SHEET NO. TOTAL SHEETS LOCATION SKETCH 100 0 100 200 SCALE IN FEET PLANS PREPARED BY: PLANS COMPLETED DATE SCALE: NTS COVER SHEET REVISIONS Buford Highway & Sugarloaf Pkwy Landscape Improvements DULUTH GATEWAY SHEET NO. EROSION CONTROL MEASURES WILL BE MAINTAINED AT ALL TIMES. IF FULL IMPLEMENTATION OF THE APPROVED PLAN DOES NOT PROVIDE FOR EFFECTIVE EROSION CONTROL, ADDITIONAL EROSION AND SEDIMENT CONTROL MEASURES SHALL BE IMPLEMENTED TO CONTROL OR TREAT THE SEDIMENT SOURCE. THE ESCAPE OF SEDIMENT FROM THE SITE SHALL BE PREVENTED BY THE INSTALLING OF EROSION AND SEDIMENT CONTROL MEASURES AND PRACTICES PRIOR TO, OR CONCURRENT WITH LAND-DISTURBING ACTIVITIES. SPECIFICATION NOTE: This project is to be constructed using the Georgia Department of Transportation's Standard Specifications 2001 Edition as approved by the Federal Highway Administration and as modified by contract documents. 50 PRIOR TO THE LAND-DISTURBING ACTIVITIES, THE CONTRACTOR SHALL SCHEDULE A PRECONSTRUCTION MEETING WITH THE AREA EROSION CONTROL/SITE DEVELOPMENT INSPECTOR. CALL 811 TO CONTACT THE INSPECTOR AND CONFIRM UTILITIES. G-001 POND AND COMPANY 3500 PARKWAY LANE, SUITE 600 ANDREA GRECO, PLA SURVEY AND COORDINATE DATA NAD 1983 State Plane Georgia West DATA IS PROVIDED BY GWINNETT COUNTY G.I.S. DEPARTMENT 1 7 SHEET INDEX Sheet Description G-001 Cover Sheet G-101 Index Map L-001 General Landscape Notes LP-101 Landscape Plan LP-102 Landscape Plan L-501 Landscape Details L-502 Landscape Notes SUGARLOAF PARKWAY SUGARLOAF PARKWAY BUFORD HIGHWAY/ SR 13/ US RT 23 BUFORD HIGHWAY / SR 13 NORFOLK SOUTHERN RAILROAD 400 Note: 1. There are no billboads with 500' of this project site.
Transcript
Page 1: NORFOLK SOUTHERN RAILROAD BUFORD HIGHWAY / SR 13 …

SHEETNO.

TOTALSHEETS

LOCATION SKETCH

100 0 100 200

SCALE IN FEET

PLANS PREPARED BY:

PLANS COMPLETEDDATE

SCALE: NTS

COVER SHEET

REVISIONS

Buford Highway & Sugarloaf PkwyLandscape Improvements

DULUTH GATEWAY

SHEET NO.

EROSION CONTROL MEASURES WILL BE MAINTAINED AT ALL TIMES. IF FULL

IMPLEMENTATION OF THE APPROVED PLAN DOES NOT PROVIDE FOR EFFECTIVE

EROSION CONTROL, ADDITIONAL EROSION AND SEDIMENT CONTROL MEASURES

SHALL BE IMPLEMENTED TO CONTROL OR TREAT THE SEDIMENT SOURCE.

THE ESCAPE OF SEDIMENT FROM THE SITE SHALL BE PREVENTED BY THE INSTALLING

OF EROSION AND SEDIMENT CONTROL MEASURES AND PRACTICES PRIOR TO, OR

CONCURRENT WITH LAND-DISTURBING ACTIVITIES.

SPECIFICATION NOTE: This project is to be constructed using the Georgia Department

of Transportation's Standard Specifications 2001 Edition as approved by the Federal

Highway Administration and as modified by contract documents.

50

PRIOR TO THE LAND-DISTURBING ACTIVITIES, THE CONTRACTOR SHALL SCHEDULE A

PRECONSTRUCTION MEETING WITH THE AREA EROSION CONTROL/SITE DEVELOPMENT

INSPECTOR. CALL 811 TO CONTACT THE INSPECTOR AND CONFIRM UTILITIES.

G-001

POND AND COMPANY

3500 PARKWAY LANE, SUITE 600

ANDREA GRECO, PLA

SURVEY AND COORDINATE DATANAD 1983 State Plane Georgia West

DATA IS PROVIDED BY GWINNETT COUNTY G.I.S. DEPARTMENT

1 7

SHEET INDEX

Sheet Description

G-001 Cover Sheet

G-101 Index Map

L-001 General Landscape Notes

LP-101 Landscape Plan

LP-102 Landscape Plan

L-501 Landscape Details

L-502 Landscape Notes

S

U

G

A

R

L

O

A

F

P

A

R

K

W

A

Y

S

U

G

A

R

L

O

A

F

P

A

R

K

W

A

Y

B

U

F

O

R

D

H

I

G

H

W

A

Y

/

S

R

1

3

/

U

S

R

T

2

3

B

U

F

O

R

D

H

I

G

H

W

A

Y

/

S

R

1

3

N

O

R

F

O

L

K

S

O

U

T

H

E

R

N

R

A

I

L

R

O

A

D

400

Note:

