The Neighborhood Concept
A residential experience that is unique to Carnegie Mellon
Vision• Three neighborhoods
that offer a mix of unit types to provide age-appropriate unit typology
• A neighborhood hub in each area
• Students could choose to live in the same neighborhood for multiple years and identify with the neighborhood community
4
Current Housing Inventory
5
Housing Master Plan – Initial Projects
265 Beds2021
265 Beds2022
169 Beds2020
Fifth/Neville
Fifth/Clyde
Forbes/Beeler
Fairfax465 Beds2019
6
2012 Institutional Master Plan
7
Doherty Apartments Site
8
Site Diagrams
Existing Conditions
9
East Campus Garage
Proposed Building
Forbes Ave
ZONING BOUNDARY
PROPERTY BOUNDARY
Proposed Residence
10
East Campus Garage
Forbes Ave
PROPERTY BOUNDARY
A
50’
15’
Proposed Building
ZONING BOUNDARY
Excerpt from 2012 Institutional Master Plan:
Setbacks in 2012 IMP
11
Excerpt from 2012 Institutional Master Plan:
Height in 2012 IMP
12
Current View
13
View into the Plaza
14
View into the Plaza
15
Forbes/Beeler Residence
16
View from Forbes and Beeler
17
View into the Plaza
18
View from Penton Rd
19
View from Penton Rd (without trees)
20
AVERAGE FINISH GRADE (960’)
AVERAGE FINISH GRADE (985.25’)
53’ 8”24.75’ FLOOR 4
FLOOR 3
FLOOR 2
FLOOR 1
Section at Entry Plaza
21
AVERAGE FINISH GRADE (960’)
56.5’AVERAGE FINISH GRADE (985.25’)
24.75’ FLOOR 4
FLOOR 3
FLOOR 2
FLOOR 1
PENTHOUSE
Section at Beeler
22
Ground Floor
First Floor PlanStudent Experience Space
Building Amenities
Shared Residential
23
Second Floor
Second Floor PlanStudent Experience Space
Building Amenities
Shared Residential
24
Third Floor
Third Floor PlanStudent Experience Space
Building Amenities
Shared Residential
25
Fourth Floor
Fourth Floor PlanStudent Experience Space
Building Amenities
Shared Residential
26
Market Space precedents
28
East Campus Garage
Existing Forest
Parking (20 spots)
Proposed Building
Forbes Ave
50’
15’ Pull-off
Dumpster &
Generator
ZONING BOUNDARY
PROPERTY BOUNDARY
Proposed Residence
29
Schedule
Permitting- Zoning Review October 2019- CDAP (Design Review) November 2019- Planning Commission December 2019 – January 2020
Construction- Demolition of Existing Building Spring 2020- Foundations Summer – Fall 2020- Superstructure & Enclosure Winter – Summer 2021- Interior Work Fall 2021 – Spring 2022- Final Fit-out & Site Work Summer 2022- Occupancy August 2022
Proposed Schedule
30
Fifth Ave Projects
Fifth/NevilleApartments
Fifth/ClydeSuites
31
Schedule
Permitting- Site Plan Review Jul 2019- PLI review Aug 2019
Construction- Asbestos Abatement Summer 2019 - Construction Start Fall 2019- Substantial Completion Jun 2020- Occupancy July 2020
Fifth/Neville Apartments
32
Fifth / Clyde Residence
33
Fifth / Clyde Residence Hall
34
Fifth / Clyde Residence
35
Schedule
Permitting- Zoning approved Jul 2019- CDAP (Design Review) Aug 2019- Planning Commission Sep 2019
Construction- Foundations Fall 2019 – Spring 2020- Superstructure & Enclosure Summer 2020- Interior Work Fall 2020 – Spring 2021- Final Fit-out & Site Work Summer 2021- Occupancy August 2021
Fifth / Clyde Residence