+ All Categories
Home > Documents > Ntpc Deposit

Ntpc Deposit

Date post: 06-Apr-2018
Category:
Upload: juhi-bhatnagar
View: 228 times
Download: 0 times
Share this document with a friend

of 64

Transcript
  • 8/3/2019 Ntpc Deposit

    1/64

    AN ORIENTATION

    REPORT ON

    INDUSTRIAL TRAINING AT

    Badarpur Thermal Power Station(BTPS)

    NTPC Badarpur Division

    New Delhi

    Submitted by

    Arjit Agarwal

    B.Tech III Year

    Department of Electrical Engineering

    Malaviya National Institute Of Technology

    Jaipur

  • 8/3/2019 Ntpc Deposit

    2/64

    CERTIFICATE

    TO WHOMSOEVER IT MAY CONCERN

    I hereby certify that Arjit Agarwal Roll No 2008UEE107 of Malaviya National

    Institute Of Technology,Jaipur has undergone 2 months industrial training from 16May 2010 to 14 July 2011 at our organization to fulfill the requirements for the

    award of degree of B.tech Electrical Engineering. She worked on Power Plant

    Overview project during the training. During his tenure with us we found himsincere and hard working.

    We wish him a great success in the future.

    Training Incharge

    NTPC Badarpur

    NEW DELHI

  • 8/3/2019 Ntpc Deposit

    3/64

    ACKNOWLEDGEMENTI am extremely thankful to my college for giving me an opportunity to undergo

    industrial training in such a wonderful enterprise. I am grateful to Mr. Rohit

    Goyal(Head of Dept. of training & placement,MNIT Jaipur) for his help and support.

    I am very much indebted to NTPC Badarpur for providing me such a wonderful 60

    days orientation programme to give us an insight and practical knowledge about our

    subject.

    They gave a new horizon to the industrial training in such a wonderful environment.

    The help rendered by Ms Rachana Singh Bhal, Supervisor, National ThermalPower Corporation for experimentation is greatly acknowledged.

    The author would like to express a deep sense of gratitude and thanks profusely to Mr.

    G.D. Sharma,Training Coordinator, without the wise counsel and able guidance, itwould have been impossible to complete the training successfully.

    My special thanks to Mr. M.K. Chopra, Mr. Rajat Garg,Mr. Saurabh Garg,Mr. RajeshGarg,Mr. Maha Singh,Mr. Rajarshi Sharma,Mr. B.P. Sinha and Ms. Usha Kumari of

    EMD-1 and EMD-2 for enlightening us with their knowledge and assigning

    technicians for plant visit.

    In the last I would like to express my gratitude to all the engineers and technicians,

    who gave me the possibility to complete my training successfully.

  • 8/3/2019 Ntpc Deposit

    4/64

    Training at BTPS

    I was appointed to do nine-weeks training at this esteemed organization from 16th

    May to 14th July 2011. In these nine weeks I was assigned to visit various division of

    the plant which were:-

    1. Electrical maintenance division I (EMD-I)2. Electrical maintenance division II (EMD-II)

    This nine-weeks training was a very educational adventure for me. It was really

    amazing to see the plant by your self and learn how electricity, which is one of our

    daily requirements of life, is produced.

    This report has been made by self-experience at BTPS. The material in this report has

    been gathered from my textbooks, senior student report, and trainer manual provided

    by training department. The specification & principles are at learned by me from the

    employee of each division of BTPS.

  • 8/3/2019 Ntpc Deposit

    5/64

    TABLE OF CONTENTS

    1. Introduction to the Company

    a. About the Company

    b. Vision

    c. Strategiesd. Evolution

    2. Introduction to the Project

    3. Project Report

    a. Operationi. Introduction

    ii. Steam Boiler

    iii. Steam Turbineiv. Turbine Generator

    b. EMD Ii. Coal Handling Plant

    ii. Motorsiii. Switchgear

    iv. High Tension Switchgearv. Direct On Line Starterc. EMD II

    i. Generatorii. Protection

    iii. Transformer

    4.Last word

    5.References

  • 8/3/2019 Ntpc Deposit

    6/64

    INTRODUCTION TO

    THE COMPANY

    About the CompanyVision

    StrategiesEvolution

    National Thermal Power Corporation Limited

    Badarpur Thermal Power Station

    Badarpur, New Delhi

  • 8/3/2019 Ntpc Deposit

    7/64

    ABOUT THE COMPANY

    NTPC, the largest power Company in India, was setup in 1975 to accelerate power developmentin the country. It is among the worlds largest and most efficient power generation companies. In

    Forbes list of Worlds 2000 Largest Companies for the year 2007, NTPC occupies 411th place.It

    is a MAHARATNAcompany

    A View of Badarpur Thermal Power Station,New Delhi

    Wagons bringing coal

    NTPC has installed capacity of 29,394 MW. It has 15 coal based power stations (23,395 MW), 7gas based power stations (3,955 MW) and 4 power stations in Joint Ventures (1,794 MW). The

    company has power generating facilities in all major regions of the country. It plans to be a75,000 MW company by 2017.

    NTPC has gone beyond the thermal power generation. It has diversified into hydro power, coalmining, power equipment manufacturing, oil & gas exploration, power trading & distribution.

    NTPC is now in the entire power value chain and is poised to become an Integrated PowerMajor.

  • 8/3/2019 Ntpc Deposit

    8/64

    NTPC's share on 31 Mar 2008 in the total installed capacity of the country was 19.1% and it

    contributed 28.50% of the total power generation of the country during 2007-08. NTPC has set

    new benchmarks for the power industry both in the area of power plant construction andoperations.

    With its experience and expertise in the power sector, NTPC is extending consultancy servicesto various organizations in the power business. It provides consultancy in the area of power

    plant constructions and power generation to companies in India and abroad.In November 2004, NTPC came out with its Initial Public Offering (IPO) consisting of 5.25% as

    fresh issue and 5.25% as offer for sale by Government of India. NTPC thus became a listedcompany with Government holding 89.5% of the equity share capital and rest held by

    Institutional Investors and Public.

    The issue was a resounding success. NTPC is among the largest five companies in India in terms

    of market capitalization.

    Recognizing its excellent performance and vast potential, Government of the India has identifiedNTPC as one of the jewels of Public Sector 'Navratnas'- a potential global giant. Inspired by itsglorious past and vibrant present, NTPC is well on its way to realize its vision of being

    "A world class integrated power major, powering India's growth, with increasing global

    presence".

    Coal Based Power Stations

    With 15 coal based power stations, NTPC is the largest thermal power generating company in the

    country. The company has a coal based installed capacity of 27,535 MW.

    COAL BASED(Owned

    by NTPC)STATE

    COMMISSIONED

    CAPACITY(MW)

    1. Singrauli Uttar Pradesh 2,000

  • 8/3/2019 Ntpc Deposit

    9/64

    2. Korba Chhattisgarh 2,600

    3. Ramagundam Andhra Pradesh 2,600

    4. Farakka West Bengal 2,100

    5. Vindhyachal Madhya Pradesh 3,260

    6. Rihand Uttar Pradesh 2,000

    7. Kahalgaon Bihar 2,340

    8. NCTPP, Dadri Uttar Pradesh 1,820

    9. Talcher Kaniha Orissa 3,000

    10. Feroze Gandhi, Unchahar Uttar Pradesh 1,050

    11. Talcher Thermal Orissa 460

    12. Simhadri Andhra Pradesh 1,500

    13. Tanda Uttar Pradesh 440

    14. Badarpur Delhi 705

    15. Sipat Chhattisgarh 1,660

    Total 27,535

    Operations

    In terms of operations, NTPC has always been considerably above the national average. The

    availability factor for coal based power stations has increased from 89.32% in 1998-99 to 91.62% in

    2010-11, which compares favourably with international standards. The PLF has increased from

    76.6% in 1998-99 to 88.29% during the year 2010-11.

  • 8/3/2019 Ntpc Deposit

    10/64

    The table below shows that while the installed capacity has increased by 73.33% in the last twelve

    years the generation has increased by 101.39%

    VISION

    A world class integrated power major, powering India's growth with increasing global presence.

    To be the worlds largest and best power producer, powering Indias growth.

