+ All Categories
Home > Documents > NFF – Norsk Forening for Fjellsprengningsteknikk 2016...

NFF – Norsk Forening for Fjellsprengningsteknikk 2016...

Date post: 30-Jul-2018
Category:
Upload: vanbao
View: 215 times
Download: 0 times
Share this document with a friend
32
Engineering Joint Venture Gotthard Base Tunnel South NFF – Norsk Forening for Fjellsprengningsteknikk 2016 „TBM Applications“ St. Gotthard Railway Tunnel Experience versus planning, lessons learned M.Sc. Thomas Jesel Amberg Engineering Ltd., Regensdorf, Switzerland
Transcript

Engineering Joint Venture Gotthard Base Tunnel South

NFF – Norsk Forening for Fjellsprengningsteknikk 2016 „TBM Applications“

St. Gotthard Railway TunnelExperience versus planning, lessons learned

M.Sc. Thomas JeselAmberg Engineering Ltd., Regensdorf, Switzerland

Engineering Joint Venture Gotthard Base Tunnel South

Engineering Joint Venture Gotthard Base Tunnel South

Tunnel SystemNFF, Bergen, Norway, June 6-7 2016

STC (Swiss Tunnel Congress) www.alptransit.ch

Engineering Joint Venture Gotthard Base Tunnel South

Geological Longitudinal Section

Aar Massife CZ

TZM

UG

Z Gotthard-Massife

Penninic gneiss zoneP

ioraGeolog.

formation

Portal Erstfeld Amsteg Sedrun Faido Portal Bodio

NFF, Bergen, Norway, June 6-7 2016

Engineering Joint Venture Gotthard Base Tunnel South

Excavation MethodNFF, Bergen, Norway, June 6-7 2016

Engineering Joint Venture Gotthard Base Tunnel South

TBMNFF, Bergen, Norway, June 6-7 2016

4 Herrenknecht TBM Open gripper shield Length

TBM: 26 mBack-up: 450 m

Cutter headDiameter: 9.43 mShifted, max: 9.53 mWeight: 240 t

Discs: Number: 66Diameter: 17’’

Engineering Joint Venture Gotthard Base Tunnel South

Experience, FaidoNFF, Bergen, Norway, June 6-7 2016

Requirements Cutter head wear Water inflow Rock burst Squeezing rock Blocked TBM

Engineering Joint Venture Gotthard Base Tunnel South

Requirements INFF, Bergen, Norway, June 6-7 2016

Reduced flexibility Small areas where support

can be applied Requirements sometimes

contra dictionary Set right focus to get right TBM! Wrong focus - wrong TBM

Engineering Joint Venture Gotthard Base Tunnel South

Requirements IINFF, Bergen, Norway, June 6-7 2016

Detailed description of geology Most probable geology Hazard scenarios Set right focus Optimize TBM for project

Worst case geology Hazard scenarios Feasibility check Action plan Must be feasible

Engineering Joint Venture Gotthard Base Tunnel South

Cutter head wear INFF, Bergen, Norway, June 6-7 2016

Abrasivity with Cherchar index Tender design: CAI 2.8 Medelser Granite CAI 4.4 Lucomagno Gneiss CAI 3.4

Medelser granite

Lucomagno Gneiss

Engineering Joint Venture Gotthard Base Tunnel South

Cutter head wear IINFF, Bergen, Norway, June 6-7 2016

Instable face Not all discs at face Reduced face pressure Reduced cutting speed Blocks at the face Cutter head as crusher Rolling blocks hits the disks

Engineering Joint Venture Gotthard Base Tunnel South

NFF, Bergen, Norway, June 6-7 2016

Cutter head wear III

CAI much higher than prognosis Damaged Disks due to blocks Often longer maintenance shifts

(less time to excavate) Reduced pressure due to instable face Determinating for advance rate

Engineering Joint Venture Gotthard Base Tunnel South

Water inflow INFF, Bergen, Norway, June 6-7 2016

Water pressure up to 200 bar Probe drillings require preventer

(in sensitive areas) Needs detailed specification in

tender docs 1:1 tests on site recommended

before entering critical zone Works well for both percussion

and core drillings

Engineering Joint Venture Gotthard Base Tunnel South

Water inflow IINFF, Bergen, Norway, June 6-7 2016

Water inflow initial max 100 l/s Ascending tunnel 600 mm drainage pipe No problem But 48°C! Cooling system limited Reduced working hours Frequent pauses required Reduced advance rate

Engineering Joint Venture Gotthard Base Tunnel South

Water inflow IIINFF, Bergen, Norway, June 6-7 2016

Drained tunnels cause settlements at surface Even in rock! Valleys open or close – depending where they

are situated on the settlement curve Can be critical for Hydropower dams (opening) Simulation and prediction very demanding Expert panel very helpful No measures from the tunnel Monitor the dam, lower the water, repair