1. There are no billboads with 500' of this project site.

Page 2: NORFOLK SOUTHERN RAILROAD BUFORD HIGHWAY / SR 13 …

1

6

4

'

-

0

"

'

2

2

4

'

-

0

"

'

1

7

3

'

-

0

"

'

2

3

6

'

-

0

"

'

L

P

-

1

0

1

G-101

LAYOUT INDEX SHEET

2

B

U

F

O

R

D

H

I

G

H

W

A

Y

L

P

-

1

0

2

B

U

F

O

R

D

H

I

G

H

W

A

Y

S

U

G

A

R

L

O

A

F

P

A

R

K

W

A

Y

S

U

G

A

R

L

O

A

F

P

A

R

K

W

A

Y

N

O

R

F

O

L

K

S

O

U

T

H

E

R

N

R

A

I

L

R

O

A

D

Note:

1. There are no billboads with 500' of this project site.

LANDSCAPE STARTING POINT ALONG BUFORD HWY SOUTHWEST FROM

CENTERLINE OF SUGARLOAF PKWY

LANDSCAPE STARTING POINT ALONG SUGARLOAF PKWY

NORTHWEST FROM THE CENTERLINE OF BUFORD HWY

LANDSCAPE END POINT ALONG BUFORD HWY NORTHEAST FROM

CENTERLINE OF SUGARLOAF PKWY

LANDSCAPE END POINT ALONG SUGARLOAF PKWY

SOUTHEAST FROM THE CENTERLINE OF BUFORD HWY

CL

CL

CL

CL

CL

CL

CL

CL

Buford Highway & Sugarloaf PkwyLandscape Improvements

POND AND COMPANY

3500 PARKWAY LANE SUITE 600

NORCROSS, GEORGIA 30092

(P) 678-336-7740 (F) 678-336-7744

SIGNATUREREQUESTED BYREVISIONSDATE

SHEETSTOTAL

NO.SHEET

Duluth Gateway

COPYRIGHT © 2010 BY POND & COMPANY. ALL RIGHTS RESERVED. NO

COPYING OR DUPLICATION OF THESE DOCUMENTS IS ALLOWED WITHOUT

THE EXPRESS WRITTEN AGREEMENT OF POND & COMPANY

7

S

R

1

3

/

U

S

R

O

U

T

E

2

3

S

R

1

3

/

U

S

R

O

U

T

E

2

3

Page 3: NORFOLK SOUTHERN RAILROAD BUFORD HIGHWAY / SR 13 …

1. THE LOCATIONS OF EXISTING UTILITIES ARE APPROXIMATE AND SHALL BE VERIFIED BY THE CONTRACTOR PRIOR TO BEGINNING

CONSTRUCTION. IF UNCHARTED UTILITIES ARE ENCOUNTERED DURING EXCAVATION OPERATIONS, THE CONTRACTOR SHALL

NOTIFY THE PROJECT OWNER IMMEDIATELY FOR INSTRUCTIONS. ANY DAMAGE OR INTERRUPTION OF EXISTING UTILITIES SHALL

BE THE SOLE RESPONSIBILITY OF THE CONTRACTOR AND SHALL BE REPAIRED PROMPTLY AT THE CONTRACTOR'S EXPENSE.

2. NAME AND ADDRESS OF SPONSOR/OWNER:

City of Duluth

3167 Main Street

Duluth, GA 30096

3. NAME AND ADDRESS OF LANDSCAPE ARCHITECT:

POND AND COMPANY

NORCROSS, GEORGIA 30092

PHONE: (678) 336-7740

FAX: (678) 336-7744

CONTACT: ANDREA GRECO, PLA

4. PRIOR TO COMMENCING LAND DISTURBANCE ACTIVITY, THE LIMITS OF LAND DISTURBANCE SHALL BE CLEARLY AND

ACCURATELY DEMARCATED WITH STAKES, RIBBONS, OR OTHER APPROPRIATE MEANS. THE LOCATION AND EXTENT OF ALL

AUTHORIZED DISTURBANCE SHALL BE DEMARCATED FOR THE DURATION OF THE CONSTRUCTION ACTIVITY. NO DISTURBANCE

SHALL OCCUR OUTSIDE THE LIMITS INDICATED ON THE DRAWINGS WITHOUT APPROVAL IN WRITING FROM THE CLIENT PROJECT

REPRESENTATIVE.

5. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE LAYOUT OF ALL CONSTRUCTION ELEMENTS, WITH SOME FIELD

ADJUSTMENTS AS NECESSARY BY THE LANDSCAPE ARCHITECT.

6. THE CONTRACTOR SHALL BE RESPONSIBLE FOR TEMPORARY AND PERMANENT GROUNDWATER CONTROL DURING

CONSTRUCTION, AS WELL AS PROVISIONS FOR CONTROLLING SURFACE WATER RUN-OFF, IN ORDER TO PREVENT PONDING IN

OPEN EXCAVATIONS AND POTENTIAL UNDERMINING OF PERMANENT CONSTRUCTION FEATURES.

7. ALL COST FOR EARTHWORK AND GRADING SHALL BE PAID FOR AT THE PRICE BID FOR GRADING COMPLETE -LUMP SUM. THE

CONTRACTOR WILL BE RESPONSIBLE FOR FURNISHING SUITABLE MATERIAL FOR THIS PROJECT, AND DISPOSE OF ANY

UNSUITABLE OR WASTE MATERIAL.

