P
T
I
EPS
###
##
#
EXISTING GROUND SURFACE
LEDGEROCK
REMOVAL OF SUBSTRUCTURES (ITEM 202.19)
DESIGNATES PAYMENT LINES FOR EXCAVATION PROTECTION SYSTEM (ITEM 552.16)
DESIGNER NOTES
LEGEND
C
OR PERMANENT STEEL SHEETING (552.11)
DESIGNATES PAYMENT LINES FOR PERMANENT TIMBER SHEETING (ITEM 552.10),
OR TEMPORARY STEEL SHEETING (552.13)
DESIGNATES PAYMENT LINES FOR TEMPORARY TIMBER SHEETING (ITEM 552.12),
OR INTERIM STEEL SHEETING (552.15)
DESIGNATES PAYMENT LINES FOR INTERIM TIMBER SHEETING (ITEM 552.14),
DESIGNATES COFFERDAM (TYPE 1) (ITEM 553.01nnnn), OR COFFERDAM (TYPE 2) (ITEM 553.02nnnn)
ALL ITEMS IN LEGEND ARE INCLUDED IN BRIDGE ESTIMATE, EXCEPT AS NOTED.
NOTE:
SELECT GRANULAR FILL, SLOPE PROTECTION - TYPE A (ITEM 203.0801)
EXCAVATION (ITEM 206.01)
AREA ENCLOSED WITHIN THESE LINES DESIGNATES PAYMENT LINES FOR STRUCTURE
** ***
* *
EMBANKMENT IN PLACE (HIGHWAY ESTIMATE)
MAXIMUM DENSITY (HIGHWAY ESTIMATE)
EMBANKMENT IN PLACE (6" TOPSIZE), COMPACTED TO 95% OF STANDARD PROCTOR
DENSITY (HIGHWAY ESTIMATE)
EMBANKMENT IN PLACE, COMPACTED TO 95% OF STANDARD PROCTOR MAXIMUM
PREFABRICATED COMPOSITE STRUCTURAL/INTEGRAL ABUTMENT DRAIN (ITEM 207.26/27)
EXCAVATION (ITEM 206.0201).
AREA ENCLOSED WITHIN THESE LINES DESIGNATES PAYMENT LINES FOR TRENCH & CULVERT
PROCTOR MAXIMUM DENSITY
SELECT STRUCTURE FILL (ITEM 203.21), COMPACTED TO 95% OF STANDARD
EXCAVATION (ITEM 206.01), OR TRENCH & CULVERT EXCAVATION (ITEM 206.0201)
BACKFILL WITH SUITABLE EXCAVATED MATERIAL AS PROVIDED FOR UNDER STRUCTURE
vDETAILS REFER TO SOIL EROSION AND SEDIMENT CONTROL STANDARD SHEETS.
20. TURBIDITY CONTROL MAY BE REQUESTED BY THE REGION TO SATISFY PERMIT CONDITIONS. FOR GUIDANCE AND
vLOCATIONS.
vWILL BE AT THE TOE OF SLOPE AT UNDER ROADWAY LOCATIONS OR AT THE EDGE OF THE STONE KEYS AT STREAM
19. THE LOCATION OF PAYMENT LINES FOR STRUCTURE EXCAVATION HORIZONTAL LIMITS IN FRONT OF THE ABUTMENT
vTHE BOTTOM OF EXCAVATION. FOR MORE GUIDANCE REFER TO SECTION 4 OF THE BRIDGE MANUAL.
18. FOR STRUCTURE EXCAVATION OVER 5'-0" DEEP USE A LAYBACK SLOPE OF 1 VERTICAL TO 1.5 HORIZONTAL FROM
vAPPROACH SLAB ON ABUTMENT STEMS.
17. PREFABRICATED COMPOSITE STRUCTURAL DRAIN (PCSD) SHALL BE PLACED TO THE LEVEL OF THE BOTTOM OF THE
16. COFFERDAM LEGEND DESIGNATIONS SHOULD BE SERIALIZED BY EACH SUBSTRUCTURE EXCAVATION (C1, C2, C3, ETC.).
vTO THE TOP OF FOOTING. OTHERWISE, STOP THE DRAIN 1'-0" BELOW THE WEEPHOLE INVERT ELEVATION.
15. IF WEEPHOLE IS WITHIN 4'-0" OF THE TOP OF FOOTING, EXTEND THE PREFABRICATED COMPOSITE STRUCTURAL DRAIN
vSHEETING AND THE EXISTING/PROPOSED ABUTMENT.
14. IF THE INTERIM SHEETING IS FOR STAGE CONSTRUCTION, SHOW THE CONNECTION BETWEEN THE INTERIM
vF.D.R. FOR THE APPROPRIATE CUT-OFF ELEVATION.
13. IF INTERIM SHEETING IS USED, INCLUDE THE FINAL CUT-OFF ELEVATION FOR THE SHEETING. REFER TO THE
vTHE SOLDIER PILE WALL SPECIFICATION FOR THE APPROPRIATE INFORMATION TO INCLUDE ON THE CONTRACT PLANS.
vTO INCLUDE ON THE CONTRACT PLANS. IF SOLDIER PILES ARE USED, REFER TO THE GUIDELINES ACCOMPANYING
12. IF SHEETING IS USED, REFER TO SECTION 4 OF THE BRIDGE MANUAL FOR THE APPROPRIATE INFORMATION
11. FOR SPECIAL DETAILS FOR INTEGRAL ABUTMENTS, SEE THE BD-IDE SHEETS.
vDETERMINED IN THE FOUNDATION DESIGN REPORT (FDR).
B. IN SOIL, THESE LINES SHALL BE SET BACK A DISTANCE OF THE FOOTING PROJECTION PLUS 3'-0", OR AS
A. IN ROCK, NOTE 2 SHALL GOVERN.
vABUTMENTS, PIERS AND WALLS SHALL BE GOVERNED BY THE FOLLOWING:
10. THE LOCATION OF PAYMENT LINES FOR SELECT STRUCTURE FILL (ITEM 203.21) AND EXCAVATION AROUND
9. FOR STREAM BANK PROTECTION NOTES, SEE BD-EE5E.
vESTIMATE.
vAND WINGWALL FOOTING OR TO THE TOE OF SLOPE, WHICHEVER IS LESS. QUANTITY TO BE INCLUDED IN HIGHWAY
vGROUND SURFACE WITHIN A RECTANGULAR OR TRAPEZOIDAL AREA BOUNDED BY LINES 15 ft. OUTSIDE THE ABUTMENT
vSHALL BE STRIPPED BENEATH ABUTMENT AND PIER FOOTINGS WHICH ARE 10 ft. OR LESS ABOVE THE ORIGINAL
8. IN FILL SITUATIONS, THE REGIONAL GEOTECHNICAL ENGINEER SHALL DETERMINE THE DEPTH THAT THE SURFACE SOILS
vEXCAVATION ITEM.
7. SEE BRIDGE MANUAL SECTION 4 FOR GUIDELINES ON SELECTING THE PROPER TRENCH & CULVERT
6. SEE BRIDGE MANUAL SECTION 4 FOR GUIDELINES ON SHEETING AND COFFERDAMS.
vUNNECESSARY FOR PILE FOUNDATIONS.
vUSED SIMILAR TO THE APPLICABLE CASE SHOWN ON BD-EE9E. A 5'-0" PAD OF SELECT STRUCTURE FILL IS
vCONSOLIDATE THE UNDERLYING MATERIAL BEFORE THE PILES ARE DRIVEN. IN THIS CASE, A DETAIL SHOULD BE
5. AT SOME SITES, FILL IS TO BE PLACED TO THE SUBGRADE OF ROADWAY AND ALLOWED TO STAND IN ORDER TO
4. SLOPE PROTECTION TREATMENT SHALL BE AS SPECIFIED BY THE DESIGNER.
vSHALL BE BACKFILLED WITH SELECT STRUCTURE FILL (ITEM 203.21) UNLESS OTHERWISE SPECIFIED.
vIN WRITING BY THE ENGINEER AFTER CONSULTATION WITH THE REGIONAL GEOTECHNICAL ENGINEER". THE EXCAVATION
vDEPTHS NOTED ON THE PLANS. NO PAYMENT WILL BE MADE FOR REMOVAL BELOW THESE DEPTHS UNLESS AUTHORIZED
vALSO PLACE THE FOLLOWING SPECIAL NOTE ON THE PLANS: "UNSUITABLE MATERIAL SHALL BE REMOVED TO THE
vUNSUITABLE MATERIAL BELOW THE BOTTOM OF FOOTING AS REPORTED IN THE FOUNDATION DESIGN REPORT (FDR).
3. IN AREAS WHERE UNSUITABLE MATERIAL REMOVAL IS REQUIRED, INDICATE ON THE PLANS THE ESTIMATED DEPTH OF
vFACES.
2. IN SOUND ROCK, THE STRUCTURE EXCAVATION PAYMENT LINES SHALL SHOW FOOTINGS BEING POURED AGAINST ROCK
vNECESSARY), AND/OR THE NECESSITY OF DOWELING OR KEYING THE FOOTING INTO THE ROCK SURFACE.
vOF THE FOOTING FROM THE FINAL ROCK SLOPE, THE DEPTH OF THE FOOTING EMBEDMENT INTO SOUND ROCK (IF
1. COORDINATE WITH THE OFFICE OF STRUCTURES FOUNDATIONS AND CONSTRUCTION UNIT FOR THE SETBACK DISTANCE
BACKFILL FOR M.S.E.S. WALL (INCLUDED IN FILL TYPE RETAINING WALL (F.T.R.W.), ITEM 554.4X)
STONE FILLING (HEAVY) (ITEM 620.05), STONE FILLING (LIGHT) (ITEM 620.03)
STONE FILLING (MEDIUM) (ITEM 620.04), STONE FILLING (FINE) (ITEM 620.02)
BEDDING MATERIAL (ITEM 620.08)
NATIVE STREAMBED MATERIAL (ITEM 613.04000001)
R1 BD-EE1E
NOTES AND LEGEND
EXCAVATION AND EMBANKMENT
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
ERRATA
09/22/17
11/25/14
BD-
EE1E
R1.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17
SECTION A-A
SECTION A-A
PARTIAL PLAN
1'-0"
(SEE NOTE 10)
3'-0" MIN.
