+ All Categories
Home > Documents > NEW MEXICO DEPARTMENT OF HEALTH - NM · Web view“Product development life cycle”...

NEW MEXICO DEPARTMENT OF HEALTH - NM · Web view“Product development life cycle”...

Date post: 29-Mar-2018
Category:
Upload: phamcong
View: 215 times
Download: 2 times
Share this document with a friend
42
N N EW EW M M EXICO EXICO D D EPARTMENT EPARTMENT OF OF H H EALTH EALTH P P UBLIC UBLIC H H EALTH EALTH D D IVISION IVISION B B ILLING ILLING AND AND E E LECTRONIC LECTRONIC H H EALTH EALTH R R ECORD ECORD (BEHR) U (BEHR) U PGRADE PGRADE P P ROJECT ROJECT PROJECT MANAGEMENT PLAN PROJECT MANAGEMENT PLAN (PMP) (PMP) EXECUTIVE SPONSOR JACK CALLAGHAN, PHD DIRECTOR, PUBLIC HEALTH DIVISION
Transcript

NNEWEW M MEXICOEXICO D DEPARTMENTEPARTMENT OFOF H HEALTHEALTH

PPUBLICUBLIC H HEALTHEALTH D DIVISIONIVISION

BBILLINGILLING ANDAND E ELECTRONICLECTRONIC H HEALTHEALTH RRECORDECORD (BEHR) U (BEHR) UPGRADEPGRADE P PROJECTROJECT

PROJECT MANAGEMENT PLAN PROJECT MANAGEMENT PLAN (PMP)(PMP)

EXECUTIVE SPONSOR – JACK CALLAGHAN, PHD DIRECTOR, PUBLIC HEALTH DIVISION

BUSINESS OWNER – MAGGI GALLAHER, MD, MPH MEDICAL DIRECTOR, PUBLIC HEALTH DIVISION

PROJECT MANAGER – DEBORAH DICKERSON

ORIGINAL PLAN DATE: AUGUST 25, 2010REVISION DATE: N/A

REVISION: 1.0

REVISION HISTORY............................................................................................................................................ IV

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

PREPARING THE PROJECT MANAGEMENT PLAN..................................................................................................V

ABOUT THIS DOCUMENT.................................................................................................................................... V

PROJECT OVERSIGHT PROCESS MEMORANDUM – DOIT, JULY 2007.....................................................................................V

1.0 PROJECT OVERVIEW...................................................................................................................................... 1

1.1 EXECUTIVE SUMMARY- RATIONALE FOR THE PROJECT................................................................................................11.2 FUNDING AND SOURCES...........................................................................................................................................11.3 CONSTRAINTS........................................................................................................................................................11.4 DEPENDENCIES.......................................................................................................................................................11.5 ASSUMPTIONS...................................................................................................................................................21.6 INITIAL PROJECT RISKS IDENTIFIED...........................................................................................................................2

2.0 PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURE.............................................................................3

2.1 STAKEHOLDERS......................................................................................................................................................32.2 PROJECT GOVERNANCE STRUCTURE...........................................................................................................................3

2.2.1 Describe the organizational structure – Org Chart.....................................................................................42.2.2 Describe the role and members of the project steering committee...........................................................42.2.3 Organizational Boundaries, interfaces and responsibilities.......................................................................6

2.3 EXECUTIVE REPORTING............................................................................................................................................6

3.0 SCOPE........................................................................................................................................................... 7

3.1 PROJECT OBJECTIVES..............................................................................................................................................73.1.1 Business Objectives....................................................................................................................................73.1.2 Technical Objectives..................................................................................................................................7

3.2 PROJECT EXCLUSIONS..............................................................................................................................................83.3 CRITICAL SUCCESS FACTORS.....................................................................................................................................8

4.0 PROJECT DELIVERABLES AND METHODOLOGY...............................................................................................8

4.1 PROJECT MANAGEMENT LIFE CYCLE..........................................................................................................................84.1.1 Project Management Deliverables.............................................................................................................94.1.2 Deliverable Approval Authority Designations............................................................................................94.1.3 Deliverable Acceptance Procedure...........................................................................................................10

4.2 PRODUCT LIFE CYCLE.......................................................................................................................................104.2.1 Technical Strategy...................................................................................................................................114.2.2 Product and Product Development Deliverables......................................................................................114.2.3 Deliverable Approval Authority Designations..........................................................................................124.2.4 Deliverable Acceptance Procedure...........................................................................................................12

5.0 PROJECT WORK........................................................................................................................................... 12

5.1 WORK BREAKDOWN STRUCTURE (WBS)..................................................................................................................125.2 SCHEDULE ALLOCATION -PROJECT TIMELINE..............................................................................................................135.3 PROJECT BUDGET.................................................................................................................................................145.4 PROJECT TEAM....................................................................................................................................................15

5.4.1 Project Team Organizational Structure....................................................................................................155.4.2 Project Team Roles and Responsibilities..................................................................................................15

5.6 PROJECT LOGISTICS.........................................................................................................................................165.6.1 Project Team Training..............................................................................................................................16

6.0 PROJECT MANAGEMENT AND CONTROLS....................................................................................................16

6.1 RISK AND ISSUE MANAGEMENT..............................................................................................................................166.1.1 Risk Management Strategy......................................................................................................................16

REVISION: 1.0 DOIT-PMO-TEM-020 ii OF vi

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

6.1.2 Project Risk Identification........................................................................................................................176.1.3 Project Risk Mitigation Approach............................................................................................................176.1.4 Risk Reporting and Escalation Strategy...................................................................................................176.1.5 Project Risk Tracking Approach................................................................................................................176.1.6 ISSUE MANAGEMENT..............................................................................................................................18

6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&V...........................................................................................186.3 SCOPE MANAGEMENT PLAN..................................................................................................................................19

6.3.1 Change Control........................................................................................................................................196.4 PROJECT BUDGET MANAGEMENT............................................................................................................................19

6.4.1 Budget Tracking.......................................................................................................................................196.5 COMMUNICATION PLAN........................................................................................................................................20

6.5.1 Communication Matrix............................................................................................................................206.5.2 Status Meetings.......................................................................................................................................206.5.3 Project Status Reports..............................................................................................................................20

