less machinery wear & tear
None
$0.00
$200.00
$0.00
One acre taken out of production, assume corn-soybean rotation
$1,618.00
Fabric Checks
Total Cost$985.00 Source: FY10 USDA-NRCS
Program Payment Database15 $42.20 $633.00
5%10
Acre
The typical application of this scenario includes one acre of constructed waterway channel (35-ft by 1,200-ft) with 15 fabric mulch checks. This practice includes all earthwork for erosion control.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
70 of 200
441_11-MicroIrrigation.xlsx CRP-Windbreak Drip System
Payment Schedule Results
441
Payment Schedule Development Methodology
$0.21$0.00$0.00$0.00$0.00$0.00
Forgone Income
$0.00$0.00
0%0%
Total CostAdministration & Permit CostsRisk
$0.44$0.00$0.00
$0.21
0%0%0%50%
$0.00$0.42
LF $0.21Micro Irrigation CRP-Windbreak Drip System
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$0.00$0.00
$0.0050%
50%
$0.02$0.00$0.00
Scenario Code
4412
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
MobilizationLabor
50%
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & Maintenance
71 of 200
441_11-MicroIrrigation.xlsx CRP-Windbreak Drip System
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
$0.42Total Cost$1,256.25 Source: FY10 USDA-NRCS
Program Payment Database
5%10LF
Drip system for irrigation of a windbreak composed of 5 rows, each 600 feet long, for a total of 3000 feet, with an average tree spacing of 9-foot.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
CP5A; CP16A; CP17A; CP22; 4/
$0.42
$0.44
$0.00
Reduced risk; improved water use efficiency and production.
None
$0.00
$0.00
$0.00
None.
5%
Total CostUnits
Price/Unit$3.75
0%
None.
3,000 $1,256.25
$0.00
$0.02
$0.00
$0.00
Cost Summary:
UnitsSupplemental Watering for Trees (T58) 335
Notes
72 of 200
484_11-Mulching.xlsx CRP-Hay Mulch
Payment Schedule Results
484
Payment Schedule Development Methodology
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & Maintenance
Scenario Code
4841
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
MobilizationLabor
50%$122.50
0%0%0%50%
$0.00$245.00
Acre $128.63Mulching CRP-Hay Mulch
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$12.25$0.00
$6.1350%
50%
$0.00$0.00$0.00
$128.63$0.00$0.00$0.00$0.00$0.00
Forgone Income
$0.00$0.00
0%0%
Total CostAdministration & Permit CostsRisk
$257.25$0.00$0.00
73 of 200
484_11-Mulching.xlsx CRP-Hay Mulch
Practice Cost Data
Materials per Acre
Equipment/Installation per AcreEquipment/Installation costs included with the cost of Materials
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
0%
Total CostUnits
Price/Unit$245.00
5%
None.
3 $735.00
$12.25
$0.00
$0.00
$0.00
Cost Summary:
UnitsMulching-critical area (G73) 3
Notes
CP8A; 3/
$245.00
$257.25
$0.00
None.
None
$0.00
$0.00
$0.00
None.
$245.00Total Cost$735.00 Source: FY10 USDA-NRCS
Program Payment Database
5%1
Acre
Mulching on 3 acres of environmentally sensitive land using straw, native hay, or other natural materials. Used in conjunction with Critical Area Planting.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
74 of 200
484_11-Mulching.xlsx CRP-Erosion Control Blanket
Payment Schedule Results
484
Payment Schedule Development Methodology
$0.62$0.00$0.00$0.00$0.00$0.000%
Total CostAdministration & Permit Costs 0%
0%Forgone Income
$0.22$0.00$0.37
0%0%
$0.00$0.73
50%
50%50%
CRP Program Payment RateCost/UnitCost Category
Sq Yd $0.62Mulching CRP-Erosion Control Blanket
$0.0350%
Equipment/InstallationMaterials
Nebraska
Risk
$0.00
$1.23$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.00$0.06$0.44
Scenario Code
4842
PracticeCost Share Program
Practice Code
CRP
CRP Producer Payment Rate
75 of 200
484_11-Mulching.xlsx CRP-Erosion Control Blanket
Practice Cost Data
Materials per Sq Yd
Equipment/Installation per Sq YdEquipment/Installation costs included with the cost of Materials
Labor per Sq Yd
Total Materials, Equipment/Installation and Labor Costs: per Sq Yd
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Sq Yd
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Sq Yd
Acquisition of Technical Knowledgeper Sq Yd
Forgone Incomeper Sq Yd
Riskper Sq Yd
Administration & Permit Costsper Sq Yd
Total Cost Estimate: per Sq Yd
Associated Practices:
Notes
5%1
Sq Yd
Installation of erosion control blanket on environmentally sensitive land using commercially available erosion control blanket. Used in conjunction with Critical Area Planting. Typical Scenario is a channel 100' long, 8' wide, 6:1 side slopes with blanket placed to a depth of 2' on sides (32' total width)
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
$0.73
Staples
Total Cost$234.00 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost Estimate
1 $30.00 $30.00
UnitsErosion Control Blanket (SY) 360
CP8A; 3/
$1.17
$1.23
$0.00
None.
None
$0.00
$0.00
$0.00
None.
None.
0%
Total CostUnits
Price/Unit$0.65
5%
Units Price/UnitLabor at 50% of Materials Cost 360
Cost Summary:360 $264.00
$0.06
$0.00
Total Cost$0.44 $158.40 Source: FY08 USDA-NRCS
Program Payment Database
$0.44
$0.00
76 of 200
512_11-PastureHayPlanting.xlsx CRP-Non-Irrigated Mix-LimitedSP
Payment Schedule Results
512
Payment Schedule Development Methodology
Nebraska
0%0%
50%
Scenario Code
5122
PracticeCost Share Program
Practice Code
CRP
Payment Rate
Unit Type
Scenario
Acre $20.53Pasture and Hay Planting CRP-Non-Irrigated Mixture-Limited Site Preparation
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
Total CostAdministration & Permit CostsRisk
$0.00
$42.23
Equipment/Installation
$20.53
Materials
Forgone Income
$0.00$8.25$11.30
0%0%0%50%
$0.00
50%$16.50$22.60
$1.17$1.96$0.00
$0.00$0.00$0.00$0.00$0.00$0.98
50%
$0.00$0.00
77 of 200
512_11-PastureHayPlanting.xlsx CRP-Non-Irrigated Mix-LimitedSP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
5%
1.00
60Units Price/Unit Total Cost
$990.00
3%
Total CostUnits1 $22.60
$1.96
$1.17
$0.00
$16.50
Cost Summary:
Cost Summary:60 $990.00
Units Total Cost
CP1; CP10; CP18B/C
$39.10
$42.23
$0.00
None.
None
$0.00
$0.00
$0.00
None.
None.
Acre
This practice includes the seeding a dryland grass mixture with or without forbs, with limited site preparation or tillage on approximately 60 acres. Limited site preparation is defined as planting directly into cover crop, crop stubble or tilled crop stubble (includes fields that have residue tilled or shredded prior to planting). This includes seed, seeding and seedbed preparation. The seeding mix used to establish a price is listed below, however any mixture that is appropriate for the geographic location and meets NRCS practice standards can be used
Nebraska
Typical Practice Scenario
Geographic AreaUnit for Cost Estimate
Practice Life (Years) 10Discount Rate (%/Year) 5%
Source: FY10 USDA-NRCS Program Payment Database
Grass Seeding
$3.72$1.28
UnitsIntermediate wheatgrass 5.20
Notes
$22.60
Orchardgrass
Total Cost$14.40
Notes
$16.50
$3.19$3.19
Source: Vendor Quotes, September 2010
1.900.60
$1.96$2.14
Price/Unit$2.77
AlfalfaSmooth bromegrass
78 of 200
512_11-PastureHayPlanting.xlsx CRP-Non-Irrigated Mix-ComplexSP
Payment Schedule Results
512
Payment Schedule Development Methodology
$34.50$22.60
$29.98$0.00$0.00$0.00Forgone Income
$0.00$17.25$11.30
0%0%0%50%
50%
$0.00$0.00$1.43
50%Equipment/InstallationMaterials
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$1.71$2.86$0.00
Scenario Code
5125
PracticeCost Share Program
Practice Code
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $29.98Pasture and Hay Planting CRP-Non-Irrigated Mixture-Complex Site Preparation
Nebraska
0%0%
50%
Total CostAdministration & Permit CostsRisk
$0.00
$61.67$0.00$0.00$0.00
Payment Rate
79 of 200
512_11-PastureHayPlanting.xlsx CRP-Non-Irrigated Mix-ComplexSP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
Practice Life (Years) 10Discount Rate (%/Year) 5%
Notes$3.19$3.72$1.28
Acre
This practice includes the seeding a dryland grass mixture with or without forbs, with complex site preparation on approximately 60 acres. Complex site preparation includes residue management measures such shredding, raking etc., application of burn down herbicides to kill annual vegetation on crop stubble/fallow to properly prepare seedbed. This practice includes all site preparation, seed, and seeding costs. The seed mixture used to establish a price is listed below, however, any mixture that is appropriate for the geographic location and meets NRCS practice standards can be used.
Nebraska
Typical Practice Scenario
Geographic AreaUnit for Cost Estimate
$22.60
Orchardgrass
Total Cost$14.40
Source: Vendor Quotes, September 2010
1.900.60
$1.96$2.14
UnitsIntermediate wheatgrass 5.20
CP1; CP10; CP18B/C
$57.10
$61.67
$0.00
None.
None
$0.00
$0.00
$0.00
None.
None.
3%
Total CostUnits
Price/Unit$2.77
AlfalfaSmooth bromegrass
5%
1.00
60
Cost Summary:
Grass Seeding
Cost Summary:
$16.50
$3.19
Seedbed Preparation (G03) 60 $18.00
60 $2,070.00Units Total Cost
1 $22.60
$2.86
$1.71
Units Price/Unit Total Cost$990.00
$0.00
$34.50
$1,080.00Source: FY10 USDA-NRCS Program Payment Database
Notes
80 of 200
512_11-PastureHayPlanting.xlsx CRP-CP1 Mix-Limited Site Prep
Payment Schedule Results
512
Payment Schedule Development Methodology
Acre $34.66Pasture and Hay Planting CRP-CP1 Mix-Limited Site Prep
Equipment/InstallationMaterials
Forgone Income
$0.00$8.25$24.76
0%0%0%50%
$16.50$49.52
$0.00$0.00$0.00$1.65
50%
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$34.66$0.00$0.00
$3.30$0.00
Scenario Code
5127
PracticeCost Share Program
Practice Code
CRP
Total CostAdministration & Permit Costs
50%
Nebraska
0%0%
50%
Risk
$0.00
$71.30$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$1.98
81 of 200
512_11-PastureHayPlanting.xlsx CRP-CP1 Mix-Limited Site Prep
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
Cost Summary:60 $990.00
Units Total Cost Notes
$16.50
$14.51
$2.26
Source: Vendor Quotes, September 2010
$49.52
10Discount Rate (%/Year) 5%
$1.13
$14.35
Total Cost$16.34
2.405.20
$5.98$2.79
Geographic Area
UnitsIntermediate wheatgrass 5.90Pubescent wheatgrassWestern wheatgrass
Practice Life (Years)Acre
This practice scenario includes seeding of a grass and legume mixture suitable as quality wildlife habitat that meets the rquirements of a CP-1 seeding in the Conservation Reserve Program with limited site preparation. Limited site preparation is defined as planting directly into cover crop, crop stubble or tilled crop stubble (includes fields that have residue tilled or shredded prior to planting). This practice includes all site preparation, seed, and seeding costs. The seed mixture used to establish a price is listed below, however, any mixture that is appropriate for the geographic location and meets NRCS practic standards can be used.
Nebraska
Typical Practice Scenario
Unit for Cost Estimate
$16.50
Cost Summary: Notes
Source: FY10 USDA-NRCS Program Payment Database
Grass Seeding
CP1; CP10; CP18B/C
$66.02
$71.30
$0.00
None.
None
$0.00
$0.00
$0.00
None.
Price/Unit$2.77
Sweetclover (yellow & white)Alfalfa 1.00 $3.19 $3.19
None.
1 $49.52
$3.30
$1.98
Units Price/Unit Total Cost$990.00
3%
Total CostUnits
5%
0.50
60
$0.00
82 of 200
512_11-PastureHayPlanting.xlsx CRP-CP1 Mix-Complex Site Prep
Payment Schedule Results
512
Payment Schedule Development Methodology
Nebraska
0%
Scenario Code
5128
PracticeCost Share Program
Practice Code
CRP
Payment Rate
Unit Type
Scenario
$0.00
0%
50%
Total CostAdministration & Permit CostsRisk
Acre $44.11Pasture and Hay Planting CRP-CP1 Mix-Complex Site Prep
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$2.52$4.20
Materials
Forgone Income
$0.00$17.25$24.76
0%0%0%50%
$0.00
50%$49.52
$0.00$0.00$0.00$2.10
50%$34.50Equipment/Installation
$0.00
$90.74 $44.11$0.00$0.00
$0.00$0.00
83 of 200
512_11-PastureHayPlanting.xlsx CRP-CP1 Mix-Complex Site Prep
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
3%
Total CostUnits
Price/Unit$2.77
Sweetclover (yellow & white)
Western wheatgrass
5%
0.50
60
1 $49.52
Units Price/Unit
Units Total Cost
CP1; CP10; CP18B/C
$84.02
$90.74
$0.00
None.
None
$0.00
$0.00
$0.00
None.
None.
$4.20
$2.52
$0.00
$34.50
Cost Summary:
UnitsIntermediate wheatgrass 5.90
Notes$1.13
$14.35$14.51Pubescent wheatgrass
Total Cost$16.34
Source: Vendor Quotes, September 2010
2.405.20
$5.98$2.79
Total Cost$990.00
60 $2,070.00
Acre
This practice scenario includes seeding of a grass and legume mixture suitable as quality wildlife habitat that meets the rquirements of a CP-1 seeding in the Conservation Reserve Program with complex site preparation. Complex site prep includes residue management measures such as shredding, raking etc., application of burn down herbicides to kill annual vegetation on crop stubble/fallow to properly prepare seedbed. This practice includes all site preparation, seed, and seeding costs. The seed mixture used to establish a price is listed below, however, any mixture that is appropriate for the geographic location and meets NRCS practic standards can be used.
Nebraska
Typical Practice Scenario
Geographic AreaUnit for Cost Estimate
Notes
$2.26
Seedbed Preparation (G03) 60 $18.00 $1,080.00Source: FY10 USDA-NRCS Program Payment Database
Grass Seeding
Cost Summary:
$16.50
Practice Life (Years) 10Discount Rate (%/Year) 5%
Alfalfa 1.00 $3.19 $3.19
$49.52
84 of 200
516_11-Pipeline.xlsx CRP-Pipeline
Payment Schedule Results
516
Payment Schedule Development Methodology
Equipment/InstallationMaterials
Forgone Income
$0.00$0.00$0.93
0%0%0%50%
$0.00$1.85
$0.00$0.00$0.00$0.06
50%50%50%
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
LF $0.99Pipeline CRP-Pipeline
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$2.02$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.04$0.13$0.00
Scenario Code
5161
PracticeCost Share Program
Practice Code
0%0%
$0.99$0.00$0.00
85 of 200
516_11-Pipeline.xlsx CRP-Pipeline
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
This practice includes 1,500 foot of 2" diameter PVC pipe with one hydrant and one air vent.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
$1.85Total Cost$2,775.00 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost Estimate
UnitsPipe (PI01) 1500
5%20LF
Price/Unit$1.85
7%
CP21; CP22; CP29; CP30
$1.85
$2.02
$0.00
None.
None
$0.00
$0.00
$0.00
None.
2%
$0.00
$0.00
Cost Summary: Notes
None.
1,500 $2,775.00
$0.13
$0.04
Total CostUnits
86 of 200
533_11-PumpingPlants.xlsx CRP-Grazing Pumping Plants
Payment Schedule Results
533
Payment Schedule Development Methodology
Nebraska
0%0%
50%
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$40.49$80.98
$400.00
$0.00
Equipment/Installation
Scenario Code
5332
PracticeCost Share Program
Practice Code
CRP
50%
Total CostAdministration & Permit CostsRisk
$4,170.47$0.00$0.00$0.00
Materials
Forgone Income
Each $2,064.99Pumping Plants CRP-Grazing Pumping Plants
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$200.00$0.00
$1,824.50
0%0%0%50%
$3,649.00
$2,064.99$0.00$0.00$0.00
$0.0050%
$0.00$0.00
$40.49
87 of 200
533_11-PumpingPlants.xlsx CRP-Grazing Pumping Plants
Practice Cost Data
Materials per EachWindmillsWindmill TowerWindmill Head
* This represents a weighted average of the three alternatives.