    MISSION

    Develop and provide reliable power related products and services at competitive prices,

    integrating multiple energy resources with innovative & Eco-friendly technologies andcontribution to the society.

    Core Values - BCOMITBusiness ethicsCustomer Focus

    Organizational & Professional PrideMutual Respect & Trust

    Innovation & Speed

    Total Quality for Excellence

    STRATEGIES-

    Technological Initiatives

    Introduction of steam generators (boilers) of the size of 800 MW

    Integrated Gasification Combined Cycle (IGCC) Technology

    Launch of Energy Technology Center -A new initiative for development of technologies

    with focus on fundamental R&D

    The company sets aside up to 0.5% of the profits for R&D

  • 8/3/2019 Ntpc Deposit

    11/64

    Roadmap developed for adopting Clean DevelopmentMechanism to help get / earn Certified Emission Reduction

    Corporate Social Responsibility

    As a responsible corporate citizen NTPC has taken up number of CSR initiatives

    NTPC Foundation formed to address Social issues at national levelNTPC has framed Corporate Social Responsibility Guidelines committing up to 0.5% of net

    profit annually for Community Welfare Measures on perennial basis

    The welfare of project affected persons and the local population around NTPC projects

    are taken care of through well drawn Rehabilitation and Resettlement policies

    The company has also taken up distributed generation for remote rural areas

    Environment Management

    All stations of NTPC are ISO 14001 certified

    Various groups to care of environmental issuesThe Environment Management Group

    Ash Utilization DivisionAfforestation Group

    Centre for Power Efficiency & Environment ProtectionGroup on Clean Development Mechanism

    NTPC is the second largest owner of trees in the country after the Forest department.

    Partnering government in various initiatives

    Consultant role to modernize and improvise several plants across the country

    Disseminate technologies to other players in the sector

    Consultant role Partnership in Excellence Programme for improvement of PLF of 15

    Power Stations of SEBs.

    Rural Electrification work under Rajiv Gandhi Grameen Vidyutikaran Yojana

    NTPC BADARPUR

    Installed capacity720 MW

    Derated Capacity705 MW LocationNew DelhiCoal SourceJharia Coal Fields Water SourceAgra Canal Beneficiary StatesDelhi

    Unit Sizes3X95 MW

    2X210 MW

    UnitsCommissionedUnit I- 95 MW - July 1973

    Unit II- 95 MW August 1974

    Unit III- 95 MW March 1975

    Unit IV - 210 MW December 1978

    Unit V - 210 MW - December 1981

    International Assistance Ownership of BTPS was transferred to NTPC with effect from

    01.06.2006 through GOIs Gazette Notification.

  • 8/3/2019 Ntpc Deposit

    12/64

    EVOLUTION

    1975-NTPC was set up in 1975 with 100% ownership by the Government ofIndia. In the last30 years, NTPC has grown into the largest power utility in India.

    1997-In 1997, Government of India granted NTPC status of Navratna being one of the ninejewels of India, enhancing the powers to the Board of Directors.

    2004-NTPC became a listed company with majority Government ownership of 89.5%.NTPCbecomes third largest by Market Capitalization of listed companies

    2005-The company rechristened as NTPC Limited in line with its changing business portfolioand transforms itself from a thermal power utility to an integrated power utility.

    2008-National Thermal Power Corporation is the largest power generation company in India.Forbes Global 2000 for 2008 ranked it 411th in the world.

    2009- 3000MW installed capacity mark crossed

    2010-Joint Venture Agreement executed between NTPC and NPCIL

  • 8/3/2019 Ntpc Deposit

    13/64

    INTRODUCTION TOTHEMAL POWER

    PLANT

    Introduction

    Classification

    Functioning

  • 8/3/2019 Ntpc Deposit

    14/64

    INTRODUCTION

    Power Station (also referred to as generating station or power plant) is an industrial facility for

    the generation of electric power. Some prefer to use the term energy center because it more

    accurately describes what the plants do, which is the conversion of other forms of energy, like

    chemical energy, gravitational potential energy or heat energy into electrical energy.

    A coal-fired Thermal Power Plant

    At the center of nearly all power stations is a generator, a rotating machine that converts

    mechanical energy into electrical energy by creating relative motion between a magnetic field

    and a conductor. The energy source harnessed to turn the generator varies widely. It depends

    chiefly on what fuels are easily available and the types of technology that the power company has

    access to.

    In thermal power stations, mechanical power is produced by a heat engine, which transforms

    thermal energy, often from combustion of a fuel, into rotational energy. Most thermal power

    stations produce steam, and these are sometimes called steam power stations. About 80% of allelectric power is generated by use of steam turbines. Not all thermal energy can be transformed

    to mechanical power, according to the second law of thermodynamics. Therefore, there is always

    heat lost to the environment. If this loss is employed as useful heat, for industrial processes ordistrict heating, the power plant is referred to as a cogeneration power plant or CHP (combined

    heat-and-power) plant. In countries where district heating is common, there are dedicated heatplants called heat-only boiler stations. An important class of power stations in the Middle East

    uses byproduct heat for desalination of water.

  • 8/3/2019 Ntpc Deposit

    15/64

    CLASSIFICATIONBy fuel

    Nuclear power plants use a nuclear reactor's heat to operate a steam turbine generator.

    Fossil fuelled power plants may also use a steam turbine generator or in the case of

    natural gas fired plants may use a combustion turbine.

    Geothermal power plants use steam extracted from hot underground rocks.

    Renewable energy plants may be fuelled by waste from sugar cane, municipal solidwaste, landfill methane, or other forms of biomass.

    In integrated steel mills, blast furnace exhaust gas is a low-cost, although low-energydensity,fuel.

    Waste heat from industrial processes is occasionally concentrated enough to use forpower generation, usually in a steam boiler and turbine.

    By prime mover

    Steam turbine plants use the dynamic pressure generated by expanding steam to turn the

    blades of a turbine. Almost all large non-hydro plants use this system.

    Gas turbine plants use the dynamic pressure from flowing gases to directly operate the

    turbine. Natural-gas fuelled turbine plants can start rapidly and so are used to supply

    "peak" energy during periods of high demand, though at higher cost than base-loaded

    plants. These may be comparatively small units, and sometimes completely unmanned,

    being remotely operated. This type was pioneered by the UK, Prince town being the

    world's first, commissioned in 1959.

    Combined cycle plants have both a gas turbine fired by natural gas, and a steam boiler

    and steam turbine which use the exhaust gas from the gas turbine to produce electricity.

    This greatly increases the overall efficiency of the plant, and many new base load powerplants are combined cycle plants fired by natural gas.

    Internal combustion Reciprocating engines are used to provide power for isolated communitiesand are frequently used for small cogeneration plants. Hospitals, office

    buildings, industrial plants, and other critical facilities also use them to provide backuppower in case of a power outage. These are usually fuelled by diesel oil, heavy oil,

    natural gas and landfill gas.

    Micro turbines, Sterling engine and internal combustion reciprocating engines are low

    cost solutions for using opportunity fuels, such as landfill gas, digester gas from water

    treatment plants and waste gas from oil production.

  • 8/3/2019 Ntpc Deposit

    16/64

    FUNCTIONINGFunctioning of thermal power plant:

    In a thermal power plant, one of coal, oil or natural gas is used to heat the boiler to convert the

    water into steam. The steam is used to turn a turbine, which is connected to a generator. When

    the turbine turns, electricity is generated and given as output by the generator, which is then

    supplied to the consumers through high-voltage power lines.

    Detailed process of power generation in a thermal power plant:

    1) Water intake: Firstly, water is taken into the boiler through a water source. If water isavailable in a plenty in the region, then the source is an open pond or river. If water is scarce,then

    it is recycled and the same water is used over and over again.2) Boiler heating: The boiler is heated with the help of oil, coal or natural gas. A furnace is used

    to heat the fuel and supply the heat produced to the boiler. The increase in temperature helps inthe transformation of water into steam.

    3) Steam Turbine: The steam generated in the boiler is sent through a steam turbine. Theturbine has blades that rotate when high velocity steam flows across them. This rotation of

    turbine blades is used to generate electricity.4) Generator: A generator is connected to the steam turbine. When the turbine rotates, the

    generator produces electricity which is then passed on to the power distribution systems.