6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS).....................................................................................206.6.1 Baselines..................................................................................................................................................216.6.2 Metrics Library.........................................................................................................................................21

6.7 QUALITY OBJECTIVES AND CONTROL..............................................................................................................216.7.1 quality Standards.....................................................................................................................................216.7.2 Project and Product Review AND ASSESSMENTS.....................................................................................236.7.3 Agency/Customer Satisfaction.................................................................................................................246.7.4 PRODUCT DELIVERABLE ACCEPTANCE PROCESS......................................................................................24

6.8 CONFIGURATION MANAGEMENT...................................................................................................................256.8.1 Version Control........................................................................................................................................256.8.2 Project Repository (Project Library).........................................................................................................25

6.9 PROCUREMENT MANAGEMENT PLAN............................................................................................................26

7. 0 PROJECT CLOSE........................................................................................................................................... 26

7.1 Administrative Close...................................................................................................................................267.2 Contract Close.............................................................................................................................................26

REVISION: 1.0 DOIT-PMO-TEM-020 iii OF vi

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

REVISION HISTORYREVISION HISTORY

RREVISIONEVISION N NUMBERUMBER DDATEATE CCOMMENTOMMENT

1.0 July 28, 2010 Planning Version for PCC certification

1.5 August 25, 2010 Implementation version

REVISION: 1.0 DOIT-PMO-TEM-020 iv OF vi

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

PREPARING THE PROJECT MANAGEMENT PLANPREPARING THE PROJECT MANAGEMENT PLANThe workbook for preparation of the Project Management Plan is built around helping the project manager and the project team to use the Project Management Plan in support of successful projects. Please refer to it while developing this PMP for your project.

ABOUT THIS DOCUMENTABOUT THIS DOCUMENT

Project Oversight Process Memorandum – DoIT, July 2007Project Oversight Process Memorandum – DoIT, July 2007

“Project management plan” is a formal document approved by the executive sponsor and the Department and developed in the plan phase used to manage project execution, control, and project close.

The primary uses of the project plan are to document planning assumptions and decisions, facilitate communication among stakeholders, and documents approved scope, cost and schedule baselines.

A project plan includes at least other plans for issue escalation, change control, communications, deliverable review and acceptance, staff acquisition, and risk management.

“Project manager” means a qualified person from the lead agency responsible for all aspects of the project over the entire project management lifecycle (initiate, plan, execute, control, close). The project manager must be familiar with project scope and objectives, as well as effectively coordinate the activities of the team. In addition, the project manager is responsible for developing the project plan and project schedule with the project team to ensure timely completion of the project. The project manager interfaces with all areas affected by the project including end users, distributors, and vendors. The project manager ensures adherence to the best practices and standards of the Department.

Project product” means the final project deliverables as defined in the project plan meeting all agreed and approved acceptance criteria.

“Product development life cycle” is a series of sequential, non-overlapping phases comprised of iterative disciplines such as requirements, analysis and design, implementation, test and deployment implemented to build a product or develop a service.

REVISION: 1.0 DOIT-PMO-TEM-020 v OF vi

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

1.0 PROJECT OVERVIEW1.0 PROJECT OVERVIEW

1.11.1 EXECUTIVE SUMMARY- RATIONALE FOR THE PROJECTEXECUTIVE SUMMARY- RATIONALE FOR THE PROJECT The Department of Health (DOH) Public Health Division (PHD) is initiating this project to upgrade the existing Billing and Electronic Health Record (BEHR) system. The BEHR system is the electronic medical record for all clinical services provided in public health offices. BEHR allows PHD to submit claims for services provided electronically and track compensation received for services performed supporting revenue recovery.

The new version will move PHD toward compliance with the federal requirements of meaningful use, part of the American Recovery and Reinvestment Act (ARRA). In addition, moving towards meaningful use will allow PHD to be eligible for incentive payments offered by the federal government for adoption of electronic medical records included in ARRA.

The BEHR system was initially implemented in 2007 with all the DOH public health offices using BEHR since early 2008. This is the first major upgrade since the initial implementation.

1.2 FUNDING AND SOURCES1.2 FUNDING AND SOURCES

SOURCESOURCE AMOUNTAMOUNT ASSOCIATED ASSOCIATED RESTRICTIONSRESTRICTIONS

APPROVERSAPPROVERS

General Appropriations Act of 2010, Laws 2010, Chapter 6, Section 4, Department of Health General Fund Appropriation.

$200,000 None Jack Callaghan, PhD

1.3 CONSTRAINTS1.3 CONSTRAINTS

NNUMBERUMBER DDESCRIPTIONESCRIPTION

1 FY11 funds must be expended by June 30, 2011 and project must be completed in FY11

2 Upgrade will go live simultaneously for all end users – training of all end users must be completed 2 weeks within to go live.

1.4 DEPENDENCIES1.4 DEPENDENCIESTypes include the following and should be associated with each dependency listed.

Mandatory dependencies are dependencies that are inherent to the work being done.

PAGE | 1

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

D- Discretionary dependencies are dependencies defined by the project management team. This may also encompass particular approaches because a specific sequence of activities is preferred, but not mandatory in the project life cycle.

E-External dependencies are dependencies that involve a relationship between project activities and non-project activities such as purchasing/procurement

NUMBENUMBERR

DESCRIPTIONDESCRIPTION TYPE M,D,ETYPE M,D,E

1 Practice Management upgrade must be completed before BEHR Upgrade Project can begin.

E, M

2 Sustained Funding for Project M

1.5 1.5 ASSUMPTIONSASSUMPTIONS

NNUMBERUMBER DDESCRIPTIONESCRIPTION

1 Public Health Division will provide appropriate resources both monetary and personnel for the project.

1.6 INITIAL PROJECT RISKS IDENTIFIED1.6 INITIAL PROJECT RISKS IDENTIFIEDRisk 1

Description – Project will be at risk if all stakeholders are not engaged at the beginning of the project

Probability LLOWOW

Impact MMEDIUMEDIUM

Mitigation Strategy: Emphasize communication to all stakeholders to be sure they understand the benefits of a successful project and will commit the required resources determined during planning. This is being managed as part of the project team and with regular communication with staff at the public health offices.Contingency Plan: This is addressed as part of the communication plan.