Equipment/Installation per EachEquipment/Installation costs included with the cost of Materials
Labor per Each
Total Materials, Equipment/Installation and Labor Costs: per EachMobilization
Total Materials, Equipment/Installation and Labor Costs. per EachOperation & Maintenance
Total Materials, Equipment/Installation and Labor Costs. per EachAcquisition of Technical Knowledge
per EachForgone Income
per EachRisk
per EachAdministration & Permit Costs
per Each
Total Cost Estimate: per Each
Associated Practices:
1%
Total CostUnits
Price/Unit$800.00
Anchors
$400.00Units Price/Unit
1 $3,280.00
2%
11
$80.00$2,400.00
Labor for Set-Up 1
1
Electric Pump
1
CP21; CP22; CP29; CP30
$4,049.00
$4,170.47
$0.00
Reduced risk, more reliable source of water
None
$0.00
$0.00
$0.00
None.
None.
$80.98
$40.49
Each
This scneario includes installation of windmill and appurtenances, an electric pump and appurtenances, or a solar panel with appurtenances for supply of water for a planned grazing system. This is not a payment for above ground or underground electrical supply lines. This scenario applies to new systems only.
Nebraska
Typical Practice Scenario
Unit for Cost EstimateGeographic Area
$400.00
$0.00
Cost Summary:
Units1
Notes
Cost Summary: Units Total Cost
$3,649.00Total Cost$800.00 Source: FY10 USDA-
NRCS Program Payment Database$80.00
$2,400.00
Pump and Pressure TankCost Summary: Units
1Units Source: FY10 USDA-NRCS
Program Payment Database
Source: FY10 USDA-NRCS Program Payment Database
Notes
Solar Panels
Array Mounting MaterialsSolar Pump, Panels, Rack (each)
1
Units Price/Unit Total Cost
Practice Life (Years)
1 $8,400.00 $8,400.00
Source: FY10 USDA-NRCS Program Payment Database
15Discount Rate (%/Year) 5%
$3,500.00 $3,500.00
$8,900.00
Price/Unit Total Cost
$500.00 $500.00
$400.00Total Cost
$3,500.00Total Cost Notes
88 of 200
550_11-RangePlanting.xls CRP-Native Mix-Limited SP
Payment Schedule Results
550
Payment Schedule Development Methodology
$27.07$0.00$0.00$0.00$0.00$0.00
$0.00$8.25
$18.29
0%0%0%50% $0.5350%50%
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $27.07Range Planting CRP-Native Mix-Limited Site Preparation
CRP
Scenario Code
5501
PracticeCost Share Program
Practice Code
Materials
Forgone Income
$16.50$36.58
$1.06$0.00
$13.50
Equipment/Installation
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.53
50%
Nebraska
0%0%
$0.00
Total CostAdministration & Permit CostsRisk
$68.18$0.00$0.00
89 of 200
550_11-RangePlanting.xls CRP-Native Mix-Limited SP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
Cost Summary:1 $16.50
$10.93
0.06
1.00
$6.11$1.02
Units Total Cost Notes
$8.99$5.98 $5.98
$3.60
Grass Seeding 1 $16.50 $16.50
$6.840.70
Sideoats grama 0.40Western wheatgrass 1.00
Geographic Area
Indiangrass
Acre
This practice includes the seeding a native grass mixture with or without forbs, with limited site preparation or tillage on approximately 80 acres. Limited site preparation is defined as planting directly into cover crop, crop stubble or tilled crop stubble (includes fields that have residue tilled or shredded prior to planting). This includes seed, seeding and seedbed preparation. The seeding mix used to establish a price is listed below, however any mixture that is appropriate for the geographic location and meets NRCS practice standards can be used.
Nebraska
Typical Practice Scenario
Unit for Cost EstimatePractice Life (Years)
$16.50
Cost Summary:
UnitsBig bluestem 0.60
Notes
$4.16Source: Vendor Quotes,
September 2010$10.93$4.79
CP2; CP4B/D; CP10; CP9; CP18B/C; CP38E
$53.08
$68.18$0.00
None.
None
$0.00
$13.50
$0.00
Total CostUnits
Price/Unit
$20.35
$6.94
Blackeyed Susan
Little bluestem
Purple prairieclover 0.30$17.02
$1.06
$0.53
Units Price/Unit Total Cost
1%
2%
$0.00
Source: FY10 USDA-NRCS Program Payment Database
15Discount Rate (%/Year) 5%
Total Cost$36.58
Loss of one year of production during installation due to deferment
None.
1 $36.58
90 of 200
550_11-RangePlanting.xls CRP-Native Mix-Intermediate SP
Payment Schedule Results
550
Payment Schedule Development Methodology
50%
Nebraska
0%
50%
$0.00
$85.30$0.00$0.00$13.50
$34.50
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.71$0.00$0.00
Scenario Code
5502
PracticeCost Share Program
Practice Code
CRP
Total CostAdministration & Permit CostsRisk
Acre $35.54Range Planting CRP-Native Mix-Intermediate Site Preparation
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Equipment/InstallationMaterials
Forgone Income
$0.00$17.25$18.29
0%0%0%50%
$36.58
$35.54$0.00$0.00$0.00$0.00$0.00$0.00
50%
0%
91 of 200
550_11-RangePlanting.xls CRP-Native Mix-Intermediate SP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
Loss of one year of production during installation due to deferment
None.
1 $36.58
$0.00
$0.71
Units Price/Unit Total Cost
1%
Total CostUnits
Price/Unit
$20.35
$6.94
Blackeyed Susan
Little bluestem
Purple prairieclover 0.30
0%
CP2; CP4B/D; CP10; CP9; CP18B/C; CP38E
$71.08
$85.30
$0.00
None.
None
$0.00
$13.50
$0.00
$36.58Total Cost
$4.16
$6.11
Source: Vendor Quotes, September 2010
$3.60$5.98
$0.00
$34.50
Cost Summary:
UnitsBig bluestem 0.60
Notes
1.00Sideoats grama 0.40
Acre
This practice includes the seeding a native grass mixture with or without forbs, with complex site preparation on approximately 80 acres. Intermediate site preparation includes seeding with pre-emergent or post-emergent herbicides or use of burn down herbicides on crop/cover crop stubble. This practice includes all site preparation, seed, and seeding costs. The seed mixture used to establish a price is listed below, however, any mixture that is appropriate for the geographic location and meets NRCS practice standards can be used.
Nebraska
Typical Practice Scenario
Unit for Cost EstimateGeographic Area
$17.02
$8.99$5.98
Indiangrass
0.06
1.000.70
Western wheatgrass
Seedbed Preparation 1 $18.00 $18.00Grass Seeding 1 $16.50 $16.50
Cost Summary:1 $34.50
Units Total Cost Notes
Source: FY10 USDA-NRCS Program Payment Database
Practice Life (Years) 15Discount Rate (%/Year) 5%
$10.93$6.84
$1.02
$10.93$4.79
92 of 200
550_11-RangePlanting.xls CRP-Native Mix-Complex SP
Payment Schedule Results
550
Payment Schedule Development Methodology
$52.50$36.58
$44.54$0.00$0.00$0.00$0.00$0.00$0.00
50%Equipment/InstallationMaterials
Forgone Income
$0.00$26.25$18.29
0%0%0%50%
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $44.54Range Planting CRP-Native Mix-Complex Site Preparation
Scenario Code
5503
PracticeCost Share Program
Practice Code
CRP
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.89$0.00$0.00
Total CostAdministration & Permit CostsRisk
$0.00
$103.48$0.00$0.00$13.50
50%
Nebraska
0%0%
50%
93 of 200
550_11-RangePlanting.xls CRP-Native Mix-Complex SP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per AcreMobilization
Total Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
Cost Summary:1 $52.50
Units Total Cost Notes
Source: FY10 USDA-NRCS Program Payment
DatabaseSeedbed Preparation-Chemical 1 $18.00 $18.00
Grass Seeding 1 $16.50 $16.50Seedbed Preparation-Mechanical
$10.93$6.84
$1.02
$10.93$4.79
$17.02
$8.991.000.70
Sideoats grama 0.40Western wheatgrass 1.00
Acre
This practice includes the seeding a native grass mixture with or without forbs, with complex site preparation on approximately 80 acres. Complex site preparation includes residue management measures such as residue removal, shredding, raking, etc. and the application of burn down herbicides to kill sod, alfalfa or other perennial vegetation. This practice includes all site preparation, seed, and seeding costs. The seed mixture used to establish a price is listed below, however, any mixture that is appropriate for the geographic location and meets NRCS practice standards can be used.
Nebraska
Typical Practice Scenario
Unit for Cost EstimateGeographic Area
$0.00
$52.50
Cost Summary:
UnitsBig bluestem 0.60
Notes
$36.58Total Cost
$4.16
$6.11
Source: Vendor Quotes, September 2010
$3.60$5.98
CP2; CP4B/D; CP10; CP9; CP18B/C; CP38E
$89.08
$103.48
$0.00
None.
None
$0.00
$13.50
$0.00
$0.89
Price/Unit
$20.35
$6.94
Blackeyed Susan
Little bluestem
Purple prairieclover 0.30
$5.98
Indiangrass
0.06
Units Price/Unit Total Cost
1%
Total CostUnits
0%
1 $18.00 $18.00
Practice Life (Years) 15Discount Rate (%/Year) 5%
Loss of one year of production during installation due to deferrment
None.
1 $36.58
$0.00
94 of 200
578_11-StreamCrossing.xlsx CRP-Concrete
Payment Schedule Results
578
Payment Schedule Development Methodology
$3.18$0.00$0.00$0.00$0.00$0.00
Forgone Income
$0.00$0.00
Administration & Permit CostsRisk
$6.48$0.00
$3.03
0%0%0%50%
$0.00$6.05
Sq Ft $3.18Stream Crossing CRP-Concrete Crossing
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$0.30$0.00
$0.1550%
$0.00
50%
Scenario Code
5781
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
$0.00$0.00
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.12
0%0%
50%
Total Cost
95 of 200
578_11-StreamCrossing.xlsx CRP-Concrete
Practice Cost Data
Materials per Sq Ft
Equipment/Installation per Sq FtEquipment/Installation costs included with the cost of Materials
Labor per Sq FtLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Sq Ft
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Sq Ft
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Sq Ft
Acquisition of Technical Knowledgeper Sq Ft
Forgone Incomeper Sq Ft
Riskper Sq Ft
Administration & Permit Costsper Sq Ft
Total Cost Estimate: per Sq Ft
Associated Practices:
5%10
Sq Ft
A stabilized area constructed across a stream to provide a travel way for livestock, equipment, or vehicles. Stream grade in the area must be stable. Typical scenario is for a 10' wide channel, 4' deep. Slopes will be shaped to 8:1 slope and concrete placed to top of banks. Typical Length is 75' long. Scenario includes excavation to shape banks, and placement of 6" of concrete, 12' wide, with steel reinforcement.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
$6.05
Concrete, Flatwork (CY)
Total Cost$369.00 Source: FY10 USDA-
NRCS Program Payment Database980
17$1.23
$227.80$1,205.40$3,872.60
CP22; CP29; CP30; 3/
$6.05
$6.48
$0.00
None.
None
$0.00
$0.00
$0.00
None.
2%
Total CostUnits
Price/Unit$2.46
Steel Reinf., Rebar (LB)
5%
None.
900 $5,447.00
$0.30
$0.12
$0.00
$0.00
Cost Summary:
UnitsExcavation, Dragline/Backhoe (CY) 150
Notes
96 of 200
578_11-StreamCrossing.xlsx CRP-Rock
Payment Schedule Results
578
Payment Schedule Development Methodology
Cost/UnitCost Category
Materials
Forgone Income
$0.00$3.11
Nebraska
0%0%
Total CostAdministration & Permit CostsRisk
$3.33
Payment Rate
Unit Type
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.00$0.00$0.00
Equipment/Installation
$0.00$0.06$0.16$0.00
Sq Ft $1.63Stream Crossing CRP-Rock Crossing
Scenario Code
5782
PracticeCost Share Program
Practice Code
CRP
Scenario
$1.63$0.00$0.00$0.00$0.00$0.00
CRP Producer Payment RateCRP Program Payment Rate
50%$0.00$0.00$1.56
$0.08
0%0%0%50%
50%
50%
97 of 200
578_11-StreamCrossing.xlsx CRP-Rock
Practice Cost Data
Materials per Sq Ft
Equipment/Installation per Sq FtEquipment/Installation costs included with the cost of Materials
Labor per Sq FtLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Sq Ft
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Sq Ft
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Sq Ft
Acquisition of Technical Knowledgeper Sq Ft
Forgone Incomeper Sq Ft
Riskper Sq Ft
Administration & Permit Costsper Sq Ft
Total Cost Estimate: per Sq Ft
Associated Practices:
$0.00
$0.00
$0.00
None.
Unit for Cost Estimate
50 $45.22 $2,261.00
900 $2,802.20
$0.16
$0.06
$0.00
$0.00
CP22; CP29; CP30; 3/
$3.11
$3.33
$0.00
None.
None
$3.11
Rock, 1' thick w/ 6" Bedding (CY)
Total Cost$541.20
UnitsExcavation, Dragline/Backhoe (CY) 220
Price/Unit$2.46
Notes
Source: FY10 USDA-NRCS Program Payment Database
2%
Total CostUnits
5%
Cost Summary:
None.
5%10
Sq Ft
A stabilized area constructed across a stream to provide a travel way for livestock, equipment, or vehicles. Stream grade in the area must be stable. Typical scenario is for a 10' wide channel, 4' deep. Slopes will be shaped to 8:1 slope and rock placed to top of banks. Typical Length is 75' long. Scenario includes excavation to shape banks, and placement of 12" of rock, and 6" of bedding 12' wide.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
98 of 200
587_11-StructureforWaterControl.xlsx CRP-CMP Pipe-Riser
Payment Schedule Results
587
Payment Schedule Development Methodology
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$1.92
0%0%
50%
Total CostAdministration & Permit CostsRisk
$0.00
$100.80$0.00
50%
Scenario Code
5871
PracticeCost Share Program
Practice Code
CRP
Cost/UnitCost Category
$0.00$0.00Forgone Income 0%
0%0%
$49.44$0.00$0.00$0.00$0.00$0.00$1.44
50%
LF $49.44Structure for Water Control CRP-CMP Pipe-Riser
CRP Producer Payment RateCRP Program Payment Rate
$2.88$0.00
Equipment/InstallationMaterials
$0.00$0.00$48.00
50%
$0.00$96.00
99 of 200
587_11-StructureforWaterControl.xlsx CRP-CMP Pipe-Riser
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
2%
Total CostUnits
Price/Unit$150.00
Pipe Support (EA)Riser Fabrication (LS)
3%
1
80 $7,680.00
CP9; CP23/A; CP27; CP30
$96.00
$100.80
$0.00
None.
None
$0.00
$0.00
$0.00
None.
None.
$2.88
$1.92
$0.00
$0.00
Cost Summary:
Units54" CMP Riser (LF) 5
Notes
$96.00
30" CMP Pipe w/ Diaphragms (LF)
Total Cost$750.00 Source: FY10 USDA-
NRCS Program Payment Database1
80$750.00$66.00
$900.00$750.00
$5,280.00
$900.00
5%20LF
This scenario includes a structure for water control consisting of a CMP Riser and Pipe water control structure, pipes, diaphragms, and appurtenances. The typical structure consists of a 54" x 5' riser, and 80' of 30" diameter outlet pipe.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
100 of 200
587_11-StructureforWaterControl.xlsx CRP-Inline WC Structure
Payment Schedule Results
587
Payment Schedule Development Methodology
Equipment/InstallationMaterials
Forgone Income
$0.00$0.00$22.63
0%0%0%50%
$0.00$45.25
$0.00$0.00$0.00$0.68
50%50%50%
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
LF $23.30Structure for Water Control CRP-Inline Water Control Structure
Nebraska
Risk
$0.00
$47.51$0.00$0.00$0.00
Total CostAdministration & Permit Costs
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.91$1.36$0.00
Scenario Code
5872
PracticeCost Share Program
Practice Code
0%0%
$23.30$0.00$0.00
101 of 200
587_11-StructureforWaterControl.xlsx CRP-Inline WC Structure
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
This scenario includes a structure for water control consisting of a commercially available water control structure, pipes, diaphragms, and appurtenances. They typical structure consists of a 6' high by 24" diameter control structure and 100' of 24" dual wall PE pipe.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
$45.25
24" Pipe
Total Cost$2,035.00 Source: FY10 USDA-
NRCS Program Payment Database
Unit for Cost Estimate
1100
$500.00$19.90
UnitsInline WC Structure 1
$500.00$1,990.00
5%20LF
Price/Unit$2,035.00
WC Structure Base and Diaphragms
3%
CP9; CP23/A; CP27; CP30
$45.25
$47.51
$0.00
None.
None
$0.00
$0.00
$0.00
None.