(TYP.)
3'-0" MIN.
3'-0" INSPECTION BERM
AT SUBGRADE OF ROADWAY
SHOULDER BREAK LINE
1 ON
FOOTING EDGE
1
ON
NO EXISTING ABUTMENT
(WORKING AREA 3'-0" OR LESS)
EXISTING ABUTMENT ADJACENT TO NEW ABUTMENT
MIN.
4'-
0"
(SEE NOTE 10 - TYP.)
3'-0" MIN.
3'-0" INSPECTION BERM
(SEE NOTE 18)5'-0" MAX.,
MIN.1'-0"
PLACED AT THE SAME TIME.
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE
SUBGRADE OF ROADWAY
0" (TYP.)
FINISHED GROUND SURFACE
3'-0" INSPECTION BERM
MIN.
4'-
0"
(SEE NOTE 10 - TYP.)
3'-0" MIN.
STRUCTURAL DRAIN (PCSD)
PREFABRICATED COMPOSITE
SUBGRADE OF ROADWAY
(SEE NOTES 15 & 17)
0 (TYP.)
FINISHED GROUND SURFACE
(HIGHWAY ESTIMATE)
UNCLASSIFIED EXCAVATION
PAYMENT LINE FOR
PLACED AT THE SAME TIME.
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE 1'-0" MIN.
SECTION A-A
3'-0" INSPECTION BERM
MIN.
4'-
0"
(SEE NOTE 10 - TYP.)
3'-0" MIN.
STRUCTURAL DRAIN (PCSD)
PREFABRICATED COMPOSITE
SUBGRADE OF ROADWAY
(SEE NOTES 15 & 17)
0 (TYP.)
FINISHED GROUND SURFACE
(HIGHWAY ESTIMATE)
UNCLASSIFIED EXCAVATION
PAYMENT LINE FOR
PLACED AT THE SAME TIME.
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE1'-0" MIN.
THAN 3'-0"
GREATER
STRUCTURAL DRAIN (PCSD)
PREFABRICATED COMPOSITE
(SEE NOTES 15 & 17)
A
AB
B
**
*
*
**
FOR NOTE G, SEE BD-EE5E.
FOR NOTES 1 THROUGH 20 AND LEGEND, SEE BD-EE1E.
FOR STRUCTURE EXCAVATION GUIDELINES, SEE NOTE 18.
SLOPE PROTECTION IN PLAN NOT SHOWN. SEE NOTES 4 & G.
DESIGN REPORT (FDR) FOR ACTUAL RECOMMENDATION.
FOR THIS DIMENSION REFER TO THE FOUNDATION
BE REMOVED IN SOME CIRCUMSTANCES.
ACTUAL RECOMMENDATION. THE ENTIRE ABUTMENT MAY
REFER TO THE FOUNDATION DESIGN REPORT (FDR) FOR
EXCAVATION LIMITS AND EXISTING SUBSTRUCTURE REMOVAL.
A FULL PLAN OF THE STRUCTURE INCLUDING STRUCTURE
PARTIAL PLAN SHOWN. CONTRACT PLANS SHOULD SHOW
SLOPE PROTECTION.
THE EXISTING SUBSTRUCTURE REMAIN IN LIEU OF
REGIONAL OFFICE MAY REQUEST THAT A PORTION OF
FOR SECTION B-B, SEE BD-EE3E.
DESIGNER NOTES:
*
REMOVAL ITEM.
OR A PORTION OF IT REMOVED UNDER THE SUBSTRUCTURE
DURING CONSTRUCTION, THE ENGINEER MAY ORDER ALL
ABUTMENT TO REMAIN WILL BE UNSTABLE OR A HAZARD
IF THE ENGINEER DETERMINES THE PORTION OF EXISTING
REMOVAL NOTE:
(SEE NOTES 4 & G)
SLOPE PROTECTION
(SEE NOTES 4 & G)
SLOPE PROTECTION
EXISTING ABUTMENT
(SEE "REMOVAL NOTE")
ABUTMENT TO REMAIN
THIS PORTION OF EXISTING
(SEE "REMOVAL NOTE")
ABUTMENT TO REMAIN
THIS PORTION OF EXISTING
(SEE NOTES 4 & G)
SLOPE PROTECTION
EXISTING ABUTMENT
1.5
1
1
1.5
1
1.5
(WORKING AREA GREATER THAN 3'-0")
EXISTING ABUTMENT ADJACENT TO NEW ABUTMENT
BD-EE2E
SOIL OR PILE FOUNDATIONS (1 OF 2)
BRIDGE SUBSTRUCTURES ON
EXCAVATION AND EMBANKMENT DETAILS
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
ERRATA
09/22/17
BD-
EE2
E.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17
(SEE NOTE 15)
SECTION B-B
1.5
1
FINISHED GROUND
1.5
1
UNSUITABLE MATERIAL REMOVAL
NO NEW ABUTMENT
BE REMOVED IN SOME CIRCUMSTANCES.
ACTUAL RECOMMENDATION. THE ENTIRE ABUTMENT MAY
REFER TO THE FOUNDATION DESIGN REPORT (FDR) FOR
PIER SECTION
SUBGRADE OF ROADWAY
PLACED AT THE SAME TIME.
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE
SHOULDER BREAK LINE
8"
1'-
0"
FINISHED GROUND SURFACE
STRUCTURAL DRAIN (PCSD)
PREFABRICATED COMPOSITE
(HIGHWAY ESTIMATE)
UNCLASSIFIED EXCAVATION
PAYMENT LINE FOR
0 (TYP.)
(SEE NOTE 10 - TYP.)
3'-0" MIN.
(SEE NOTE 18)5'-0" MAX.,
REMOVAL DEPTH
SEE NOTE 3 FOR
SEE NOTE 18
0
(SEE NOTE 18)5'-0" MAX.,
(SEE NOTE 10 - TYP.)
3'-0" MIN.
FINISHED GROUND SURFACE
STANDARD SHEET FOR DETAILS.
THE APPROPRIATE HIGHWAY
IS 1 ON 3 OR STEEPER. SEE
BENCHED IF EXISTING SLOPE
EXISTING GROUND TO BE
0 (TYP.)
0 (TYP.)
FAREWELL DOT TH
ANKS FOR 33 GOOD
YEARS - MHM - F
OR ASSISTANCE CA
LL 867-5309
(SEE NOTES 4 & G)
SLOPE PROTECTION
SLOPE PROTECTION.
THE EXISTING SUBSTRUCTURE REMAIN IN LIEU OF
REGIONAL OFFICE MAY REQUEST THAT A PORTION OF
FOR ADDITIONAL NOTES AND LEGEND, SEE BD-EE1E.
FOR STRUCTURE EXCAVATION GUIDELINES, SEE NOTE 18.
FOR NOTE G, SEE BD-EE5E.
FOR NOTES 1 THROUGH 20 AND LEGEND, SEE BD-EE1E.
FOR SECTION B-B LOCATION, SEE BD-EE2E.
DESIGNER NOTES:
FINISHED GRADE
4'-0" MIN. BELOW
BOTTOM OF FOOTING
DESIGN REPORT
IN THE FOUNDATION
OTHERWISE NOTED
3'-0" (TYP.) UNLESS
DETAILS ABOVE THIS LINE
EXCAVATION AND BACKFILL
CURRENT BD SHEETS FOR
SEE VARIOUS DETAILS ON
*
REMOVAL ITEM.
OR A PORTION OF IT REMOVED UNDER THE SUBSTRUCTURE
DURING CONSTRUCTION, THE ENGINEER MAY ORDER ALL
ABUTMENT TO REMAIN WILL BE UNSTABLE OR A HAZARD
IF THE ENGINEER DETERMINES THE PORTION OF EXISTING
REMOVAL NOTE:
*
FOOTING
SUBSTRUCTURE
EXISTING SUBSTRUCTURE
(SEE REMOVAL NOTE)
ABUTMENT TO REMAIN
THIS PORTION OF EXISTING
BD-EE3E
SOIL OR PILE FOUNDATION (2 OF 2)
BRIDGE SUBSTRUCTURES ON
EXCAVATION AND EMBANKMENT DETAILS
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
ERRATA
09/22/17
BD-
EE3
E.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17
FOR ADDITIONAL NOTES AND LEGEND, SEE BD-EE1E.
FOR STRUCTURE EXCAVATION GUIDELINES, SEE NOTE 18.
EXCAVATION LIMITS AND EXISTING SUBSTRUCTURE REMOVAL.
A FULL PLAN OF THE STRUCTURE INCLUDING STRUCTURE
PARTIAL PLAN SHOWN. CONTRACT PLANS SHOULD SHOW
DESIGNER NOTES:
1.5
1
1.5
1
1 ON __
1
ON __
1.5
1
(SEE NOTE 15)
1.5
1
SEE NOTE 103'-0" MIN.
1'-0"
SEE NOTE 103'-0" MIN.
SEE NOTE 103'-0" MIN.
AT SUBGRADE OF ROADWAY
SHOULDER BREAK LINE
FOOTING EDGE
TOP OF FINAL ROCK SLOPE
SUBGRADE OF ROADWAYPLACED AT THE SAME TIME.
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE
0 (TYP.)
STRUCTURAL DRAIN (PCSD)
PREFABRICATED COMPOSITE
0 (TYP.) SEE NOTE 1
PLACED AT THE SAME TIME.
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE
SUBGRADE OF ROADWAY
STRUCTURAL DRAIN (PCSD)
PREFABRICATED COMPOSITE
FINISHED GROUND SURFACE
0 (TYP.)
SEE NOTE 1
SEE NOTE 10
3'-0" MIN.
SEE NOTE 10
3'-0" MIN.
(HIGHWAY ESTIMATE)
UNCLASSIFIED EXCAVATION
PAYMENT LINE FOR
SEE NOTE 10
3'-0" MIN.
SEE NOTES 1 & 2
0 (TYP.)
SEE NOTE 185'-0" MAX.
EXISTING & FINISHED GROUND
SEE NOTE 103'-0" MIN.