Risk 2

Description – Project will be at risk if the implementation vendor resources are not available

Probability LOWLOW

Impact HHIGHIGH

Mitigation Strategy: Contract with the implementation vendor must be negotiated and executed in September 2010. Weekly meetings with the vendor have been established. Once the contract is executed, a detailed project plan will be completed with committed resources assigned.

PAGE | 2

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

Contingency Plan: Review the schedule monthly with the vendor to address any scheduling issues.

Risk 3

Description – Project will be at risk if the state withdraws the funding for cost containment purposes

Probability LOWLOW

Impact HHIGHIGH

Mitigation Strategy: Show how services will become more cost effective and the ability to generate revenue recovery if this project is completed. Commitment from the DOH PHD management must continue to financially support project.Contingency Plan: There is no contingency plan. If funding is cut or no longer available, project will not be viable. There may be some opportunity to reduce costs with implementation that would be explored.

2.0 PROJECT AUTHORITY AND ORGANIZATIONAL 2.0 PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURESTRUCTURE

2.1 STAKEHOLDERS2.1 STAKEHOLDERS

NAMENAME STAKE IN PROJECTSTAKE IN PROJECT ORGANIZATIONORGANIZATION TITLETITLE

Jack Callaghan, PhD Executive Sponsor Public Health Division (PHD)

Director

Maggi Gallaher, MD, MPH Project Director PHD Medical Director

PHD Staff Users of system PHD

Citizens of New Mexico Receive services at Public Health Offices

2.2 PROJECT GOVERNANCE STRUCTURE2.2 PROJECT GOVERNANCE STRUCTURE

PAGE | 3

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

2.2.1 D2.2.1 DESCRIBEESCRIBE THETHE ORGANIZATIONALORGANIZATIONAL STRUCTURESTRUCTURE – O – ORGRG C CHARTHART

2.2.2 D2.2.2 DESCRIBEESCRIBE THETHE ROLEROLE ANDAND MEMBERSMEMBERS OFOF THETHE PROJECTPROJECT STEERINGSTEERING COMMITTEECOMMITTEE

NNAMEAME GGROUPROUP RROLEOLE RRESPONSIBILITYESPONSIBILITY

Jack Callaghan, PhD, PHD Director

NMDOH

Executive Project Sponsor

Steering Committee

Member

Ensure project staff availability, funding, and contract management

Approve project charter Review and accept the initial risk assessment,

management plan, project plan, and budget Provide management review and accept

changes to project plan, contract or deliverables

Attend executive requirements reviews and resolve requirements problems

Empower the Project Director and the Project Manager

Communicate with the Department of Health Champion the project Contribute to lessons learned

Maggi Gallaher, MD, MPH, PHD Medical Director

NMDOH Project Director

Facilitate Steering Committee Meetings Participate in planning sessions Ensure project staff availability, funding, and

PAGE | 4

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

Steering Committee

Member

contract management Review and accept the initial risk assessment,

management plan, project plan, and budget Appoint Project Committee and Team

members Provide management review and accept

changes to project plan, contracts or deliverables

Ensure user and sponsor acceptance Attend executive requirements reviews and

resolve requirements problems Adjudicate any appeals relative to Steering

Committee decisions Cast the deciding vote where a consensus

cannot be reached by the Steering Committee Empower the Project Manager Communicate with the Executive Sponsor and

NMDOH Champion the project Contribute to lessons learned

Sean Pearson NMDOH

Agency CIO

Steering Committee

Member

Provide Information Technology guidance Attend and participate in meetings Review and accept deliverables Review presented documentation Balance larger picture versus details of project Review project funding and expenditures Champion the project

Robert Horwitz NMDOH

Division CFO and Deputy

Director

Steering Committee

Member

Provide PHD Financial/Program Support guidance

Provide PHD Bureau guidance Attend and participate in meetings Review and accept deliverables Review presented documentation Balance larger picture versus details of project Review project funding and expenditures Champion the project

Jane Peacock NMDOH

Division Deputy Director

Steering Committee

Member

Provide PHD Bureau guidance Attend and participate in meetings Review and accept deliverables Review presented documentation Balance larger picture versus details of project Review project funding and expenditures Champion the project

Barbara Hickok NMDOH

Division Chief Nurse

Steering Committee

Member

Provide Clinical Services perspective Attend and participate in meetings Review and accept deliverables Review presented documentation Balance larger picture versus details of project Review project funding and expenditures Champion the project

PAGE | 5

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

Linda Monk NMDOH

Division Regional

Manager and Region

Representative

Steering Committee

Member

Provide Regional perspective Attend and participate in meetings Review and accept deliverables Review presented documentation Balance larger picture versus details of project Review project funding and expenditures Champion the project

Deborah Dickerson NMDOH

Project Manager

Advisory Steering

Committee Member

Develop initial management plan and project plan

Provide leadership for a coordinated project effort

Document project assumptions, constraints, and critical success factors

Conduct initial risk assessment Facilitate project meetings Assign tasks Manage schedule, budget and scope Develop detailed plans with project team for

risk, change, quality Ensure project consensus Manage expectations Report on project status Maintain issues log Maintain action items log Promote and practice change management Close-out action items Value teamwork, cooperation, and planning Champion the project Facilitate lessons learned process

2.2.3 O2.2.3 ORGANIZATIONALRGANIZATIONAL B BOUNDARIESOUNDARIES, , INTERFACESINTERFACES ANDAND RESPONSIBILITIESRESPONSIBILITIES

Use this section to describe any special considerations regarding contact between the project team, the project manager, and individuals from various organizations involved in the project: Boundary, interface and responsibilities at the interface

The project director will be primarily responsible for interfacing with Public Health office staff and the project manager will be primarily responsible for the administration and interface with the implementation vendor.