8. THE TOPOGRAPHIC INFORMATION HAS BEEN PROVIDED BY THE GWINNETT COUNTY G.I.S. DEPARTMENT. AND IS REFERENCED

TO THE GEORGIA STATE PLANE COORDINATE SYSTEM (WEST ZONE).

9. DEMOLITION DEBRIS SHALL BECOME PROPERTY OF THE CONTRACTOR AND WASTE SOILS, VEGETATION, AND OTHER

DELETERIOUS MATERIALS SHALL BE HAULED OFF-SITE AND BE DISPOSED OF AT AN APPROVED LOCATION IN ACCORDANCE WITH

LOCAL, STATE, AND FEDERAL REGULATIONS.

10. ALL TREE SAVE AREAS SHALL BE CLEARLY IDENTIFIED WITH FLAGGING AND/OR FENCING PRIOR TO COMMENCEMENT OF ANY

LAND DISTURBANCE. THE CONTRACTOR SHALL BE RESPONSIBLE FOR PERFORMING EARTHWORK OPERATIONS SO THAT NO

DAMAGE TO EXISTING TREES AND ROOT SYSTEMS OCCURS. TREE PROTECTION MEASURES SHALL BE COORDINATED WITH THE

LANDSCAPE ARCHITECT (REFER TO SPECIFICATIONS).

11. THE CONTRACTOR SHALL ENSURE THE POSITIVE AND ADEQUATE DRAINAGE IS MAINTAINED AT ALL TIMES WITHIN THE

PROJECT LIMITS. THIS MAY INCLUDE, BUT NOT LIMITED TO PLACEMENT OR RECONSTRUCTION OF EXISTING DRAINAGE

STRUCTURES THAT HAVE BEEN DAMAGED OF REMOVED, OR RE-GRADING AS REQUIRED BY THE ENGINEER. EXCEPT FOR THOSE

DRAINAGE ITEMS SHOWN AT SPECIFIC PAY ITEMS IN THE DETAILED ESTIMATE. NO SEPARATE PAYMENT WILL BE MADE FOR ANY

COST INCURRED TO COMPLY WITH THIS REQUIREMENT.

12. NO CONSTRUCTION ACTIVITY, STORAGE OF MATERIALS, OR PARKING VEHICLES IS ALLOWED WITHIN THE HIGHWAY CLEAR

ZONE WHICH IS EQUAL TO 14' FROM THE EDGE OF THE TRAVELED WAY OF THE LANES OF HWY 13.

13. PLANS SUPERSEDE SPECIFICATIONS.

14. CONTRACTOR TO PROVIDE TRAFFIC CONTROL MEASURES. TRAFFIC CONTROL MEASURES TO BE COORDINATED WITH GDOT

DISTRICT 1. NO LANE CLOSURES WILL BE ALLOWED AT ANY TIME FOR THIS PROJECT.

UTILITY COMPANIES:UTILITIES ARE LOCATED INTHE AREA. CONTACT 811 TOCONFIRM LOCATIONS.

NOTES1. INFORMATION REGARDING THE REPUTED PRESENCE, SIZE, CHARACTER, AND LOCATION OF EXISTING

UNDERGROUND UTILITIES AND STRUCTURES IS SHOWN HEREON. THERE IS NO CERTAINTY OF THE ACCURACY

OF THIS INFORMATION AND IT SHALL BE CONSIDERED IN THAT LIGHT BY THOSE USING THIS DRAWING. THE

LOCATION AND ARRANGEMENT OF UNDERGROUND UTILITIES AND STRUCTURES SHOWN HEREON MAY BE

INACCURATE AND UTILITIES AND STRUCTURES NOT SHOWN MAY BE ENCOUNTERED. THE OWNER, HIS

EMPLOYEES, HIS CONSULTANTS, HIS CONTRACTORS, AND / OR HIS AGENTS SHALL HEREBY DISTINCTLY

UNDERSTAND THAT THE SURVEYOR IS NOT RESPONSIBLE FOR THE CORRECTNESS OR SUFFICIENCY OF THIS

INFORMATION SHOWN HEREON AS TO SUCH UNDERGROUND INFORMATION.

2. RIGHT-OF-WAYS ARE BASED ON CENTERLINES OF EXISTING PATHS OF TRAVEL, UNLESS NOTED OTHERWISE.

3. ALL MATTERS PERTAINING TO TITLE AREA EXCEPTED.

4. IF EXCAVATION IS REQUIRED WITHIN 1000 FEET OF ANY EXISTING TRAFFIC SIGNAL, CONTACT STEVE KELLEY

WITH GDOT DISTRICT TRAFFIC OPERATIONS AT PHONE NUMBER (770) 718-5036 BEFORE ANY EXCAVATION

OCCURS. APPROPRIATE MEASURES SHALL BE TAKEN TO PROTECT THOSE WIRES DURING PERFORMANCE OF

THE WORK. THE WORK AUTHORIZED BY THIS PERMIT MAY NOT BEGIN UNTIL TRAFFIC SIGNAL ACTIVATION

WIRES/INTERCONNECT HAVE BEEN LOCATED AND IDENTIFIED. ANY TRAFFIC SIGNAL FACILITIES DAMAGED WILL

BE REPLACED BY THE PERMITTEE TO THE SATISFACTION OF THE DEPARTMENT.