(HIGHWAY ESTIMATE)
UNCLASSIFIED EXCAVATION
PAYMENT LINE FOR
SEE NOTE 1
ROCK SURFACE
PROPOSED FINAL
1'-0" APPROX.
B B
A
A
SECTION A-A
0 (TYP.)NOTE 1
SEE
SECTION A-A
1.5
1
NO EXISTING ABUTMENT
SEE NOTE 103'-0" MIN.
SEE NOTE 1
(SEE NOTES 15 & 17)
PIER SECTION
SECTION B-B
STRUCTURAL DRAIN (PCSD)
PREFABRICATED COMPOSITE
PLACED AT THE SAME TIME.
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE
SUBGRADE OF ROADWAY
ROCK SURFACE
PROPOSED FINAL
SEE NOTE 19
SEE NOTE 10
3'-0" MIN.
PLAN
ABUTMENT
EXISTING
SEE NOTE 19
(SEE NOTES 15 & 17)
BD-EE4E
ROCK FOUNDATION
BRIDGE SUBSTRUCTURES ON
EXCAVATION AND EMBANKMENT DETAILS
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
ERRATA
09/22/17
BD-
EE4
E.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17
2
1
SOIL AT TOE
PARTIALLY VEGETATED STONE SLOPE PROTECTION (OPTIONAL)
(SOIL AT TOE SHOWN)
"CHOKE" THE STONE BELOW THE 1 FOOT THICKNESS SHOWN. RETENTION INCLUDED IN TOPSOIL ITEM.
OR SELECT GRANULAR FILL OR SUITABLE EXCAVATED MATERIAL OR SUFFICIENT TOPSOIL MAY BE PLACED TO
FOR RETENTION OF THE TOPSOIL, THE SURFACE OF THE STONE FILL MAY BE GRADED OFF WITH FINE STONE
CONTRACTOR NOTE:
*
STONE APRON AT STRUCTURE OUTLET
2
1
ROCK AT TOE
RECONSTRUCTION WITH NATIVE STREAMBED MATERIAL
STREAM REALIGNMENT OR
***
BRIDGES & CULVERTS WITH CUT OFF WALL PROTECTION
***
* **
****
***
** * ** * *
****
* **
**
*
PROPOSED FINISHED GROUND LINE
1'-0" ABOVE DESIGN HIGH WATER ELEVATION
5'-0"
4'-
0"
0 (TYP.)
STREAM BED
EXISTING
TOE OF SLOPE
5'-0"
4'-
0"
1'-0" ABOVE ORDINARY HIGH WATER ELEVATION
SEE NOTES I & J1'-0" TOP SOIL
TREES MAY BE PLANTED ABOVE THIS ELEVATION
1'-0" ABOVE DESIGN HIGH WATER ELEVATION
PROPOSED FINISHED GROUND LINE
TOE OF SLOPE
STREAM BED
EXISTING
0 (TYP.)
SEE NOTE M
TO BANK FULL ELEVATION (TYP.)
TO 1'-0" ABOVE DHW (TYP.)
0 (TYP.)
1'-0"
0 (TYP.)
1'-0"
TO 1'-0" ABOVE DHW (TYP.)
5'-0"
1'-0" ABOVE DESIGN HIGH WATER ELEVATION
PROPOSED FINISHED GROUND LINE
TOE OF SLOPE
ASSUMED LEDGE ROCK SURFACE
EXISTING STREAM BED AND
AT TOE OF SLOPE1'-0" KEY INTO ROCK0 (TYP.)
4'-
0"
5'-0"
STREAM BED
EXISTING
(SEE NOTE L)
25'-0"
CUT OFF WALL
********
*** *
* * *
*****
** *
STRUCTURAL SPAN
AS SHOWN ON PLANS
CHANNEL WIDTH
OR 2'-6" STONE FILLING (HEAVY)
2'-0" STONE FILLING (MEDIUM)
OR 2'-6" STONE FILLING (HEAVY)
2'-0" STONE FILLING (MEDIUM)
OR 2'-6" STONE FILLING (HEAVY)
2'-0" STONE FILLING (MEDIUM)
OR 2'-6" STONE FILLING (HEAVY)
2'-0" STONE FILLING (MEDIUM)
OR 2'-6" STONE FILLING (HEAVY)
2'-0" STONE FILLING (MEDIUM)
OR 2'-6" STONE FILLING (HEAVY)
2'-0" STONE FILLING (MEDIUM)
SEE NOTE G
SEE NOTE G
SEE NOTE F
TYPE BRIDGE
BOX CULVERT
SEE NOTE G
2
1
ON BD-EE1E
SEE NOTE 20
ON BD-EE1E
SEE NOTE 20
ON BD-EE1E
SEE NOTE 20
ON BD-EE1E
SEE NOTE 20
ON BD-EE1E
SEE NOTE 20
ON BD-EE1E
SEE NOTE 20
FILLING (MEDIUM/HEAVY)
MATERIAL UNDER STONE
9" THICK BEDDING
FILLING (MEDIUM/HEAVY)
MATERIAL UNDER STONE
9" THICK BEDDING
FILLING (MEDIUM/HEAVY)
MATERIAL UNDER STONE
9" THICK BEDDING
FILLING (MEDIUM/HEAVY)
MATERIAL UNDER STONE
9" THICK BEDDING
FILLING (MEDIUM/HEAVY)
MATERIAL UNDER STONE
9" THICK BEDDING
FILLING (MEDIUM/HEAVY)
MATERIAL UNDER STONE
9" THICK BEDDING
(SEE NOTE P)
NATIVE STREAMBED MATERIAL
(SEE NOTE P)
NATIVE STREAMBED MATERIAL
(SEE NOTE P)
NATIVE STREAMBED MATERIAL
vTHE PLACEMENT OF NATIVE STREAMBED MATERIAL ON TOP OF THE STONE FILLING.
vENVIRONMENTAL UNIT (OR THEIR REPRESENTATIVE) TO DETERMINE THE NEED FOR
vPLACED WITHIN THE STREAM, THE DESIGNER SHALL CONSULT WITH THE REGIONAL
P. WHEN IN-STREAM WORK OR REALIGNMENT IS NECESSARY AND STONE FILLING IS
vDEPTH OF 5'-0".
vPROTECTION USE A THICKNESS OF 3'-6", A KEY WIDTH OF 6'-0", A KEY
O. WHEN EXTRA HEAVY STONE FILL TYPE B IS SPECIFIED FOR STREAM BANK
N. FOR ADDITIONAL NOTES AND LEGEND, SEE BD-EE1E.
M. TO DETERMINE BANK FULL ELEVATION, SEE EI 10-028.
vHYDRAULIC ENGINEERING UNIT.
vSCOUR POTENTIAL WITH CONCURRENCE OF REGIONAL HYDRAULIC ENGINEER OR
L. RECOMMENDED MINIMUM. CAN BE MODIFIED BASED ON SCOUR HISTORY AND/OR
vDETAILS WITH THE HYDRAULICS ENGINEERING UNIT.
K. WHEN STREAM BANK PROTECTION REQUIRES EXTRA HEAVY STONE FILL, COORDINATE
vLIMIT OF THE DETAIL WITHIN 100 FEET OF THE BRIDGE FASCIA.
vDETAIL. NO LARGER TREES OR SHRUBS MAY BE PLANTED BELOW THE ELEVATION
vLARGER TREES AND SHRUBS MAY BE USED ABOVE THE ELEVATION LIMIT OF THE
vLESS AT FULL GROWTH MAY BE USED FOR TOPSOIL PLANTING WITH THIS DETAIL.
J. ANY NYSDOT-APPROVED VEGETATION HAVING A STEM DIAMETER OF 1 INCH OR
vSOIL DETAIL MAY BE RETAINED AND SHADE-TOLERANT VEGETATION USED.
vSUFFICIENT SUNLIGHT WILL REACH THE AREA TO SUPPORT VEGETATION, THE
vCONSULTATION WITH THE LANDSCAPE ARCHITECT, DETERMINES THAT
vBENEATH THE STRUCTURE. IN THE EVENT THAT THE DESIGNER, IN
I. IT IS RECOMMENDED THAT THE TOP SOIL BE REPLACED BY FINE STONE FILL
vAREA OF VEGETATED COVER IS DESIRED.
vOF TYPICAL STONE SLOPE PROTECTION AT THE DESIGNERS OPTION, WHERE GREATER
H. PARTIALLY VEGETATED STONE SLOPE PROTECTION DETAIL MAY BE USED INSTEAD
vSTREAM BED PROTECTION TO FACE OF SUBSTRUCTURE.
vPROTECTION (STRUCTURAL) OR OTHER APPROVED MATERIAL FROM UPPER LIMIT OF
G. ON SLOPES BENEATH SUPERSTRUCTURES, PLACE SELECT GRANULAR FILL SLOPE
vBASED ON TYPE AND CONDITION OF ROCK, SLOPE AND STREAM VELOCITY.
F. THE FOUNDATION DESIGN REPORT WILL NOTE IF ROCK DOWELS WILL BE REQUIRED
vARE SUBJECT TO APPROVAL BY THE DEPUTY CHIEF ENGINEER (STRUCTURES).
vEXISTING GROUND OR STREAM BED AT THE LOCATION. ANY MODIFICATIONS
vBASED ON ANTICIPATED SCOUR CONDITIONS OR ROCK BEING LOCATED AT
E. THE STONE FILL ANCHORAGE TRENCH SHOULD BE MODIFIED IN SPECIAL CASES
vAS STREAM BANK PROTECTION WITH SOIL AT TOE OF SLOPE.
D. A STONE FILL ANCHORAGE TRENCH IS REQUIRED WHEREVER STONE FILL IS USED
C. TOE OF SLOPE TO BE LABELED IN PLAN VIEW.
vIS BEING PLACED UNDER HIGHWAY ESTIMATE.