2.3 EXECUTIVE REPORTING2.3 EXECUTIVE REPORTINGThe Project Manager will communicate on a regular basis regarding all aspects of the BEHR Upgrade Project. To facilitate effective communication and provide accurate updates on progress, the Project Manager shall report on the Project in the following manner:

Project Meetings: Project meetings will be held bi-weekly to discuss the current activities, the schedule of future activities, prioritized risks and the status of project issues. Special focus will

PAGE | 6

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

be given to those activities and action items that were planned, but not accomplished. If necessary meetings will be held on a more frequent. As the go live date approached in 2nd quarter of CY11, it is expected that the project team will meet weekly. The BEHR Upgrade Project Manager will facilitate these meetings. Steering Committee meetings will be held monthly to update the membership on status, schedule, and budget, and to receive direction on project issues or decisions. These will be facilitated by the project director.

Status Reporting: The BEHR Upgrade Project Manager will meet Project Director on a bi-weekly basis or provide a written status report to discuss the current activities, the schedule of future activities, prioritized risks and the status of project issues.

Monthly Progress Reporting to DoIT: The BEHR Upgrade Project Manager will submit monthly reports using the DoIT template.

Other Communications: The BEHR Upgrade Project Manager will use email, telephone calls, conference calls, and additional meetings and presentations to communicate with the vendor, project team, and other stakeholders as needed.

3.0 SCOPE3.0 SCOPE

3.1 PROJECT OBJECTIVES3.1 PROJECT OBJECTIVES3.1.1 B3.1.1 BUSINESSUSINESS O OBJECTIVESBJECTIVES

NNUMBERUMBER DDESCRIPTIONESCRIPTION

Bus. Objective 1 Alignment of BEHR toward meaningful use as defined by the HITECH Act.

Bus. Objective 2 Increase functionality and workflow of BEHR in order to prepare for interfacing with the state laboratory division’s Laboratory Information Management System (LIMS) and the New Mexico Statewide Immunization Information System (NMSIIS) as well as private laboratories.

Bus. Objective 3 Increase revenue recovery by enhancing electronic claiming from BEHR

Bus. Objective 4 Train all public health office staff on the new version of BEHR.

3.1.2 T3.1.2 TECHNICALECHNICAL O OBJECTIVESBJECTIVES

NNUMBERUMBER DDESCRIPTIONESCRIPTION

Tech. Objective 1 Requirement and configuration documents completed.

Tech. Objective 2 Implement upgraded EHR application in test and training environment.

Tech. Objective 3 Develop test plan and scripts. Execute test scripts in test environment. Track and fix defects.

PAGE | 7

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

NNUMBERUMBER DDESCRIPTIONESCRIPTION

Tech. Objective 4 Upgrade BEHR EHR application in production.

3.2 PROJECT EXCLUSIONS3.2 PROJECT EXCLUSIONSExclusions to the BEHR Upgrade Project include an upgrade to the v.11 note and the implementation of electronic lab ordering and result processes.

3.3 CRITICAL SUCCESS FACTORS3.3 CRITICAL SUCCESS FACTORS

NUMBERNUMBER DESCRIPTIONDESCRIPTION

QUALITY METRICS 1 Data is converted properly from existing BEHR system.

QUALITY METRICS 2 Billing interfaces are working properly and electronic claim submission is not interrupted.

QUALITY METRICS 3 Implementation vendor and end user testing is successful by developing a test plan and test scripts.

QUALITY METRICS 4 Independent verification and validation review will be conducted on all project deliverables.

4.0 PROJECT DELIVERABLES AND METHODOLOGY4.0 PROJECT DELIVERABLES AND METHODOLOGY

4.1 PROJECT MANAGEMENT LIFE CYCLE4.1 PROJECT MANAGEMENT LIFE CYCLE

Phase Summary of Phase Key Deliverables

Initiation This phase defines overall parameters of the project and established the appropriate project management and quality environment required to complete the project.

Project Charter, Initial Risk Assessment, High level schedule, Procurement Strategy, Approval for next phase

Planning This phase defines the exact parameters of the project and ensures all the pre-requisites for execution and control are in place.

Project Management Plan, Team members identified, Final scope statement, High level WBS, Resources identified, High level Schedule, Budget and Communication Plans, Roles and Responsibilities, Status reports,

PAGE | 8

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

Approval for next phase

Implementation The phase configures and deploys the system.

Configuration Documentation, Testing Documentation, Training Documentation, Updated Project Schedule, Updated Budget, Risk Management Log, Issue Log, Status Report, Acceptance of Contract Deliverables

Closeout The phase accesses the project and derives any lessons learned and best practices.

Post Implementation Review and Report, Administrative Close-Out

4.1.1 P4.1.1 PROJECTROJECT M MANAGEMENTANAGEMENT D DELIVERABLESELIVERABLES

4.1.1.1 Project CharterDescription – The initial project deliverable plan will contain the Project Charter. This deliverable may be revised during planning phase.

Deliverable Acceptance Criteria – Sign-off by Project Sponsor or Project DirectorStandards for Content and Format – Use of DoIT Project Charter templateQuality Review -.Peer review for grammar and spellingKey project team members review for consensus

4.1.1.2 Project Management PlanDescription – The Project Management Plan will be the guide used throughout the Project. This plan will contain the following plans: Scope Management, Schedule Management, Budget, Risk Management, Communications, Change Management, and Roles/Responsibilities of team members. This plan is an evolving document as new information will be added and existing information will be revised during initiation and planning phase.

Deliverable Acceptance Criteria – Approval by Project Team and Steering CommitteeSign-off by Project Sponsor or Project Director Standards for Content and Format – Use of DoIT Project Management Plan templateQuality Review – Peer review for grammar and spellingKey project team members review for consensusFinal review by Steering Committee, Project Director and Sponsor

4.1.2 D4.1.2 DELIVERABLEELIVERABLE A APPROVALPPROVAL A AUTHORITYUTHORITY D DESIGNATIONSESIGNATIONS

PAGE | 9

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

DDELIVERABLEELIVERABLE NNUMBERUMBER

DDELIVERABLEELIVERABLE AAPPROVERSPPROVERS (W (WHOHO CANCAN APPROVEAPPROVE))

DDATEATE AAPPROVEDPPROVED

PRJ-DEL-001 Project Charter Jack Callaghan, PhD

Maggi Gallaher, MD, MPH

8/5/2010

PRJ-DEL-002 Project Management Plan (PMP) Jack Callaghan, PhD

Maggi Gallaher, MD, MPH

4.1.3 D4.1.3 DELIVERABLEELIVERABLE A ACCEPTANCECCEPTANCE P PROCEDUREROCEDURE

The Project Director and the Project Sponsor will review and accept the project documents. There will be a formal acceptance and sign-off for the BEHR Upgrade Project Charter and Project Management Plan.