LEGEND BY:

POND AND COMPANY

3500 PARKWAY LANE, SUITE 600

NORCORSS, GA 30092

PHONE: (678) 336-7740

FAX: (678) 336-7744

SURVEY IS COMPILED FROM THE FOLLOWING INFORMATION:

GWINNETT COUNTY G.I.S. DEPARTMENT (2010)

PROJECT NOTES

NOTE: IF CONFLICT BETWEEN

LEGENDS, CONTACT LANDSCAPE

ARCHITECT.

GENERAL NOTESL-001

Know what's

R

EROSION AND SEDIMENT CONTROL NOTESESPCP GENERAL NOTES:

The escape of sediment from the site shall be prevented by the installation of erosion and sediment control measures and

practices prior to, or concurrent with, land disturbing activities. Erosion control measures will be maintained at all times. If full

implementation of the approved plan does not provide for effective erosion control, additional erosion and sediment control

measures shall be implemented to control or treat the sediment source.

Buford Highway & Sugarloaf PkwyLandscape Improvements

POND AND COMPANY

3500 PARKWAY LANE SUITE 600

NORCROSS, GEORGIA 30092

(P) 678-336-7740 (F) 678-336-7744

SIGNATUREREQUESTED BYREVISIONSDATE

SHEETSTOTAL

NO.SHEET

Duluth Gateway

COPYRIGHT © 2010 BY POND & COMPANY. ALL RIGHTS RESERVED. NO

COPYING OR DUPLICATION OF THESE DOCUMENTS IS ALLOWED WITHOUT

THE EXPRESS WRITTEN AGREEMENT OF POND & COMPANY

73

Page 4: NORFOLK SOUTHERN RAILROAD BUFORD HIGHWAY / SR 13 …

S

F

S

F

LP-101

LANDSCAPE PLAN

4

Buford Highway & Sugarloaf PkwyLandscape Improvements

POND AND COMPANY

3500 PARKWAY LANE SUITE 600

NORCROSS, GEORGIA 30092

(P) 678-336-7740 (F) 678-336-7744

SIGNATUREREQUESTED BYREVISIONSDATE

SHEETSTOTAL

NO.SHEET

Duluth Gateway

COPYRIGHT © 2010 BY POND & COMPANY. ALL RIGHTS RESERVED. NO

COPYING OR DUPLICATION OF THESE DOCUMENTS IS ALLOWED WITHOUT

THE EXPRESS WRITTEN AGREEMENT OF POND & COMPANY

7

AARON'S BEARD ST. JOHNS WORT, 36" O.C.

LEGEND

REDBUD, AS SHOWN

VIRGINIA MAGNOLIA, AS SHOWN

SERVICEBERRY, AS SHOWN

FLORIDA JASMINE, 36" O.C.

(1) REDBUD

(1) TEDDY BEAR SOUTHERN MAGNOLIA

(3) REDBUD

(7) WASHINGTON HAWTHORNE

(5) TEDDY BEAR SOUTHERN MAGNOLIA

(3) REDBUD

EXISTING TREELINE

EXISTING TREELINE

(3) VIRGINIA MAGNOLIA

(47) VIRGINIA SWEETSPIRE

WASHINGTON HAWTHORNE, AS SHOWN

TEDDY BEAR MAGNOLIA, AS SHOWN

VIRGINIA SWEETSPIRE, 4' O.C.

G

D

O

T

C

L

E

A

R

Z

O

N

E

GD

OT

C

LE

AR

Z

ON

E

SUGARLOAF PARKWAY

BU

FO

RD

H

IG

HW

AY

NO

RF

OL

K S

OU

TH

ER

N R

AIL

RO

AD

(67) FLORIDA

JASMINE

14' LANDSCAPE SETBACK FOR

GDOT CLEAR ZONE

EXISTING GUARDRAIL

EXISTING GUARDRAIL

Clearing Note:

1. Contractor to remove trees under 4” caliper from the project site. If Contractor finds

trees 4” caliper or over in size within project limits, please notify Project Representative.

2. Soil Enhancements to be made within shrub and groundcover planting beds only.

(Areas where Jasmine, St.Johns Wort and Virginia Sweetspire are planted). Refer to Sheet

L-502 for information planting specs.

LIMITS OF MULCH

BEDS

LIMITS OF MULCH

BEDS

14' LANDSCAPE SETBACK FOR

GDOT CLEAR ZONE

14' LANDSCAPE

SETBACK FOR GDOT

CLEAR ZONE

BEDLINE LIMITS OF SOIL ENHANCEMENTS

EXISTING SIDEWALK

EXISTING SIDEWALK

(38) ST. JOHNS

WORT

(3) SERVICEBERRY

MULCH AREA BETWEEN SIDEWALK AND

PLANTING BEDS WITHIN LIMITS OF

WORK

S.R

. 13/ U

S R

T 23

Page 5: NORFOLK SOUTHERN RAILROAD BUFORD HIGHWAY / SR 13 …

LP-102

LANDSCAPE PLAN

5

Buford Highway & Sugarloaf PkwyLandscape Improvements

POND AND COMPANY

3500 PARKWAY LANE SUITE 600

NORCROSS, GEORGIA 30092

(P) 678-336-7740 (F) 678-336-7744

SIGNATUREREQUESTED BYREVISIONSDATE

SHEETSTOTAL

NO.SHEET

Duluth Gateway

COPYRIGHT © 2010 BY POND & COMPANY. ALL RIGHTS RESERVED. NO

COPYING OR DUPLICATION OF THESE DOCUMENTS IS ALLOWED WITHOUT

THE EXPRESS WRITTEN AGREEMENT OF POND & COMPANY

7

AARON'S BEARD ST. JOHNS WORT, 36" O.C.