B. COORDINATE WITH REGION OFFICE WHEN ADDITIONAL STREAM BANK PROTECTION
vMINIMUM OF 10'-0" BEHIND THE WINGWALL AS MEASURED ALONG THE STATION LINE.
vBANK PROTECTION IS REQUIRED BEHIND AN ABUTMENT, IT SHALL EXTEND A
vPERPENDICULAR TO THE STATION LINE OF THE ROADWAY. WHERE THE STREAM
vEMBANKMENT TO 10'-0" BEYOND THE END OF EACH WINGWALL MEASURED
vTHE STREAM BANK PROTECTION SHALL EXTEND FULL WIDTH OF THE ABUTMENT
vWHERE EXISTING EMBANKMENTS ARE CUT OR FILL IS PLACED. AS A MINIMUM
A. STREAM BANK PROTECTION SHALL BE PLACED AT ALL STREAM CROSSINGS
DESIGNER NOTES:
R2 BD-EE5E
PROTECTION DETAILS
STREAM BANK
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
ERRATA
09/22/17
11/25/14
BD-
EE5
ER2.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17
1 ON __
1
ON __
(SEE NOTE 15)
1
1
1
1
5'-
0"
3'-0"
3'-0"
1'-0"
3'-
0"
10SEE NOTE
SUBGRADE ELEVATION
EMBANKMENT ATOUTSIDE OF ABUTMENT WINGWALL AREA.
IS PARALLEL TO ABUTMENT STEM
TO BOTTOM OF FOOTING ELEVATION
LIMIT OF SELECT STRUCTURE FILL
EDGE OF FOOTING (TYP.)
A
A
B
B
MIN.
1'-
0"
MIN.
4'-
0"
1'-0" MIN.
8"
1'-0"
5'-
0"
3'-0" (TYP.)MIN.4'-0"
FINISHED GRADE
STRUCTURAL DRAIN (PCSD)
PREFABRICATED COMPOSITE
FINISHED GROUND
EXISTING GROUND (SEE NOTE 8)
(SEE NOTE 15)
FINISHED GRADE
STRUCTURAL DRAIN (PCSD)
PREFABRICATED COMPOSITE
1
1
EXISTING GROUND (SEE NOTE 8)
5'-
0"
MIN.
1'-
0"
MIN.
4'-
0"
MIN.4'-0"FINISHED GROUND
1'-0" MIN.
3'-0" (TYP.)
50'-0" MIN.
CONSTRUCTION (SEE NOTE 5)
PRIOR TO PILE DRIVING AND ABUTMENT
EMBANKMENT PLACED TO THIS LEVEL
HORIZONTAL OR FLATTER
SLOPE 1 VERTICAL ON 3
SUBGRADE OF ROADWAY
3'-0"
15 & 17
SEE NOTES
END OF WINGWALL
FINISHED GROUND
ABUTMENTS ON FILL WITH SPREAD FOOTINGS
PARTIAL PLAN
(U-WINGWALL TYPE SHOWN)
ABUTMENT ON FILL - PILE FOUNDATION
SECTION B-B
SECTION A-A
THE ABUTMENTv/vWINGWALL AND THE EXISTING GROUND.
ABUTMENT STEM LOCATED AT THE OUTER MOST REAR OF
BOTTOM OF FOOTING RUNNING PARALLEL TO THE
POINT OF INTERSECTION OF A 1:1 FROM A LINE AT THE
THIS LINE REPRESENTS A VERTICAL PLANE FROM THE
FOR NOTE G, SEE BD-EE5E.
FOR NOTES 1 THROUGH 20 AND LEGEND, SEE BD-EE1E.
SLOPE PROTECTION NOT SHOWN IN PLAN.
SHOW A FULL PLAN OF THE STRUCTURE.
PARTIAL PLAN SHOWN. CONTRACT PLANS SHOULD
DESIGNER NOTES:
*
* SEE DESIGNER NOTE
PLACED AT THE SAME TIME.
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE
(SEE NOTES 4 & G)
SLOPE PROTECTION
PLACED AT THE SAME TIME.
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE
(SEE NOTES 4 & G)
SLOPE PROTECTION
PLACED AT THE SAME TIME.
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE
(SEE NOTES 4 & G)
SLOPE PROTECTION
BD-EE6E
FOR ABUTMENTS ON FILL
EMBANKMENT DETAILS
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
ERRATA
09/22/17
BD-
EE6
E.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17
SECTION A-A
1
1
c
TYPICAL CROSS SECTION
SLOPE PROTECTION NOT SHOWN)
(LOOKING AT ABUTMENT FACE
ABUTMENT CONSTRUCTION
OF FOOTING ELEVATION AFTER
MATERIAL PLACED ABOVE BOTTOM
LIMITS OF HIGHWAY EMBANKMENT
TOE OF SLOPE
50'-0" MIN.
3'-0
" (T
YP.)
50'-0" MIN.
SUBGRADE OF ROADWAY
PRIOR TO ABUTMENT CONSTRUCTION
PLACE EMBANKMENT TO THIS LINE
HORIZONTAL OR FLATTER
SLOPE 1 VERTICAL ON 3
(SEE NOTE 8)
EXISTING GROUND SURFACE
5'-
0"
5'-0"
3'-0"
(SEE NOTE 8)
EXISTING GROUND SURFACE
5'-
0"
SUBGRADE OF ROADWAY
SUBGRADE ELEVATION
EMBANKMENT AT
*
AA
TYPICAL EMBANKMENT PLAN ON FILL(SLOPE PROTECTION NOT SHOWN)
5'-0"
THIS LINE WILL DEPEND ON THE ACTUAL SITE CONDITIONS.
ILLUSTRATIVE PURPOSES ONLY. THE ACTUAL LOCATION OF
AS SHOWN IN SECTION A-A. THE LINE SHOWN IS FOR
THE ABUTMENTv/vWINGWALL AND THE EXISTING GROUND,
ABUTMENT STEM LOCATED AT THE OUTER MOST REAR OF
BOTTOM OF FOOTING RUNNING PARALLEL TO THE
POINT OF INTERSECTION OF A 1:1 FROM A LINE AT THE
THIS LINE REPRESENTS A VERTICAL PLANE FROM THE
ON FILL, SEE BD-EE6E.
FOR ADDITIONAL EMBANKMENT DETAILS FOR ABUTMENTS
FOR NOTE G, SEE BD-EE5E.
FOR NOTES 1 THROUGH 20 AND LEGEND, SEE BD-EE1E.
SLOPE PROTECTION NOT SHOWN IN PLAN.
DESIGNER NOTES:
SEE DESIGNER NOTE*
PLACED AT THE SAME TIME.
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE
SEE DESIGNER NOTE*(SEE NOTES 4 & G)
SLOPE PROTECTION
PRIOR TO ABUTMENT CONSTRUCTION
BOTTOM OF FOOTING ELEVATION
SELECT STRUCTURE FILL PLACED TO
IS PARALLEL TO ABUTMENT STEM (TYP.)
TO BOTTOM OF FOOTING ELEVATION
LIMIT OF SELECT STRUCTURE FILL
TO ABUTMENT CONSTRUCTION
TO BOTTOM OF FOOTING ELEVATION PRIOR
LIMITS OF SELECT STRUCTURE FILL PLACED
BD-EE7E
FOOTINGS ON FILL
ABUTMENTS WITH SPREAD
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
ERRATA
09/22/17
BD-
EE7
E.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17
c
1
1.5
DESIGNER NOTES:
SEE BD-EE2E.
FOR ADDITIONAL EXCAVATION AND EMBANKMENT DETAILS,
PRESCRIBED WAITING PERIOD.
SHOWING EXCAVATION AND EMBANKMENT AFTER THE
TO START OF WAITING PERIOD, A PLAN SHOULD BE SHOWN
IN ADDITION TO THE PLAN SHOWING EMBANKMENT PRIOR
1
1
SEE DESIGNER NOTE*
*
SEE DESIGNER NOTE*
FOR NOTE G, SEE BD-EE5E.
FOR NOTES 1 THROUGH 20 AND LEGEND, SEE BD-EE1E.
THE WAITING PERIOD.
ON THE PLANS THAT WILL INDICATE THE DURATION OF
THE REPORT WILL ALSO CONTAIN A NOTE TO BE PLACED
INDICATED IN THE FOUNDATION DESIGN REPORT.
USE OF THE DETAILS SHOWN ON THIS SHEET WILL BE
THIS LINE WILL DEPEND ON THE ACTUAL SITE CONDITIONS.
ILLUSTRATIVE PURPOSES ONLY. THE ACTUAL LOCATION OF
AS SHOWN IN SECTION A-A. THE LINE SHOWN IS FOR
THE ABUTMENTv/vWINGWALL AND THE EXISTING GROUND,
ABUTMENT STEM LOCATED AT THE OUTER MOST REAR OF
BOTTOM OF FOOTING RUNNING PARALLEL TO THE
POINT OF INTERSECTION OF A 1:1 FROM A LINE AT THE
THIS LINE REPRESENTS A VERTICAL PLANE FROM THE
3'-0
"
5'-0"
3'-0"
5'-0" (TYP.)
50'-0"
PARALLEL TO ABUTMENT STEM.
BY THIS POINT. LIMIT IS
LOCATION OF LIMIT DETERMINED
SUBGRADE ELEVATION
EMBANKMENT AT
PROPOSED FOOTING
SECTION A-A
MATERIAL PLACED AS SHOWN IN
LIMITS OF HIGHWAY EMBANKMENT
PLACED TO BOTTOM OF FOOTING
LIMITS OF SELECT STRUCTURE FILL
TOE OF SLOPE
PROPOSED ABUTMENT
50'-0" MIN.
SUBGRADE OF ROADWAY
HORIZONTAL OR FLATTER
SLOPE 1 VERTICAL ON 3
SEE DETAIL "A"
(SEE NOTE 8)
EXISTING GROUND SURFACE
PLACED AT THE SAME TIME.
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE
SUBGRADE OF ROADWAY
(SEE NOTE 8)
EXISTING GROUND SURFACE
SUBGRADE OF ROADWAY
0 TYP.
PROPOSED ABUTMENT
5'-0"
5'-0"
5'-0"
(SEE NOTE 10)
3'-0" (TYP.)