    5) Special mountings: There is some other equipment like the economizer and air pre-heater.

    An economizer uses the heat from the exhaust gases to heat the feed water. An air pre-heater

    heats the air sent into the combustion chamber to improve the efficiency of the combustion

    process.

    6) Ash collection system: There is a separate residue and ash collection system in place to collect

    all the waste materials from the combustion process and to prevent them from

    escaping into the atmosphere.

    There are various other monitoring systems and instruments in place to keep track of the

    functioning of all the devices.

  • 8/3/2019 Ntpc Deposit

    17/64

    PROJECT

    REPORT

    OPERATION

    EMD I

    EMD II

  • 8/3/2019 Ntpc Deposit

    18/64

    Module I

    OPERATION

    Introduction

    Steam Generator or Boiler

    Steam Turbine

    Electric Generator

  • 8/3/2019 Ntpc Deposit

    19/64

    IntroductionThe operating performance of NTPC has been considerably above the national average. The

    availability factor for coal stations has increased from 85.03 % in 1997-98 to 90.09 % in 2006-

    07, which compares favourably with international standards. The PLF has increased from 75.2%

    in 1997-98 to 89.4% during the year 2006-07 which is the highest since the inception of NTPC.

    Operation Room of Power Plant

    In a Badarpur Thermal Power Station, steam is produced and used to spin a turbine that operates

    a generator. Water is heated, turns into steam and spins a steam turbine which drives an electrical

    generator. After it passes through the turbine, the steam is condensed in a condenser; this is

    known as a Rankine cycle. The electricity generated at the plant is sent to consumers through

    high-voltage power lines.

    The Badarpur Thermal Power Plant has Steam Turbine-Driven Generators which has a collective

    capacity of 705MW. The fuel being used is Coal which is supplied from the Jharia Coal Field inJharkhand. Water supply is given from the Agra Canal.Table: Capacity of Badarpur Thermal Power Station, New Delhi

    Sr.No. Capacity No. No.of Generators Total Capacity

    1. 210MW 2 420MW

    2. 95MW 3 285MW

    Total 705MW

    There are basically three main units of a thermal power plant:

    1. Steam Generator or Boiler

    2. Steam Turbine

    3. Electric GeneratorWe have discussed about the processes of electrical generation further.A complete detailed description of the three units is given further.

  • 8/3/2019 Ntpc Deposit

    20/64

    Typical Diagram of a Coal based Thermal

    Power Plant

    1. Cooling tower 2. Cooling water

    pump

    3. Transmission line (3-

    phase)

    4. Unit transformer (3-

    phase)

    5. Electric generator

    (3-phase)

    6. Low pressure turbine

    7. Condensate

    extraction pump

    8. Condensor 9. Intermediate

    pressure turbine

    10. Steam governor

    valve

    11. High pressure

    turbine

    12. Deaerator

    13. Feed heater 14. Coal conveyor 15. Coal hopper

    16. Pulverised fuel

    mill

    17. Boiler drum 18. Ash hopper

  • 8/3/2019 Ntpc Deposit

    21/64

    19. Superheater 20. Forced draught

    fan

    21. Reheater

    22. Air intake 23. Economiser 24. Air preheater

    25. Precipitator 26. Induced draught 27. Chimney Stack

    Coal is conveyed (14) from an external stack and ground to a very fine powder by large metal

    spheres in the pulverised fuel mill (16). There it is mixed with preheated air (24) driven by the

    forced draught fan (20). The hot air-fuel mixture is forced at high pressure into the boiler whereit rapidly ignites. Water of a high purity flows vertically up the tube-lined walls of the

    boiler,where it turns into steam, and is passed to the boiler drum, where steam is separated fromany

    remaining water. The steam passes through a manifold in the roof of the drum into the pendantsuperheater (19) where its temperature and pressure increase rapidly to around 200 bar and

    540C, sufficient to make the tube walls glow a dull red. The steam is piped to the high pressureturbine (11), the first of a three-stage turbine process. A steam governor valve (10) allows for

    both manual control of the turbine and automatic set-point following. The steam is exhausted

    from the high pressure turbine, and reduced in both pressure and temperature, is returned to the

    boiler reheater (21). The reheated steam is then passed to the intermediate pressure turbine

    (9),and from there passed directly to the low pressure turbine set (6). The exiting steam, now a

    little above its boiling point, is brought into thermal contact with cold water (pumped in from the

    cooling tower) in the condensor (8), where it condenses rapidly back into water, creating near

    vacuum-like conditions inside the condensor chest. The condensed water is then passed by a feed

    pump (7) through a deaerator (12), and pre-warmed, first in a feed heater (13) powered by steamdrawn from the high pressure set, and then in the economiser (23), before being returned to the

    boiler drum. The cooling water from the condensor is sprayed inside a cooling tower (1),creating

    a highly visible plume of water vapor, before being pumped back to the condensor (8)in cooling

    water cycle.The three turbine sets are sometimes coupled on the same shaft as the three-phase

    electrical generator (5) which generates an intermediate level voltage (typically 20-25 kV). Thisis stepped up by the unit transformer (4) to a voltage more suitable for transmission (typically

    250-500 kV)and is sent out onto the three-phase transmission system (3).Exhaust gas from theboiler is drawn by the induced draft fan (26) through an electrostatic precipitator (25) and is then

    vented through the chimney stack (27).

    Steam Generator or Boiler

    The boiler is a rectangular furnace about 50 ft (15 m) on a side and 130 ft (40 m) tall. Its wallsare made of a web of high pressure steel tubes about 2.3 inches (60 mm) in diameter.

    Pulverized coal is air-blown into the furnace from fuel nozzles at the four corners and it rapidly

    burns, forming a large fireball at the center. The thermal radiation of the fireball heats the water

    that circulates through the boiler tubes near the boiler perimeter. The water circulation rate in theboiler is three to four times the throughput and is typically driven by pumps. As the water in the

    boiler circulates it absorbs heat and changes into steam at 700 F (370 C) and 3,200 psi(22.1MPa). It is separated from the water inside a drum at the top of the furnace. The saturated

    steam is introduced into superheat pendant tubes that hang in the hottest part of the combustion

  • 8/3/2019 Ntpc Deposit

    22/64

    gases as they exit the furnace. Here the steam is superheated to 1,000 F (540 C) to prepare it forthe turbine.The steam generating boiler has to produce steam at the high purity, pressure and

    temperaturerequired for the steam turbine that drives the electrical generator. The generator includes the

    economizer, the steam drum, the chemical dosing equipment, and the furnace with its steam

    generating tubes and the superheater coils. Necessary safety valves are located at suitable points

    to avoid excessive boiler pressure. The air and flue gas path equipment include: forced draft(FD)fan, air preheater (APH), boiler furnace, induced draft (ID) fan, fly ash collectors(electrostatic

    precipitator)and the flue gas stack.

    Schematic diagram of a coal-fired power plant steam generator

    For units over about 210 MW capacity, redundancy of key components is provided by installing

    duplicates of the FD fan, APH, fly ash collectors and ID fan with isolating dampers.

    Boiler Furnace and Steam Drum

    Once water inside the boiler or steam generator, the process of adding the latent heat ofvaporization or enthalpy is underway. The boiler transfers energy to the water by the chemicalreaction of burning some type of fuel.The water enters the boiler through a section in the

    convection pass called the economizer. From the economizer it passes to the steam drum. Oncethe water enters the steam drum it goes down,the down comers to the lower inlet water wall

    headers. From the inlet headers the water rises through the water walls and is eventually turnedinto steam due to the heat being generated by the burners located on the front and rear water

    walls (typically). As the water is turned into steam/vapor in the water walls, the steam/vapor onceagain enters the steam drum.

  • 8/3/2019 Ntpc Deposit

    23/64

    External View of an Industrial Boiler at Badarpur Thermal Power Station, New Delhi

    The steam/vapour is passed through a series of steam and water separators and then dryers inside

    the steam drum. The steam separators and dryers remove the water droplets from the steam andthe cycle through the water walls is repeated. This process is known as natural circulation.The

    boiler furnace auxiliary equipment includes coal feed nozzles and igniter guns, soot blowers,water lancing and observation ports (in the furnace walls) for observation of the furnace interior.