4.2 PRODUCT LIFE CYCLE4.2 PRODUCT LIFE CYCLE

Phase Summary of Phase Key Deliverables

Configuration Determine the templates to be changed or added. Document all configuration changes previously made and identify those that will be in new version.

Application configuration in new version.

Testing Testing of configuration. Test plan, test scripts and final acceptance.

Conversion Preparation of specific data format for conversion.

Current production data in upgraded system.

Training Training on system for all users. Training Documentation and tools. Training plan and schedule.

Deployment Deployment of system to all trained users, both Agency and contracted Providers.

Go live weekend testing and deployment plan.

Transition to Production Completed System Deployment and move to close-out Project.

Application support plan updated.

PAGE | 10

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

4.2.1 T4.2.1 TECHNICALECHNICAL S STRATEGYTRATEGY

Certify system performance after test upgrade and migration to new version

Upgrade to production environment, configuration, testing and signoff

4.2.2 P4.2.2 PRODUCTRODUCT ANDAND P PRODUCTRODUCT D DEVELOPMENTEVELOPMENT D DELIVERABLESELIVERABLES

4.2.2.1 Configuration

Description- Configuration Deliverable Acceptance Criteria – Sign-off by Project Team Standards for Content and Format – MS Word, Excel, Visio, and Adobe PDFQuality Review – Reviewed by project team members, director, and sponsor for completeness

4.2.2.2 Testing

Description – Testing Plan and Test Scripts

Deliverable Acceptance Criteria – Sign-off by Project TeamStandards for Content and Format – MS Word, Excel, Visio, and Adobe PDFQuality Review – Reviewed by project team members, director, and sponsor for completeness

4.2.2.3 Conversion

Description – Data Conversion Deliverable Acceptance Criteria – Sign-off by Project TeamStandards for Content and Format – MS Word, Excel, Visio, and Adobe PDFQuality Review – Reviewed by project team members, director, and sponsor for completeness

4.2.2.4 Training

Description – Training Plan Deliverable Acceptance Criteria – Sign-off by Project TeamStandards for Content and Format – MS Word, Excel, Visio, and Adobe PDFQuality Review – Reviewed by project team members, director, and sponsor for completeness

4.2.2.5 Deployment

Description – Deployment Deliverable Acceptance Criteria – Sign-off by Project TeamStandards for Content and Format – MS Word, Excel, Visio, and Adobe PDF

Quality Review – Reviewed by project team members, director, and sponsor for completeness

PAGE | 11

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

4.2.3 D4.2.3 DELIVERABLEELIVERABLE A APPROVALPPROVAL A AUTHORITYUTHORITY D DESIGNATIONSESIGNATIONS

DDELIVERABLEELIVERABLE NNUMBERUMBER

DDELIVERABLEELIVERABLE AAPPROVERSPPROVERS (W (WHOHO CANCAN APPROVEAPPROVE))

DDATEATE AAPPROVEDPPROVED

1 Configuration Project Director

2 Testing Plan Project Director

3 Data Conversion Project Director

4 Training Plan Project Director

5 Deployment Project Director

4.2.4 D4.2.4 DELIVERABLEELIVERABLE A ACCEPTANCECCEPTANCE P PROCEDUREROCEDURE

As part of the Deliverable Acceptance Procedure, the Project Team will review each of the deliverables. During the Project Team review period, any issues identified will be documented in the issue log and resolved, if possible, prior to the next step. After a deliverable is reviewed, a recommendation from the Project Team for acceptance will be sent to the Project Director for final sign-off.

5.0 PROJECT WORK5.0 PROJECT WORK

5.1 WORK BREAKDOWN STRUCTURE (WBS)5.1 WORK BREAKDOWN STRUCTURE (WBS)

PAGE | 12

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

IIDENTIFIERDENTIFIERWWORKORK P PACKAGEACKAGE DDESCRIPTIONESCRIPTION

DDEFINITIONEFINITION/ / OOBJECTIVEBJECTIVE

MMILESTONEILESTONE/ D/ DELIVERABLEELIVERABLE

1.0 Initiation Phase This phase defines overall parameters of the project and established the appropriate project management and quality environment required to complete the project

Project Charter, Initial Risk Assessment, High-level schedule, Approval for next phase.

2.0 Planning Phase This phase identifies the implementation approach, procurement method and establishes all necessary documentation.

Contract Amendment Negotiated and Executed, IV&V Contract Executed, Finalize PMP, Commit Resources. Approval for next phase.

3.0 Implementation Phase This phase deploys the upgraded system to a prepared set of users and positions on-going support and maintenance.

Confirm Schedule, Configuration, Testing, Training, and Deployment.

4.0 Closeout Phase This phase closes out the project and completes the Transition to Production.

Closeout report, Transition to Production document, Lessons Learned

5.2 SCHEDULE ALLOCATION -PROJECT TIMELINE5.2 SCHEDULE ALLOCATION -PROJECT TIMELINE

PAGE | 13

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

IIDENTIFIDENTIFIERER

TTASKASK/ / AACTIVITYCTIVITY NNAMEAME

RRESOURCEESOURCE NNAMEAME

MMILESTOILESTONENE (Y/N) (Y/N)

EEFFORTFFORT/ / DDURATIONURATION

SSTARTTART FFINISHINISH DDEPENDENTEPENDENT TTASKASK

1.0 Initiation Phase Project Director Project Team Steering Committee

Y

1 month 7/2010 7/2010 Confirm Funding

2.0 Planning PhaseProject Director Project Team Steering Committee

Y

1 month 7/2010 8/2010Execute Vendor Contract Amendment

3.0 Implementation Phase Project

Director Project Team Steering Committee

Vendor Resources

Y

10 months 8/2010 5/2011Completion of Planning Phase

4.0 Closeout PhaseProject Director Project Team Steering Committee

Vendor Resources

Y

1 month 5/2011 6/2011Completion of Implementation Phase

5.3 PROJECT BUDGET5.3 PROJECT BUDGETCosts estimates are the costs applied to an activity in a project by assigning resources with associated rates or fees. Resources can include equipment, material, technology, processing cycles, or people. The total cost is critical and should be consistent with the proposal; include breakdowns as needed. Match these cost estimates with the actual billed amounts. Use an appropriate format for the project size and customer requirements (e.g., by WBS, milestone, or deliverable).