LEGEND

REDBUD, AS SHOWN

VIRGINIA MAGNOLIA, AS SHOWN

SERVICEBERRY, AS SHOWN

FLORIDA JASMINE, 36" O.C.

(3) SERVICEBERRY

(1) TEDDY BEAR SOUTHERN MAGNOLIA

(1) REDBUD

(5) TEDDY BEAR SOUTHERN MAGNOLIA

EXISTING

TREELINE

EXISTING TREELINE

(3) VIRGINIA MAGNOLIA

WASHINGTON HAWTHORNE, AS SHOWN

TEDDY BEAR MAGNOLIA, AS SHOWN

VIRGINIA SWEETSPIRE, 4' O.C.

(3) REDBUD

(7) WASHINGTON HAWTHORNE

(3) REDBUD

14' LANDSCAPE SETBACK

FOR GDOT CLEAR ZONE

1

4

'

G

D

O

T

C

L

E

A

R

Z

O

N

E

14' G

DO

T C

LE

AR

Z

ON

E

SUGARLOAF PARKWAY

BU

FO

RD

H

IG

HW

AY

NO

RF

OL

K S

OU

TH

ER

N R

AIL

RO

AD

14' LANDSCAPE SETBACK FOR

GDOT CLEAR ZONE

(66) FLORIDA JASMINE

EXISTING GUARDRAIL

Clearing Note:

1. Contractor to remove trees under 4” caliper from the project site. If Contractor finds

trees 4” caliper or over in size within project limits, please notify Project Representative.

2. Soil Enhancements to be made within shrub and groundcover planting beds only.

(Areas where Jasmine, St.Johns Wort and Virginia Sweetspire are planted). Refer to Sheet

L-502 for information planting specs.

LIMITS OF MULCH BEDS

EXISTING GUARDRAIL

LIMITS OF MULCH

BEDS

BEDLINE LIMITS OF SOIL AMENDMENTS

EXISTING SIDEWALK

EXISTING SIDEWALK

(36) AARON'S BEARD

ST. JOHNS WORT

(46) VIRGINIA SWEETSPIRE

MULCH AREA BETWEEN SIDEWALKS AND PLANTING BEDS

WITHIN LIMITS OF WORK

S.R

. 13/ U

S R

T 23

Page 6: NORFOLK SOUTHERN RAILROAD BUFORD HIGHWAY / SR 13 …

L-501

LANDSCAPE DETAILS

6

Buford Highway & Sugarloaf PkwyLandscape Improvements

POND AND COMPANY

3500 PARKWAY LANE SUITE 600

NORCROSS, GEORGIA 30092

(P) 678-336-7740 (F) 678-336-7744

SIGNATUREREQUESTED BYREVISIONSDATE

SHEETSTOTAL

NO.SHEET

Duluth Gateway

COPYRIGHT © 2010 BY POND & COMPANY. ALL RIGHTS RESERVED. NO

COPYING OR DUPLICATION OF THESE DOCUMENTS IS ALLOWED WITHOUT

THE EXPRESS WRITTEN AGREEMENT OF POND & COMPANY

7

Duluth Gateway Landscape

PLANT MATERIAL SCHEDULE:

QTY.SIZE BOTANICAL NAME COMMON NAME SPACING NOTES

12 10-12' HT

Magnolia grandiflora 'Teddy Bear'

TEDDY BEAR MAGNOLIA AS SHOWN

6 8-10' HT

Magnolia virginiana

SWEETBAY MAGNOLIA AS SHOWN

14 3"-3.5" CAL

Cercis canadensis 'Appalachian Red'

APPALACHIAN RED REDBUD AS SHOWN

6 3"-3.5" CAL Amelanchier arborea SERVICEBERRY AS SHOWN

14 3"-3.5" CAL

Crataegus phaenopyrum

WASHINGTON HAWTHORNE AS SHOWN

94 3 Gal

Itea virginica

VIRGINIA SWEETSPIRE 4' O.C.

133 3 Gal Jasminum floridum FLORIDA JASMINE 36" O.C.

74 1 Gal Hypericum

calycinum

AARONS BEARD ST.

JOHNS WORT

36" O.C.

Page 7: NORFOLK SOUTHERN RAILROAD BUFORD HIGHWAY / SR 13 …

NOTE:

1. PLANS SUPERCEDE SPECIFICATIONS

A. MATERIALS

NUTRIENT GRADE COMPOST: QUALITY COMPOST MUST BE MANUFACTURED BY A COMPOSTER ENROLLED

IN THE UNITED STATES COMPOST COUNCIL'S (USCC) SEAL OF TESTING ASSURANCE (STA) PROGRAM.