    Furnace explosions due to any accumulation of combustible gases after a trip-out

    are avoided by flushing out such gases from the combustion zone before igniting the coal.The

    steam drum (as well as the superheater coils and headers) have air vents and drains needed

    for initial startup. The steam drum has an internal device that removes moisture from the wet

    steam entering the drum from the steam generating tubes. The dry steam then flows into the

    superheater coils.

    Fuel Preparation System

    In coal-fired power stations, the raw feed coal from the coal storage area is first crushed into

    small pieces and then conveyed to the coal feed hoppers at the boilers. The coal is next

    pulverized into a very fine powder. The pulverizers may be ball mills, rotating drum grinders, orother types of grinders.

  • 8/3/2019 Ntpc Deposit

    24/64

    Boiler Side of the Badarpur Thermal Power Station, New Delhi

    Fuel Firing System and Igniter System

    From the pulverized coal bin, coal is blown by hot air through the furnace coal burners at an

    angle which imparts a swirling motion to the powdered coal to enhance mixing of the coal

    powder with the incoming preheated combustion air and thus to enhance the combustion.To

    provide sufficient combustion temperature in the furnace before igniting the powdered coal,the

    furnace temperature is raised by first burning some light fuel oil or processed natural gas (by

    using auxiliary burners and igniters provide for that purpose).

    A

    ir PathExternal fans are provided to give sufficient air for combustion. The forced draft fan takes air

    from the atmosphere and, first warming it in the air preheater for better combustion, injects it viathe air nozzles on the furnace wall.The induced draft fan assists the FD fan by drawing out

    combustible gases from the furnace,maintaining a slightly negative pressure in the furnace.At thefurnace outlet, and before the furnace gases are handled by the ID fan, fine dust carried by the

    outlet gases is removed to avoid atmospheric pollution. This is an environmental limitationprescribed by law, and additionally minimizes erosion of the ID fan.

    Auxiliary Systems-

    Fly Ash Collection

    Fly ash is captured and removed from the flue gas by electrostatic precipitators located at the

    outlet of the furnace and before the induced draft fan.The fly ash is periodically removed from

    the collection hoppers below the precipitators . Generally, the fly ash is pneumatically

    transported to storage silos for subsequent

    transport by trucks or railroad cars.

  • 8/3/2019 Ntpc Deposit

    25/64

    Bottom Ash Collection and DisposalAt the bottom of every boiler, a hopper has been provided for collection of the bottom ash from

    the bottom of the furnace. This hopper is always filled with water to quench the ash and clinkersfalling down from the furnace.Some arrangement is included to crush the clinkers and for

    conveying the crushed clinkers and bottom ash to a storage site.

    Boiler Make-up Water Treatment Plant and StorageSince there is continuous withdrawal of steam and continuous return of condensate to the

    boiler,losses due to blow-down and leakages have to be made up for so as to maintain the desired

    water level in the boiler steam drum. For this, continuous make-up water is added to the boiler

    water system. The impurities in the raw water input to the plant generally consist of calcium and

    magnesium salts which impart hardness to the water. Hardness in the make-up water to the boiler

    will form deposits on the tube water surfaces which will lead to overheating and failure of the

    tubes. Thus, the salts have to be removed from the water and that is done by a water

    demineralising treatment plant (DM). A DM plant generally consists of cation, anion and mixed

    bed exchangers. The final water from this process consists essentially of hydrogen ions and

    hydroxide ions which is the chemical composition of pure water. The DM water, being very pure, becomes highly corrosive once it absorbs oxygen from the atmosphere because of its very high

    affinity for oxygen absorption. The capacity of the DM plant is dictated by the type and quantityof salts in the raw water input.

    Ash Handling System at Badarpur Thermal Power Station, New Delhi

    However, some storage is essential as the DM plant may be down for maintenance. For this

    purpose, a storage tank is installed from which DM water is continuously withdrawn for boilermake-up.The storage tank for DM water is made from materials not affected by corrosive

    water,such as PVC.DM water make-up is generally added at the steam space of the surface

    condenser (i.e., the vacuum side). This arrangement not only sprays the water but also DM water

    gets deaerated, with the dissolved gases being removed by the ejector

    of the condenser itself.

  • 8/3/2019 Ntpc Deposit

    26/64

    Steam Turbine

    Steam turbines are used in all of our major coal fired power stations to drive the generators oralternators, which produce electricity. The turbines themselves are driven by steam generated in

    'Boilers' or 'Steam Generators' as they are sometimes called.

    Energy in the steam after it leaves the boiler is converted into rotational energy as it passes

    through the turbine. The turbine normally consists of several stages with each stage consisting ofa stationary blade (or nozzle) and a rotating blade. Stationary blades convert the potential energy

    of the steam (temperature and pressure) into kinetic energy (velocity) and direct the flow onto

    the rotating blades. The rotating blades convert the kinetic energy into forces, caused by pressure

    drop, which results in the rotation of the turbine shaft. The turbine shaft is connected to a

    generator, which produces the electrical energy. The rotational speed is 3000 rpm for Indian

    System (50 Hz) systems and 3600 for American (60 Hz) systems.

    In a typical larger power stations, the steam turbines are split into three separate stages, the first

    being the High Pressure (HP), the second the Intermediate Pressure (IP) and the third the Low

    Pressure (LP) stage, where high, intermediate and low describe the pressure of the steam. After

    the steam has passed through the HP stage, it is returned to the boiler to be re-heated to itsoriginal temperature although the pressure remains greatly reduced. The reheated steam then

    passes through the IP stage and finally to the LP stage of the turbine.Steam turbines can be configured in many different ways. Several IP or LP stages can be

    incorporated into the one steam turbine. A single shaft or several shafts coupled together may beused. Either way, the principles are the same for all steam turbines. The configuration is decided

    by the use to which the steam turbine is put, co-generation or pure electricity production.

    Nozzles and Blades

  • 8/3/2019 Ntpc Deposit

    27/64

    Steam enthalpy is converted into rotational energy as it passes through a turbine stage. A turbinestage consists of a stationary blade and a rotating blade. Stationary blades convert the potential

    energy of the steam (temperature and pressure) into kinetic energy and direct the flow onto therotating blades. The rotating blades convert the kinetic energy into impulse and reaction forces

    caused by pressure drop, which results in the rotation of the turbine shaft or rotor.Steam turbines

    are machines which must be designed, manufactured and maintained to high tolerances so that

    the design power output and availability is obtained. They are subject to a number of damagemechanisms, with two of the most important being:

    Erosion due to Moisture: - The presence of water droplets in the last stages of a turbine causes

    erosion to the blades.

    Solid Particle Erosion: - The entrainment of erosive materials from the boiler in the steam causes

    wear to the turbine blades.

    Cogeneration Cycles

    In cogeneration cycles, steam is typically generated at a higher temperature and pressure than

    required for a particular industrial process. The steam is expanded through a turbine to produce

    electricity and the resulting extractions at the discharge are at the temperature and pressurerequired by the process.

    Bearings and Lubrication

    Two types of bearings are used to support and locate the rotors of steam turbines:Journal bearings are used to support the weight of the turbine rotors. A journal bearing consists

    of two half-cylinders that enclose the shaft and are internally lined with Babbitt, ametal alloy usually consisting of tin, copper and antimony; and

    Thrust bearings axially locate the turbine rotors.

    High-pressure oil is injected into the bearings to provide lubrication. The oil is carefully filtered

    to remove solid particles.

    Shaft Seals

    The shaft seal on a turbine rotor consist of a series of ridges and groves around the rotor and its

    housing which present a long, tortuous path for any steam leaking through the seal. The seal

    therefore does not prevent the steam from leaking, merely reduces the leakage to a minimum.

    Turning Gear

    Large steam turbines are equipped with "turning gear" to slowly rotate the turbines after they

    have been shut down and while they are cooling. This evens out the temperature distribution

    around the turbines and prevents bowing of the rotors.

    VibrationThe balancing of the large rotating steam turbines is a critical component in ensuring the reliable

    operation of the plant. Most large steam turbines have sensors installed to measure the movement

    of the shafts in their bearings. This condition monitoring can identify many potential problemsand allows the repair of the turbine to be planned before the problems become serious.