DDESCRIPTIONESCRIPTION FY11FY11 FY12FY12Consulting Services IV&V

Implementation Vendor$200,000

Hardware N/A

PAGE | 14

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

Software N/A

TTOTALOTAL $200,000

5.4 PROJECT TEAM5.4 PROJECT TEAM5.4.1 P5.4.1 PROJECTROJECT T TEAMEAM O ORGANIZATIONALRGANIZATIONAL S STRUCTURETRUCTURE

Insert a graphical Organization Chart here. The Organizational Structure (OS) is a hierarchical configuration defining levels of program management and may identify all project personnel. The OS should be simple and straightforward. Include role names and people’s names. Consider identifying the core project team by shading their respective boxes on the chart. On complex projects, consider using a second OS to identify core project team. The OS can also be used for management reporting.

Maggi Gallaher, MD, MPH

Project Director

Deborah Dickerson

Project Manager

Business Process Team

Vendor Contract Resources

DOH Technical Team

5.4.2 P5.4.2 PROJECTROJECT T TEAMEAM R ROLESOLES ANDAND R RESPONSIBILITIESESPONSIBILITIES

RROLEOLE RRESPONSIBILITYESPONSIBILITY NNAMEAME FFUNCTIONALUNCTIONAL AAREAREA

Project Director To ensure business requirements are met and to provide project leadership

Maggi Gallaher, MD, MPH

NMDOH PHD

Project Manager To provide project management

Deborah Dickerson NMDOH ITSD

DOH Technical resources

To provide technical leadership and provide project technical resources

TBD NMDOH ITSD

Business Process Team

To provide business process and program area leadership, and to provide project business process resources

Barbara Hickok, Debbie Lopez, Paula Timmerman, Carrie White, Lisa Elkins

NMDOH PHD

PAGE | 15

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

RROLEOLE RRESPONSIBILITYESPONSIBILITY NNAMEAME FFUNCTIONALUNCTIONAL AAREAREA

Vendor Project Manager

To provide vendor leadership and project resources

Jan Frey MedNetwoRx

5.6 PROJECT LOGISTICS5.6 PROJECT LOGISTICS5.6.1 P5.6.1 PROJECTROJECT T TEAMEAM T TRAININGRAINING

The BEHR Project Team will use tools available at NMDOH and the Implementation Vendor to work together. These tools include telephone calls, conference calls and web meetings. The Project Team will also use resident software packages such as MS Word, Excel, Visio, Project and Adobe PDF. Trainers, Regional Support Users and others will be identified and training provided for these resources.

6.0 PROJECT MANAGEMENT AND CONTROLS6.0 PROJECT MANAGEMENT AND CONTROLS

6.1 RISK AND ISSUE MANAGEMENT6.1 RISK AND ISSUE MANAGEMENT6.1.1 R6.1.1 RISKISK M MANAGEMENTANAGEMENT S STRATEGYTRATEGY

Projects have many inherent risks associated with them. The technology itself, risks associated with introduction of new and/or innovative ideas, organizational change issues, internal project issues, external issues such as politics and the economy not to mention social concerns around the introduction of technology. The list of potential risks is almost limitless.

Risk management is the process of identifying potential project risk, assessing the probability and severity of risk events, and planning appropriate responses. Risk management is a priority task on any IT project and is managed just like cost, schedule, scope and quality.

The best way to deal with a large amount of data/information is to categorize it in such a way that you can begin to understand the relationships between the data and start to see structure.

1. Risk Identification – The process of identifying potential risks and documenting the specific characteristics of each.

2. Risk Analysis – The process of determining the impact and likelihood of the identified risks. This process may employ both qualitative and quantitative techniques as deemed necessary to objectively evaluate potential risks to the project.

3. Risk Mitigation – The process of mitigating the possibility of the risk and assigning responsible individuals to identified risks. All identified risks will have appropriate mitigation strategies/plans. For those risks that are highly probable and have significant impact to the project will develop contingency plans.

4. Risk Monitoring and Control – The process of tracking, evaluating and responding to ongoing developments relative to project plans, risk mitigation plans and specific contingency plans. Risk management is an integral component of integrated project control. This is an ongoing process for the duration of the project and will be part of every project status meeting.

PAGE | 16

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

6.1.2 P6.1.2 PROJECTROJECT R RISKISK I IDENTIFICATIONDENTIFICATION This is the process of identifying potential risks and documenting the specific characteristics of each. The BEHR Upgrade Project Team will discuss the project risks on a periodic basis or as a specific risk occurs.

6.1.3 P6.1.3 PROJECTROJECT R RISKISK M MITIGATIONITIGATION A APPROACHPPROACH

The approach for the BEHR Upgrade Project will be the process of mitigating the possibility of the risk and assigning a responsible individual to monitor identified risks. All identified risks will have appropriate mitigation strategies/plans. For those risks that are highly probable and have significant impact to the project will develop contingency plans.

6.1.4 R6.1.4 RISKISK R REPORTINGEPORTING ANDAND E ESCALATIONSCALATION S STRATEGYTRATEGY

Once a risk is identified, the BEHR Upgrade Project Team will analyze the risk to determine the source, the probability it will happen and the impact to time, cost, quality and scope. An initial strategy may be laid out. Risks will be prioritized and assigned to a team member. The team member’s manager will be required to document the response to the potential risk and assumes responsibility for communicating and escalating to the appropriate parties.

6.1.5 P6.1.5 PROJECTROJECT R RISKISK T TRACKINGRACKING A APPROACHPPROACH

Potential risks will be tracked using a Risk Tracking Log.