2%
$0.00
$0.00
Cost Summary: Notes
None.
100 $4,525.00
$1.36
$0.91
Total CostUnits
102 of 200
589C_11-CrossWindTrapStrips.xlsx CRP-Cross Wind Trap Strips
Payment Schedule Results
589C
Payment Schedule Development Methodology
50%
$28.68$0.00
50%
$16.50
0%0%
$0.00
$0.00$8.25
0%
0%0%Risk
$0.00$0.00
50%
$175.00Acquisition of Tech. Knowledge $0.00
Total CostAdministration & Permit Costs
Payment Rate
Unit Type
Scenario
$1.64$2.73$0.00
$38.14
Acre $28.68CRP-Cross Wind Trap Strips
Practice
Cross Wind Trap Strips
Equipment/Installation
Operation & MaintenanceMobilizationLabor
50%
$0.00$1.37
CRP Producer Payment Rate
$19.07
Nebraska
$0.00
$234.01
$0.00
Scenario Code
5891
Cost Share Program
Practice Code
CRP
CRP Program Payment RateCost/Unit
Materials
Cost Category
Forgone Income
103 of 200
589C_11-CrossWindTrapStrips.xlsx CRP-Cross Wind Trap Strips
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
5
Source: Vendor Quotes, September 2010$3.51
$8.50
Price/Unit$4.75$7.73
Total Cost
Alfalfa $3.19
$26.13Units
$38.14
Acre
This practice includes the seedbed preparation, seeding and seed to plant trap strips to permanent vegetation. The grass seeding used to establish the cost is a mixture of Tall wheatgrass, Switchgrass and Alfalfa, however any seed mix that is appropriate for the geographic location and meets NRCS practice standards may be used. The typcial application for this practice is two 25-feet wide cross wind trap strips on a 160 acre cropland field resulting in 3 acres of cross wind trap strips.
Nebraska
Typical Practice Scenario
Unit for Cost EstimateGeographic Area
Discount Rate (%/Year) 5%Practice Life (Years)
Tall Wheatgrass 5.50Switchgrass
1.101.10
Grass Seeding
Units Total Cost
1 $16.50
CP24
$54.64
$234.01
$0.00
Reduced risk, less wind erosion, less machinery wear & tear
None
$0.00
1 $16.50
$175.00
$0.00None.
Three acres of cropland taken out of production. Assuming a corn-soybean rotation minus the value of an occassional hay/forage crop from the herbaceous cover crop.
3%
Total CostUnits
$16.50
Cost Summary:
Notes
$1.64
$2.73
Units Price/Unit
$0.00
1 $38.14Cost Summary:
Source: FY10 USDA-NRCS Program Payment Database
5%
$16.50
Notes
Total Cost
104 of 200
612_11-TreeShrubEstablishment.xlsx CRP-Trees with Mulch-Limited SP
Payment Schedule Results
612
Payment Schedule Development Methodology
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & Maintenance
Scenario Code
6121
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
MobilizationLabor
50%$0.46
0%0%0%50%
$0.00$0.92
LF $0.47Tree-Shrub Establishment CRP-Trees with Mulch-Limited Site Preparation
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$0.02$0.00
$0.0150%
50%
$0.09$0.00$0.01
$0.47$0.00$0.00$0.00$0.00$0.00
Forgone Income
$0.00$0.00
0%0%
Total CostAdministration & Permit CostsRisk
$1.04$0.00$0.00
105 of 200
612_11-TreeShrubEstablishment.xlsx CRP-Trees with Mulch-Limited SP
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
10%
Total CostUnits
Price/Unit$0.27
2%
Loss of production on approximately 1 acre of cropland
None.
3,000 $2,760.00
$0.02
$0.09
$0.00
$0.00
Cost Summary:
UnitsTrees (bare root) & machine plant (TS03) 3000
Notes
CP3/A; CP4B/D; CP11; CP31; CP33; CP38E; 4/
$0.92
$1.04
$0.00
None.
None
$0.00
$0.01
$0.00
Includes the cost to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
$0.92
Fabric Mulch (TS05)
Total Cost$810.00 Source: FY10 USDA-NRCS
Program Payment Database3000 $0.65 $1,950.00
5%25LF
This practice includes limited site preparation, planting, grass and seeding (if required), trees and fabric mulch or animal protection devices for a 3,000-feet windbreak, which includes five rows of trees, each row 600-feet long. Limited site preparation is defined as planting directly into cover crop, crop stubble or tilled crop stubble (includes fields that have residue tilled or shredded prior to planting.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
106 of 200
612_11-TreeShrubEstablishment.xlsx CRP-Trees with Mulch-Complex SP
Payment Schedule Results
612
Payment Schedule Development Methodology
Administration & Permit CostsRisk
0%0%
CRP Program Payment RateCost/UnitCost Category
LF $0.53Tree-Shrub Establishment CRP-Trees with Mulch-Complex Site Preparation
Materials
Forgone Income
$0.00$0.06$0.46
0%0%0%50%
$0.00
$0.92
$0.00$0.00$0.00$0.01
50%$0.11
50%
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.10$0.02$0.00
Scenario Code
6122
PracticeCost Share Program
Practice Code
CRP
CRP Producer Payment Rate
50%
$0.00$0.00$0.01
$0.53$0.00$0.00
$1.16
Equipment/Installation
Total Cost
107 of 200
612_11-TreeShrubEstablishment.xlsx CRP-Trees with Mulch-Complex SP
Practice Cost Data
Materials per LF
Equipment/Installation per LF
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
3,000 $330.00Cost Summary: Units Total Cost Notes
Practice Life (Years) 25Discount Rate (%/Year) 5%
Site Preparation for trees (TS02) 3000
LF
This practice includes complex site preparation, planting, grass and seeding (if required), trees and fabric mulch or animal protection devices for a 3,000-feet windbreak, which includes five rows of trees, each row 600-feet long. Complex site preparation includes residue managment measures such as residue removal, shredding, raking, etc. and the application of burn down herbicides to kill sod, alfalfa or other perennial vegetation.
Nebraska
Typical Practice Scenario
Geographic Area
$0.00
$0.11
Cost Summary:
UnitsTrees (bare root) & machine plant (TS03) 3000
Source: FY10 USDA-NRCS Program Payment Database
$0.11 $330.00
CP3/A; CP4B/D; CP11; CP31; CP33; CP38E; 4/
$1.03
$1.16
$0.00
None.
None
Notes
$0.92
Fabric Mulch (TS05)
Total Cost$810.00 Source: FY10 USDA-NRCS
Program Payment Database
Price/Unit$0.27
$0.00
$0.01
$0.00
Includes the cost to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
10%
Total CostUnits
2%
Units Price/Unit
Loss of production on approximately 1 acre of cropland
None.
3,000 $2,760.00
$0.02
$0.10
Total Cost
Unit for Cost Estimate
3000 $0.65 $1,950.00
108 of 200
612_11-TreeShrubEstablishment.xlsx CRP-Trees wo Mulch-Limited SP
Payment Schedule Results
612
Payment Schedule Development Methodology
Equipment/InstallationMaterials
Forgone Income
$0.00$0.00$0.14
0%0%0%50%
$0.00$0.27
$0.00$0.00$0.00$0.00
50%50%50%
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
LF $0.14Tree-Shrub Establishment CRP-Trees without Mulch-Limited Site Preparation
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$0.31$0.00$0.00$0.01
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.03$0.01$0.00
Scenario Code
6123
PracticeCost Share Program
Practice Code
0%0%
$0.14$0.00$0.00
109 of 200
612_11-TreeShrubEstablishment.xlsx CRP-Trees wo Mulch-Limited SP
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
This practice includes limited site preparation, planting, grass and seeding (if required), and trees for a 3,000-feet windbreak, which includes five rows of trees, each row 600-feet long. Limited site preparation is defined as planting directly into cover crop, crop stubble or tilled crop stubble (includes fields that have residue tilled or shredded prior to planting.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
$0.27Total Cost$810.00 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost Estimate
UnitsTrees (bare root) & machine plant (TS03) 3000
5%25LF
Price/Unit$0.27
2%
CP3/A; CP4B/D; CP11; CP31; CP33; CP38E; 4/
$0.27
$0.31
$0.00
None.
None
$0.00
$0.01
$0.00
Includes the cost to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
10%
$0.00
$0.00
Cost Summary: Notes
Loss of production on approximately 1 acre of cropland
None.
3,000 $810.00
$0.01
$0.03
Total CostUnits
110 of 200
612_11-TreeShrubEstablishment.xlsx CRP-Trees wo Mulch-Complex SP
Payment Schedule Results
612
Payment Schedule Development Methodology
Labor
$0.04$0.01
0%Total CostAdministration & Permit Costs
$0.44$0.00
$0.19$0.00
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$0.11$0.27Materials $0.14
Nebraska
50%
Scenario Code
6124
PracticeCost Share Program
Practice Code
CRP
Payment Rate
Unit Type
Scenario
LF $0.19Tree-Shrub Establishment CRP-Trees without Mulch-Complex Site Preparation
$0.00$0.00$0.00$0.00$0.00
50%Equipment/Installation
Forgone Income
$0.00$0.06
0%0%0%50%
$0.00
0%
50%
Risk
$0.00
$0.00$0.01
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilization
111 of 200
612_11-TreeShrubEstablishment.xlsx CRP-Trees wo Mulch-Complex SP
Practice Cost Data
Materials per LF
Equipment/Installation per LF
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
10%
Total CostUnits
Price/Unit$0.27
2%
Units Price/UnitSite Preparation for trees (TS02) 3000
3,000 $810.00
$0.11
CP3/A; CP4B/D; CP11; CP31; CP33; CP38E; 4/
$0.38
$0.44
$0.00
None.
None
$0.00
$0.01
$0.00
Includes the cost to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
Loss of production on approximately 1 acre of cropland
None.
$0.01
$0.04
$0.00
$0.11
Cost Summary:
UnitsTrees (bare root) & machine plant (TS03) 3000
Notes
Source: FY10 USDA-NRCS Program Payment Database
Total Cost$810.00 Source: FY10 USDA-NRCS
Program Payment Database
Total Cost
This practice includes complex site preparation, planting, grass and seeding (if required), and trees for a 3,000-feet windbreak, which includes five rows of trees, each row 600-feet long. Complex site preparation includes residue managment measures such as residue removal, shredding, raking, etc. and the application of burn down herbicides to kill sod, alfalfa or other perennial vegetation.
Nebraska
Typical Practice Scenario
Geographic AreaUnit for Cost Estimate
Practice Life (Years) 25Discount Rate (%/Year) 5%
3,000 $330.00
$0.27
LF
$330.00
Cost Summary: Units Total Cost Notes
112 of 200
612_11-TreeShrubEstablishment.xlsx CRP-Replants
Payment Schedule Results
612
Payment Schedule Development Methodology
Equipment/InstallationMaterials
Forgone Income
$0.00$0.00$1.00
0%0%0%50%
$0.00$2.00
$0.00$0.00$0.00$0.03
50%50%50%
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Each $1.03Tree-Shrub Establishment CRP-Replants
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$2.27$0.00$0.00$0.01
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.20$0.06$0.00
Scenario Code
6125
PracticeCost Share Program
Practice Code
0%0%
$1.03$0.00$0.00
113 of 200
612_11-TreeShrubEstablishment.xlsx CRP-Replants
Practice Cost Data
Materials per Each
Equipment/Installation per EachEquipment/Installation costs included with the cost of Materials
Labor per EachLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Each
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Each
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Each
Acquisition of Technical Knowledgeper Each
Forgone Incomeper Each
Riskper Each
Administration & Permit Costsper Each
Total Cost Estimate: per Each
Associated Practices:
This practice includes the replanting of select trees due to death or damage of the seedlings following an initial windbreak/shelterbelt establishment.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
$2.00
(weighted avg TS11&TS13)
Total Cost$2.00 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost Estimate
UnitsTrees & hand plant 1
5%25
Each
Price/Unit$2.00
3%
CP3/A; CP4B/D; CP11; CP31; CP33; CP38E; 4/
$2.00
$2.27
$0.00
None.
None
$0.00
$0.01
$0.00
Includes the cost to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
10%
$0.00
$0.00
Cost Summary: Notes
Loss of production on approximately 1 acre of cropland
None.
1 $2.00
$0.06
$0.20
Total CostUnits
114 of 200
612_11-TreeShrubEstablishment.xlsx CRP-Direct Seeding
Payment Schedule Results
612
Payment Schedule Development Methodology
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$5.72
0%0%
50%
Total Cost
Scenario Code
6126
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
$0.00$0.01
$125.00
0%0%0%50%
$36.00$250.00
Acre $147.29Tree-Shrub Establishment CRP-Direct Seeding
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$8.58$0.00
$4.2950%
$0.00
50%
$147.29$0.00$0.00$0.00$0.00$0.00
Forgone Income
$0.00$18.00
Administration & Permit CostsRisk
$300.31$0.00
115 of 200
612_11-TreeShrubEstablishment.xlsx CRP-Direct Seeding
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
2%
Total CostUnits
Price/Unit$250.00
3%
Mechanical Seedbed Preparation 1 $18.00
Cost Summary:
1 $250.00
Units Price/Unit
Chemical Seedbed Preparation 1 $18.00Units Total Cost
1 $36.00
CP3/A; CP4B/D; CP11; CP31; CP33; CP38E
$286.00
$300.31
$0.00
None.
None
$0.00
$0.01
$0.00
Includes the cost to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
Loss of production on approximately 1 acre of cropland
None.
$8.58
$5.72
$0.00
$36.00
Cost Summary:
UnitsSeed & Seed Collection 1
Notes
$250.00Total Cost$250.00
Total Cost$18.00 Source: FY10 USDA-NRCS
Program Payment Database$18.00Notes
Source: FY10 USDA-NRCS Program Payment Database
5%25
Acre
This practice includes the seed, seed collection, and site preparation for trees or shrubs which are direct seeded. This scenario is typically used to direct seed large seeded species such as Oaks or Walnuts using a tree seed planter. Site preparation could include residue management measures such as residue removal, shredding, raking, etc., and the application of burn down herbicides to kill sod, alfalfa, or other perennial vegetation. This practice meets the requirements listed in the 380 Windbreak/Shelterbelt Establishment Tree Planting Procedures. Typical application of this scenario is 5 acres.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
116 of 200
612_11-TreeShrubEstablishment.xlsx CRP-Shrub Thicket
Payment Schedule Results
612
Payment Schedule Development Methodology
$0.26$0.00$0.00$0.00$0.00$0.00$0.01
50% $0.00$0.04$0.21
0%0%0%50%
$0.08$0.42
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
LF $0.26Tree-Shrub Establishment CRP-Shrub Thickets
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$0.57$0.00$0.00$0.01
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.05$0.01$0.00
Scenario Code
6127
PracticeCost Share Program
Practice Code
0%0%
50%50%
Equipment/InstallationMaterials
Forgone Income
117 of 200
612_11-TreeShrubEstablishment.xlsx CRP-Shrub Thicket
Practice Cost Data
Materials per LF
Equipment/Installation per LF
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
Notes
$40.00 Source: FY10 USDA-NRCS Program Payment Database
Chemical Seedbed Preparation
5%25LF
This practice for a wildlife shrub thicket includes mechanical/chemical site preparation, planting, and shrubs for a 30' x 50' thicket containing 150 shrubs planted in 10 rows 50 feet long with shrubs at 3 1/2 foot spacing.
Nebraska
$0.42Total Cost$210.00 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost Estimate
UnitsTree & Shrub Planting 500
Total Cost
CP4B/D; CP31; CP38E
$0.50
$0.57
$0.00
None.
None
$0.00
$0.01
$0.00
Includes the cost to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
None
None.
$0.01
$0.0510%
Total CostUnits
Price/Unit$0.42
2%
500 $0.08
Cost Summary: Units
Cost Summary:500 $210.00
Units Price/Unit
$0.00
$0.08
500 $40.00Total Cost Notes
118 of 200
614_11-WateringFacility.xls CRP-Steel Tank, Steel Bottom
Payment Schedule Results
614
Payment Schedule Development Methodology
50%
Nebraska
0%
50%
Total CostAdministration & Permit CostsRisk
$0.00
$63.74$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$3.04$0.00$0.00
Scenario Code
6141
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
Dia-Ft $30.35Watering Facility CRP-Steel Tank with Steel Bottom
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Forgone Income
$0.00$0.00$30.35
0%0%0%50%
$0.00$60.70
$0.0050%
$30.35$0.00$0.00$0.00$0.00$0.00
0%
119 of 200
614_11-WateringFacility.xls CRP-Steel Tank, Steel Bottom
Practice Cost Data
Materials per Dia-Ft
Equipment/Installation per Dia-FtEquipment/Installation costs included with the cost of Materials
Labor per Dia-FtLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Dia-Ft
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Dia-Ft
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Dia-Ft
Acquisition of Technical Knowledgeper Dia-Ft
Forgone Incomeper Dia-Ft
Riskper Dia-Ft
Administration & Permit Costsper Dia-Ft
Total Cost Estimate: per Dia-Ft
Associated Practices:
None.