  • 8/3/2019 Ntpc Deposit

    28/64

    Electric GeneratorThe steam turbine-driven generators have auxiliary systems enabling them to work satisfactorily

    and safely. The steam turbine generator being rotating equipment generally has a heavy, large

    diameter shaft. The shaft therefore requires not only supports but also has to be kept in position

    while running. To minimize the frictional resistance to the rotation, the shaft has a number of

    bearings. The bearing shells, in which the shaft rotates, are lined with a low friction material like

    Babbitt metal. Oil lubrication is provided to further reduce the friction between shaft and bearingsurface and to limit the heat generated.

    A 95 MW Generator at Badarpur Thermal Power Station, New Delhi

    Turning Gear

    Turning gear is the term used for the mechanism provided for rotation of the turbine generator

    shaft at a very low speed (about one revolution per minute) after unit stoppages for any reason.

    Once the unit is "tripped" (i.e., the turbine steam inlet valve is closed), the turbine starts slowingor "coasting down". When it stops completely, there is a tendency for the turbine shaft to deflect

    or bend if allowed to remain in one position too long. This deflection is because the heat insidethe turbine casing tends to concentrate in the top half of the casing, thus making the top half

    portion of the shaft hotter than the bottom half. The shaft therefore warps or bends by millionthsof inches, only detectable by monitoring eccentricity meters.But this small amount of shaft

    deflection would be enough to cause vibrations and damage the entire steam turbine generatorunit when it is restarted. Therefore, the shaft is not permitted to come to a complete stop by a

    mechanism known as "turning gear" that automatically takes over to rotate the unit at a preset

    low speed.If the unit is shut down for major maintenance, then the turning gear must be kept in

    service until the temperatures of the casings and bearings are sufficiently low.

    Condenser

    The surface condenser is a shell and tube heat exchanger in which cooling water is circulated

    through the tubes. The exhaust steam from the low pressure turbine enters the shell where it is

  • 8/3/2019 Ntpc Deposit

    29/64

    cooled and converted to condensate (water) by flowing over the tubes as shown in the adjacentdiagram.

    A Typical Water Cooled Condenser

    For best efficiency, the temperature in the condenser must be kept as low as practical in order toachieve the lowest possible pressure in the condensing steam. Since the condenser temperature

    can almost always be kept significantly below 100oC where the vapor pressure of water is much

    less than atmospheric pressure, the condenser generally works under vacuum. Plants operating inhot climates may have to reduce output if their source of condenser cooling water becomes

    warmer; unfortunately this usually coincides with periods of high electrical demand for airconditioning. The condenser generally uses either circulating cooling water from a cooling tower

    to reject waste heat to the atmosphere, or once-through water from a river, lake or ocean.

    Feedwater HeaterA Rankine cycle with a two-stage steam turbine and a single feedwater heater.In the case of a

    conventional steam-electric power plant utilizing a drum boiler, the surface condenser removes

    the latent heat of vaporization from the steam as it changes states from vapour to liquid. The heatcontent in the steam is referred to as Enthalpy. The condensate pump then pumps the condensate

    water through a feedwater heater. The feedwater heating

    equipment then raises the temperature of the water by utilizing extraction steam from various

    stages of the turbine.

  • 8/3/2019 Ntpc Deposit

    30/64

    A Rankine cycle with a two-stage steam turbine and a single feedwater heater

    Preheating the feedwater reduces the irreversibilities involved in steam generation and therefore

    improves the thermodynamic efficiency of the system.[9] This reduces plant operating costs and

    also helps to avoid thermal shock to the boiler metal when the feedwater is introduced back into

    the steam cycle.

    Superheater

    As the steam is conditioned by the drying equipment inside the drum, it is piped from the upper

    drum area into an elaborate set up of tubing in different areas of the boiler. The areas known as

    superheater and reheater. The steam vapor picks up energy and its temperature is nowsuperheated above the saturation temperature. The superheated steam is then piped through the

    main steam lines to the valves of the high pressure turbine.

    Deaerator

    A steam generating boiler requires that the boiler feed water should be devoid of air and otherdissolved gases, particularly corrosive ones, in order to avoid corrosion of the metal. Generally, power stations use a deaerator to provide for the removal of air and other dissolved gases from

    the boiler feedwater.

  • 8/3/2019 Ntpc Deposit

    31/64

    Auxiliary Systems

    Oil System

    An auxiliary oil system pump is used to supply oil at the start-up of the steam turbine generator.It

    supplies the hydraulic oil system required for steam turbine's main inlet steam stop valve, the

    governing control valves, the bearing and seal oil systems, the relevant hydraulic relays and othermechanisms.

    Generator Heat Dissipation

    The electricity generator requires cooling to dissipate the heat that it generates. While small units

    may be cooled by air drawn through filters at the inlet, larger units generally require special

    cooling arrangements. Hydrogen gas cooling, in an oil-sealed casing, is used because it has the

    highest known heat transfer coefficient of any gas and for its low viscosity which

    reduces windage losses. This system requires special handling during start-up, with air in thechamber first displaced by carbon dioxide before filling with hydrogen. This ensures that the

    highly flammable hydrogen does not mix with oxygen in the air.The hydrogen pressure inside thecasing is maintained slightly higher than atmospheric pressure to avoid outside air ingress. The

    hydrogen must be sealed against outward leakage where the shaft emerges from the casing.Mechanical seals around the shaft are installed with a very small annular gap to avoid rubbing

    between the shaft and the seals. Seal oil is used to prevent the hydrogen gas leakage toatmosphere. The generator also uses water cooling. Demineralized water of low conductivity is

    used.

    Generator High Voltage System

    The generator voltage ranges from 10.5 kV in smaller units to 15.75 kV in larger units. The

    generator high voltage leads are normally large aluminum channels because of their high current

    as compared to the cables used in smaller machines. They are enclosed in well-grounded

    aluminum bus ducts and are supported on suitable insulators. The generator high voltage

    channels are connected to step-up transformers for connecting to a high voltage electrical

    substation (of the order of 220 kV) for further transmission by the local power grid. Thenecessary protection and metering devices are included for the high voltage leads. Thus, the

    steam turbine generator and the transformer form one unit

    Other Systems-

    Monitoring and Alarm systemMost of the power plants operational controls are automatic. However, at times, manual

    intervention may be required. Thus, the plant is provided with monitors and alarm systems thatalert the plant operators when certain operating parameters are seriously deviating from their

    normal range.

    MAIN GENERATOR

    Maximum continuous KVA rating 24700KVA

    Maximum continuous KW 210000KW

    Rated terminal voltage 15750V

    Rated Stator current 9050 A

  • 8/3/2019 Ntpc Deposit

    32/64

    Rated Power Factor 0.85 lag

    Excitation current at MCR Condition 2600 A

    Slip-ring Voltage at MCR Condition 310 V

    Rated Speed 3000 rpm

    Rated Frequency 50 Hz

    Short circuit ratio 0.49

    Efficiency at MCR Condition 98.4%

    Direction of rotation viewed Anti Clockwise

    Phase Connection Double Star

    MAIN TURBINE DATA

    Rated output of Turbine

    210 MW

    Rated speed of turbine 3000 rpm

    Rated pressure of steam before emergency 130 kg/cm^2

    Stop valve rated live steam temperature 535 degree Celsius

    Rated steam temperature after reheat at inlet to receptor

    valve535 degree Celsius

    Steam flow at valve wide open condition 670 tons/hour

    Rated quantity of circulating water through condenser 27000 cm/hour

    1. For cooling water temperature (degree Celsius) 24,27,30,33

    1.Reheated steam pressure at inlet of interceptor valve in

    kg/cm^2 ABS23,99,24,21,24,49,24.82

    2.Steam flow required for 210 MW in ton/hour 68,645,652,662

    3.Rated pressure at exhaust of LP turbine in mm of Hg 19.9,55.5,65.4,67.7

  • 8/3/2019 Ntpc Deposit

    33/64

    An Engineer monitoring the various parameters at NTPC, New Delhi

    Battery Supplied Emergency Lighting & Communication

    A central battery system consisting of lead acid cell units is provided to supply emergency

    electric power, when needed, to essential items such as the power plant's control systems,

    communication systems, turbine lube oil pumps, and emergency lighting. This is essential for a

    safe, damage-free shutdown of the units in an emergency situation.