6.1.6 ISSUE MANAGEMENT6.1.6 ISSUE MANAGEMENT

6.1.6.1 Internal Issue Escalation and Resolution ProcessWhen an issue is identified, most likely by the project team, it will be added to the Issue Tracking Log. An issue can also be identified by anyone affiliated with the project; however the project team will be primarily responsible for tracking issues through to resolution. The project team will review the issues list on a periodic basis. Issues which could negatively impact the project or require senior level participation will be brought to executive sponsor’s and project manager’s attention for resolution.

6.1.6.2 External Issue Escalation and Resolution ProcessThe process for issue escalation and resolution for issues that cannot be addressed within NMDOH will be handled in the same manner as internal issues. If necessary, resources outside the agency maybe brought in to resolve the issue. If at any time it is apparent the issue needs escalation outside of NMDOH, the Project Sponsor will communicate with the resource and ask for assistance in resolving the issue.

6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&V6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&V

Independent Verification and Validation (IV&V) is a risk mitigation strategy designed to provide management with project oversight through an independent evaluation a project’s product and process quality. The project has adopted a low risk implementation strategy by upgrading an existing application with a well-established and tested version. The IV&V plan will be tailored to address the unique risks associated with the upgrade.

The IV&V plan will:

1. Evaluate and validate that products and deliverables of a given development phase fulfill the requirements and performance outcomes set forth in the scope and project plan.

PAGE | 17

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

2. Provide a “close-out” report to the Steering Committee at the end of project

Specific deliverables from the IV&V contract: IV&V Project Management Plan. Initial Review and Risk Assessment. Periodic Reviews Close-out Report

6.3 SCOPE MANAGEMENT PLAN6.3 SCOPE MANAGEMENT PLANMost changes to scope are requests that add, change, or delete project objective or deliverables. Changes in scope, if at all possible, will be avoided and any new objectives and/or deliverables deferred to a follow-on project. Any proposed changes in scope will be analyzed for impacts on the project including schedule, budget and quality. The findings will be presented to the Steering Committee for approval or rejection.

6.3.1 C6.3.1 CHANGEHANGE C CONTROLONTROL

6.3.1.1 Change Control Process

Project changes will follow a decision making process. These changes include modifications to scope, schedule, budget, and quality. Significant changes of these planning components will be reviewed and approved or disproved by the Steering Committee. If a modification or enhancement to the project has been identified, a change request form will be completed. The Steering Committee will review the request to determine impacts to scope, schedule, budget, quality and resources. The Steering Committee will recommend accepting the change, rejecting the change, or may request additional information. The request will be documented by the Project Manager and if the change is approved, appropriate changes will be made to the Project Management Plan and other project documentation.

6.3.1.2 Change Control Board (CCB)During the course of the BEHR Upgrade Project, the Steering Committee will fill the role of the Change Control Board. A production-based Change Control Board is already established for the existing BEHR system and will resume their duties upon the successful implementation of the upgraded BEHR system. Due to the limited scope and time frame of the BEHR upgrade project, it is expected there will be little or no change to the project.

6.4 PROJECT BUDGET MANAGEMENT6.4 PROJECT BUDGET MANAGEMENT6.4.1 B6.4.1 BUDGETUDGET T TRACKINGRACKING

Costs estimates are the costs applied to an activity in a project by assigning resources with associated rates or fees. Resources may include equipment, material, technology, processing cycles, or people. The total cost is critical and should be consistent with the proposal and include breakouts per category as needed. The Project Manager will verify these cost estimates and proposed amounts with the actual billed amounts. The Project Manager will present updated financials at the monthly steering committee meeting.

6.5 COMMUNICATION PLAN6.5 COMMUNICATION PLAN

PAGE | 18

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

Communication will be effected through the distribution of Project Management deliverables as specified below. This PMP and any changes to it constitute one of the deliverables. Status Reports will be distributed as indicated below and for other communication needs, appropriate communication methods will be utilized. This includes regular communication with the public health office staff that is impacted by the BEHR upgrade.

Status, issues, and risks will also be discussed at regularly scheduled meetings preceded by the distribution of an agenda and followed by the distribution of meeting minutes or notes.

6.5.1 C6.5.1 COMMUNICATIONOMMUNICATION M MATRIXATRIX

Meetings Status Reports/Updates

Other Communications

To Executive Sponsor Monthly Monthly As Needed

To Steering Committee Monthly Monthly As Needed

To Project Director Bi-Weekly Monthly As Needed

To Project Team Bi-Weekly Receive From Members

As Needed

To Public Health Office staff None Quarterly As Needed

To Stakeholders None As Needed As Needed

6.5.2 S6.5.2 STATUSTATUS M MEETINGSEETINGS

Status Meetings with the core project team will be held on a weekly basis. This will include the project manager, project director and vendor project manager. Project Status will be the first agenda item. If needed, special meetings will be called to discuss and address issues.

6.5.3 P6.5.3 PROJECTROJECT S STATUSTATUS R REPORTSEPORTS

Project Status Reports will be distributed to the Project Sponsor and the Project Director and will be presented at each Steering Committee Meeting. As the project moves into implementation and the vendor is engaged, status reports will be required from the vendor as well as from BEHR Upgrade Project Resources. These status reports will be rolled up into the Steering Committee status report and reviewed at each meeting.

The monthly DoIT Status Report will be completed by the Project Manager and submitted per the DoIT process.

6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS)6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS)6.6.1 B6.6.1 BASELINESASELINES

The Project Manager will meet with the Project Sponsor and Project Director to define the project metrics that will be used to control the project. At a minimum, metrics will be established for time (schedule), cost (budget) and scope (quality).

PAGE | 19

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

Project Area Category Measure

Schedule Milestone performance Milestone dates

Status reports, issue log, risk log, and other identified measures

Budget Financial performance Actual versus budgeted costs

Quality Business Process Upgrade configuration and supporting business processes, data conversion, uninterrupted electronic claim submission, users trained on new version

6.6.2 M6.6.2 METRICSETRICS L LIBRARYIBRARY

The reviewed metrics in various software programs will be versioned by date and saved to the Project Library.