(SLOPE PROTECTION NOT SHOWN)
(PRIOR TO START OF WAITING PERIOD)
TYPICAL EMBANKMENT PLAN ON FILL
(PRIOR TO START OF WAITING PERIOD)
SECTION A-A
PRESCRIBED WAITING PERIOD - SLOPE PROTECTION NOT SHOWN)
(LOOKING AT PROPOSED ABUTMENT FACE AFTER
TYPICAL CROSS SECTION
(AFTER THE PRESCRIBED WAITING PERIOD)
DETAIL "A"
A A
(SEE NOTES 4 & G)
SLOPE PROTECTION
SEE DETAIL "A".
AT STRUCTURE EXCAVATION LOCATIONS,
SUITABLE EXCAVATED MATERIAL REQUIRED
HIGHWAY EMBANKMENT SHOWN,
(SEE NOTES 4 & G)
SLOPE PROTECTION
BD-EE8E
AND WAITING PERIOD
ON FILL/STRUCTURE LOADING
ABUTMENTS WITH SPREAD FOOTINGS
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
ERRATA
09/22/17
BD-
EE8
E.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17
5'-0"
3'-0
"
5'-0"
3'-0"
50'-0" MIN.
(TO BE PLACED IN STEP 2)
FOOTING LOCATION
PROPOSED ABUTMENT
FOOTING ELEVATION
BELOW BOTTOM OF
STRUCTURAL FILL
LIMITS OF SELECT
PRESCRIBED WAITING PERIOD
MATERIAL PLACED PRIOR TO
TOE OF EMBANKMENT
TOE OF SLOPE
HIGHWAY EMBANKMENT MATERIAL
SUBGRADE OF ROADWAY
5'-0"
c
(SEE NOTE 8)
EXISTING GROUND
3'-0"
5'-0"
PLACED AT THE SAME TIME.
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE
50'-0" MIN.
5'-0"
1.5
1
1.5
1
1
1
SUBGRADE OF ROADWAY
SUBGRADE OF ROADWAY
(SEE NOTE 8)
EXISTING GROUND
3'-0" (TYP.)
3'-0" (T
YP.)
SECTION A-A
CONSTRUCTION
FOR STEP 2
SEE DETAIL "A"
A A
PRIOR TO PRESCRIBED WAITING PERIOD
TO BOTTOM OF FOOTING ELEVATION
SELECT STRUCTURE FILL PLACED
ABUTMENT STEM.
AND IS PARALLEL TO
LOCATED BY THIS POINT
TOE OF EMBANKMENT
SUBGRADE ELEVATION
EMBANKMENT AT
EMBANKMENT CONSTRUCTION - STEP 2
A A
SEE DESIGNER NOTE*
EMBANKMENT CONSTRUCTION - STEP 2
EMBANKMENT CONSTRUCTION - STEP 2
EMBANKMENT CONSTRUCTION - STEP 1
WAITING PERIOD
BACKFILL DETAILS AFTER
STEP 2
DETAIL "A"
SEE DESIGNER NOTE*
(SLOPE PROTECTION NOT SHOWN)
TYPICAL FRONT ELEVATION
*
HORIZONTAL OR FLATTER
SLOPE 1 VERTICAL ON 3EMBANKMENT CONSTRUCTION - STEP 1
SEE NOTE 4 & G)
SLOPE PROTECTION
SEE NOTE 4 & G)
SLOPE PROTECTION
SLOPE PROTECTION NOT SHOWN)
(SINGLE ABUTMENT. FLARED AND IN LINE WALLS,
EMBANKMENT DETAILS PRIOR TO WAITING PERIOD
STEP 1
TYPICAL EMBANKMENT PLAN ON FILL
THIS LINE WILL DEPEND ON THE ACTUAL SITE CONDITIONS.
ILLUSTRATIVE PURPOSES ONLY. THE ACTUAL LOCATION OF
AS SHOWN IN SECTION A-A. THE LINE SHOWN IS FOR
THE ABUTMENTv/vWINGWALL AND THE EXISTING GROUND,
ABUTMENT STEM LOCATED AT THE OUTER MOST REAR OF
BOTTOM OF FOOTING RUNNING PARALLEL TO THE
POINT OF INTERSECTION OF A 1:1 FROM A LINE AT THE
THIS LINE REPRESENTS A VERTICAL PLANE FROM THE
ON FILL, SEE BD-EE6.
FOR ADDITIONAL EMBANKMENT DETAILS FOR ABUTMENTS
FOR NOTE G, SEE BD-EE5E.
FOR NOTES 1 THROUGH 20 AND LEGEND, SEE BD-EE1E.
THE WAITING PERIOD.
ON THE PLANS THAT WILL INDICATE THE DURATION OF
THE REPORT WILL ALSO CONTAIN A NOTE TO BE PLACED
INDICATED IN THE FOUNDATION DESIGN REPORT.
USE OF THE DETAILS SHOWN ON THIS SHEET WILL BE
DESIGNER NOTES:
BD-EE9E
WITH WAITING PERIOD
FOOTINGS ON FILL
ABUTMENTS WITH SPREAD
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
ERRATA
09/22/17
BD-
EE9
E.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17
A
A
TYP.
EMBEDMENT DEPTH
SPECIFY MINIMUM
BRACED EXCAVATION PLAN
DETAIL "D"SECTION A-A
DETAIL "C"
WELD SIZE
DESIGNER TO DETERMINE
FOR ADDITIONAL NOTES, SEE BD-EE1E.
DETAILS SHALL BE DESIGNED AT EACH LOCATION.
NECESSARY LEVEL OF DETAIL REQUIRED. CONNECTION
PURPOSES ONLY AND ARE INTENDED TO SHOW THE
CONNECTION DETAILS SHOWN ARE FOR ILLUSTRATIVE
DESIGNER NOTES:
(SPECIFY TREMIE SEAL, IF APPROPRIATE)
TIMES DURING CONSTRUCTION OPERATIONS.
CONTRACTOR SHALL PROTECT STRUTS AT ALL
STRUTS ARE INSTALLED.
2'-0" BELOW THE WALE/STRUT ELEVATION UNTIL THE WALES AND
DO NOT PROGRESS THE EXCAVATION AT THE WALL FACE FARTHER THAN
NOTES:
X XX
X
XX
X
X
XX
3'-0" (TYP.)
FOOTING
OF c
SEE DETAIL "C"
PROPOSED FOOTING
SEE DETAIL "A" SEE DETAIL "B"
SEE DETAIL "D" (TYP.)
SHIM AS NECESSARY
SIZE (TYP.)pINDICATE STIFFENER
SIZE (TYP.)p
INDICATE STIFFENER
DETAIL "A"
DETAIL "B"
SIZE (TYP.)p
INDICATE STIFFENER
TYP.
SHIM AS NECESSARY
REQUIRED BY DESIGN)
SIZE (TYP.) (IF p
INDICATE STIFFENER
REQUIRED BY DESIGN)
SIZE (TYP.) (IF p
INDICATE STIFFENER
SECTION MODULUS
INDICATE WALE
INDICATE WALE SIZE
SOLDIER PILE WALL, SEE NOTE 12)
INDICATE MATERIAL (SHEET PILING OR
SECTION MODULUS
INDICATE WALE
INDICATE WALE SIZE
INDICATE STRUT SIZE
INDICATE WALE SIZE
INDICATE ANGLE SIZE
INDICATE ANGLE SIZE
INDICATE WALE SIZE
GROUND ELEVATION
INDICATE EXISTING
WALE(S) ELEVATION
INDICATE STRUT(S) AND
BY DESIGNER
AS DETERMINED
SECTION MODULUS
INDICATE REQUIRED
EXCAVATION ELEVATION
INDICATE BOTTOM OF
INDICATE WALE SIZEINDICATE STRUT SIZE
(SEE NOTE 12)
SOLDIER PILE WALL
STEEL SHEETING OR
INDICATE WALE SIZE
INDICATE STRUT SIZE
INDICATE STRUT SIZE
INDICATE ANGLE SIZE
INDICATE WALE SIZE
(SEE NOTE 12)
SOLDIER PILE WALL
STEEL SHEETING OR
INDICATE STRUT SIZE
INDICATE STRUT SIZE
H.S. BOLTS (TYP.)
ASTM F3125, GRADE A325
H.S. BOLTS (TYP.)
ASTM F3125, GRADE A325
H.S. BOLTS (TYP.)
OF ASTM F3125, GRADE A325c
H.S. BOLTS (TYP.)
ASTM F3125, GRADE A325
BD-EE10E
BRACED EXCAVATION DETAILS
EXCAVATION AND EMBANKMENT
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
ERRATA
09/22/17
BD-
EE10
E.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17
1 2 3 4 5 6
FOR PILES PLACED IN A HOLE
SECTION Y-Y
FOR DRIVEN PILES
SECTION X-X
PRECAST CONCRETE LAGGING
DETAIL "A"
1.5
1
SPECIFICATION TOLERANCES AFFECT THE LENGTH OF LAGGING.
EQUIPMENT AND/OR PROCEDURES.
NO EXTRA PAYMENT WILL BE MADE FOR SPECIAL
MAY REQUIRE SPECIAL EQUIPMENT AND/OR PROCEDURES.
IN EARTH FOR SOLDIER PILE AND LAGGING WALL, ITEM
DUE TO THE PRESENCE OF , PROGRESSING THE HOLES
EXTRA PAYMENT WILL BE MADE FOR THE CASING.
HOLES IN EARTH FOR SOLDIER PILE AND LAGGING WALLS. NO
TEMPORARY SLEEVES OR CASINGS ARE REQUIRED FOR ITEM
ASTM A572 GRADE 50 STEEL.
PROVIDE SOLDIER PILE SECTIONS MEETING THE REQUIREMENTS OF
OF 2'-0" BELOW FINAL GROUND SURFACE.
SURFACE. CUT OFF AND REMOVE SOLDIER PILES TO A MINIMUM
REMOVE LAGGING TO A MINIMUM OF 2'-0" BELOW FINAL GROUND
WHEN NO LONGER NECESSARY FOR EXCAVATION SUPPORT,
AND REMOVE SOLDIER PILES TO THE SUBGRADE SURFACE.