Engineering Joint Venture Gotthard Base Tunnel South

Rock burst INFF, Bergen, Norway, June 6-7 2016

Difficult to predict Without warning – suddenly! Rock support cannot prevent

rock burst But must protect staff

TBM helps! Absorbe kinetic energy Not easy to classify,

subjective Code of classification Potential measures

Engineering Joint Venture Gotthard Base Tunnel South

Rock burst IINFF, Bergen, Norway, June 6-7 2016

Engineering Joint Venture Gotthard Base Tunnel South

NFF, Bergen, Norway, June 6-7 2016

Squeezing rock I

Started with Steel arches androck bolts and shotcrete

Soon deformations (30cm) Shotcrere destroyed Steel arches plastified

Engineering Joint Venture Gotthard Base Tunnel South

NFF, Bergen, Norway, June 6-7 2016

Second TBM even worse Back up was squeezed in Heave in the invert Reconstruction of the invert

still under the TBM

Squeezing rock II

Engineering Joint Venture Gotthard Base Tunnel South

NFF, Bergen, Norway, June 6-7 2016

TBM got through – at the end Intensive back calculations Neu loads, new design Tunnel redone on 400 m

Squeezing rock V

Engineering Joint Venture Gotthard Base Tunnel South

NFF, Bergen, Norway, June 6-7 2016

D&B in this area had less problemsRock support can be installed faster

Distance between tunnels importantOptimisation process

Implementation of shotcrete in L1 has to be avoided, but worked well if necessary

Styrofoam elements worked well to protect shotcrete

Inclined cross passages allowed to redo the tunnels without interrupting the TBM

Squeezing rock VI

Engineering Joint Venture Gotthard Base Tunnel South

NFF, Bergen, Norway, June 6-7 2016

Blocked TBM I

First machine passed Some over brake Second machine got stocked Several attempts with backing

and restart were not successful 1’100 m spiles installed Voids filled up with 48 m3

concrete and 47 m3 grout

Engineering Joint Venture Gotthard Base Tunnel South

NFF, Bergen, Norway, June 6-7 2016

Blocked TBM II

Still not successful A lot of material was taken

out without any progress Massive cavern above the

tunnel Extensive probe drilling

Engineering Joint Venture Gotthard Base Tunnel South

NFF, Bergen, Norway, June 6-7 2016

Blocked TBM III

Stabilize loos material Grouting campaign Counter heading

Engineering Joint Venture Gotthard Base Tunnel South

NFF, Bergen, Norway, June 6-7 2016

Blocked TBM IV

Action plan was very helpful, reduced reaction time significantly

Expert panel was important Close collaboration and clear

communication was crucial

Decision need to be taken fast, immediately at the face

Willingness to solve the problem compulsory

Engineering Joint Venture Gotthard Base Tunnel South

Advance rate INFF, Bergen, Norway, June 6-7 2016

Expectations from design phase: 2.33 m/h

Ost WestPenetration mm/U 8.28 8.46Netto advance rate m/h 2.51 2.64

Engineering Joint Venture Gotthard Base Tunnel South

Advance rate IINFF, Bergen, Norway, June 6-7 2016

Joint and foliation angle important influence

Penetration around 10 mmwhile perpendicular

Drops down to 70% while flat

Engineering Joint Venture Gotthard Base Tunnel South

Advance rate IIINFF, Bergen, Norway, June 6-7 2016

m/d Design Ost west

10.8 13.0 12.8

‐ 20% 18%

7.4 9.6 9.3

‐ 30% 25%

8.9 9.3 8.9

‐ 4% 0%

12.2 10.0 10.5

‐ ‐18% ‐14%

Erstfeld

Amsteg

Faido

Bodio

Engineering Joint Venture Gotthard Base Tunnel South

Lessons learned INFF, Bergen, Norway, June 6-7 2016

Optimize TBM for most probable geology – set right focus

Make sure, that TBM can handle worst case (not necessarily efficient)

Open gripper TBM was right decisionFlexibility was needed

Shotcrete in L1 was necessary and feasible, main shotcrete in L2

Rock bolts in L2 were not used. Bolts are needed as close to the face as possible

Engineering Joint Venture Gotthard Base Tunnel South

Lessons learned IINFF, Bergen, Norway, June 6-7 2016

A continuous probe drilling from the TBM was very useful (low cost, no time)

In such difficult geology it is inevitable to have competent staff on site (contractor, designer bust also client)

Decisions need to be taken fast, to keep TBM running

Logistic is important. Keep other activities as low as possible

TBM produces a lot of data. Data evaluation needs a clear concept to get significant results

Engineering Joint Venture Gotthard Base Tunnel South

Final remarkNFF, Bergen, Norway, June 6-7 2016

Main problem: Communication!

Engineering Joint Venture Gotthard Base Tunnel South

Thank you for your [email protected]


Recommended