1. COMPOST MUST MEET THE FOLLOWING PARAMETERS AS TESTED BY AN STA APPROVED LAB USING

THE TEST METHODS FOR EVALUATING COMPOST AND COMPOST MANUFACTURES METHOD.

2. PLANT NUTRIENTS %, DRY WEIGHT BASIS TMECC METHOD

NITROGEN >1.2 4.02D

PHOSPHORUS >0.50 CALC.

POTASSIUM >0.50 CALC.

CALCIUM >0.90 4.05

MAGNESIUM >0.20 4.05

ORGANIC MATTER CONTENT >50% 5.07-A

3. SOLUBLE SALTS DS/M (MMHOS/CM) <4.0 4.08-A

4. PARTICLE SIZE % UNDER 9.5 MM 95% OR GREATER 2.02-B

5. STABILITY INDICATOR (RESPIROMETRY)

CO2 EVOLUTION MG CO2-C/G OM/DAY <2 5.08-F777

6. MATURITY INDICATOR (BIOASSAY)

PERCENT EMERGENCE 85% OR GREATER 5.05-A

RELATIVE SEEDLING VIGOR 85% OR GREATER

7. SELECT PATHOGENS PASS STANDARD

(PASS/FAIL PER US EPA CLASS A STANDARD, 40 CFR 503.32(A) ) METHOD 9221E

NOTE: THE USE OF COMPOST WILL REDUCE FERTILIZER REQUIREMENTS. THE COMPOST GENERATOR

SHALL SUPPLY THE SPECIFIER WITH A NUTRIENT ANALYSIS TO DETERMINE THESE REQUIREMENTS.

B. CONSTRUCTION REQUIREMENTS

1. 4" OF COMPOST SHALL BE APPLIED OVER PLANTING BED AREA AT 50% INCLUSION RATE AND

UNIFORMLY INCORPORATED WITHIN THE FIRST 8" OF THE SOIL PROFILE.

2. WATER THOROUGHLY AFTER INSTALLATION.

C. BIOLOGICAL REQUIREMENTS FOR ORGANIC COMPOST INCLUDE:

1. TESTING SHALL BE DONE FOR ACTIVE BACTERIA, TOTAL BACTERIA, ACTIVE FUNGI, TOTAL FUNGI,

FLAGELLATES, AMOEBAE, CILIATES, TOTAL NEMATODES, ACTINO BACTERIA, PLAT AVAILABLE N SUPPLY

AND DETAILS ON THE NEMATODES FOUND INCLUDING TYPE, GENUS AND QUANTITY.

2. FLAGELLATES PRESENT: 10,000 / GRAM MINIMUM

3. AMOEBAE PRESENT: 10,000 / GRAM MINIMUM

4. CILIATES PRESENT: 10,000 / GRAM MINIMUM

5. TOTAL NEMATODES: 20 / GRAM

6. ORGANISM BIOMASS RATIOS SHALL BE IN THE RANGE OF:

A. TOTAL FUNGI TO TOTAL BACTERIA: 0.75 TO 1.5

B. ACTIVE FUNGI TO TOTAL FUNGI: 0.01 TO 0.1

C. ACTIVE BACTERIA TO TOTAL BACTERIA: 0.01 TO 0.1

D. ACTIVE FUNGI TO ACTIVE BACTERIA: 0.75 TO 1.5

D. MICROBIOLOGY MATERIAL TEST REPORTS: FOR COMPOST

1. COLLECT TWO CUPS OF COMPOST FROM PILE THAT WILL BE USED TO SUPPLY PROJECT. SAMPLES

SHALL BE COLLECTED IN A CLEAN PLASTIC CONTAINER AND SHIP IMMEDIATELY VIA NEXT DAY AIR TO

'SOIL FOODWEB OREGON' FOR FULL FOODWEB ANALYSIS. DO NOT FREEZE SAMPLES PRIOR TO SENDING.

ANALYSIS TO INCLUDE TOTAL BACTERIA / TOTAL FUNGI, ACTIVE BACTERIA / ACTIVE FUNGI, PROTOZOA,

NEMATODES, E. COLI, ELECTRICAL CONDUCTIVITY AND pH (COMPOST/BIOLOGICAL AMENDMENT - FULL

FOODWEB). COLLECT SAMPLES PER SAMPLING INSTRUCTIONS PROVIDED BY SOIL FOODWEB OREGON.

ORDER FORM FOR FOODWEB BIOLOGY REPORT CAN BE FOUND AT www.earthfort.com/lab-services.html 2.

ANALYSIS SHALL INCLUDE INTERPRETATION OF RESULTS AND RECOMMENDATIONS FOR CORRECTIVE

ACTION.

3. ANALYSIS SHOULD BE LESS THAN 15 DAYS OLD.

4. PRIOR TO PLANTING BUT AFTER MIXING COMPOST INTO EXISTING SOIL , SEND PLANTING SOIL SAMPLES

TO 'SOIL FOODWEB OREGON' FOR RECOMMENDATIONS ON SOIL AMENDMENTS FOR SHRUBS,

GROUNDCOVERS, TREES, AND TURF. SAMPLING LOCATIONS SHALL BE TAKEN IN A ZIG ZAG PATTERN

ACROSS SITE, AS RECOMMENDED BY THE UNIVERSITY OF GEORGIA COOPERATIVE EXTENSION

PUBLICATION C896 "SOIL TESTING HOME LAWNS, GARDENS, AND WILDLIFE FOOD PLOTS". COLLECT A

MINIMUM OF 8 SAMPLES PER JOB SITE ACRE AND MIX AS INDICATED. REFERENCE PUBLICATION C896 FOR

SAMPLING METHOD AND PROCEDURES. INCORPORATE SOIL AMENDMENTS AS NEEDED TO MEET

LABORATORY RECOMMENDATIONS.