11 $667.70
$0.00
$3.045%
Total CostUnits
Price/Unit$60.70
0%
CP21; CP22; CP29; CP30
$60.70
$63.74
$0.00
Reduced risk; more reliable source of water for livestock
None
$0.00
$0.00
$0.00
None.
Total Cost$667.70 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost EstimateGeographic Area
$0.00
$0.00
Cost Summary:
UnitsSteel tank with Steel bottom (TA01) 11
Notes
$60.70
5%10
Dia-Ft
The typical application of this scenario is an 11-foot diameter steel bottom tank (1,422 gallon capacity). This scenario also includes those situations in which a plastic tank is installed.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
120 of 200
614_11-WateringFacility.xls CRP-Steel Tank, Concrete Bottom
Payment Schedule Results
614
Payment Schedule Development Methodology
0%
$92.53$0.00$0.00$0.00$0.00$0.000%
50%
$0.00$176.25
$4.4150%
Dia-Ft $92.53Watering Facility CRP-Steel Tank with Concrete Bottom
Forgone Income
$0.00$0.00$88.13
0%0%
Equipment/InstallationMaterials
50%
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Scenario Code
6142
PracticeCost Share Program
Practice Code
CRP
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$8.81$8.81$0.00
50%
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$193.88$0.00$0.00$0.00
0%
121 of 200
614_11-WateringFacility.xls CRP-Steel Tank, Concrete Bottom
Practice Cost Data
Materials per Dia-Ft
Equipment/Installation per Dia-FtEquipment/Installation costs included with the cost of Materials
Labor per Dia-FtLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Dia-Ft
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Dia-Ft
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Dia-Ft
Acquisition of Technical Knowledgeper Dia-Ft
Forgone Incomeper Dia-Ft
Riskper Dia-Ft
Administration & Permit Costsper Dia-Ft
Total Cost Estimate: per Dia-Ft
Associated Practices:
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
Notes
5%10
Dia-Ft
The typical application of this scenario is a 20-foot diameter concrete bottom tank (4,700 gallon capacity) with a 2-foot concrete apron around the tank.
Nebraska
$176.25
Concrete-horizontal (C03)
Total Cost$3,159.00 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost Estimate
3 $122.00 $366.00
Units
CP21; CP22; CP29; CP30
$176.25
$193.88
$0.00
Reduced risk; more reliable source of water for livestock
None
$0.00
$0.00
$0.00
None.
5%
Total CostUnits
Price/Unit$157.95
5%
Cost Summary:
Steel Tank with Concrete bottom (TA02) 20
None.
20 $3,525.00
$8.81
$8.81
$0.00
$0.00
122 of 200
614_11-WateringFacility.xls CRP-Steel Tank, NonCncrt Bottom
Payment Schedule Results
614
Payment Schedule Development Methodology
50%
Nebraska
0%
50%
Total CostAdministration & Permit CostsRisk
$0.00
$90.83$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$3.95$7.90$0.00
Scenario Code
6143
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
Dia-Ft $43.44Watering Facility CRP-Steel Tank with Non-Concrete Bottom
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Forgone Income
$0.00$0.00$39.49
0%0%0%50%
$0.00$78.98
$3.9550%
$43.44$0.00$0.00$0.00$0.00$0.00
0%
123 of 200
614_11-WateringFacility.xls CRP-Steel Tank, NonCncrt Bottom
Practice Cost Data
Materials per Dia-Ft
Equipment/Installation per Dia-FtEquipment/Installation costs included with the cost of Materials
Labor per Dia-FtLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Dia-Ft
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Dia-Ft
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Dia-Ft
Acquisition of Technical Knowledgeper Dia-Ft
Forgone Incomeper Dia-Ft
Riskper Dia-Ft
Administration & Permit Costsper Dia-Ft
Total Cost Estimate: per Dia-Ft
Associated Practices:
None.
20 $1,579.60
$7.90
$3.955%
Total CostUnits
Price/Unit$78.98
10%
CP21; CP22; CP29; CP30
$78.98
$90.83
$0.00
Reduced risk; more reliable source of water for livestock
None
$0.00
$0.00
$0.00
None.
Total Cost$1,579.60 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost EstimateGeographic Area
$0.00
$0.00
Cost Summary:
UnitsSteel Tank w/ Non-Concrete bottom(TA03) 20
Notes
$78.98
5%10
Dia-Ft
The typical application of this scenario is a 20-foot diameter concrete bottom tank (4,700 gallon capacity) without a concrete apron around the tank.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
124 of 200
614_11-WateringFacility.xls CRP-Rubber Tire(Non-Steel) Tank
Payment Schedule Results
614
Payment Schedule Development Methodology
0%
$72.45$0.00$0.00$0.00$0.00$0.000%
50%
$0.00$131.73
$6.5950%
Dia-Ft $72.45Watering Facility CRP-Rubber Tire Tank
Forgone Income
$0.00$0.00$65.87
0%0%
Equipment/InstallationMaterials
50%
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Scenario Code
6144
PracticeCost Share Program
Practice Code
CRP
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$6.59$13.17$0.00
50%
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$151.49$0.00$0.00$0.00
0%
125 of 200
614_11-WateringFacility.xls CRP-Rubber Tire(Non-Steel) Tank
Practice Cost Data
Materials per Dia-Ft
Equipment/Installation per Dia-FtEquipment/Installation costs included with the cost of Materials
Labor per Dia-FtLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Dia-Ft
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Dia-Ft
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Dia-Ft
Acquisition of Technical Knowledgeper Dia-Ft
Forgone Incomeper Dia-Ft
Riskper Dia-Ft
Administration & Permit Costsper Dia-Ft
Total Cost Estimate: per Dia-Ft
Associated Practices:
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
Notes
5%10
Dia-Ft
The typical application of this scenario is a 8-foot diameter (752 gallon capacity) non-steel or rubber tire tank, with a concrete base and a 2-foot concrete apron around the outside base of the tank. This scenario also includes those situations in which a fiberglass tank is installed.
Nebraska
$131.73
Concrete-Horizontal (C03)
Total Cost$687.84 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost Estimate
3 $122.00 $366.00
Units
CP21; CP22; CP29; CP30
$131.73
$151.49
$0.00
Reduced risk; more reliable source of water for livestock
None
$0.00
$0.00
$0.00
None.
5%
Total CostUnits
Price/Unit$85.98
10%
Cost Summary:
Non-Steel Tank (TA04) 8
None.
8 $1,053.84
$13.17
$6.59
$0.00
$0.00
126 of 200
614_11-WateringFacility.xls CRP-Wildlife Guzzler
Payment Schedule Results
614
Payment Schedule Development Methodology
50%
Nebraska
0%
50%
Total CostAdministration & Permit CostsRisk
$0.00
$1,388.40$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$13.35$40.05$0.00
Scenario Code
6145
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
Each $687.53Watering Facility CRP-Wildlife Guzzler
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Forgone Income
$0.00$0.00
$667.50
0%0%0%50%
$0.00$1,335.00
$20.0350%
$687.53$0.00$0.00$0.00$0.00$0.00
0%
127 of 200
614_11-WateringFacility.xls CRP-Wildlife Guzzler
Practice Cost Data
Materials per Each
Equipment/Installation per EachEquipment/Installation costs included with the cost of Materials
Labor per EachLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Each
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Each
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Each
Acquisition of Technical Knowledgeper Each
Forgone Incomeper Each
Riskper Each
Administration & Permit Costsper Each
Total Cost Estimate: per Each
Associated Practices:
None.
1 $1,335.00
$40.05
$13.351%
Total CostUnits
Price/Unit$1,335.00
3%
As required due to ranking
$1,335.00
$1,388.40
$0.00
None
None
$0.00
$0.00
$0.00
None.
Total Cost$1,335.00 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost EstimateGeographic Area
$0.00
$0.00
Cost Summary:
UnitsRain Traps & Guzzlers (T80) 1
Notes
$1,335.00
5%10
Each
The typical application of this scenario is construction of a wildlife watering facility. This application includes a 14-foot by 14-foot rain collection roof with gutter and a 300 gallon storage tank.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
128 of 200
620_11_UndergroundOutlet.xlsx CRP-Wetland
Payment Schedule Results
620
Payment Schedule Development Methodology
Equipment/InstallationMaterials
Forgone Income
$0.00$0.00$18.50
0%0%0%50%
$0.00$37.00
$0.00$0.00$0.00$0.93
50%50%50%
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
LF $19.43Underground Outlet Wetland
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$39.96$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$1.11$1.85$0.00
Scenario Code
6204
PracticeCost Share Program
Practice Code
0%0%
$19.43$0.00$0.00
129 of 200
620_11_UndergroundOutlet.xlsx CRP-Wetland
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
This practice includes installation of outlet works for wetland situations. Single outlet includes 100 feet of 12" pipe (HDPE or PVC) with inline water control structure and CMP on inlet and outlet sections.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
$37.00
18" inline water control structure
Total Cost$1,490.00 Source: FY10 USDA-
NRCS Program Payment Database
Unit for Cost Estimate
201
$43.50$1,340.00
Units12" 32.5sdr 125 psi or less PVC pipe 100
$870.00$1,340.00
5%20LF
Price/Unit$14.90
15" CMP (P05)
5%
CP8A; CP9; CP21; CP23/A; CP27; CP29; CP30
$37.00
$39.96
$0.00
None.
None
$0.00
$0.00
$0.00
O&M Plan is required. Regular inspection and maintenance of facility, including records is required.
3%
$0.00
$0.00
Cost Summary: Notes
None.
None.
100 $3,700.00
$1.85
$1.11
Total CostUnits
130 of 200
638_11_WaterSedControlBasin.xlsx CRP-Basin
Payment Schedule Results
638
Payment Schedule Development Methodology
Equipment/InstallationMaterials
Forgone Income
$0.00$0.00$0.85
0%0%0%50%
$0.00$1.70
$0.00$0.00$0.00$0.04
50%50%50%
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Cu Yd $0.89Water and Sediment Control Basin
CRP-Basin
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$1.80$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.02$0.09$0.00
Scenario Code
6381
PracticeCost Share Program
Practice Code
0%0%
$0.89$0.00$0.00
131 of 200
638_11_WaterSedControlBasin.xlsx CRP-Basin
Practice Cost Data
Materials per Cu Yd
Equipment/Installation per Cu YdEquipment/Installation costs included with the cost of Materials
Labor per Cu YdLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Cu Yd
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Cu Yd
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Cu Yd
Acquisition of Technical Knowledgeper Cu Yd
Forgone Incomeper Cu Yd
Riskper Cu Yd
Administration & Permit Costsper Cu Yd
Total Cost Estimate: per Cu Yd
Associated Practices:
The construction of an water and sediment control basin which has a drainage area of less than or equal to 30 acres. The typical size of the practice is 500 cubic yards.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
$1.70Total Cost$850.00 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost Estimate
UnitsEarthfill-Class C Compaction (E02) 500
5%10
Cu Yd
Price/Unit$1.70
5%
$1.70
$1.80
$0.00
None.
None
$0.00
$0.00
$0.00
None.
1%
$0.00
$0.00
Cost Summary: Notes
None.
500 $850.00
$0.09
$0.02
Total CostUnits
132 of 200
642_11_WaterWell.xlsx CRP-Depth <= 100 feet
Payment Schedule Results
642
Payment Schedule Development Methodology
$11.18$0.00$0.00$0.00$0.00$0.00
Forgone Income
$0.00$0.00
0%0%
Total CostAdministration & Permit CostsRisk
$22.48$0.00$0.00
$6.60
0%0%0%50%
$0.00$13.20
LF $11.18Water Well CRP-Depth of <= 100 feet
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$9.15$0.00
$4.5850%
50%
$0.13$0.00$0.00
Scenario Code6421
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
MobilizationLabor
50%
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & Maintenance
133 of 200
642_11_WaterWell.xlsx CRP-Depth <= 100 feet
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationFlat fee for set up charge of $550 per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
$13.20Total Cost$792.00 Source: FY10 USDA-NRCS
Program Payment Database
5%20LF
This practice includes the drilling, casing, and gravel pack for one livestock well to a depth of 60' below the ground surface.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
CP21; CP22; CP29; CP30
$13.20
$22.48
$0.00
Reduced risk; more reliable source of water.
None
$0.00
$0.00
$0.00
None.
1%
Total CostUnits
Price/Unit$13.20
None.
60 $792.00
$9.15
$0.13
$0.00
$0.00
Cost Summary:
UnitsWell drilling & casing (W42) 60
Notes
134 of 200
642_11_WaterWell.xlsx CRP-Depth > 100 feet
Payment Schedule Results
642
Payment Schedule Development Methodology
0%0%
$6.60$0.00$0.00
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$13.33$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.13$0.00$0.00
Scenario Code6422
PracticeCost Share Program
Practice Code
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
LF $6.60Water Well CRP-Depth of > 100 feet
Equipment/InstallationMaterials
Forgone Income
$0.00$0.00$6.60
0%0%0%50%
$0.00$13.20
$0.00$0.00$0.00$0.00
50%50%50%
135 of 200
642_11_WaterWell.xlsx CRP-Depth > 100 feet
Practice Cost Data
Materials per LF
Equipment/Installation per LFEquipment/Installation costs included with the cost of Materials
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LF
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per LF
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per LF
Acquisition of Technical Knowledgeper LF
Forgone Incomeper LF
Riskper LF
Administration & Permit Costsper LF
Total Cost Estimate: per LF
Associated Practices:
$0.00
$0.00
Cost Summary: Notes
None.
200 $2,640.00
$0.00
$0.13
Total CostUnits
0%
CP21; CP22; CP29; CP30
$13.20
$13.33
$0.00
Reduced risk; more reliable source of water.
None
$0.00
$0.00
$0.00
None.
1%
$13.20Total Cost$2,640.00 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost Estimate
UnitsWell drilling & casing (W42) 200
5%20LF
Price/Unit$13.20
This practice includes the drilling, casing, and gravel pack for one livestock well to a depth of 200' below the ground surface.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
136 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-Basic Mix-Limited SP
Payment Schedule Results
643
Payment Schedule Development Methodology
Nebraska
0%0%
50%
Total CostAdministration & Permit CostsRisk
$0.00
$83.07$0.00$0.00$0.00
Payment Rate
Unit TypeScenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$1.58$2.37$0.00
Scenario Code
6431
PracticeCost Share Program
Practice Code
CRP
50%Equipment/InstallationMaterials
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $40.74Restoration and Management of Declining Habitats
CRP-Basic Mix-Limited Site Preparation
Forgone Income
$0.00$8.25
$31.31
0%0%0%
50%
50%
$0.00$0.00$1.19
$16.50$62.61
$40.74$0.00$0.00$0.00
137 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-Basic Mix-Limited SP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per AcreMobilization
Total Materials, Equipment/Installation and Labor Costs. per AcreOperation & Maintenance
Total Materials, Equipment/Installation and Labor Costs. per AcreAcquisition of Technical Knowledge
per AcreForgone Income
per AcreRisk
per AcreAdministration & Permit Costs
per AcreTotal Cost Estimate: per Acre
Associated Practices:
Prairie aster 0.01 141.25 $1.41
Canada milkvetch 0.02 $37.70 $0.75Cudweed sagewort 0.01 $159.92 $1.60
Plains coreopsis 0.05 $16.95 $0.85
Indiangrass 0.40 $6.84 $2.74Little bluestem 1.00 $10.93 $10.93
Slender wheatgrass 0.50 $4.39 $2.20
Grass SeedingCost Summary:
20 $330.00
Prairie junegrass 0.03 $41.62 $1.25Sideoats grama 0.50 8.99 $4.50
Black-eyed Susan 0.04 $17.02 $0.68Western wheatgrass 0.55
Showy partridgepea 0.10 $11.68 $1.17Stiff goldenrod
1 $62.61
$2.37
$1.58
Units Price/Unit Total Cost
$0.00
$16.50
$16.50 $330.00Units Total Cost Notes20
Source: FY10 USDA-NRCS Program Payment Database
2%
Total CostUnits
Price/Unit
$28.99
$6.94
Upright coneflower
Canada wildrye
Western yarrow 0.02
3%
Cost Summary:
UnitsBig bluestem 0.60Blue grama
0.04
0.500.10
Purple prairieclover 0.05
Stiff sunflower 0.04
False sunflower
CP25
$79.11
$83.07$0.00
None.
None
$0.00
$0.00
$0.00
None.
None.