REMOVE LAGGING TO THE SUBGRADE SURFACE AND CUT OFF
WHEN NO LONGER NECESSARY FOR EXCAVATION SUPPORT,
PILE AND LAGGING WALL.
ITEM INSTALLING SOLDIER PILES FOR SOLDIER
LEFT IN PLACE. USED MATERIAL IS NOT PERMITTED FOR
THE SOLDIER PILE AND LAGGING WALL SHOWN WILL BE
USE THE FOLLOWING NOTE FOR PRECAST CONCRETE LAGGING:
USE THE FOLLOWING NOTE:
POSSIBLY REQUIRE SPECIAL EQUIPMENT AND/OR PROCEDURES,
INSTALLING HOLES IN THE EARTH WILL BE VERY DIFFICULT AND
WHERE THE GEOTECHNICAL ENGINEERING BUREAU DETERMINES THAT
ADJACENT STRUCTURES, UTILITIES, ETC.), USE THE FOLLOWING NOTE:
(I.E. DUE TO LOOSE COHESIONLESS SOIL, HIGH GROUND-WATER,
CASING WILL BE NECESSARY FOR INSTALLING HOLES IN THE EARTH
WHERE THE GEOTECHNICAL ENGINEERING BUREAU IDENTIFIES THAT
NECESSARY FOR SOLDIER PILES:
USE THE FOLLOWING NOTE IF A HIGHER YIELD STRESS IS
OR UTILITIES MIGHT BE DAMAGED BY REMOVAL OPERATIONS:
OUTSIDE THE ROAD-BED LIMITS WHERE ADJACENT STRUCTURES
USE THE FOLLOWING NOTE FOR TEMPORARY WALLS LOCATED
INSIDE THE ROAD-BED LIMITS:
USE THE FOLLOWING NOTE FOR TEMPORARY WALLS LOCATED
USE THE FOLLOWING NOTE FOR PERMANENT WALLS:
DESIGNER NOTES:
FOR ADDITIONAL NOTES, SEE BD-EE1E.
STAGE ONE LAGGING SHOWN.
SPECIFY LAGGING TYPE.
DO NOT USE WEATHERING STEEL (ASTM A588) FOR SOLDIER PILES.
BE DIFFERENT.
DETAIL REQUIRED. THE ACTUAL PROJECT REQUIREMENTS MAY
ONLY AND ARE INTENDED TO SHOW THE NECESSARY LEVEL OF
CONNECTION DETAILS SHOWN ARE FOR ILLUSTRATIVE PURPOSES
SOLDIER PILE AND LAGGING WALL
PLAN
SOLDIER PILE AND LAGGING WALL
ELEVATION
FOR ANTICIPATED CONSTRUCTION LOADING.
SUPPORT SYSTEM USED MUST BE DESIGNED
SUPPORT SYSTEM AS DETAILED, ANY EXCAVATION
SLOPE BACK AND NOT USE THE EXCAVATION
IF CONTRACTOR ELECTS NOT TO LAY
NOTE:
IN EARTH TRENCH
2'-0" MIN. EMBEDMENT
FOR INSTALLING LAGGING
LINE, EXCEPT WHAT'S REQUIRED
CONTRACTOR EXCAVATE BELOW THIS
UNDER NO CIRCUMSTANCES MAY THE
EXISTING GROUND
PILE AND LAGGING WALL
LAGGING FOR SOLDIER
PAYMENT LINES FOR INSTALLING
2'-0"
EXISTING ABUTMENT
LAGGING (TYP.) SOLDIER PILE (TYP.)
PROPOSED ROADWAY SURFACE
ASSUMED TOP OF ROCK
AND LAGGING WALLPILES FOR SOLDIER PILEINSTALLING SOLDIERPAYMENT LIMITS FOR
EXCAVATION LINE LI
MIT
OF
GR
OU
T
BA
CK
FIL
L
BA
CK
FIL
L
LI
MIT
OF
CO
NC
RE
TE
ASSUMED TOP OF ROCK
AND LAGGING WALLPILES FOR SOLDIER PILEINSTALLING SOLDIERPAYMENT LIMITS FOR
PILE AND LAGGING WALLIN EARTH FOR SOLDIERPAYMENT LIMITS FOR HOLES
AND LAGGING WALLSOCKETS FOR SOLDIER PILE PAYMENT LIMITS FOR ROCK
GIVE LENGTH
GIV
E
DE
PT
H
REINFORCING BARS (TYP.)
GIV
E
DE
PT
H
STIRRUP (TYP.)
REINFORCING BAR (TYP.)
STIRRUPS (TYP.)
EXCAVATION LINE
NO. - DENOTES PILE PLACED IN HOLE.
NO. - DENOTE DRIVEN PILE.
Y
Y
X
X
1 2 3 4 5 6
PANELS, SEE DETAIL "A".
SHEETING. FOR PRECAST CONCRETE
WOOD, UNTREATED WOOD OR STEEL
GIVE DIMENSIONS FOR TREATED
NUMBER
PILESTATION
(IN FEET)
OFFSET
(IN FEET)
ELEVATIONS
PILE TOP
(IN FEET)
DEPTH OF EXCAVATION
(IN FEET)
ELEVATION
ASSUMED ROCK
(IN FEET)
ROCK SOCKET
MINIMUM
(IN FEET)
SECTION MODULUS
MINIMUM PILE
SECTION
SOLDIER PILE
RECOMMENDED
(IN INCHES)
OF HOLE
MINIMUM DIA.
(IN FEET)
LENGTH
AS-BUILT PILE
1
2
3
4
5
6
EXISTING ABUTMENT
DURING STAGE 1
CONSTRUCTED
PROPOSED ABUTMENT
CONSTRUCTED DURING STAGE 2
PROPOSED ABUTMENT TO BE
ANGLE TO BE DESIGNED.
SUBSTRUCTURE WITH A BOLTED
ATTACH LAGGING TO EXISTING
EXISTING ABUTMENT
TO BE BRACED TO
TIMBER LAGGING
THIS P0RTION OF
WALL
PILE AND LAGGING
REMOVAL OF SOLDIER
COMPLETED AFTER
EXCAVATION TO BE
ABUTMENT
PROPOSED
SOLDIER PILE
SOLDIER PILE
PANELS, SEE DETAIL "A".
SHEETING. FOR PRECAST CONCRETE
WOOD, UNTREATED WOOD OR STEEL
GIVE DIMENSIONS FOR TREATED
(IN FEET)
PILE TIP ELEV.
REQUIRED
(IN FEET)
PILE LENGTH
REQUIRED
BD-EE11E
LAGGING WALL SAMPLE DETAILS
SOLDIER PILE AND
EXCAVATION AND EMBANKMENT
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
ERRATA
09/22/17
BD-
EE11E.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17
8% SLOPE
4'-0" (SEE NOTE "A")
STEEL TIES TO A DEADMAN
TYPICAL SECTIONGROUTED TIEBACK WALL
TYPICAL SECTION
TEMPORARY STEEL TIES
SECTION A-A
PERMANENT STEEL TIES
SECTION A-A
*3'-0"
MIN. EMBEDMENT DEPTH
SET-BACK (MIN. DISTANCE)
*3'-0"
LOAD & MAX. SPACING
NUMBER, DESIGN
STEEL TIE ITEM
EXISTING GROUND ELEV.
AND SIZE
DEADMAN TYPE
STEEL TIEBACK ELEV.
(SEE NOTE 12)
SOLDIER PILE WALL
STEEL SHEETING OR
EXCAVATION ELEV.
BOTTOM OF
2'-0" (SEE NOTE "A")
STEEL TIE(IF NECESSARY)
CARRIER CONDUIT
EXCAVATION ELEV.
BOTTOM OF
EXISTING GROUND
A
A
GROUTED TIEBACK
STEEL TIE OR
SIZE (TYP.)
INDICATE BOLT
TEMPORARY WELD
WALL OR DEADMAN
SIZE (TYP.)
INDICATE PIPE SEPARATOR
INDICATE WALE SIZE
2" MIN. COV. (TYP.)
WALL OR DEADMAN
1" MIN. (TYP.)
TEMPERATURE REINFORCEMENT
1" CHAMFER (TYP.)
DRIP GROOVE
(SEE NOTE 12)
SOLDIER PILE WALL
STEEL SHEETING OR
STEEL TIEBACK ELEV.
EXCAVATION ELEV.
BOTTOM OF
MAXIMUM SPACING
DESIGN LOAD AND
EXISTING GROUND ELEV.
MINIMUM FREE LENGTH
OV
ER
GR
OU
T
ZO
NE
15'-
0"
MIN.
CO
VE
R
ANCHOR ANGLE
MIN. EMBEDMENT DEPTH
STEEL TIE
MIN.
4"
EXCAVATION ELEV.
BOTTOM OF
EXISTING GROUND
0" (TYP.)
0" (TYP.)
CORROSION PROTECTION) PLUS 1'-0".
TIE (INCLUDING ANY NECESSARY CONDUIT OR
OF THE TRENCH IS THE DIMENSION OF THE STEEL
INSTEAD OF SOIL, THE MINIMUM REQUIRED WIDTH
CONTROLLED LOW STRENGTH MATERIAL (C.L.S.M.)
IF THE DESIGNER ELECTS TO BACKFILL WITH
NOTE "A":
DESIGNER NOTES:
*
PRIOR TO WALL CONSTRUCTION.
FOR CARRIER CONDUIT INSTALLATION TO THE ENGINEER FOR APPROVAL
STAGES WHILE MAINTAINING EXISTING TRAFFIC. SUBMIT THE PROCEDURE
PRIOR TO WALL CONSTRUCTION, INSTALL THE CARRIER CONDUIT IN
INSTALLATION OF STEEL TIES:
USE THE FOLLOWING NOTE IF CARRIER CONDUIT IS REQUIRED FOR THE
BEFORE THE BACKFILLING OPERATION RESUMES.
STEEL TIES MUST BE LOCKED-OFF AT A LOAD OF 2.2 kips PER STRAND
IF THE CONTRACTOR ELECTS TO USE SEVEN-WIRE STRAND CABLES, THE
USE THE FOLLOWING NOTE FOR WALLS CONSTRUCTED "BOTTOM UP":
THE EXCAVATION AT THE WALL FACE RESUMES.