L-502

LANDSCAPE DETAILS

7

Buford Highway & Sugarloaf PkwyLandscape Improvements

POND AND COMPANY

3500 PARKWAY LANE SUITE 600

NORCROSS, GEORGIA 30092

(P) 678-336-7740 (F) 678-336-7744

SIGNATUREREQUESTED BYREVISIONSDATE

SHEETSTOTAL

NO.SHEET

Duluth Gateway

COPYRIGHT © 2010 BY POND & COMPANY. ALL RIGHTS RESERVED. NO

COPYING OR DUPLICATION OF THESE DOCUMENTS IS ALLOWED WITHOUT

THE EXPRESS WRITTEN AGREEMENT OF POND & COMPANY

7

GENERAL PLANTING NOTES1. ALL PLANTS SHALL BE HEALTHY, VIGOROUS, FREE OF PESTS AND DISEASE.

2. ALL PLANTS SHALL BE CONTAINER-GROWN, OR BALLED AND BURLAPPED AS SPECIFIED.

3. ALL TREES SHALL BE STRAIGHT TRUNKED, FULL HEADED AND MEET ALL REQUIREMENTS SPECIFIED.

4. ALL PLANTS ARE SUBJECT TO THE APPROVAL OF THE DESIGN PROFESSIONAL BEFORE, DURING, AND AFTER INSTALLATION.

5. ALL TREES SHALL BE GUYED OR STAKED AS SHOWN, EXCLUDING WHIPS.

6. ALL PLANTS AND PLANTING AREAS SHALL BE COMPLETELY MULCHED AS SPECIFIED.

7. THE CONTRACTOR SHALL NOTIFY ALL NECESSARY UTILITY COMPANIES 72 HRS MINIMUM PRIOR TO DIGGING FOR FIELD

VERIFICATION OF ALL UNDERGROUND UTILITIES, AND OTHER ELEMENTS, AND COORDINATE WITH THE DESIGN PROFESSIONAL

PRIOR TO INITIATING OPERATIONS. THE CONTRACTOR SHALL AVOID DAMAGE TO ALL UTILITIES DURING THE COURSE OF

WORK.

8. THE CONTRACTOR IS RESPONSIBLE FOR REPAIRING ALL DAMAGE TO UTILITIES, STRUCTURES, SITE APPURTENANCES, ETC.

WHICH OCCURS AS A RESULT OF LANDSCAPE CONSTRUCTION.

9. THE CONTRACTOR IS RESPONSIBLE FOR VERIFYING ALL QUANTITIES SHOWN ON THESE PLANS BEFORE PRICING THE WORK.

10. THE DESIGN PROFESSIONAL SHALL APPROVE THE STAKED LOCATION OF ALL PLANT MATERIAL PRIOR TO INSTALLATION.

11. CONTRACTOR SHALL PROTECT ALL EXISTING PLANT MATERIALS INDICATED ON PLANS TO REMAIN. ALL PLANT MATERIAL

INDICATED TO REMAIN THAT IS DAMAGED BY THE CONTRACTOR SHALL BE REPLACED BY THE CONTRACTOR AT NO

ADDITIONAL COST TO THE OWNER WITH THE SAME SIZE, QUALITY, AND TYPE OF PLANT MATERIAL OR AS REQUIRED BY THE

LOCAL REVIEWING AUTHORITY, WHICHEVER HAS A GREATER RECOMPENSE VALUE.

12. THE CONTRACTOR SHALL PROVIDE ALL NECESSARY SAFETY MEASURES DURING CONSTRUCTION OPERATIONS TO PROTECT

THE PUBLIC ACCORDING TO ALL APPLICABLE CODES AND RECOGNIZED LOCAL PRACTICES.

13. THE CONTRACTOR SHALL REPORT ANY DISCREPANCIES BETWEEN THE CONSTRUCTION DRAWINGS AND FIELD CONDITIONS

TO THE DESIGN PROFESSIONAL PRIOR TO STARTING CONSTRUCTION. FOLLOW THE DESIGN PROFESSIONAL'S INSTRUCTIONS

ON RESOLVING ANY DISCREPANCIES.

14. THE CONTRACTOR IS RESPONSIBLE FOR MAINTAINING ALL PLANTING UNTIL FINAL ACCEPTANCE.

15. AFTER BEING DUG AT THE NURSERY SOURCE, ALL TREES IN LEAF SHALL BE ACCLIMATED FOR TWO (2) WEEKS UNDER A MIST

SYSTEM PRIOR TO INSTALLATION.

16. ANY PLANT MATERIAL WHICH DIES, TURNS BROWN, OR DEFOLIATES (PRIOR TO FINAL ACCEPTANCE OF WORK) SHALL BE

PROMPTLY REMOVED FROM THE SITE & REPLACED WITH MATERIAL OF THE SAME SPECIES, QUANTITY, SIZE AND MEETING ALL

PLANT LIST SPECIFICATIONS.