$62.61Total Cost$4.16
$0.58
Source: Vendor Quotes, September 2010
$1.02
$13.43
$2.94$1.71
$3.29
$2.13
Notes
Leadplant 0.02 $85.38
Acre
This practice includes the seeding of a basic prairie seed mix (approximately 20 species) with limited site preparation. Limited site preparation includes planting directly into a cover crop, crop stubble or tilled crop stubble. The seed mixture used to establish this price is based on the mixture shown below, however, any mixture which is appropriate for the geographic area as well as meets NRCS practice standards can be used. This practice is typically applied on 20 acres.
Nebraska
Typical Practice Scenario
Unit for Cost EstimateGeographic Area
0.08
$6.73$9.19
$1.01
$3.37$0.92
$25.19
$20.35
$335.67
$36.70
5.98
0.02 $106.74
Practice Life (Years) 15Discount Rate (%/Year) 5%
138 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-Basic Mix-Complex SP
Payment Schedule Results
643
Payment Schedule Development Methodology
$26.25$32.03
0%0%0%
50%
$0.00
50%$52.50$64.06
$60.03$0.00$0.00$0.00$0.00$0.00$1.75
50%
$0.00
$0.00
Materials
Forgone Income
MobilizationLabor
$2.33$3.50$0.00
Total CostAdministration & Permit CostsRisk
$0.00
$122.39$0.00
Acre $60.03Restoration and Management of Declining Habitats
CRP-Basic Mix-Complex Site Preparation
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Equipment/Installation
Nebraska
0%0%
50%
Scenario Code
6432
PracticeCost Share Program
Practice Code
CRP
Payment Rate
Unit TypeScenario
Acquisition of Tech. KnowledgeOperation & Maintenance
139 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-Basic Mix-Complex SP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per AcreMobilization
Total Materials, Equipment/Installation and Labor Costs. per AcreOperation & Maintenance
Total Materials, Equipment/Installation and Labor Costs. per AcreAcquisition of Technical Knowledge
per AcreForgone Income
per AcreRisk
per AcreAdministration & Permit Costs
per AcreTotal Cost Estimate: per Acre
Associated Practices:
Big bluestem 0.60Price/Unit
Source: FY10 USDA-NRCS Program Payment
Database
Grass Seeding
$6.73$9.19
$1.01
$3.37$0.92
$25.19
$20.35
$36.70
0.10
Purple prairieclover 0.05
Stiff sunflower 0.04
Acre
This practice includes the seeding of a basic prairie seed mix (approximately 20 species) with complex site preparation. Complex site preparation includes residue management measures such as residue removal, shredding, raking, etc. and application of burn down, pre-emergent or post-emergent herbicides on existing grass sod. The seed mixture used to establish this price is based on the mixture shown below, however, any mixture which is appropriate for the geographic area as well as meets NRCS practice standards can be used. This practice is typically applied on 20 acres.
Nebraska
Typical Practice Scenario
Unit for Cost EstimateGeographic Area 15
5%
$64.06Total Cost$4.16
$0.58
Source: Vendor Quotes, September 2010
$1.02
$13.43
$2.94$1.71
$1.41
$0.75
$0.85
$10.93$2.74
$4.50$1.25
CP25
$116.56
$122.39$0.00
None.
None
$0.00
$0.00
$0.00
None.
None.
$2.33
$3.50
$0.00
$52.50
Cost Summary:
Cost Summary:20 $1,050.00
Units Total Cost Notes
Seedbed Preparation-Mechanical$330.00
Units Price/Unit Total Cost
Notes
Seedbed Preparation-Chemical 20 $18.00 $360.0020 $18.00 $360.00
2%
Total CostUnits
3%
20 $16.50
Leadplant 0.02 $85.38
1 $64.06
Prairie aster 0.01 141.250.05 $16.95
$28.99Upright coneflowerWestern yarrow 0.02
0.04$335.67
Plains coreopsis
Black-eyed Susan 0.04 $17.02 $0.68
Slender wheatgrass 0.50
Stiff goldenrod 0.02 $106.74 $2.13Showy partridgepea 0.10 $11.68 $1.17
Cudweed sagewort 0.01 $304.45 $3.04Canada milkvetch 0.02 $37.70
False sunflower 0.08
$4.39
Practice Life (Years)Discount Rate (%/Year)
Western wheatgrass 0.55 5.98 $3.29
Sideoats grama 0.50$2.20
$6.94
Canada wildryeBlue grama
0.50
Little bluestem 1.00 $10.93Indiangrass 0.40 $6.84
8.99Prairie junegrass 0.03 $41.62
Units
140 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-HighDiversityMix-LimitedSP
Payment Schedule Results
643
Payment Schedule Development Methodology
$187.50
0%0%0%
50%
$16.50$375.00
$201.62$0.00$0.00$0.00$0.00$0.00$5.87
50%
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$7.83$11.75$0.00
Total CostAdministration & Permit CostsRisk
$0.00
$411.08$0.00$0.00$0.00Forgone Income
Scenario Code
6433
PracticeCost Share Program
Practice Code
CRP
Payment Rate
Unit TypeScenario
Nebraska
0%0%
50%
Acre $201.62Restoration and Management of Declining Habitats
CRP-High Diversity Local Ecotype Mixture-Limited Site
Preparation
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
50%Equipment/InstallationMaterials
$0.00$8.25
141 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-HighDiversityMix-LimitedSP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
$375.00Total Cost$7,500.00 Source: FY10 USDA-NRCS
Program Payment Database
Source: FY10 USDA-NRCS Program Payment Database
Grass Seeding
$16.50
Cost Summary:
UnitsHigh Diversity Seed Mixture 20.00
Notes
Price/Unit
Acre
This practice includes the seeding of a high diversity seed mix (approximately 50-200 species) from a local ecotype seed source with limited site preparation. Limited site preparation includes planting directly into a cover crop, crop stubble or tilled crop stubble. This practice is typically applied on 20 acres. The seed mixture used to establish this price is on file in the State Office, please contact the Wildlife Biologist fur futher assistance with this pracitce.
Nebraska
Typical Practice Scenario
Geographic AreaUnit for Cost Estimate
Units Total Cost Notes
2%
Total CostUnits
3%
CP25
$391.50
$411.08
$0.00
None.
None
$0.00
$0.00
$0.00
None.
Practice Life (Years) 15Discount Rate (%/Year) 5%
None.
20 $7,500.00
$11.75
$7.83
20 $16.50Units Price/Unit Total Cost
$330.00
$0.00
$375.00
Cost Summary:20 $330.00
142 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-HighDiversityMix-ComplexSP
Payment Schedule Results
643
Payment Schedule Development Methodology
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$448.88$0.00$0.00$0.00
Payment Rate
Unit TypeScenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$8.55$12.83$0.00
Scenario Code
6434
PracticeCost Share Program
Practice Code
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $220.16Restoration and Management of Declining Habitats
CRP-High Diversity Local Ecotype Mixture-Complex
Site PreparationCRP
Materials
Forgone Income
$0.00$26.25$187.50
0%0%0%
50%
$52.50$375.00
50%50%
$220.16$0.00$0.00$0.00$0.00$0.00$6.41
50%Equipment/Installation
0%0%
143 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-HighDiversityMix-ComplexSP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per AcreMobilization
Total Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
$12.83
$8.55
Units Price/Unit Total Cost$330.00
$0.00
$52.50
$360.00$360.00
Source: FY10 USDA-NRCS Program Payment
Database
Notes
2%
Total CostUnits
Price/Unit$375.00
3%
20 $16.50
Seedbed Preparation-Chemical 20
Cost Summary:
$18.0020 $18.00
20 $7,500.00
Grass Seeding
Cost Summary:20 $1,050.00
Units Total Cost
Seedbed Preparation-Mechanical
CP25
$427.50
$448.88
$0.00
None.
None
$0.00
$0.00
$0.00
None.
None.
Notes
5%15
Acre
This practice includes the seeding of a high diversity seed mix (approximately 50-200 species) from a local ecotype seed source with site preparation. Site preparation could include residue management measures such as residue removal, shredding, raking, etc. and application of burn down, pre-emergent, post-emergent herbicides on existing grass sod. This practice is typically applied on 20 acres. The seed mixture used to establish this price is on file in the State Office, please contact the Wildlife Biologist for further assistance with this practice.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
$375.00Total Cost$7,500.00 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost Estimate
UnitsHigh Diversity Seed Mixture 20.00
144 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-Trees with Mulch
Payment Schedule Results
643
Payment Schedule Development Methodology
$8.25$633.26
0%0%
$12.83
$654.34$0.00$0.00$0.00
$0.00
Forgone Income
$0.00
$1,436.97$0.00$0.00$0.00
Acre $654.34Restoration and Management of Declining Habitats
Cost Category
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$128.30$25.66$0.00
Administration & Permit CostsRisk
$0.00
$16.50$1,266.51
0%50%
50%
50%
$0.00
CRP-Trees with Mulch
CRP Producer Payment RateCRP Program Payment RateCost/Unit
Equipment/InstallationMaterials
Nebraska
0%0%
50%
Scenario Code
6435
PracticeCost Share Program
Practice Code
CRP
Total Cost
Payment Rate
Unit Type
145 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-Trees with Mulch
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
10 $165.00
$0.00
UnitsSideoats grama 2.40
$0.85
$165.00
White prairieclover 0.17 $23.85 $4.05
$1,266.51
Cost Summary: Units Total Cost Notes
$9.19$10.93
$1.84$19.67
Source: FY10 USDA-NRCS Program Payment Database
Grass Seeding 10
Little bluestem0.201.80
$16.50
Cost Summary:
Blue gramaBlack-eyed Susan 0.05 $17.02
Acre
This practice includes the planting of trees with simple site preparation. Simple site preparation includes planting into crop stubble or strips. The tree planting will include approximately 100 large trees, 220 large shrubs or small trees, and 320 small shrubs each per acre. The grass mixture used to establish prices is listed below, however, any mixture that is appropriate for the geopgraphic location and also meets NRCS practice standards may be used. The typical application of this practice is 10 acres.
Nebraska
Typical Practice Scenario
Unit for Cost EstimateGeographic Area Practice Life (Years) 15
Discount Rate (%/Year) 5%
CP25; 4/
$1,283.01
$1,436.97
$0.00
None.
None
$0.00
$0.00
$0.00
Includes the cost to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
None.
None.
Total Cost$21.58 Source: FY10 USDA-
NRCS Program Payment Database
Total CostUnits
640 $0.85 $544.00640
$8.99Price/Unit
1 $1,266.51
$25.66
$128.30
Upright coneflower 0.10 $25.19 $2.52
$1.05 $672.00Weed Control for Trees (TS08)
Notes
Trees & Machine Planting
Units Price/Unit Total Cost$16.50
2%
10%
146 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-Trees without Mulch
Payment Schedule Results
643
.
Payment Schedule Development Methodology
0%0%
Administration & Permit CostsRisk
Nebraska
$0.00
$827.83$0.00$0.00$0.00
50%
Total Cost
Payment Rate
Unit TypeScenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$73.91$14.78
Scenario Code
6436
PracticeCost Share Program
Practice Code
CRP
Cost/UnitCost Category
Forgone Income 0%$0.00
Equipment/Installation
Acre $376.96Restoration and Management of Declining Habitats CRP-Trees without Mulch
50%
50%
50%
$0.00
CRP Producer Payment RateCRP Program Payment Rate
Materials$16.50$722.63
$0.00$8.25
$361.32
0%0% $0.00
$7.39
$376.96$0.00$0.00$0.00
147 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-Trees without Mulch
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & Maintenanceper Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
$25.19 $2.52
$9.04
Blue grama
White prairieclover 0.17 $23.85 $4.05
Source: FY10 USDA-NRCS Program Payment Database
Trees & Machine Planting 640 $1.05 $672.00
None
$0.00
$0.00
$0.00
Total Materials, Equipment/Installation and Labor Costs. Includes cost to control competitive10%
Price/Unit$722.63
Total Cost$21.70 Source: FY10 USDA-
NRCS Program Payment Database
$165.00
Total Cost
None.
None.
1 $722.63
$14.78
$73.91
Black-eyed Susan
Units
Units Price/Unit
CP25
$739.13
$827.83
$0.00
None.
Geographic Area
$0.00
$16.50
Cost Summary:
UnitsSideoats grama 2.40
Units Total Cost Notes10 $165.00
Notes
Total Cost
Acre
This practice includes the planting of trees with simple site preparation. Simple site preparation includes planting into crop stubble or strips. The tree planting will include approximately 100 large trees, 220 large shrubs or small trees, and 320 small shrubs each per acre. The grass mixture used to establish prices is listed below, however, any mixture that is appropriate for the geopgraphic location and also meets NRCS practice standards may be used. The typical application of this practice is 10 acres.
Nebraska
Typical Practice Scenario
Unit for Cost Estimate
$10.93$1.84
$19.67Little bluestem0.201.80
$9.19
species, thinning, monitor & control pests, maintain central stems, control erosion & exclude livestock.
Practice Life (Years) 15Discount Rate (%/Year) 5%
$16.50
2%
Grass Seeding
Cost Summary:
10
0.05 $17.02 $0.85Upright coneflower 0.10
148 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-Direct Seeding
Payment Schedule Results
643
Payment Schedule Development Methodology
$147.29Restoration and Management of
CRP-Direct Seeding
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$300.30$0.00$0.00$0.00
$147.29$0.00$0.00$0.00
Equipment/InstallationMaterials
Forgone Income
$36.00$250.00
Total CostAdministration & Permit CostsRisk
Operation & MaintenanceMobilizationLabor
$5.72$8.58$0.00
Acre
$0.000%0%0%
50%50%
$0.00$0.00$4.29
Payment Rate
Unit TypeScenario
$0.00$18.00$125.00
Nebraska
0%0%
50%50%
Scenario Code6437
PracticeCost Share Program
Practice Code
CRP
Acquisition of Tech. Knowledge
149 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-Direct Seeding
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Equipment/Installation
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
Seedbed Preparation-MechanicalSeedbed Preparation-Chemical
$250.00
$36.00
Cost Summary:
UnitsSeed and Seed Collection 1.00
Acre
This practice includes the seed, seed collection, and site preparation for trees or shrubs which are direct seeded. This scenario is typically used to direct seed large seeded species such as Oaks or Walnuts using a tree seed planter. Site preparation includes residue management measures such as residue removal, shredding, raking, etc., and the application of burn down herbicides to kill sod, alfalfa, or other perennial vegetation. This practice meets the requirements listed in the 380 Windbreak/Shelterbelt Establishment Tree Planting Procedures. Typical application of this scenario is 5 acres.
Nebraska
Typical Practice Scenario
Geographic AreaUnit for Cost Estimate
Notes
$360.00 Source: FY10 USDA-NRCS Program Payment Database
Cost Summary:
Total Cost$250.00 Source: FY10 USDA-NRCS
Program Payment Database
Price/Unit$250.00
Total Cost
$360.00
Price/UnitUnits
CP25
$286.00
$300.30
$0.00
None.
None
$0.00
$0.00
$0.00
None.
None.
$0.00
2%
Total CostUnits
Total Cost Notes
Practice Life (Years) 15Discount Rate (%/Year) 5%
1 $250.00
$8.58
$5.72
3%
20 $18.0020 $18.00
20 $720.00Units
150 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-Replants
Payment Schedule Results
643
Payment Schedule Development Methodology
Nebraska
0%0%
50%
0%0%0%
50%
Total CostAdministration & Permit CostsRisk
$0.00
$2.26$0.00$0.00$0.00
Payment Rate
Unit TypeScenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.20$0.06$0.00
Scenario Code
6438
PracticeCost Share Program
Practice Code
CRP
50%
50%
Each
Equipment/InstallationMaterials
Forgone Income
$1.00
$1.03Restoration & Management of Declining Habitats
CRP-Replants
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$0.00$2.00
$1.03$0.00$0.00$0.00$0.00$0.00$0.03$0.00$0.00
151 of 200
643_11_RestorationMgmtDecliningHabitat.xlsx CRP-Replants
Practice Cost Data
Materials per Each
Equipment/Installation per EachEquipment/Installation costs included with the cost of Materials
Labor per Each
Total Materials, Equipment/Installation and Labor Costs: per Each
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Each
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Each
Acquisition of Technical Knowledgeper Each
Forgone Incomeper Each
Riskper Each
Administration & Permit Costsper Each
Total Cost Estimate: per Each
Associated Practices:CP5A; CP16A; CP17A;
$2.00
$2.26
$0.00
None.
None
$0.00
$0.00
$0.00
None
3%
Total CostUnits
Price/Unit$2.00
None.
1 $2.00
$0.06
$0.20Includes the costs to control competitive species, thinning, monitor and control pests, maintain central stems, control erosion and exclude livestock.
