News da LHC… *** Discussion title: CMS Commissioning Notes from 09:00 meeting 100627 Current fill (1182) has now been in stable beams for >12 hours. Delivered lumi ~15/nb. The machine will handshake for adjust and do some end of fill studies and dump the beam. Then they will refill again for 3x3. There will be a few more 3x3 fills before going to 6x6. -Anders Dallo scorso week-end la macchina ha cominciato a dare fasci stabili, con luminosita’ ~5*10 29 (10 11 p/bunch) previsti ~ 40-100 nb-1 per meta’ luglio Sperabilmente stiamo entrando in un periodo di physics running
Transcript
Page 1: News da LHC… *** Discussion title: CMS Commissioning Notes from 09:00 meeting 100627 Current fill (1182) has now been in stable beams for >12 hours. Delivered.

News da LHC…

*** Discussion title: CMS Commissioning Notes from 09:00 meeting 100627 Current fill (1182) has now been in stable beams for >12 hours. Delivered lumi ~15/nb. The machine will handshake for adjust and do some end of fill studies and dump the beam. Then they will refill again for 3x3. There will be a few more 3x3 fills before going to 6x6. -Anders

Dallo scorso week-end la macchina ha cominciatoa dare fasci stabili, con luminosita’ ~5*1029 (1011 p/bunch)

previsti ~ 40-100 nb-1 per meta’ luglio

Sperabilmente stiamo entrando in un periododi physics running

Page 2: News da LHC… *** Discussion title: CMS Commissioning Notes from 09:00 meeting 100627 Current fill (1182) has now been in stable beams for >12 hours. Delivered.

CMS: impegni MoA, shifts, ecc..….

http://cms.cern.ch/iCMS/

“Memorandum Of Agreement”:tra le altre cose, ogni istituzione e’ tenuta a fornire all’ esperimentouna certa quota di “servizi” in ragione delle firme che le competono

Page 3: News da LHC… *** Discussion title: CMS Commissioning Notes from 09:00 meeting 100627 Current fill (1182) has now been in stable beams for >12 hours. Delivered.

CMS: MoA

29 “firme” (DT + Tk) nel 2010

3 m.u. “dovuti” / firma => pe PD: 87 m.u. di servizi

Core sw/computing (es.: T2 managements (Biasotto, Ezio…);CRAB (federica, Stefano) )

Central shifts(DAQ, shift leader…)

N.B:- Il grosso e’ sui detectors- non tutti i servizi sono shifts (ovviamente)- non tutti i servizi sono al CERN (e.g. off-line DQM, T1/T2 operations, Physics Quality Data certification, contributi a offline core sw…, upgrade developments…)- ci sono meccanismi (semi)-automatici per riconoscere parte di questo nei finanziamenti INFN nell’ assegnazione delle M.E. (“MoA CERN”) (insieme con le responsabilita’, in aggiunta al puro “metabolismo”)

Page 4: News da LHC… *** Discussion title: CMS Commissioning Notes from 09:00 meeting 100627 Current fill (1182) has now been in stable beams for >12 hours. Delivered.

MoA “pledges”: esempi

Shifts… (on-line/on-call, off-line “prompt analysis)

Ci sono inoltre servizi centrali,cui va dato un contributo(e. DAQ, central DQM, shift leader/ run field manager ...): 6 “punti” (~ shifts; peso 0.8-1.2 )/firma

Grosso modo 24 settimane di shifts

“centrali” per Pd

Page 5: News da LHC… *** Discussion title: CMS Commissioning Notes from 09:00 meeting 100627 Current fill (1182) has now been in stable beams for >12 hours. Delivered.

DT shifts

Week #1

Week #2

Da giugno, durante il running, al Cern: 2 shifters “on-call” in contemporanea;=> Pd : ~ 1 shifter x 1 settimana al mese

Page 6: News da LHC… *** Discussion title: CMS Commissioning Notes from 09:00 meeting 100627 Current fill (1182) has now been in stable beams for >12 hours. Delivered.

Shifts stat

Off-line

Page 7: News da LHC… *** Discussion title: CMS Commissioning Notes from 09:00 meeting 100627 Current fill (1182) has now been in stable beams for >12 hours. Delivered.

Shifts: training

http://indico.cern.ch/conferenceDisplay.py?confId=94051

Vi sara’ una nuova training sessionMerc. 7 luglio mattinaAl Muon Barrel workshophttp://indico.cern.ch/conferenceDisplay.py?confId=99769

Page 8: News da LHC… *** Discussion title: CMS Commissioning Notes from 09:00 meeting 100627 Current fill (1182) has now been in stable beams for >12 hours. Delivered.

Training

Page 9: News da LHC… *** Discussion title: CMS Commissioning Notes from 09:00 meeting 100627 Current fill (1182) has now been in stable beams for >12 hours. Delivered.

Training: DQM

Page 10: News da LHC… *** Discussion title: CMS Commissioning Notes from 09:00 meeting 100627 Current fill (1182) has now been in stable beams for >12 hours. Delivered.

DQM: esempio

Page 11: News da LHC… *** Discussion title: CMS Commissioning Notes from 09:00 meeting 100627 Current fill (1182) has now been in stable beams for >12 hours. Delivered.

DT offline prompt analysishttps://twiki.cern.ch/twiki/bin/view/CMS/DTAnalysisLHCRuns

http://cmsdoc.cern.ch/cms/MUON/dt/sx5/Results/GlobalRuns/BeamCommissioning2010/Run138767/

Esempio di output:

Page 12: News da LHC… *** Discussion title: CMS Commissioning Notes from 09:00 meeting 100627 Current fill (1182) has now been in stable beams for >12 hours. Delivered.

Shift bookinghttp://cmsdoc.cern.ch/cms/MUON/dt/sx5/ Scroll on the left in the page,

Find & click on “ONLINE shifts LIST”