17. STANDARDS SET FORTH IN ' AMERICAN STANDARDS FOR NURSERY STOCK' REPRESENT GUIDELINE SPECIFICATIONS ONLY

AND CONSTITUTE MINIMUM QUALITY REQUIREMENTS FOR PLANT MATERIAL.

18. ALL SOD AND SEED TO BE AS SPECIFIED. TEMPORARY GRASS TO BE A COMBINATION OF ANNUAL RYE AND FESCUE SEED.

19. PLANT SYMBOLS ON THE LANDSCAPE PLAN SUPERCEDE QUANTITIES SHOWN IN THE PLANT LIST.

20. IN DETERMINING SIZE-GRADING FOR b&b TREES, CALIPER SHALL TAKE PRECEDENT OVER HEIGHT.

21. ALL PLANTING BEDS TO BE SUPPLEMENTED WITH 4" ORGANIC COMPOST MIX TILLED INTO SOIL DEPTH OF 8". ALL PLANTING

BEDS TO RECEIVE SHREDDED HARDWOOD MULCH PER DETAILS.

22. ACTION SUBMITTALS:

A. PRODUCT DATA: FOR EACH TYPE OF PRODUCT:

1. PLANT MATERIALS: INCLUDE QUANTITIES, SIZES, QUALITY AND SOURCES FOR PLANT MATERIALS.

2. PLANT PHOTOGRAPHS: INCLUDE COLOR PHOTOGRAPHS IN DIGITAL, MIN 150 DPI FORMAT OF THE REQUIRED SPECIES

AND SIZE OF PLANT MATERIAL AS IT WILL BE FURNISHED TO PROJECT. TAKE PHOTOGRAPHS FROM AN ANGLE

DEPICTING TRUE SIZE AND CONDITION OF THE TYPICAL PLANT TO BE FURNISHED. INCLUDE A SCALE ROD OR

OTHER MEASURING DEVICE IN EACH PHOTOGRAPH. FOR SPECIES WHERE MORE THAN 20 PLANTS ARE REQUIRED,

INCLUDE A MINIMUM OF THREE PHOTOGRAPHS SHOWING THE AVERAGE PLANT, THE BEST QUALITY PLANT, AND THE

WORST QUALITY PLANT TO BE FURNISHED. IDENTIFY EACH PHOTOGRAPH WITH THE FULL SCIENTIFIC NAME OF THE

PLANT, PLANT SIZE, AND NAME OF THE GROWING NURSERY.

B. SAMPLES FOR VERIFICATION:

1. ORGANIC COMPOST MULCH: 1-PINT (.5-L) VOLUME OF EACH ORGANIC MULCH REQUIRED; IN SEALED PLASTIC BAGS

LABELED WITH COMPOSITION OF MATERIALS BY PERCENTAGE OF WEIGHT AND SOURCE OF MULCH. EACH SAMPLE

SHALL BE TYPICAL OF THE LOT OF THE MATERIAL TO BE FURNISHED; PROVIDE AN ACCURATE REPRESENTATION OF

COLOR, TEXTURE AND ORGANIC MAKEUP.

23. WARRANTY: CONTRACTOR TO PROVIDE WARRANTY.

A. SPECIAL WARRANTY: INSTALLER AGREES TO REPAIR OR REPLACE PLANTINGS & ACCESSORIES THAT FAIL IN MATERIALS,

WORKMANSHIP OR GROWTH WITHIN SPECIFIED WARRANTY PERIOD.

i. FAILURES INCLUDE BUT ARE NOT LIMITED TO, THE FOLLOWING:

a. DEATH AND UNSATISFACTORY GROWTH, EXCEPT FOR DEFECTS RESULTING FROM ABUSE, LACK OF ADEQUATE

MAINTENANCE, OR NEGLECT BY OWNER.

b. STRUCTURAL FAILURES INCLUDING PLANTINGS FALLING OR BLOWING OVER.

c. FAULTY PERFORMANCE OF TREE STABILIZATION AND TREE GRATES.

d. DETERIORATION OF METALS, METAL FINISHES, AND OTHER MATERIALS BEYOND NORMAL WEATHERING.

B. WARRANTY PERIOD FROM DATE OF SUBSTANTIAL COMPLETION:

i. TREES, SHRUBS, VINES AND ORNAMENTAL GRASSES: 12 MONTHS.

ii. GROUND COVERS, BIENNIALS, PERENNIALS AND OTHER PLANTS:12 MONTHS

C. INCLUDE THE FOLLOWING REMEDIAL ACTIONS AS A MINIMUM:

i. IMMEDIATELY REMOVE DEAD PLANTS AND REPLACE UNLESS REQUIRED TO PLANT IN THE SUCCEEDING PLANTING

SEASON.

ii. REPLACE PLANTS THAT ARE MORE THAN 25 PERCENT DEAD OR IN AN UNHEALTHY CONDITION AT THE END OF THE

WARRANTY PERIOD.

iii. A LIMIT OF ONE REPLACEMENT OF EACH PLANT IS REQUIRED EXCEPT FOR LOSSES OR REPLACEMENTS DUE TO

FAILURE TO COMPLY WITH REQUIREMENTS.

ORGANIC COMPOST