STEEL TIES MUST BE LOCKED-OFF AT 80% OF THE DESIGN LOAD BEFORE
IF THE CONTRACTOR ELECTS TO USE SEVEN-WIRE STRAND CABLES, THE
USE THE FOLLOWING NOTE FOR WALLS CONSTRUCTED "TOP DOWN":
INSTALLED AND LOCKED-OFF.
2'-0" BELOW THE STEEL TIE ELEVATION UNTIL THE STEEL TIES ARE
DO NOT PROGRESS THE EXCAVATION AT THE WALL FACE LOWER THAN
NOTES FOR WALLS WITH STEEL TIES:
TIEBACKS ARE INSTALLED AND TESTED.
2'-0" BELOW THE GROUTED TIEBACK ELEVATION UNTIL THE GROUTED
DO NOT PROGRESS THE EXCAVATION AT THE WALL FACE LOWER THAN
NOTE FOR WALLS WITH GROUTED TIEBACKS:
FOOTING
PROPOSED
SIZE (TYP.)
INDICATE STIFFENER
FOOTING
PROPOSED
CONTRACTOR
NUMBER, DESIGNED BY
GROUTED TIEBACK ITEM
PROTECTION
CONCRETE CORROSION
ANCHOR HEADS AND WALES
ENCAPSULATION DETAIL FOR PERMANENT
SEE DETAIL "A" (TYP.)
INDICATE ANCHOR PLATE SIZE
INDICATE BEARING PLATE SIZE
SEE DETAIL "A"
(SHOWN AT BEARING LOCATION)
ANCHOR HEAD AND WALE DETAIL
DETAIL "A"
ANCHOR PLATE, AND PIPE SEPARATORS.
SPACING SHOWN, THE CONTRACTOR SHALL RESIZE THE BEARING PLATE,
IF THE ASSUMED SPACING BETWEEN THE WALES IS GREATER THAN THE
PLATE RESIZING NOTE:
ENCAPSULATION EXTENDS LATERALLY TO ENCASE THE ENTIRE WALE.
NOTE:
CONCRETE ITEM
FOR ADDITIONAL NOTES AND LEGEND, SEE BD-EE1E.
SPACING WALES.
SHALL CONSIDER THE SIZE OF A "TRUMPET" WHEN
"TRUMPET" IN THE ANCHORAGE ZONE. DESIGNER
GROUTED TIEBACK ANCHORS REQUIRE THE USE OF A
REQUIREMENTS.
SHALL BE AS REQUIRED TO MEET THE PROJECT
FOR STAGED CONSTRUCTION THIS DIMENSION
TIEBACKS ARE INSTALLED.
PLATE WHEN INCLINED STEEL TIES OR GROUTED
DETAIL A BEVELED PLATE INSTEAD OF A BEARING
NOTE "B":
(SEE "PLATE RESIZING NOTE")
INDICATE ASSUMED DIMENSION
BD-EE12E
TIEBACK WALL DETAILS
EXCAVATION AND EMBANKMENT
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
ERRATA
09/22/17
BD-
EE12
E.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17
**EL.EL.
EL.
EL.
SEE NOTE "A"
**ALL REQUIRED ELEVATIONS AT TOPS OF PRECAST PANELS SHALL BE INCLUDED ON THE PLANS.
NOTE:
MIN.
7'-6"
MIN.
2'-0" PROPOSED FOOTING
INDICATE STATION
OF BEARINGScPROPOSED
OF BRGS.c
T.G.L. & STATION LINE
INDIC
ATE AZIM
UTH
INDICATE AZIMUTH
SAME TIME
BE PLACED TOGETHER AT THE
OF THE VERTICAL LINE SHALL
MATERIALS ON BOTH SIDES
(MAY BE SLOPED OR HORIZONTAL)
FINISHED GROUND SURFACE
PRECAST) INCLUDED IN F.T.R.W. ITEM
COPING (MAY BE CAST-IN-PLACE OR
BY CONTRACTOR
F.T.R.W. OPTION SELECTED
GROUND SURFACE
EXISTING & FINISHED
TOP OF LEVELING PAD
1'-0"
6"
INCLUDED IN F.T.R.W. ITEM
UNREINFORCED LEVELING PAD
0 (TYP.)
1'-0"
(TYP.)
3'-0"
SEE NOTE "A"
EXISTING GROUND
2'-0" (MIN.)
SAME TIME
BE PLACED TOGETHER AT THE
OF THE VERTICAL LINE SHALL
MATERIALS ON BOTH SIDES
BRGS.c
7'-6" (MIN.)
CONCRETE COPING
4"
2'-0" (MIN.)
0 (TYP.) 6"
1'-0"
3'-0"
TOP OF LEVELING PAD
2'-
0" (M
IN.)
INDICATE ANGLE
B
GROUND LINE
PROPOSED FINISHED
F.T.R.W.
A CONCRETE COPING SHALL BE PLACED ON THE TOPS OF ALL EXPOSED
ALL DIMENSIONS ARE MEASURED PARALLEL TO WALL.
NOTES:
PAYMENT LINES FOR F.T.R.W.
EL.
EL.
LE
VE
LIN
G
PA
D
6"
GROUND LINE
PROPOSED FINISHED
SECTION A-A
SECTION B-B
PLAN
A
A
FILL TYPE RETAINING WALL
ELEVATION
B
EL.
ANGLEINDICATE
NOTE: PILES NOT SHOWN FOR CLARITY.
INCLUDED IN F.T.R.W. ITEM
UNREINFORCED LEVELING PAD
SUPPORT AN ABUTMENT.
TO THE M.S.E.S. TYPE WHEN USED TO
CONTRACT PLANS SHALL LIMIT THE F.T.R.W.
ABUTMENT. NOTES AND DETAILS IN THE
F.T.R.W. APPROVED TO SUPPORT AN
(M.S.E.S) WALLS ARE THE ONLY TYPE OF
MECHANICALLY STABILIZED EARTH SYSTEMS
F.T.R.W.
MOMENT SLABv/vBARRIER DETAILS ON
REFER TO THE BD-SA SHEETS FOR
ARE FOR THE TOP OF THE LEVELING PAD.
GIVEN AT THE BOTTOM OF THE F.T.R.W.
TO THE HEIGHT OF WALL. ELEVATIONS
PURPOSES IT IS ASSUMED TO BE EQUAL
BY THE CONTRACTOR. FOR ESTIMATING
BY THE F.T.R.W. MANUFACTURER SELECTED
THIS DIMENSION IS TO BE DETERMINED
NOTE "A":
SEE BD-EE1E.
FOR ADDITIONAL NOTES AND LEGEND,
REINFORCED BACKFILL ZONE.
PLACED WITHIN OR UNDERNEATH THE
NO UTILITY OF ANY NATURE MAY BE
DESIGNER NOTES:
SLOPE TO DRAIN
BD-EE13E
RETAINING WALL DETAILS
SAMPLE - FILL TYPE
EXCAVATION AND EMBANKMENT
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
ERRATA
09/22/17
BD-
EE13
E.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17
FLATTER
1 ON 3 OR1
ON 2
0 (TYP.)
1
ON 2
EL.
EL.
EL.
2
1
EL.
EL.
EL.
EL.
EL.
1
2EL.
SECTION A-A
SECTION B-B
FL
OW
ST
RE
AM
*
REMOVAL (TYP.)
SUBSTRUCTURE
AZIMUTH
(HIGHWAY ESTIMATE)
MEDIUM STONE FILL
PAY LINES FOR
STRUCTURAL DRAIN
COMPOSITE
PREFABRICATED
(SEE NOTE 15 & 17)
AT SUBGRADE
EMBANKMENT
50'-0"
3'-0" (TYP.)
TOE OF SLOPE
CENTERLINE
EXISTING ROADWAY
(HIGHWAY ESTIMATE)
MEDIUM STONE FILL
PAY LINES FOR
1'-0" (TYP.)
FLATTER
1 ON 3 OR
1
ON 2
0 (TYP.)
1
ON 2
*
TO BE REMOVED
EXISTING SUPERSTRUCTURE
(HIGHWAY ESTIMATE)
MEDIUM STONE FILL
PAY LINES FOR
STRUCTURAL DRAIN
COMPOSITE
PREFABRICATED
(SEE NOTE 15 & 17)
AT SUBGRADE
EMBANKMENT
50'-0"
3'-0" (TYP.)
TOE OF SLOPE
(HIGHWAY ESTIMATE)
MEDIUM STONE FILL
PAY LINES FOR
1'-0" (TYP.)
10'-0"
STATION
OF BEARINGSc
50'-0" (MIN.)50'-0" (MIN.)
3'-0"
STRUCTURAL DRAIN (PCSD)
PREFABRICATED COMPOSITE
(SEE NOTE 15 & 17)FLATTER
1 ON 3 OR
SUBGRADE OF ROADWAYSTRUCTURAL DRAIN (PCSD)
PREFABRICATED COMPOSITE
(SEE NOTE 15 & 17)SUBGRADE OF ROADWAY
FLATTER
1 ON 3 OR
3'-0" (TYP.)
1 ON 1
1 ON 1
AA
BB
EXISTING PIER
STREAM BED
TOP OF FOOTING
3'-0" 3'-0"
0 (TYP.)
PLAN
3'-0"
0 (TYP.)
STATION
OF BEARINGSc
STATION
OF BEARINGSc
1
ON 2
PLACED AT THE SAME TIME. (TYP.)
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE
10'-0"
*
COORDINATE BACKFILL TYPE WITH THE REGIONAL OFFICE.
FOR PIERS REMOVED THAT ARE NOT IN A STREAM,
MATERIAL OR NATIVE STREAMBED MATERIAL IF NECESSARY.
STREAM LOCATIONS SHALL BE EITHER SUITABLE EXCAVATED
THE BACKFILL USED FOR EXISTING PIER REMOVAL IN
ESTIMATE.
OF SLOPE PROTECTION TO BE INCLUDED IN THE BRIDGE
THIS DIMENSION IS TYPICAL FOR THE SIDE LIMIT
FOR ADDITIONAL NOTES AND LEGEND, SEE BD-EE1E.