  • 8/3/2019 Ntpc Deposit

    34/64

    Module II

    EMD I

    Coal Handling Plant

    Motors

    Switchgear

    High Tension Switchgear

    Direct On Line Starter

  • 8/3/2019 Ntpc Deposit

    35/64

    It is responsible for maintenance of:

    1. Boiler side motors

    2. Turbine side motors

    3. Outside motors

    4. Switchgear

    1. Boiler side motors:

    For 1, units 1, 2, 3

    1.1D Fans 2 in no.

    2.F.D Fans 2 in no.

    3.P.A.Fans 2 in no.

    4.Mill Fans 3 in no.

    5.Ball mill fans 3 in no.

    6.RC feeders 3 in no.

    7.Slag Crushers 5 in no.

    8.DM Make up Pump 2 in no.

    9.PC Feeders 4 in no.

    10.Worm Conveyor 1 in no.

    11.Furnikets 4 in no.

    For stage units 1, 2, 3

    1.I.D Fans 2 in no.

    2.F.D Fans 2 in no.

    3.P.A Fans 2 in no.

    4.Bowl Mills 6 in no.

    5.R.C Feeders 6 in no.

    6.Clinker Grinder 2 in no.

    7.Scrapper 2 in no.

    8.Seal Air Fans 2 in no.

    9.Hydrazine and Phosphorous Dozing 2 in no.

    2/3 in no.

  • 8/3/2019 Ntpc Deposit

    36/64

    Coal Handling PlantCoal is delivered by highway truck, rail, barge or collier ship. Some plants are even built near

    coal mines and coal is delivered by conveyors. A large coal train called a "unit train" may be a

    kilometers (over a mile) long, containing 60 cars with 100 tons of coal in each one, for a total

    load of 6,000 tons. A large plant under full load requires at least one coal delivery this size every

    day. Plants may get as many as three to five trains a day, especially in "peak season", during the

    summer months when power consumption is high. A large thermal power plant such as the

    Badarpur Thermal Power Station, New Delhi stores several million tons of coal for use whenthere is no wagon supply.

    Coal Handling Plant Layout

    The unloader includes a train positioner arm that pulls the entire train to position each car over a

    coal hopper. The dumper clamps an individual car against a platform that swivels the car upsidedown to dump the coal.

  • 8/3/2019 Ntpc Deposit

    37/64

    Layout of Coal Handling Plant at Badarpur Thermal Power Station, New Delhi

    Coal is prepared for use by crushing the rough coal to pieces less than 2 inches (50 mm) in

    size.The coal is then transported from the storage yard to in-plant storage silos by rubberized

    conveyor belts at rates up to 4,000 tons/hour.In plants that burn pulverized coal, silos feed coal

    pulverizers (coal mill) that take the larger 2 inch pieces grind them into the consistency of face

    powder, classify them, and mixes them with primary combustion air which transports the coal to

    the furnace and preheats the coal to drive off excess moisture content.

    Run-Of-Mine (ROM) CoalThe coal delivered from the mine that reports to the Coal Handling Plant is called Run-of-

    mine,coal. This is the raw material for the CHP, and consists of coal, rocks,minerals and

    contamination. Contamination is usually introduced by the mining process.ROM coalcan have a large variability of moisture and maximum particle size.

    Coal HandlingCoal needs to be stored at various stages of the preparation process, and conveyed around the

    CHP facilities. Coal handling is part of the larger field of bulk material handling, and is a

    complex and vital part of the CHP.

    Stockpiles

    Stockpiles provide surge capacity to various parts of the CHP. ROM coal is delivered with large

    variations in production rate of tonnes per hour (tph). A ROM stockpile is used to allow the

    washplant to be fed coal at lower, constant rate.

  • 8/3/2019 Ntpc Deposit

    38/64

    Coal Handling Division of Badarpur Thermal Power Station, New Delhi

    A simple stockpile is formed by machinery dumping coal into a pile, either from dump

    trucks,pushed into heaps with bulldozers or from conveyor booms.Taller and wider stockpiles

    reduce the land area required to store a set tonnage of coal.

    Coal Sampling

    Sampling of coal is an important part of the process control in the CHP. A grab sample is a

    oneoff sample of the coal at a point in the process stream, and tends not to be very representative.

    Aroutine sample is taken at a set frequency, either over a period of time or per shipment.

    ScreeningScreens are used to group process particles into ranges by size. These size ranges are also called

    grades. Screens can be static, or mechanically vibrated.

    Magnetic Separation

    Magnetic separators shall be used in coal conveying systems to separate tramp iron from the coal.

    Basically, two types are available. One type incorporates permanent or electromagnets into thehead pulley of a belt conveyor. The tramp iron clings to the belt as it goes around the pulley drum

    and falls off into a collection hopper or trough after the point at which coal is charged from thebelt. The other type consists of permanent or electromagnets incorporated into a belt conveyor

    that is suspended above a belt conveyor carrying coal. The tramp iron is pulled from the movingcoal to the face of the separating conveyor, which in turn holds and carries the tramp iron to a

    collection hopper or trough. Magnetic separators shall be used just ahead of the coal crusher.Coal Crusher

    Before the coal is sent to the plant it has to be ensured that the coal is of uniform size, and so it is

    passed through coal crushers. Also power plants using pulverized coal specify a maximum coal

    size that can be fed into the pulverizer and so the coal has to be crushed to the specified size

    using the coal crusher. Rotary crushers are very commonly used for this purpose as they can

    provide a continuous flow of coal to the pulverizer.

  • 8/3/2019 Ntpc Deposit

    39/64

    PulverizerMost commonly used pulverizer is the Boul Mill. The arrangement consists of 2 stationary rollers

    and a power driven baul in which pulverization takes place as the coal passes through the sides ofthe rollers and the baul. A primary air induced draught fan draws a stream of heated air through

    the mill carrying the pulverized coal into a stationary classifier at the top of the pulverizer.

    An external view of a Coal Pulverizer

    Advantages of Pulverized Coal

    Pulverized coal is used for large capacity plants.It is easier to adapt to fluctuating load as there are no limitations on the combustion capacity.

    Coal with higher ash percentage cannot be used without pulverizing because of the problem oflarge amount ash deposition after combustion.

    Increased thermal efficiency is obtained through pulverization.The use of secondary air in the combustion chamber along with the powered coal helps in

    creating turbulence and therefore uniform mixing of the coal and the air during combustion.

    Greater surface area of coal per unit mass of coal allows faster combustion as more coal isexposed to heat and combustion.The boiler can be easily started from cold condition in case of emergency.

    The furnace volume required is less as the turbulence caused aids in complete combustion of

    the coal with minimum travel of the particles.

    The pulverized coal is passed from the pulverizer to the boiler by means of the primary air that is

    used not only to dry the coal but also to heat is as it goes into the boiler. The secondary air is

    used to provide the necessary air required for complete combustion.The coal is sent into the

    boiler through burners. A very important and widely used type of burner arrangement is the

    Tangential Firing arrangement.

    Tangential Burners:The tangential burners are arranged such that they discharge the fuel air mixture tangentially toan imaginary circle in the center of the furnace. The swirling action produces sufficient

    turbulence in the furnace to complete the combustion in a short period of time and avoid thenecessity of producing high turbulence at the burner itself. High heat release rates are possible

    with this method of firing.The burners are placed at the four corners of the furnace. At theBadarpur ThermalPower Station five sets of such burners are placed one above the other to form

    six firing zones.

  • 8/3/2019 Ntpc Deposit

    40/64

    Ash HandlingThe ever increasing capacities of boiler units together with their ability to use low grade high ash

    content coal have been responsible for the development of modern day ash handling systems.TheHydraulic Ash handling system is used at the Badarpur Thermal Power Station.

    Hydraulic Ash Handling System

    The hydraulic system carried the ash with the flow of water with high velocity through a channeland finally dumps into a sump. The ash is carried along with the water and they are separated at

    the sump.NEW COAL HANDLING PLANT (N.C.H.P)

    The old coal handling plant caters to the need of units 2,3,4,5 and 1 whereas the latter supplies

    coal to units 4 and V.O.C.H.P. supplies coal to second and third stages in the advent coal to

    usable form to (crushed) form its raw form and send it to bunkers, from where it is send to

    furnace.

