2
Welcome to the first edition of the Dargues Gold Mine— Newsletter for 2019. I joined the Dargues Gold Mine team in January 2019 in the role of General Manager. Im a mining engineer with 17 years of experience and have worked at a number mines here in Australia and overseas. Im looking forward to getting to know the local area and community over the coming months and years. It is a very busy time at the Dargues Gold Mine, with underground mining well progressed and the process plant steel erection commencing. The Tailings Storage Facility bulk earthworks will commence next month along with the installation of water bores and other supporting infrastructure. I look forward to providing regular updates moving forwards and please do not hesitate to contact us on the information over the page should you wish to find out more. Shannon Green General Manager Dargues Gold Mine www.DivMinerals.com.au NEWSLETTER June 2019 At the end of May, the underground workings had advanced 669.5 metres from the portal (entrance to the underground mine). The mine is now 115 metres below ground level with over 1,198.6 metres of underground development now completed. The image below shows the Boxcut (light green) which contains the portal, the underground development completed to date (red), the planned development for the next three months (green), Ventilation and Escape Way (blue) and the old historical workings (purple). Ore (Photo on the Left) was intersected on 65 level on 29 May 2019. The ore was sourced from an area of mineralisation called Main Lode which varies in width from 1m to 3.5m, averaging about 3 metres in width. The ore brought to surface contains approximately three grams of gold per one tonne of ore. Mining is planned to intersect further ore on 65 Level in June. Although some ore has been intersected early, no processing of the ore is able to be completed until the process plant is constructed. Construction of the process plant is expected to be completed in the first quarter of 2020.
Transcript
Page 1: NEWSLETTER - Diversified Minerals · At the end of May, the underground workings had advanced 669.5 metres from the portal (entrance to the underground mine). The mine is now 115

Welcome to the first edition

of the Dargues Gold Mine—

Newsletter for 2019.

I joined the Dargues Gold Mine team in January 2019 in the role of General Manager. I’m a mining engineer with 17 years of experience and have worked at a number mines here in Australia and overseas.

I’m looking forward to getting to know the local area and community over the coming months and years.

It is a very busy time at the Dargues Gold Mine, with underground mining well progressed and the process plant steel erection commencing. The Tailings Storage Facility bulk earthworks will commence next month along with the installation of water bores and other supporting infrastructure.

I look forward to providing regular updates moving forwards and please do not hesitate to contact us on the information over the page should you wish to find out more.

Shannon Green General Manager Dargues Gold Mine www.DivMinerals.com.au

NEWSLETTER

June 2019

At the end of May, the underground workings had advanced 669.5 metres from the portal (entrance to the underground mine). The mine is now 115 metres below ground level with over 1,198.6 metres of underground development now completed.

The image below shows the Boxcut (light green) which contains the portal, the underground development completed to date (red), the planned development for the next three months (green), Ventilation and Escape Way (blue) and the old historical workings (purple).

Ore (Photo on the Left) was intersected on 65 level on 29 May 2019. The ore was sourced from an area of mineralisation called Main Lode which varies in width from 1m to 3.5m, averaging about 3 metres in width. The ore brought to surface contains approximately three grams of gold per one tonne of ore. Mining is planned to intersect further ore on 65 Level in June.

Although some ore has been intersected early, no processing of the ore is able to be completed until the process plant is constructed. Construction of the process plant is expected to be completed in the first quarter of 2020.

Page 2: NEWSLETTER - Diversified Minerals · At the end of May, the underground workings had advanced 669.5 metres from the portal (entrance to the underground mine). The mine is now 115

The best source of up-to-date infor-mation is our website

www.divminerals.com.au

Or

https://www.facebook.com/DivMinerals/

For more detailed assistance please call the Dargues Gold Mine Information Line on

1800 732 002

Or email

[email protected]

Interested in working with us?

Visit the Pybar careers page for more information :

https://careers.pybar.com.au/

Interested in supplying to us?

Head to our website and register:

http://www.divminerals.com.au/dargues-gold-mine/suppliers/

NEWSLETTER

June 2019

During June, eight members of the Dargues Gold Mine team completed the first stage of a Certificate III in Mine Emergency Response and Rescue. These team members will form the basis of the mines Emergency Rescue Team.

All mines in NSW are required to have an emergency rescue capabilities.

The Dargues Gold Mine is in the process of finalising a community grants program. The community grants program is set to commence next financial year. The Program will aim to support and enhance the community groups, organisations and infrastructure which provide a sustainable foundation for the Braidwood and Majors Creek communities.

Watch this space for the first round of application dates.

The Dargues Gold Mine aims to provide a clear pathway for resolving issues locally in an appropriate and timely manner. Issue resolution applies to all of our company’s suppliers, community members and government stakeholders.

It is important to call Dargues Gold Mine when an issue occurs so we can determine the cause and act to rectify.

Key contact information:

• Phone (free call) - 1800 732 002

• Email - [email protected]

The process plant at the Dargues Gold Mine is progressing well (image over page), with the concrete foundations completed and steel work starting to be erected. The below image is a model view showing the general layout of the process plant once completed.