6.7 QUALITY OBJECTIVES AND CONTROL6.7 QUALITY OBJECTIVES AND CONTROL

PAGE | 20

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

6.7.1 6.7.1 QUALITYQUALITY S STANDARDSTANDARDS

PAGE | 21

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

NNOO.. QQUALITYUALITY S STANDARDTANDARD TTRACKINGRACKING T TOOLOOL OROR M MEASUREEASURE

1 Project Charter approved • Project charter approved by Executive Sponsor

2 Project management plan approved and followed• PMP signed off by Steering

Committee• Project status reports

3 Certification to proceed to next phase by DoIT• Approval from DoIT Project

Certification Committee and release of funds

4 Project risks documented, mitigated and tracked • Risk Management Log

5 Project issues documented, tracked, and worked to resolution

• Issue Log

6 Project is within budget • Project status• Budget management

7 Independent Verification and Validation• Periodic reviews• Respond to identified issues and

risks

8 Project completed based on the original project scope and approved scope changes

• Project Management Plan• Change Control Process• Scope Management• Steering Committee Meeting

Decisions

PAGE | 22

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

6.7.2 P6.7.2 PROJECTROJECT ANDAND P PRODUCTRODUCT R REVIEWEVIEW AND ASSESSMENTSAND ASSESSMENTS

Review Type Quality Standard Tools Reviewer Reports

Plans Plans are created with input from all project team members, approved by project team and the Steering Committee

Meetings, MS Project, Visio, and other software

Project TeamProject Director

Monthly or as presented

Milestones Milestones are met by date; reported to Steering Committee

MS Project Project DirectorSteering Committee

Monthly or as presented

Meeting Minutes, Issues Log, Risk Log

Documents are up-to-date and accurate

MS Word versions of documents

Project TeamProject Director

Monthly or as presented

Configuration/ Requirements

Configuration and Requirements are understood by all project team members; approved by Project Director

Various software packages

Project TeamProject Director

Workflow Analysis and templates

Data Conversion Data conversion is understood by all project team members; approved by Project Director

Various software packages

Project TeamProject Director

Data Conversion Plan

Testing Test results verified by Project Team testing resources

Various software packages

Project Team Test Plan and acceptance testing report

Training Training is understood by all project team members; approved by Project Director

Various software packages Project Director

Training Plan

6.7.3 A6.7.3 AGENCYGENCY/C/CUSTOMERUSTOMER S SATISFACTIONATISFACTION

PAGE | 23

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

Areas of feedback When How Often

PHD user awareness Feedback from the NMDOH PHD employees and end-users

Frequently

Quality of communications; Productive meetings

Feedback during the various meetings

At Project Team meetings and Steering Committee meetings; other meetings when held

Manages project tasks; Achieving project tasks

Feedback from Project Sponsor, Steering Committee, Project Director

Monthly

Selected solution – business process, usability

Feedback from Project Sponsor, Steering Committee, Project Director, Project Team, Testers, Training Attendees, Deployment Users

Monthly and per phase of the project

6.7.4 PRODUCT DELIVERABLE ACCEPTANCE PROCESS6.7.4 PRODUCT DELIVERABLE ACCEPTANCE PROCESS

Deliverable Final Approval Process Customer Acceptance Criteria

Workflow Analysis & Configuration Project Team Review; Project Director sign-off

System set up per agreed upon configuration and work flow documents

Data ConversionProject Team Review; Project Director sign

Data successfully converted based upon agreed data conversion plan

Testing Project Team Review; Project Director sign

Testing environment set up and system tested for accuracy

Training Project Team Review; Project Director sign

Training completed based upon agreed training plan and training documents

6.8 CONFIGURATION MANAGEMENT6.8 CONFIGURATION MANAGEMENT6.8.1 V6.8.1 VERSIONERSION C CONTROLONTROL

Documents will be stored on the NMDOH SharePoint server in the BEHR Upgrade Project Folder. If a document needs to be changed or updated, the document must be checked out from SharePoint. After changes or updates are made, the document must be checked in to SharePoint. SharePoint automatically keeps different versions with who and when they were edited.

PAGE | 24

PROJECT MANAGEMENT PLAN FOR BEHR UPGRADE PROJECT

Larger documents such as the Project Management Plan will be controlled by the revision history log. Entries will be made into the revision history log when changes are made. A copy of the Project Library will be placed on a PHD share drive on a monthly basis.

6.8.2 P6.8.2 PROJECTROJECT R REPOSITORYEPOSITORY (P (PROJECTROJECT L LIBRARYIBRARY))The BEHR Upgrade Project has a folder on a PHD share drive and on the NMDOH SharePoint server for all project documentation.

6.9 PROCUREMENT MANAGEMENT PLAN6.9 PROCUREMENT MANAGEMENT PLANThe BEHR Upgrade Project will be accomplished using an amendment under the existing contract with Mednetworx. The procurement will follow the State Purchasing Division’s process and protocol.

The IV&V vendor will be procured executing a contract against a statewide price agreement or with NM Abilities.

7. 0 PROJECT CLOSE7. 0 PROJECT CLOSE Project Close consists of administrative project activities and contractual project completion activities. It is important for the proper project closeout to complete both sets of activities. Administrative closeout activities complete the agency requirements for the NMDOH who is responsible for managing the project. This includes developing the lessons learned, processing the last of the invoices, and providing a transition plan for system and staff to the production mode. Contract closeout activities complete the contracting requirements, such as the formal acceptance of the project work products and final invoice processing. Required documentation and presentations will also be completed.

7.1 A7.1 ADMINISTRATIVEDMINISTRATIVE C CLOSELOSE

Administrative Close occurs at both the end of each phase and at the end of project. This closeout activity consists of verification that deliverables were met. Acceptance is formalized and phase activities are administratively closed out. The identification of closeout activities for the BEHR Upgrade Project will be the final deployment of the upgrade and the transition to production. The final closeout will include the completion of NMDOH documentation, the DoIT closeout report and a presentation to the DoIT Project Certification Committee for approval to formally close the project.

7.2 C7.2 CONTRACTONTRACT C CLOSELOSE

Contract closeout activities will include the verification of all contracting requirements, deliverables, and work products. It will also include confirming that all final invoices have been submitted for the Project.

PAGE | 25


Recommended