10%
Geographic Area
$0.00
$0.00
Cost Summary:
UnitsTrees & Hand Planting (weight avg TS11 & TS1 1
Notes
$2.00Total Cost
$2.00 Source: FY10 USDA-NRCS Program Payment Database
5%15
Each
This practice includes the replanting of select trees due to death or damage of the seedlings following an initial windbreak/shelterbelt establishment.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost Estimate
152 of 200
644_11_WetlandWildlifeHabitatMgmt.xlsx CRP-HighDiversityMix-LimitedSP
Payment Schedule Results
644
Payment Schedule Development Methodology
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$7.83
0%0%
50%
Total CostAdministration & Permit CostsRisk
$0.00
$411.08$0.00
50%
Scenario Code
6441
PracticeCost Share Program
Practice Code
CRP
Materials
$0.00$0.00
$11.75
0%0%0%50%
Forgone Income
Acre $201.62Wetland Wildlife Habitat Management
CRP-High Diveristy Mixture-Limited Site Preparation
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Equipment/Installation $8.25$187.50
$16.50$375.00
$0.00$5.87
50%
$201.62$0.00$0.00$0.00$0.00$0.00
$0.00
153 of 200
644_11_WetlandWildlifeHabitatMgmt.xlsx CRP-HighDiversityMix-LimitedSP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
2%
Total CostUnits
Price/Unit$375.00
3%
20 $16.50
20 $7,500.00
Units Price/Unit
Total Cost
CP9; CP23/A; CP27; CP30
$391.50
$411.08
$0.00
None.
None
$0.00
$0.00
$0.00
None.
None.
$11.75
$7.83
$0.00
$16.50
Cost Summary:
UnitsHigh Diversity Local Ecotype Mixture 20
Notes
$375.00Total Cost$7,500.00 Source: Vendor Quotes,
September 2009
Total CostGrass Seeding
Cost Summary:
$330.00
20 $330.00Units
5%1
Acre
This practice includes the seeding of a diverse mixture of wetland plant species including grasses, sedges, rushes, and forbs typically following a restorataion or enhancement activity within the wetland. Typical application of this scenario is 20 acres. The seed mixture used to establish this cost is on file in the state office, please contact the State Wildlife Biologist for further assistance with this practice.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
Notes$0.00
Source: FY09 USDA-NRCS Program Payment Database
154 of 200
644_11_WetlandWildlifeHabitatMgmt.xlsx CRP-Vegetation Mats & Plugs
Payment Schedule Results
644
Payment Schedule Development Methodology
$6.1050%
$67.10$0.00$0.00$0.000%
0%0%50%
$0.00$0.00
0%0%
$75.00
CRP Program Payment Rate
Acre
Payment Rate
$67.10Wetland Wildlife Habitat Management
CRP-Vegetation Mats & Plugs
$37.5050%
$0.00
$140.30$0.00$0.00$0.00
Total CostAdministration & Permit CostsRisk
Acquisition of Tech. KnowledgeForgone Income
Nebraska
Unit Type
Scenario
Operation & MaintenanceMobilizationLabor
$6.10
Equipment/Installation
CRP
$12.20$18.00
CRP Producer Payment Rate
Materials
Cost/UnitCost Category
$9.00$14.50
Scenario Code
6442
PracticeCost Share Program
Practice Code
50%$29.00
155 of 200
644_11_WetlandWildlifeHabitatMgmt.xlsx CRP-Vegetation Mats & Plugs
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per Acre
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
Practice Life (Years) 1Discount Rate (%/Year) 5%
$75.00Source: FY10 USDA-NRCS Program Payment Database
$18.00
Typical Practice Scenario
Geographic AreaUnit for Cost Estimate Acre
This practice includes the seeding and planting a wetland with plant materials other than traditional seed. the use of seed-bearing topsoil, transplanted vegetation mats and plugs, and other appropriate methods are used to treat approximately 10% to 25% in patches of each wetland acre. This will allow for future conlonization of the remainder of the wetland. Typical application of this scenario is 10 acres.
Nebraska
Pickup Truck
Cost Summary:
Units
NotesUnits
Price/Unit$75.00Plugs, Vegetation Mats 10
Total Cost$750.00
10 $750.00
Units Price/Unit
CP9; CP23/A; CP27; CP30
$122.00
$140.30
$0.00
None.
None
$0.00
$0.00
$0.00
None.
None.
$12.20
$6.10
Total Cost
10%
2 $120.00
UnitsTransplanting 30 $18.00 $540.00
30 $540.00Cost Summary: Units Total Cost Notes
Price/Unit
$29.00
Total Cost
Total Cost
Shovels, Miscellaneous Equipment
5%
$240.00
Cost Summary:1 $50.00
Units Total Cost Notes10 $290.00
$50.00
Source: FY10 USDA-NRCS Program Payment Database
Source: FY10 USDA-NRCS Program Payment Database
156 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-SinglePurposeMix-LimitedSP
Payment Schedule Results
645
Payment Schedule Development Methodology
Nebraska
0%
Scenario Code
6451
PracticeCost Share Program
Practice Code
CRP
Payment Rate
Unit Type
Scenario
Acre $27.21Upland Wildlife Habitat Management
CRP-Single Purpose Grass Mixture-Limited Site
Preparation
CRP Producer Payment RateCRP Program Payment Rate
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.52$2.59$0.00
0%
50%
$0.00
$82.61
$17.32
$27.21$0.00$0.00$0.00$0.00$0.00
$0.00$27.68
0%50%
$34.50
Cost/UnitCost Category
Equipment/InstallationMaterials
Forgone Income
$0.00$17.25$8.66
0%0%
$0.00
50%
$1.3050%
Total CostAdministration & Permit CostsRisk
157 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-SinglePurposeMix-LimitedSP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per AcreMobilization
Total Materials, Equipment/Installation and Labor Costs. per AcreOperation & Maintenance
Total Materials, Equipment/Installation and Labor Costs. per AcreAcquisition of Technical Knowledge
per AcreForgone Income
per Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:CP4B/D; CP38E
$51.82
$82.61$0.00None
$27.68
1%
Total CostUnits
5%
1 $18.00Grass Seeding (G130 1Seedbed Preparation (G03)
Cost Summary:
None.
1 $17.32
$2.59
$0.52
Units Price/Unit
$17.32
Switchgrass
Total Cost$3.47
Source: Vendor Quotes, September 2010
0.31.0
Total Cost
$2.26$7.73
Cost Summary:
UnitsBig bluestem 0.5
Notes
$6.94
Yellow sweet cloverMaximillian sunflower
$3.87
$2.26
0.5$25.76$7.73
Price/Unit
$0.00
$34.50
$16.50 $16.50$18.00
$34.50
$0.00
$0.00
50% chance of unsuccessful planting (50% of materials, labor, installation)
None.
Source: FY10 USDA-NRCS Program Payment Database
1Units Total Cost Notes
Acre
This scenario applies to wildlife seedings which are designed for single purpose (i.e. winter cover or food plot) and typically have limited diversity (approximately 3 to 5 species) containing either grasses and/or forbs. This scenario includes limited seedbed preparation, seeding and grass seed for a single purpose grass mixture in an upland wildlife habitat management project. Limited site preparation includes measures to plant into existing crops or cover crop stubble and can include tillage, herbicide application and other measures necessary to adequately prepare site for planting. The seed mixture used to establish the cost is a typical nesting cover mixture of Big bluestem, Swtichgrass, Maximillian sunflower, and Yellow sweet clover, however, any mixture which is appropriate for the geographic area and meets NRCS practice standards may be used. The typical application of this practice is 25 acres.
Nebraska
Typical Practice Scenario
Geographic AreaUnit for Cost Estimate
Practice Life (Years) 1Discount Rate (%/Year) 5%
158 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-SinglePurposeMix-ComplexSP
Payment Schedule Results
645
Payment Schedule Development Methodology
$52.50$17.32
$36.66$0.00$0.00$0.00
$0.00$36.30
Forgone Income
$0.00$26.25$8.66
0%0%0%50%
50%
$0.00$0.00$1.75
50%Equipment/InstallationMaterials
$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.70$3.49$0.00
Scenario Code
6452
PracticeCost Share Program
Practice Code
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $36.66Upland Wildlife Habitat Management
CRP-Single Purpose Grass Mixture-Complex Site
Preparation
Nebraska
0%0%
50%
Total CostAdministration & Permit CostsRisk
$0.00
$110.31
159 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-SinglePurposeMix-ComplexSP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per AcreMobilization
Total Materials, Equipment/Installation and Labor Costs. per AcreOperation & Maintenance
Total Materials, Equipment/Installation and Labor Costs. per AcreAcquisition of Technical Knowledge
per AcreForgone Income
per AcreRisk
per AcreAdministration & Permit Costs
per AcreTotal Cost Estimate: per Acre
Associated Practices:
Practice Life (Years) 1Discount Rate (%/Year) 5%
Cost Summary:
UnitsBig bluestem 0.5
Notes
$6.94
Yellow sweet cloverMaximillian sunflower
Acre
This scenario applies to wildlife seedings which are designed for single purpose (i.e. winter cover or food plot) and typically have limited diversity (approximately 3 to 5 species) containing either grasses and/or forbs. This scenario includes complex seedbed preparation, seeding and grass seed for a single purpose grass mixture in an upland wildlife habitat management project. Complex site preparation includes residue management measures such as residue removal, shredding, raking, etc. , and the application of burn down herbicides to kill sod, alfalfa, or other perennial vegetation. The seed mixture used to establish the cost is a typical nesting cover mixture of Big bluestem, Swtichgrass, Maximillian sunflower, and Yellow sweet clover, however, any mixture which is appropriate for the geographic area and meets NRCS practice standards may be used. The typical application of this practice is 25 acres.
Nebraska
Typical Practice Scenario
Geographic AreaUnit for Cost Estimate
$17.32
Switchgrass
Total Cost$3.47
Source: Vendor Quotes, September 2010
0.30.5
$25.76$7.73
Price/Unit
$3.87
CP4B/D; CP38E
$69.82
$110.31$0.00None
$36.30
$0.00
$0.00
50% chance of unsuccessful planting (50% of materials, labor, installation)
None.
1 $17.32
$3.49
$0.70
1.0
Total Cost
$2.26$7.73
Total CostUnits
1 $18.00
$0.00
$52.50
$2.26
$16.50 $16.50$18.00 $18.00
$18.00
1 $52.50
Units Price/UnitSource: FY10 USDA-
NRCS Program Payment Database
1Grass Seeding (G130 1
Seedbed Preparation (G03)Seedbed Preparation (G03)
None.
1%
5%
Cost Summary: Units Total Cost Notes
160 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-High Quality Mix-Limited SP
Payment Schedule Results
645
Payment Schedule Development Methodology
$0.00
$0.00$2.75
50% $0.00
$57.70$0.00
Upland Wildlife Habitat Management
CRP-High Quality Grass Mixture-Limited Site
Preparation
Equipment/InstallationMaterials
$5.50$0.00
$17.08$37.88
50%
$34.15$75.75
CRP Producer Payment RateCRP Program Payment RateCost/Unit
Nebraska
0%0%
50%
Risk
$0.00
$169.37$0.00$52.87$0.00
Payment Rate
Scenario Code
6453
PracticeCost Share Program
Practice Code
CRP
Total CostAdministration & Permit Costs
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$1.10
50%
Forgone Income
Cost Category
0%0%0%
Acre
$0.00$0.00
$57.70
161 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-High Quality Mix-Limited SP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
$1.16
Cudweed sagewort 0.01 $304.45 $3.04
$23.29 $2.33Purple prairieclover 0.10 $20.35 $2.04Purple coneflower 0.10Plains coreopsis 0.03 $16.95 $0.51Pitcher sage 0.03 $185.55 $5.57
$9.04 $0.09
Western wheatgrass 0.20 $5.98 $1.20Sideoats grama 0.20 $8.99 $1.80Sand lovegrass 0.01
$2.64$159.92 $4.80
Maximillian sunflower 0.02 $25.76 $0.52Illinois bundleflower 0.30 $16.52 $4.96
0.10 $36.70 $3.67Grayhead coneflower
Common evening primrose 0.02 $42.69 $0.85Canada tick-trefoil 0.03
$2.87
Little bluestem 0.70 $10.93 $7.65Prairie junegrass 0.02 $41.62 $0.83
Blue grama 0.04 $0.37 Source: Vendor Quotes, September 20100.40
0.20$5.02$6.73$9.19
Green needlegrass
$1.90
$2.32 $0.46$443.35$120.27 $2.41$11.68 $4.67
$17.02 $1.02
$8.87
$189.92$106.74 $1.07
15%
$73.09 $1.46
Acre
This scenario applies to wildlife seedings which have moderate diversity (typically >15 species) and are commonly seeded at 20 PLS/sq ft or greater to provide multiple habitat functions such as nesting and pollinating. This scenario includes limited seedbed preparation, seeding and grass seed for a single purpose grass mixture in an upland wildlife habitat management project. Limited site preparation includes measures to plant into existing crops or cover crop stubble and can include tillage, herbicide application and other measures necessary to adequately prepare site for planting. The seed mixture used to establish the cost is shown below, however, any mixture which is appropriate for the geographic area and meets NRCS practice standards may be used. The typical application of this practice is 25 acres.
Nebraska
Typical Practice Scenario
Notes
$75.75
Canada wildrye
Seedbed Preparation (G03)
Cost Summary:
$1.19$23.85
$25.19 $1.51
Red clover 0.20Rough gayfeather 0.02Roundhead lespedeza 0.02Showy partridgepea
$2.01$1.35
American vetch 0.02Alfalfa 0.30 $3.19 $0.96
Geographic Area
Units
Unit for Cost EstimatePractice Life (Years)Discount Rate (%/Year)
Total CostPrice/Unit
$34.15
$34.15
Blackeyed Susan 0.06
Western yarrow 0.04
Units Price/Unit Total Cost$17.901 $17.90
Grass Seeding (G130 1 $16.25
1Units Total Cost Notes
$16.25Source: FY10 USDA-NRCS Program Payment Database
1 $75.75
0.40
0.10 $28.68
Cost Summary:
Canada milkvetch 0.07 $37.70
Total CostUnitsWhite prairieclover
$28.990.05
Upright coneflower 0.06
Stiff goldenrod 0.01Tall boneset 0.01
False sunflower
162 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-High Quality Mix-Limited SP
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
$0.00
1%
CP4B/D; CP38E
$109.90
$169.37
$0.00None
$52.87
$0.00
$0.00
50% chance of unsuccessful planting (50% of materials, labor, installation)
None.
None.
$5.50
$1.10
5%
163 of 200
THIS PAGE INTENTIONALLY LEFT BLANK
164 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-High Quality Mix-Complex SP
Payment Schedule Results
645
Payment Schedule Development Methodology
Nebraska
0%Total CostAdministration & Permit CostsRisk
$0.00
$197.44$0.00$61.50$0.00
50%
Scenario Code
6454
PracticeCost Share Program
Practice Code
CRP
Payment Rate
Unit Type
Scenario
Acre $67.33Upland Wildlife Habitat Management
CRP-High Quality Grass Mixture-Complex Site
Preparation
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Equipment/InstallationMaterials
Forgone Income
$0.00$26.25$37.87
0%0%0%50%
$1.28$6.41$0.00
50%$52.50$75.75
$0.00$0.00$0.00$3.21
50%
0%
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$67.33$0.00$0.00
165 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-High Quality Mix-Complex SP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Tall boneset 0.01
Western yarrow 0.04
Total Cost
Total CostUnits
1 $18.00 $18.00
Grass Seeding (G130 1
1 $75.75
Units Price/Unit
Seedbed Preparation (G03) 1
$52.50
Cost Summary:
UnitsBlue grama 0.04
Notes
$9.19
White prairieclover
Green needlegrassCanada wildrye
Total Cost$0.37 Source: Vendor Quotes,
September 20100.400.20
$5.02$6.73
Price/Unit
0.05
Upright coneflower 0.06
Stiff goldenrod 0.01
$1.19
Acre
This scenario applies to wildlife seedings which have moderate diversity (typically >15 species) and are commonly seeded at 20 PLS/sq ft or greater to provide multiple habitat functions such as nesting and pollinating. This scenario includes complex seedbed preparation, seeding and grass seed for a single purpose grass mixture in an upland wildlife habitat management project. Complex site preparation includes residue management measures such as residue removal, shredding, raking, etc., and the application of burn down herbicides to kill sod, alfalfa, or other perennial vegetation. The seed mixture used to establish the cost is shown below, however, any mixture which is appropriate for the geographic area and meets NRCS practice standards may be used. The typical application of this practice is 25 acres.