    Major Components

    1. Wagon Tippler: - Wagons from the coal yard come to the tippler and are emptied here. The process is

    performed by a slip ring motor of rating: 55 KW, 415V, 1480 RPM. This motor turns the wagon by 135degrees and coal falls directly on the conveyor through vibrators. Tippler has raised lower system which

    enables is to switch off motor when required till is wagon back to its original position. It is titled byweight balancing principle. The motor lowers the hanging balancing weights, which in turn tilts the

    conveyor. Estimate of the weight of the conveyor is made through hydraulic weighing machine.2. Conveyor: - There are 14 conveyors in the plant. They are numbered so that their function can beeasily demarcated. Conveyors are made of rubber and more with a speed of 250-300m/min. Motors

    employed for conveyors has a capacity of 150 HP. Conveyors have a capacity of carrying coal at the rate

    of 400 tons per hour. Few conveyors are double belt, this is done for imp. Conveyors so that if a beltdevelops any problem the process is not stalled. The conveyor belt has a switch after every 25-30 m on

    both sides so stop the belt in case of emergency. The conveyors are 1m wide, 3 cm thick and made of

    chemically treated vulcanized rubber. The max angular elevation of conveyor is designed such as never toexceed half of the angle of response and comes out to be around 20 degrees.

    3. Zero Speed Switch:-It is safety device for motors, i.e., if belt is not moving and the motor is on the

    motor may burn. So to protect this switch checks the speed of the belt and switches off the motor whenspeed is zero.

    4. Metal Separators: - As the belt takes coal to the crusher, No metal pieces should go alongwith coal. To achieve this objective, we use metal separators. When coal is dropped to the

    crusher hoots, the separator drops metal pieces ahead of coal. It has a magnet and a belt and the

    belt is moving, the pieces are thrown away. The capacity of this device is around 50 kg. .The

    CHP is supposed to transfer 600 tons of coal/hr, but practically only 300-400 tons coal is transfer

    5. Crusher: - Both the plants use TATA crushers powered by BHEL. Motors. The crusher is of

    ring type and motor ratings are 400 HP, 606 KV. Crusher is designed to crush the pieces to 20

    mm size i.e. practically considered as the optimum size of transfer via conveyor.

    6. Rotatory Breaker: - OCHP employs mesh type of filters and allows particles of 20mm size to

    go directly to RC bunker, larger particles are sent to crushes. This leads to frequent clogging.

    NCHP uses a technique that crushes the larger of harder substance like metal impurities easing

    the load on the magnetic separators.

  • 8/3/2019 Ntpc Deposit

    41/64

    MILLING SYSTEM

    1. RC Bunker: - Raw coal is fed directly to these bunkers. These are 3 in no. per boiler. 4 & tons of coal are fed in 1 hr. the depth of bunkers is 10m.

    2. RC Feeder: - It transports pre crust coal from raw coal bunker to mill. The quantity of raw

    coal fed in mill can be controlled by speed control of aviator drive controlling damper and aviatorchange.

    3. Ball Mill: - The ball mill crushes the raw coal to a certain height and then allows it to fall

    down. Due to impact of ball on coal and attraction as per the particles move over each other as

    well as over the Armor lines, the coal gets crushed. Large particles are broken by impact and full

    grinding is done by attraction. The Drying and grinding option takes place simultaneously inside

    the mill.

    4. Classifier:- It is an equipment which serves separation of fine pulverized coal particles

    medium from coarse medium. The pulverized coal along with the carrying medium strikes theimpact plate through the lower part. Large particles are then transferred to the ball mill.

    5. Cyclone Separators: - It separates the pulverized coal from carrying medium. The mixture of

    pulverized coal vapour caters the cyclone separators.

    6. The Tturniket: - It serves to transport pulverized coal from cyclone separators to pulverizedcoal bunker or to worm conveyors. There are 4 turnikets per boiler.

    7. Worm Conveyor: - It is equipment used to distribute the pulverized coal from bunker of one

    system to bunker of other system. It can be operated in both directions.

    8. Mills Fans: - It is of 3 types:

    Six in all and are running condition all the time.

    (a) ID Fans: - Located between electrostatic precipitator and chimney.

    Type-radical

    Speed-1490 rpm

    Rating-300 KW

    Voltage-6.6 KV

    Lubrication-by oil

    (b) FD Fans: - Designed to handle secondary air for boiler. 2 in number and provide ignition of

    coal.

    Type-axial

    Speed-990 rpmRating-440 KWVoltage-6.6 KV

    (c)Primary Air Fans: - Designed for handling the atmospheric air up to 50 degrees Celsius, 2 in

    number

    And they transfer the powered coal to burners to firing.

  • 8/3/2019 Ntpc Deposit

    42/64

    Type-Double suction radialRating-300 KW

    Voltage-6.6 KVLubrication-by oil

    Type of operation-continuous

    9. Bowl Mill: - One of the most advanced designs of coal pulverizes presently manufactured.

    Motor specification squirrel cage induction motor

    Rating-340 KW

    Voltage-6600KV

    Curreen-41.7A

    Speed-980 rpm

    Frequency-50 Hz

    No-load current-15-16 A

    NCHP

    1. Wagon Tippler:-

    Motor Specification(i) H.P 75 HP

    (ii) Voltage 415, 3 phase(iii) Speed 1480 rpm

    (iv) Frequency 50 Hz

    (v) Current rating 102 A

    2. Coal feed to plant:-

    Feeder motor specification

    (i) Horse power 15 HP

    (ii) Voltage 415V,3 phase

    (iii) Speed 1480 rpm

    (iv) Frequency 50 Hz

    3. Conveyors:-10A, 10B

    11A, 11B

    12A, 12B13A, 13B14A, 14B

    15A, 15B

    16A, 16B

    17A, 17B

    18A, 18B

    4. Transfer Point 6

  • 8/3/2019 Ntpc Deposit

    43/64

    5. Breaker House

    6. Rejection House

    7. Reclaim House

    8. Transfer Point 7

    9. Crusher House

    10. Exit

    The coal arrives in wagons via railways and is tippled by the wagon tipplers into the hoppers. If

    coal is oversized (>400 mm sq) then it is broken manually so that it passes the hopper mesh.

    From the hopper mesh it is taken to the transfer point TP6 by conveyor 12A ,12B which takes the

    coal to the breaker house , which renders the coal size to be 100mm sq. the stones which are not

    able to pass through the 100mm sq of hammer are rejected via conveyors 18A,18B to therejection house . Extra coal is to sent to the reclaim hopper via conveyor 16. From breaker house

    coal is taken to the TP7 via Conveyor 13A, 13B. Conveyor 17A, 17B also supplies coal fromreclaim hopper, From TP7 coal is taken by conveyors 14A, 14B to crusher house whose function

    is to render the size of coal to 20mm sq. now the conveyor labors are present whose function is torecognize and remove any stones moving in the conveyors . In crusher before it enters the

    crusher. After being crushed, if any metal is still present it is taken care of by metal detectorsemployed in conveyor 10.

  • 8/3/2019 Ntpc Deposit

    44/64

    ELECTRIC MOTORSAn electric motor uses electrical energy to produce mechanical energy. The reverse process that

    of using mechanical energy to produce electrical energy is accomplished by a generator or

    dynamo.

    A High Power Electric Motor

    Categorization of Electric Motors

    The classic division of electric motors has been that of Direct Current (DC) types vs AlternatingCurrent (AC) types.There is a clearer distinction between a synchronous motor and asynchronous

    types. In the synchronous types, the rotor rotates in synchrony with the oscillating field or current

    (eg.permanent magnet motors). In contrast, an asynchronous motor is designed to slip; the most

    ubiquitous example being the common AC induction motor which must slip in order to generate

    torque.