FOR STRUCTURE EXCAVATION GUIDANCE, SEE NOTE 18.
PURPOSES ONLY AND ARE SOLELY INTENDED AS AN EXAMPLE.
THE DETAILS ON THIS DRAWING ARE FOR ILLUSTRATIVE
DESIGNER NOTES:
SEE DETAILS ON BD-EE5E
SEE NOTE 20 (TYP.)
SEE NOTE 20
SEE NOTE 20 (TYP.)
(SEE DESIGNER NOTE)
FILLING (MEDIUM/HEAVY)
MATERIAL UNDER STONE
9" THICK BEDDING FILLING (MEDIUM/HEAVY)
MATERIAL UNDER STONE
9" THICK BEDDING
R1 BD-EE14E
SAMPLE DRAWINGS
EXCAVATION AND EMBANKMENT
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
ERRATA
09/22/17
BD-
EE14
ER1.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17
I I
FL
OW
I
+
I II
1
ON 2
1
ON 2
1 ON 2
1
ON 2
1 ON 2
1
ON 2
PROPOSED TOE OF SLOPE (TYP.)
STA.
OF BRGS.c
BOTH SIDES)
STAGE II CONSTRUCTION (TYP.
STAGE I CONSTRUCTION PRIOR TO
ATTACH LAGGING TO COMPLETED
(SEE NOTE 15 & 17)
STRUCTURAL DRAIN
PREFABRICATED COMPOSITE
STAGE REMOVAL JOINT (TYP.)
PROPOSED FOOTING
SUBGRADE (TYP.)
EMBANKMENT AT
FLATTER
1 ON 3 OR
(TYP.)
10'-0"
SEE DESIGNER NOTE (TYP.)
C3
C3
C3
C3
C3C3
C4
C4
C4
C4
C4
C4
C1
C1
C1
C1C1
C2
C2
C2
C2C2
C2
TO STAGE II CONSTR. (TYP.)SHEETING AS REQUIRED PRIORCUT OFF OR REMOVE
JOINT (TYP.)
CONSTRUCTION
STAGE
(TYP.)
3'-0"
C1
(TYP.)
3'-0"
ST
AG
E I
ST
AG
E II
0 (TYP.)
0 (TYP.)
(TYP.)1'-0"
(TYP.)
1'-0"
(TYP.)
10'-0"
0 (TYP.)
PROPOSED TOE OF SLOPE (TYP.)
FLATTER
1 ON 3 OR
SUBGRADE (TYP.)
EMBANKMENT AT STATION LINE
OF ROADWAY &c
ON BD-EE16E
SEE LAGGING DETAIL
0 (TYP.)
c
STA.
OF BRGS.
(SEE NOTE 15 & 17)
STRUCTURAL DRAIN
PREFABRICATED COMPOSITE
PROPOSED FOOTING
(TYPICAL BOTH SIDES)
50'-0"
D
D
C C
H H
F
F
A A
GG
B
B
E
EPLAN
FOR ADDITIONAL NOTES AND LEGEND, SEE BD-EE1E.
REQUIRED FOR AN ACTUAL PROJECT.
THE DESIGNER SHALL DETERMINE IF THESE DETAILS ARE
SECTIONS A-A, B-B, E-E, F-F AND ELEVATION G-G NOT SHOWN.
FOR SECTIONS C-C, D-D AND ELEVATION H-H, SEE BD-EE16E.
SEE BRIDGE MANUAL FOR GUIDANCE.
DESIGNER MUST DETERMINE THE APPROPRIATE COFFERDAM TYPE.
EXAMPLE, SEE THE F.D.R. FOR ACTUAL WALL RECOMMENDATIONS.
INTERIM SHEETING AND LAGGING SHOWN AS AN
REQUIREMENTS.
MAY BE REQUIRED TO ADEQUATELY DEPICT THE PROJECT
SHOW THE DESIRED DETAILS ARE GIVEN. ADDITIONAL SECTIONS
ONLY THOSE PORTIONS OF THE STRUCTURE NECESSARY TO
THIS DRAWING IS SOLELY INTENDED AS AN EXAMPLE AND
CONDITIONS.
PURPOSES ONLY AND DO NOT REPRESENT ACTUAL PROJECT
THE DETAILS ON THIS DRAWING ARE FOR ILLUSTRATIVE
DESIGNER NOTES:
BOTTOM OF FOOTING.
ORIGINATING FROM A PARALLEL LINE OFFSET 3'-0" FROM THE
PROPOSED GROUND SURFACE AND A 1 ON 1.5 UP-SLOPE
CONSTRUCTION IS DETERMINED BY THE INTERSECTION OF THE
THE REQUIRED LENGTH OF THE INTERIM SHEETING FOR STAGE
SEE NOTE 20 (TYP.)
BD-EE15E
STAGE CONSTRUCTION (1 OF 2)
SAMPLE DRAWINGS OF
EXCAVATION AND EMBANKMENT
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
ERRATA
09/22/17
BD-
EE15
E.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17
EL.
EL.
1
2
EL.
EL.
EL.
1
1.5
FOR ANTICIPATED CONSTRUCTION LOADING.
SUPPORT SYSTEM USED MUST BE DESIGNED
SHEETING AS DETAILED, ANY EXCAVATION
SLOPE BACK AND NOT USE INTERIM
IF CONTRACTOR ELECTS NOT TO LAY
NOTE:
2
1
F.D.R. FOR ACTUAL WALL RECOMMENDATIONS.
INTERIM SHEETING AND LAGGING SHOWN AS AN EXAMPLE, SEE THE
WHERE SECTIONS MUST BE TAKEN.
ARE GIVEN. ON AN ACTUAL PROJECT, THE DESIGNER SHALL DETERMINE
PORTIONS OF THE STRUCTURE NECESSARY TO SHOW THE DESIRED DETAILS
THIS DRAWING IS SOLELY INTENDED AS AN EXAMPLE AND ONLY THOSE
AND DO NOT REPRESENT ACTUAL PROJECT CONDITIONS.
THE DETAILS ON THIS DRAWING ARE FOR ILLUSTRATIVE PURPOSES ONLY
DESIGNER NOTES:
1.5
11.5
1
1.5
1
FOR STRUCTURE EXCAVATION GUIDELINES, SEE NOTE 18 ON BD-EE1E.
FOR ADDITIONAL NOTES AND LEGEND, SEE BD-EE1E.
3'-0" FROM THE BOTTOM OF FOOTING.
AND A 1 ON 1.5 UP-SLOPE ORIGINATING FROM A PARALLEL LINE OFFSET
IS DETERMINED BY THE INTERSECTION OF THE PROPOSED GROUND SURFACE
THE REQUIRED LENGTH OF THE INTERIM SHEETING FOR STAGE CONSTRUCTION
PROPOSED SUBGRADE
FLATTER (TYP.)
1 ON 3 OR
EXISTING GROUND
PLACED AT THE SAME TIME.
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE
STRUCTURAL DRAIN
PREFABRICATED COMPOSITE
(SEE NOTES 15 & 17)
(TYP.)
3'-0" 0 (TYP.)
3'-0"
0 (TYP.)
EXCAVATION (HIGHWAY ESTIMATE)
PAYMENT LIMITS FOR UNCLASSIFIED
PLACED AT THE SAME TIME.
VERTICAL PAYMENT LINE SHALL BE
MATERIALS ON BOTH SIDES OF THE
SUBGRADE OF ROADWAY
STRUCTURAL DRAIN
PREFABRICATED COMPOSITE
(SEE NOTE 15)
1'-0"
(TYP.)
3'-0"
EXISTING GROUNDPROPOSED ROADWAY SURFACE
CONTRACTOR EXCAVATE BELOW THIS LINE.
UNDER NO CIRCUMSTANCES MAY THE
PROPOSED FINISHED GRADE
ANGLE TO BE DESIGNED.
SUBSTRUCTURE WITH A BOLTED
ATTACH LAGGING TO EXISTING
EXCAVATION LIMIT INDICATE MIN. EMBEDMENT
3'-0"
SEE LAGGING DETAIL
PROPOSED ABUTMENT
STATION LINE
OF ROADWAY &c INTERIM SHEETING
OR STEEL SHEETING
APPROPRIATELY SIZED TIMBER LAGGING
PRIOR TO BACKFILLING STAGE I, INSTALL
PROPOSED ABUTMENT
BACK OF STEM
STRUCTURAL DRAIN
PREFABRICATED COMPOSITE
(SEE NOTES 15 & 17)
ST
AG
E I
ST
AG
E II
0 (TYP.)
(TYP.)
0
SECTION D-DSECTION C-C
LAGGING DETAIL
INTERIM SHEETING DETAIL
ELEVATION H-H
SEE DETAILS ON BD-EE5E
STAGE I CONSTRUCTION
NEWLY BUILT ABUTMENT
STAGE II CONSTRUCTION
ABUTMENT TO BE BUILT DURING
EXISTING ABUTMENT
SIZED TIMBER LAGGING
INSTALL APPROPRIATELY
TO STAGE II CONSTRUCTION
THE CROSS HATCHED AREA PRIOR
CUT AND REMOVE SHEETING IN
INDICATE SECTION MODULUS
FILLING (MEDIUM/HEAVY)
MATERIAL UNDER STONE
9" THICK BEDDING
FILLING (MEDIUM/HEAVY)
MATERIAL UNDER STONE
9" THICK BEDDING
R1 BD-EE16E
STAGE CONSTRUCTION (2 OF 2)
SAMPLE DRAWING OF
EXCAVATION AND EMBANKMENT
REVISED
(STRUCTURES)
DEPUTY CHIEF ENGINEER
Office of Structures
Department of Transportation
ORIGINAL ISSUED UNDER EB 08-002
ERRATA
09/22/17
BD-
EE16
ER1.d
gn
20-
MA
R-2018 14:1
6
FIL
E
NA
ME
=
DA
TE/
TI
ME
=
LETTING OF 05/01/2018
EFFECTIVE WITH THE
CURRENT ISSUED UNDER EB 17-037
RICHARD MARCHIONE, P.E.
vvORIGINAL SIGNED BY
vAPPROVED: 09/22/17