Nebraska
Typical Practice Scenario
Geographic AreaUnit for Cost Estimate
1 $52.50Units Total Cost Notes
$16.50 $16.50
Source: FY10 USDA-NRCS Program Payment
Database$18.00 $18.00
Cost Summary:
Seedbed Preparation (G03)
$23.85
$25.19 $1.51
$106.74 $1.07
$8.87
$189.92
$41.62 $0.83
$1.80
$28.99 $1.16
$1.90
$0.46
$0.96
$28.62 $2.86False sunflower
Illinois bundleflower 0.30 $16.52
$7.65Prairie junegrass 0.02
Canada tick-trefoil 0.03 $159.92 $4.80Common evening primrose 0.02 $42.69 $0.85
0.30 $3.19
$2.01$1.35
Plains coreopsis 0.03 $16.95 $0.51
Maximillian sunflower 0.02 $25.76 $0.52Pitcher sage 0.03 $185.55 $5.57
$1.46
Sideoats grama 0.20 $8.99
Little bluestem 0.70 $10.93
Showy partridgepea 0.40 $11.68 $4.67
Rough gayfeather 0.02 $443.35Roundhead lespedeza
Purple prairieclover 0.10 $20.35 $2.04
1Discount Rate (%/Year) 5%
$120.27 $2.41
$75.75
Cudweed sagewort 0.01 $304.45 $3.04
Blackeyed Susan 0.06 $17.02 $1.02Canada milkvetch 0.07 $37.70 $2.64
AlfalfaWestern wheatgrass 0.20 $5.98 $1.20
Sand lovegrass
American vetch
0.02
Red clover 0.20 $2.32
Practice Life (Years)
0.01 $9.04 $0.09
Purple coneflower 0.10 $23.29 $2.33
$4.96
0.10 $36.70 $3.67Grayhead coneflower 0.10
0.02 $73.09
166 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-High Quality Mix-Complex SP
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per AcreMobilization
Total Materials, Equipment/Installation and Labor Costs. per AcreOperation & Maintenance
Total Materials, Equipment/Installation and Labor Costs. per AcreAcquisition of Technical Knowledge
per AcreForgone Income
per AcreRisk
per AcreAdministration & Permit Costs
per AcreTotal Cost Estimate: per Acre
Associated Practices:
1%
5% $6.41
$1.28
$0.00
CP4B/D; CP38E
$128.25
$197.44$0.00None
$61.50
$0.00
$0.00
50% chance of unsuccessful planting (50% of materials, labor, installation)
None.
None.
167 of 200
THIS PAGE INTENTIONALLY LEFT BLANK
168 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-Low Density Mix-Limited SP
Payment Schedule Results
645
Payment Schedule Development Methodology
Nebraska
0%0%
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.79$3.93$0.00
Total CostAdministration & Permit CostsRisk
$0.00
$123.04$0.00$39.75$0.00
Scenario Code
6455
PracticeCost Share Program
Practice Code
CRP
Payment Rate
Unit Type
Scenario
0%50%
$34.50
Acre $41.25Upland Wildlife Habitat Management
CRP-Low Density Grass Mixture-Limited Site
Preparation
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Equipment/Installation50%$44.07
$41.25$0.00$0.00$0.00$0.00$0.00$1.96
50%50%
Materials
Forgone Income
$0.00$17.25$22.04
0%0%
169 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-Low Density Mix-Limited SP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total CostUnits
1 $18.00Grass Seeding (G130 1Seedbed Preparation (G03)
Cost Summary:1 $34.50
Units Price/Unit
Units Total Cost
Total Cost$2.08
Source: Vendor Quotes, September 2010
$1.37$2.69
$1.15
$16.50 $16.50Source: FY10 USDA-NRCS Program Payment Database
$0.26
$0.00
Total Cost$18.00
Notes
$44.07
Canada wildrye
Unit for Cost Estimate
0.200.40
$6.84$6.73
Price/Unit$6.94
Indiangrass
$34.50
Cost Summary:
UnitsBig bluestem 0.30
Notes1 $44.07
Acre
This scenario applies to wildlife seedings which have moderate diversity (typically >15 species) and have a low density (10 PLS/sq ft to 19 PLS/sq ft) in order to maintain early succession habitat and promote brood-rearing habitat with limited site preparation. Limited site prep includes measures to plant into existing crops or cover crop stubble and can include tillage, herbicide application and other measures necessary to adequately prepare site for planting. The seed mixture used to establish the cost is a shown below, however, any mixture which is appropriate for the geographic area and meets NRCS practice standards may be used. The typical application of this practice is 25 acres
Nebraska
Typical Practice Scenario
Geographic Area
0.04 $23.85 $0.95Wild bergamot 0.01 $115.21White prairieclover
Purple coneflower 0.04 $23.29 $0.93$0.81
Roundhead lespedeza 0.02 $120.27
Maximillian sunflower 0.01 $25.76
Purple prairieclover 0.04 $20.35
Upright coneflower 0.04 $25.19 $1.01Western yarrow 0.02 $28.99 $0.58
$2.410.15 $11.68 $1.75
Tall boneset 0.01 $189.92 $1.90Showy partridgepea
Slender wheatgrass 0.30 $4.39 $1.32Western wheatgrass 0.30 $5.98 $1.79
Little bluestem 0.60 $10.93 $6.56Prairie junegrass 0.02 $41.62 $0.83
Cudweed sagewort 0.01 $304.45 $3.04
Blackeyed Susan 0.05 $17.02 $0.85Canada milkvetch 0.08 $37.70 $3.02
Practice Life (Years) 1Discount Rate (%/Year) 5%
Illinois bundleflower 0.12 $16.52 $1.98Leadplant 0.03 $85.38 $2.56
False sunflower 0.08 $36.70 $2.94Grayhead coneflower 0.03 $28.62 $0.86
Common evening primrose 0.01 $42.69 $0.43
170 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-Low Density Mix-Limited SP
Total Materials, Equipment/Installation and Labor Costs: per AcreMobilization
Total Materials, Equipment/Installation and Labor Costs. per AcreOperation & Maintenance
Total Materials, Equipment/Installation and Labor Costs. per AcreAcquisition of Technical Knowledge
per AcreForgone Income
per AcreRisk
per AcreAdministration & Permit Costs
per AcreTotal Cost Estimate: per Acre
Associated Practices:
1%
5%
CP4B/D; CP38E
$78.57
$123.04$0.00None
$39.75
$0.00
$0.00
50% chance of unsuccessful planting (50% of materials, labor, installation)
None.
$0.79
$3.93
None.
171 of 200
THIS PAGE INTENTIONALLY LEFT BLANK
172 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-Low Density Mix-Complex SP
Payment Schedule Results
645
Payment Schedule Development Methodology
Forgone Income
$0.00$26.25$22.04
0%0%
$50.70$0.00$0.00$0.00$0.00$0.00
$52.50$44.07
0%50%
Total CostAdministration & Permit Costs
$4.83$0.00
$2.4150%
Equipment/InstallationMaterials
$0.97
Scenario Code
6456
PracticeCost Share Program
Practice Code
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $50.70Upland Wildlife Habitat Management
CRP-Low Density Grass Mixture-Complex Site
Preparation
50%
Nebraska
0%0%
50%
Risk
$0.00
$150.74$0.00$48.37$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
173 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-Low Density Mix-Complex SP
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
$18.00
Leadplant 0.03 $85.38 $2.56
$25.19 $1.01Western yarrow 0.02 $28.99 $0.58Upright coneflower 0.04
$1.15
Total Cost
$2.41
$0.26Purple coneflower 0.04 $23.29 $0.93
$18.00
$1.75Tall boneset
Slender wheatgrass 0.30 $4.39 $1.32
Blackeyed Susan 0.05 $17.02 $0.85Western wheatgrass 0.30 $5.98 $1.79
0.01 $304.45 $3.04
Illinois bundleflower 0.12 $16.52 $1.98Grayhead coneflower 0.03 $28.62 $0.86
0.01 $189.92 $1.90
False sunflower 0.08 $36.70 $2.94
Showy partridgepea$120.27
Acre
This scenario applies to wildlife seedings which have moderate diversity (typically >15 species) and have a low density (10 PLS/sq ft to 19 PLS/sq ft) in order to maintain early succession habitat and promote brood-rearing habitat with complex site preparation. Complex site prep includes residue management measures such as residue removal, shredding, raking, etc., and the application of burn down herbicides to kill sod, alfalfa, or other perennial vegetation. The seed mixture used to establish the cost is a shown below, however, any mixture which is appropriate for the geographic area and meets NRCS practice standards may be used. The typical application of this practice is 25 acres.
Nebraska
Typical Practice Scenario
Geographic AreaUnit for Cost Estimate
$0.00
$52.50
Cost Summary:
UnitsBig bluestem 0.30
Notes
$44.07
Canada wildrye
White prairieclover 0.04 $23.85 $0.95Wild bergamot 0.01 $115.21
Maximillian sunflower 0.01 $25.76
Purple prairieclover 0.04 $20.35Roundhead lespedeza 0.02
0.40$6.84$6.73
Price/Unit$6.94
Indiangrass
$0.81
Little bluestem 0.60 $10.93 $6.56Prairie junegrass 0.02 $41.62 $0.83
$37.70 $3.02Common evening primrose 0.01 $42.69 $0.43Canada milkvetch 0.08
Cudweed sagewort
Total CostUnits
1 $18.00
Grass Seeding (G13) 1
Seedbed Preparation (G03)
Cost Summary:
Units Price/Unit
$16.50Seedbed Preparation (G03) 1 $18.00
Practice Life (Years) 1Discount Rate (%/Year) 5%
1 $44.07
1 $52.50Units Total Cost Notes
Total Cost$2.08
Source: Vendor Quotes, September 2010
$1.37$2.69
$16.50
Source: FY10 USDA-NRCS Program Payment Database
0.15 $11.68
0.20
174 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-Low Density Mix-Complex SP
Total Materials, Equipment/Installation and Labor Costs: per AcreMobilization
Total Materials, Equipment/Installation and Labor Costs. per AcreOperation & Maintenance
Total Materials, Equipment/Installation and Labor Costs. per AcreAcquisition of Technical Knowledge
per AcreForgone Income
per AcreRisk
per AcreAdministration & Permit Costs
per AcreTotal Cost Estimate: per Acre
Associated Practices:CP4B/D; CP38E
$96.57
$150.74$0.00None
$48.37
$0.00
$0.00
50% chance of unsuccessful planting (50% of materials, labor, installation)
None.
None.
$0.971%
5% $4.83
175 of 200
THIS PAGE INTENTIONALLY LEFT BLANK
176 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-Shrub Thickets
Payment Schedule Results
645
Payment Schedule Development Methodology
Total CostAdministration & Permit CostsRisk
$0.00
$0.53$0.00$0.00$0.00
Nebraska
0%0%
50%
LF $0.26Upland Wildlife Habitat Management CRP-Shrub Thickets
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Scenario Code
645A
PracticeCost Share Program
Practice Code
CRP
Payment Rate
Unit Type
Scenario
Equipment/InstallationMaterials
Forgone Income
$0.00$0.04$0.21
0%0%0%50%
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.01$0.03$0.00
$0.42
$0.26$0.00$0.00$0.00$0.00$0.00$0.01
50%
50%$0.08
177 of 200
645_11_UplandWildlifeHabitatMgmt.xlsx CRP-Shrub Thickets
Practice Cost Data
Materials per LF
Equipment/Installation per LF
Labor per LFLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per LFMobilization
Total Materials, Equipment/Installation and Labor Costs. per LFOperation & Maintenance
Total Materials, Equipment/Installation and Labor Costs. per LFAcquisition of Technical Knowledge
per LFForgone Income
per LFRisk
per LFAdministration & Permit Costs
per LFTotal Cost Estimate: per LF
Associated Practices:
1%
5%
$0.00
$0.08
CP4B/D; CP38E
$0.50
$0.53$0.00None
$0.00
$0.00
$0.00
None
None.
$0.03
$0.01
None.
UnitsShrub Planting 500
$40.00
500 $210.00
Source: FY10 USDA-NRCS Program Payment Database
Cost Summary:
$0.42
Chemical Seedbed Preparation 500 $0.08
Total Cost$210.00
Units Price/Unit Total Cost
Units
Practice Life (Years)
500 $40.00Units Total Cost Notes
Total Cost
Price/Unit
LF
This practice for a wildlife shrub thicket includes mechanical/chemical site preparation, planting, and shrubs for a 30' x 50' thicket containing 150 shrubs planted in 10 rows 50 feet long with shrubs at 3 1/2 foot spacing.
Nebraska
Typical Practice Scenario
Geographic Area 1Discount Rate (%/Year) 5%
$0.42
Unit for Cost Estimate
Source: FY10 USDA-NRCS Program Payment Database
Cost Summary: Notes
178 of 200
647_11_EarlySuccessionalHabitatDevelop.xlsx CRP-Introduced
Payment Schedule Results
647
Payment Schedule Development Methodology
$0.00
Forgone Income
$0.00
Acre $25.92Early Successional Habitat and Development
CRP-Management Activity and Introduced Species
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$1.2350%
Scenario Code
6471
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
$0.00$0.00 0%
0%0%50%
$34.50$14.88
Administration & Permit CostsRisk
$0.00
$52.34$0.00
50%
$2.47$0.00
$17.25$7.44
$25.92$0.00$0.00$0.00$0.00
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.49
0%0%
50%
Total Cost
179 of 200
647_11_EarlySuccessionalHabitatDevelop.xlsx CRP-Introduced
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
Seedbed Preparation (G03) $18.00
Cost Summary: Units Total Cost Notes$16.50 $16.50
Source: FY10 USDA-NRCS Program Payment Database
5%15
Acre
This practice includes a management activity (disking, prescribed burning, herbicide application, disturbance grazing) plus seeding and seed. The seed mixture used to establish the price is an introduced mixture of alfalfa, red clover, and sweetclover, however, any mixture that both is appropriate for the geographic location and meets NRCS practice standards can be used. The typical application of this practice is 50 acres.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
$0.00
$34.50
Cost Summary:
UnitsAlfalfa 2.50
Notes
$14.88
Red clover
Total Cost$7.98
Source: Vendor Quotes, September 20101.00
2.00$2.26$2.32
$2.26$4.64
Total Cost
1 $34.50
MCM 1/
$49.38
$52.34
$0.00
None.
None
$0.00
$0.00
$0.00
None.
None.
$2.47
$0.491%
Total CostUnits
Price/Unit$3.19
Sweet clover
5%
1 $18.00Grass Seeding
1 $14.88
Units Price/Unit
1
180 of 200
647_11_EarlySuccessionalHabitatDevelop.xlsx CRP-Native
Payment Schedule Results
647
Payment Schedule Development Methodology
Nebraska
0%0%
Total CostAdministration & Permit CostsRisk
$0.00
$96.99$0.00$0.00$0.00
Unit Type
Scenario
Acquisition of Tech. Knowledge
Labor
$0.91$4.57$0.00
50%
Scenario Code
6472
PracticeCost Share Program
Practice Code
CRP
Materials
Forgone Income
$34.50
0%50%
50%$57.00
$0.00$0.00$0.00$0.00$0.00$2.29
50% $0.00
Payment Rate
Acre $48.04Early Successional Habitat and Development
CRP-Management Activity and Native Species
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Equipment/Installation $17.25$28.50
0%0%
Operation & MaintenanceMobilization
$48.04
181 of 200
647_11_EarlySuccessionalHabitatDevelop.xlsx CRP-Native
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per AcreMobilization
Total Materials, Equipment/Installation and Labor Costs. per AcreOperation & Maintenance
Total Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
0.100.05
Grass Seeding
Upright coneflower $25.19$17.02
1
Blackeyed Susan
1%
Total CostUnitsCost Summary:
None.
$4.57
$0.91
Price/Unit Total Cost
5%
$0.00
$34.50
$16.50Source: FY10 USDA-NRCS Program Payment Database
Notes
$18.00
1 $57.00
Units
MCM 1/
$91.50
$96.99$0.00
None.
None
$0.00
$0.00
$0.00
None.
Cost Summary:1 $34.50
1 $16.50Units Total Cost Notes
Purple prarieclover 0.25 $20.35
Price/UnitUnitsCanada milkvetch 0.25
$14.60Illinois bundleflower 1.25 $16.52 $20.65
Maximillian sunflower 0.15
Acre
This practice includes a management activity (disking, prescribed burning, herbicide application, disturbance grazing) plus seeding and seed. The seed mixture used to establish the price is a native mixture of Canada milkvetch, Illinois bundleflower, Showy partridgepea, Maximillian sunflower, Purple prairieclover, Blackeyed Susan, and Upright coneflower, however, any mixture that both is appropriate for the geographic location and meets NRCS practice standards can be used. The typical application of this practice is 50 acres.
Nebraska
Typical Practice Scenario
Geographic AreaUnit for Cost Estimate
$18.00
Showy partridgepea 1.25 $11.68
$2.52
Total Cost
Seedbed Preparation (G03)
Practice Life (Years)
$0.85
15Discount Rate (%/Year) 5%
$5.09
Source: Vendor Quotes, September 2010
$57.00
$37.70 $9.43
$25.76 $3.86
182 of 200
647_11_EarlySuccessionalHabitatDevelop.xlsx CRP-Interseeding-Forbs
Payment Schedule Results
647
Payment Schedule Development Methodology
Nebraska
0%0%
Total CostAdministration & Permit CostsRisk
$0.00
$77.91$0.00$0.00$0.00
Unit Type
Scenario
Acquisition of Tech. Knowledge
Labor
$0.73$3.67$0.00
50%
Scenario Code
6473
PracticeCost Share Program
Practice Code
CRP
Materials
Forgone Income
$16.50
0%50%
50%$57.00
$0.00$0.00$0.00$0.00$0.00$1.84
50% $0.00
Payment Rate
Acre $38.59Early Successional Habitat and Development
CRP-Interseeding without Management Activity-Forbs
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Equipment/Installation $8.25$28.50
0%0%
Operation & MaintenanceMobilization
$38.59
183 of 200
647_11_EarlySuccessionalHabitatDevelop.xlsx CRP-Interseeding-Forbs
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per AcreMobilization
Total Materials, Equipment/Installation and Labor Costs. per AcreOperation & Maintenance
Total Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
0.100.05
Upright coneflower $25.19$17.02
1
Blackeyed Susan
1%
Total CostUnitsCost Summary:
None.
$3.67
$0.73
Price/Unit Total Cost
5%
$0.00
$16.50
Source: FY10 USDA-NRCS Program Payment Database
Notes
$16.50
1 $57.00
Units
MCM 1/
$73.50
$77.91$0.00
None.
None
$0.00
$0.00
$0.00
None.
Cost Summary:1 $16.50
Units Total Cost Notes
Purple prarieclover 0.25 $20.35
Price/UnitUnitsCanada milkvetch 0.25
$14.60Illinois bundleflower 1.25 $16.52 $20.65
Maximillian sunflower 0.15
Acre
This scenario applies to situations where the existing vegetation is being treated prior to interseeding with another practice, such as prescribed burning or where payment is not being made, such as disturbance grazing or haying followed by interseeding forbs with a no-till drill. No payment will be made on "set-back" treatment areas. The seed mixture used to establish the price is a native mixture of Canada milkvetch, Illinois bundleflower, Showy partridgepea, Maximillian sunflower, Purple prairieclover, Blackeyed Susan, and Upright coneflower, however, any mixture that both is appropriate for the geographic location and meets NRCS practice standards can be used.Typical application is 50 acres
Nebraska
Typical Practice Scenario
Geographic AreaUnit for Cost Estimate
$16.50
Showy partridgepea 1.25 $11.68
$2.52
Total Cost
Grass Seeding
Practice Life (Years)
$0.85
15Discount Rate (%/Year) 5%
$5.09
Source: Vendor Quotes, September 2010
$57.00
$37.70 $9.43
$25.76 $3.86
184 of 200
647_11_EarlySuccessionalHabitatDevelop.xlsx CRP-Interseeding-Legumes
Payment Schedule Results
647
Payment Schedule Development Methodology
$16.47$0.00
0%0%0%50% $0.7850%
$0.00
$0.00
$0.00$0.00$0.00$0.00
Cost Category
Payment Rate
Acre $16.47Early Successional Habitat and Development
CRP-Interseeding without Management Activity-
Legumes
Unit Type
6474
Equipment/InstallationMaterials
Practice
$7.4450%
$14.88$16.50
Acquisition of Tech. Knowledge
0%0%
Total CostAdministration & Permit CostsRisk
Cost Share Program
Practice Code
CRP
Scenario Code
$0.31$1.57$0.00
50%
Operation & MaintenanceMobilizationLabor
Scenario
$8.25
CRP Producer Payment RateCRP Program Payment RateCost/Unit
Nebraska
$33.26$0.00$0.00$0.00Forgone Income
185 of 200
647_11_EarlySuccessionalHabitatDevelop.xlsx CRP-Interseeding-Legumes
Practice Cost Data
Materials per Acre
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per AcreMobilization
Total Materials, Equipment/Installation and Labor Costs. per AcreOperation & Maintenance
Total Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
Total Cost$7.98
Practice Life (Years) 15Discount Rate (%/Year) 5%
Source: Vendor Quotes, September 2010
$14.88
Unit for Cost Estimate
Sweet clover 1.00 $2.26 $2.26
Acre
This practice includes a management activity (disking, prescribed burning, herbicide application, disturbance grazing) plus seeding and seed. The seed mixture used to establish the price is an introduced mixture of alfalfa, red clover, and sweetclover, however, any mixture that both is appropriate for the geographic location and meets NRCS practice standards can be used. The typical application of this practice is 50 acres.
Nebraska
Typical Practice Scenario
Geographic Area
Units Price/Unit$3.19Alfalfa 2.50
Red clover 2.00 $2.32 $4.64
$0.00
$16.50
Notes
$16.50 Source: FY10 USDA-NRCS Program Payment Database
$0.00
$0.00
$0.00
None.
Cost Summary:1 $16.50
Units Total Cost
MCM 1/
$31.38
$33.26$0.00
None.
None
1%
Total CostUnits
None.
$1.57
$0.31
Price/Unit Total Cost
Cost Summary:
5%
1 $16.50
1 $14.88
UnitsGrass Seeding
Notes
186 of 200
657_11_WetlandResoration.xlsx CRP-Saturated Soils
Payment Schedule Results
657
Payment Schedule Development Methodology
Equipment/InstallationMaterials
Forgone Income
$0.00$0.00
$2,640.00
0%0%0%50%
$0.00$5,280.00
$0.00$0.00$0.00$79.20
50%50%50%
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $2,719.20Wetland Restoration CRP-Saturated Soils
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$5,544.00$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$105.60$158.40$0.00
Scenario Code
6571
PracticeCost Share Program
Practice Code
0%0%
$2,719.20$0.00$0.00
187 of 200
657_11_WetlandResoration.xlsx CRP-Saturated Soils
Practice Cost Data
Materials per Acre
Equipment/Installation per AcreEquipment/Installation costs included with the cost of Materials
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
This scenario includes the cost of excavating an average of approximately 24-inches of saturated soil in order to restore wetland characteristics to original functions and values. Practice units and payments are based on excavated area. The costs in this scenario are based on excavation of 25% of hydric soil area (1 of 4 acres in this example) within a larger contract.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
$5,280.00Total Cost$5,280.00 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost Estimate
UnitsExcavation-dragline/backhoe (E06) 3200
5%15
Acre
Price/Unit$1.65
3%
CP23/A; CP27; CP30
$5,280.00
$5,544.00
$0.00
None.
None
$0.00
$0.00
$0.00
None.
2%
$0.00
$0.00
Cost Summary: Notes
None.
1 $5,280.00
$158.40
$105.60
Total CostUnits
188 of 200
657_11_WetlandResoration.xlsx CRP-Unsaturated Soils
Payment Schedule Results
657
Payment Schedule Development Methodology
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & Maintenance
Scenario Code
6572
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
MobilizationLabor
50%$1,920.00
0%0%0%50%
$0.00$3,840.00
Acre $1,977.60Wetland Restoration CRP-Unsaturated Soils
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$115.20$0.00
$57.6050%
50%
$76.80$0.00$0.00
$1,977.60$0.00$0.00$0.00$0.00$0.00
Forgone Income
$0.00$0.00
0%0%
Total CostAdministration & Permit CostsRisk
$4,032.00$0.00$0.00
189 of 200
657_11_WetlandResoration.xlsx CRP-Unsaturated Soils
Practice Cost Data
Materials per Acre
Equipment/Installation per AcreEquipment/Installation costs included with the cost of Materials
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
2%
Total CostUnits
Price/Unit$1.20
3%
None.
1 $3,840.00
$115.20
$76.80
$0.00
$0.00
Cost Summary:
UnitsExcavation-dragline/backhoe (E07) 3200
Notes
CP23/A; CP27; CP30
$3,840.00
$4,032.00
$0.00
None.
None
$0.00
$0.00
$0.00
None.
$3,840.00Total Cost$3,840.00 Source: FY10 USDA-NRCS
Program Payment Database
5%15
Acre
This scenario includes the cost of excavating an average of approximately 24-inches of saturated soil in order to restore wetland characteristics to original functions and values. Practice units and payments are based on excavated area. The costs in this scenario are based on excavation of 25% of hydric soil area (1 of 4 acres in this example) within a larger contract.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
190 of 200
658_11_WetlandCreation.xlsx CRP-Saturated Soils
Payment Schedule Results
658
Payment Schedule Development Methodology
Equipment/InstallationMaterials
Forgone Income
$0.00$0.00
$2,640.00
0%0%0%50%
$0.00$5,280.00
$0.00$0.00$0.00$79.20
50%50%50%
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $2,719.20Wetland Restoration CRP-Saturated Soils
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$5,544.00$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$105.60$158.40$0.00
Scenario Code
6581
PracticeCost Share Program
Practice Code
0%0%
$2,719.20$0.00$0.00
191 of 200
658_11_WetlandCreation.xlsx CRP-Saturated Soils
Practice Cost Data
Materials per Acre
Equipment/Installation per AcreEquipment/Installation costs included with the cost of Materials
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
This scenario includes the cost of excavating an average of approximately 24-inches of saturated soil in order to create wetland characteristics. Practice units and payments are based on excavated area. The costs in this scenario are based on excavation of 25% of hydric soil area (1 of 4 acres in this example) within a larger contract
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic Area
$5,280.00Total Cost$5,280.00 Source: FY10 USDA-NRCS
Program Payment Database
Unit for Cost Estimate
UnitsExcavation-dragline/backhoe (E06) 3200
5%15
Acre
Price/Unit$1.65
3%
CP23/A; CP27; CP30
$5,280.00
$5,544.00
$0.00
None.
None
$0.00
$0.00
$0.00
None.
2%
$0.00
$0.00
Cost Summary: Notes
None.
1 $5,280.00
$158.40
$105.60
Total CostUnits
192 of 200
658_11_WetlandCreation.xlsx CRP-Unsaturated Soils
Payment Schedule Results
658
Payment Schedule Development Methodology
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & Maintenance
Scenario Code
6582
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
MobilizationLabor
50%$1,920.00
0%0%0%50%
$0.00$3,840.00
Acre $1,977.60Wetland Restoration CRP-Unsaturated Soils
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$115.20$0.00
$57.6050%
50%
$76.80$0.00$0.00
$1,977.60$0.00$0.00$0.00$0.00$0.00
Forgone Income
$0.00$0.00
0%0%
Total CostAdministration & Permit CostsRisk
$4,032.00$0.00$0.00
193 of 200
658_11_WetlandCreation.xlsx CRP-Unsaturated Soils
Practice Cost Data
Materials per Acre
Equipment/Installation per AcreEquipment/Installation costs included with the cost of Materials
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
2%
Total CostUnits
Price/Unit$1.20
3%
None.
1 $3,840.00
$115.20
$76.80
$0.00
$0.00
Cost Summary:
UnitsExcavation-dragline/backhoe (E07) 3200
Notes
CP23/A; CP27; CP30
$3,840.00
$4,032.00
$0.00
None.
None
$0.00
$0.00
$0.00
None.
$3,840.00Total Cost$3,840.00 Source: FY10 USDA-NRCS
Program Payment Database$0.00
5%15
Acre
This scenario includes the cost of excavating an average of approximately 24-inches of unsaturated soil in order to create wetland characteristics. Practice units and payments are based on excavated area. The costs in this scenario are based on excavation of 25% of hydric soil area (1 of 4 acres in this example) within a larger contract.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)
Geographic AreaUnit for Cost Estimate
194 of 200
660_11_TreeShrubPruning.xlsx CRP-Pruning
Payment Schedule Results
660
Payment Schedule Development Methodology
0%0%
50%50%
Equipment/Installation
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$68.90$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$0.65$3.25$0.00
Scenario Code
6601
PracticeCost Share Program
Practice Code
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $34.13Tree-Shrub Pruning CRP-Pruning
$34.13$0.00$0.00$0.00$0.00$0.00$1.63
Materials
Forgone Income
$0.00$32.50$0.00
0%0%0%50%
50%$65.00$0.00
195 of 200
660_11_TreeShrubPruning.xlsx CRP-Pruning
Practice Cost Data
Materials per AcreMaterials costs included with the cost of Equipment/Installation
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:MCM 1/
$65.00
$68.90
$0.00
None.
None
$0.00
$0.00
$0.00
$0.00
None.
Cost Summary:60 $3,900.00
Units Total Cost
Source: FY10 Nebraska Program Payment Database
None.
$3.25
$0.65
Tree Pruning
1%
5%
$0.00
60 $65.00 $3,900.00
Notes
5%10
Acre
This practice includes the treatment of forestland to improve site conditions for tree & shrub production and fire protection. It typically involves the removal of all or parts of selected branches or leaders from trees and shrubs. This practice is used in conjunction with 666-Forest Stand Improvement. This practice is typically applied on 20 acres.
Nebraska
$65.00Units Price/Unit Total Cost
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost EstimateGeographic Area
196 of 200
666_11_ForestStandImprovement.xlsx CRP-Thin with Slash Treatment
Payment Schedule Results
666
Payment Schedule Development Methodology
$165.38$0.00$0.00$0.00$0.00$0.00
Forgone Income
$0.00$157.50
Administration & Permit CostsRisk
$333.90$0.00
$0.00
0%0%0%50%
$315.00$0.00
Acre $165.38Forest Stand Improvement CRP-Thinning with Slash Treatment
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
$15.75$0.00
$7.8850%
$0.00
50%
Scenario Code
6661
PracticeCost Share Program
Practice Code
CRP
Equipment/InstallationMaterials
$0.00$0.00
Nebraska
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$3.15
0%0%
50%
Total Cost
197 of 200
666_11_ForestStandImprovement.xlsx CRP-Thin with Slash Treatment
Practice Cost Data
Materials per AcreMaterials costs included with the cost of Equipment/Installation
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
5%10
Acre
The practice includes the manipulation of species composition, stand structure, and stocking by cutting or killing selected trees and understory vegetation. This scenario will also include slash treatments. This level of treatment must be maintained for the life of the practice. The typical application of this scenario is 10 acres.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost EstimateGeographic Area
$315.00
$0.00
10 $110.00 $1,100.00Thinning slash treatment 10
MCM 1/
$315.00
$333.90
$0.00
None.
None
$0.00
$0.00
$0.00
None.
5%
$205.00 $2,050.00
Cost Summary:10 $3,150.00
Units Total Cost
None.
$15.75
$3.15
Units Price/Unit Total CostSource: FY10 USDA-NRCS Program Payment Database
Thinning or release cuts
Notes
1%
$0.00
198 of 200
666_11_ForestStandImprovement.xlsx CRP-Thin without Slash Trmt
Payment Schedule Results
666
Payment Schedule Development Methodology
0%$57.75$0.00
Nebraska
Total CostAdministration & Permit CostsRisk
$0.00
$116.60$0.00$0.00$0.00
Payment Rate
Unit Type
Scenario
Acquisition of Tech. KnowledgeOperation & MaintenanceMobilizationLabor
$1.10$5.50$0.00
Scenario Code
6662
PracticeCost Share Program
Practice Code
CRP
CRP Producer Payment RateCRP Program Payment RateCost/UnitCost Category
Acre $57.75Forest Stand Improvement CRP-Thinning without Slash Treatment
$0.00$0.00$0.00$0.00$2.75
50%Equipment/InstallationMaterials
Forgone Income
$0.00$55.00$0.00
0%0%0%50%
$110.00$0.00
0%
50%50%
199 of 200
666_11_ForestStandImprovement.xlsx CRP-Thin without Slash Trmt
Practice Cost Data
Materials per AcreMaterials costs included with the cost of Equipment/Installation
Equipment/Installation per Acre
Labor per AcreLabor costs included with the cost of Materials
Total Materials, Equipment/Installation and Labor Costs: per Acre
MobilizationTotal Materials, Equipment/Installation and Labor Costs. per Acre
Operation & MaintenanceTotal Materials, Equipment/Installation and Labor Costs. per Acre
Acquisition of Technical Knowledgeper Acre
Forgone Incomeper Acre
Riskper Acre
Administration & Permit Costsper Acre
Total Cost Estimate: per Acre
Associated Practices:
1%
$0.00
5%
Cost Summary:10 $1,100.00
Units
$5.50
Source: FY10 USDA-NRCS Program Payment Database
Thinning or release cuts
Notes
MCM 1/
$110.00
$116.60
$0.00
None.
None
$0.00
$0.00
$0.00
None.
None.
$1.10
$110.00
$0.00
10 $110.00 $1,100.00
Total Cost
5%10
Acre
Units Price/Unit Total Cost
The practice includes the manipulation of species composition, stand structure, and stocking by cutting or killing selected trees and understory vegetation. This scenario does not include slash treatments. This level of treatment must be maintained for the life of the practice. The typical application of this scenario is 10 acres.
Nebraska
Typical Practice Scenario
Discount Rate (%/Year)Practice Life (Years)Unit for Cost EstimateGeographic Area
200 of 200