    AC Motor

    Internal View of AC Motors

  • 8/3/2019 Ntpc Deposit

    45/64

    An AC motor is an electric motor that is driven by an alternating current. It consists of two basicparts, an outside stationary stator having coils supplied with AC current to produce a rotating

    magnetic field, and an inside rotor attached to the output shaft that is given a torque by therotating field.There are two types of AC motors, depending on the type of rotor used. The first is

    the synchronous motor, which rotates exactly at the supply frequency. The magnetic field on the

    rotor is either generated by current delivered through sliprings or a by a permanent magnet.

    The second type is the induction motor, which turns slightly slower than the supplyfrequency.The magnetic field on the rotor of this motor is created by an induced current.

    Synchronous Motor

    A synchronous electric motor is an AC motor distinguished by a rotor spinning with coils passing

    magnets at the same rate as the alternating current and resulting magnetic field which drives it.

    Another way of saying this is that it has zero slip under usual operating conditions.Contrast this

    with an induction motor, which must slip in order to produce torque.Sometimes a synchronous

    motor is used, not to drive a load, but to improve the power factor on

    the local grid it's connected to. It does this by providing reactive power to or consuming reactive

    power from the grid. Electrical power plants almost always use synchronous generators because

    it's very important to keep the frequency constant at which the generator is connected.Advantages

    Synchronous motors have the following advantages over non-synchronous motors:Speed is independent of the load, provided an adequate field current is applied.

    Their power factor can be adjusted to unity by using a proper field current relative to the load.Also, a "capacitive" power factor, (current phase leads voltage phase), can be obtained by

    increasing this current slightly, which can help achieve a better power factor correction for thewhole installation.

    Their construction allows for increased electrical efficiency when a low speed is required

    Induction Motor

    An induction motor (IM) is a type of asynchronous AC motor where power is supplied to the

    rotating device by means of electromagnetic induction.An electric motor converts electrical

    power to mechanical power in its rotor (rotating part).An induction motor is sometimes called a

    rotating transformer because the stator(stationary part) is essentially the primary side of the

    transformer and the rotor (rotating part) is the secondary side.

    Induction motors are now the preferred choice for industrial motors due to their rugged

    construction and lack of brushes (which are needed in most DC Motors)

    Construction

    The stator consists of wound 'poles' that carry the supply current that induces a magnetic field in

    the conductor. The number of 'poles' can vary between motor types but the poles are always inpairs (i.e. 2, 4, 6 etc). There are two types of rotor:

    1. Squirrel-cage rotor2. Slip ring rotor

    The most common rotor is a squirrel-cage rotor. It is made up of bars of either solid copper (most

    common) or aluminum that span the length of the rotor, and are connected through a ring at eachend. The rotor bars in squirrel-cage induction motors are not straight, but have some skew toreduce noise and harmonics.

    Principle of Operation

    The basic difference between an induction motor and a synchronous AC motor is that in the latter

    a current is supplied onto the rotor. This then creates a magnetic field which, through magnetic

    interaction, links to the rotating magnetic field in the stator which in turn causes the rotor to turn.

    It is called synchronous because at steady state the speed of the rotor is the same as the speed of

    the rotating magnetic field in the stator.

  • 8/3/2019 Ntpc Deposit

    46/64

    By way of contrast, the induction motor does not have any direct supply onto the rotor; instead,asecondary current is induced in the rotor. To achieve this, stator windings are arranged around

    the rotor so that when energised with a polyphase supply they create a rotating magnetic fieldpattern which sweeps past the rotor. This changing magnetic field pattern can induce currents in

    the rotor conductors. These currents interact with the rotating magnetic field created by the stator

    and the rotor will turn. However, for these currents to be induced, the speed of the physical rotor

    and the speed of the rotating magnetic field in the stator must be different, or else the magneticfield will not be

    moving relative to the rotor conductors and no currents will be induced. If by some chance this

    happens, the rotor typically slows slightly until a current is re-induced and then the rotor

    continues as before. This difference between the speed of the rotor and speed of the rotating

    magnetic field in the stator is called slip. It has no unit and the ratio between the relative speed of

    the magnetic field as seen by the rotor to the speed of the rotating field. Due to this an induction

    motor is sometimes referred to as an asynchronous machine.

    Types:

    1. Squirrel cage induction motor

    2. Slip ring induction motor

  • 8/3/2019 Ntpc Deposit

    47/64

    SWITCHGEARThe term switchgear, used in association with the electric power system, or grid, refers to the

    combination of electrical disconnects, fuses and/or circuit breakers used to isolate electrical

    equipment. Switchgear is used both to de-energize equipment to allow work to be done and to

    clear faults downstream.

    Today, oil-filled equipment has largely been replaced by air-blast, vacuum, or SF6 equipment,allowing large currents and power levels to be safely controlled by automatic equipment

    incorporating digital controls,mrotection, metering and communications.

    A View of Switchgear at a Power Plant

    TypesA piece of switchgear may be a simple open air isolator switch or it may be insulated by some

    other substance. An effective although more costly form of switchgear is "gas insulated

    switchgear" (GIS), where the conductors and contacts are insulated by pressurized (SF6) sulfurhexafluoride gas. Other common types are oil [or vacuum] insulated switchgear.

    Circuit breakers are a special type of switchgear that are able to interrupt fault currents. Their

    construction allows them to interrupt fault currents of many hundreds or thousands of amps. The

    quenching of the arc when the contacts open requires careful design, and falls into four types:Oil circuit breakers rely upon vaporization of some of the oil to blast a jet of oil through the arc.

    At badarpur

    Type-HKH 12/1000c Rated Voltage-66 KV

    Normal Current-1250A Frequency-5Hz

    Breaking Capacity-3.4+KA Symmetrical 3.4+KA Asymmetrical

    360 MVA Symmetrical

    Operating Coils-CC 220 V/DC

    FC 220V/DC

    Motor Voltage-220 V/DC

    Gas (SF6) circuit breakers sometimes stretch the arc using a magnetic field, and then rely upon

    the dielectric strength of the SF6 to quench the stretched arc.

  • 8/3/2019 Ntpc Deposit

    48/64

    At badarpur Circuit Breakers-HPA

    Standard-1 EC 56 Rated Voltage-12 KV

    Insulation Level-28/75 KV

    Rated Frequency-50 Hz

    Breaking Current-40 KA Rated Current-1600 A

    Making Capacity-110 KA

    Rated Short Time Current 1/3s -40 A

    Mass Approximation-185 KG

    Auxiliary Voltage

    Closing Coil-220 V/DC

    Opening Coil-220 V/DC

    Motor-220 V/DC

    SF6 Pressure at 20 Degree Celsius-0.25 KG

    SF6 Gas Per pole-0.25 KG

    Vacuum circuit breakers have minimal arcing (as there is nothing to ionize other than the

    contact material).At badarpur

    Rated frequency-50 Hz

    Rated making Current-10 Peak KA

    Rated Voltage-12 KV

    Supply Voltage Closing-220 V/DC

    Rated Current-1250 A

    Supply Voltage Tripping-220 V/DC

    Insulation Level-IMP 75 KVP

    Rated Short Time Current-40 KA (3 SEC)

    Weight of Breaker-8 KG

    Air circuit breakers may use compressed air to blow out the arc.

    Circuit breakers are usually able to terminate all current flow very quickly: typically between30ms and 150 ms depending upon the age and construction of the device.

    FunctionsOne of the basic functions of switchgear is protection, which is interruption of short-circuit and

    overload fault currents while maintaining service to unaffected circuits. Switchgear also provides

    isolation of circuits from power supplies. Switchgear also is used to enhance system availabilityby allowing more than one source to feed a load.Safety

    To help ensure safe operation sequences of switchgear, trapped key interlocking provides

    predefined scenarios of operation.

  • 8/3/2019 Ntpc Deposit

    49/64

    HIGH TENSION SWITCHGEARHigh voltage switchgear is any switchgear and switchgear assembly of rated voltage higher than

    1000 volts. High voltage switchgear is any switchgear used to connect or to disconnect a part of a

    high voltage power system. These switchgears are essential elements for the protection and for a

    safety operating mode without interruption of a high voltage power system.The high voltage is avoltage above 1000 V for alternating current and above 1500 V for direct current.

    High Tension Switchgear of a Thermal Power Plant

    Functional Classification

    Disconnectors and Earthing Switches

    They are above all safety devices used to open or to close a circuit when there is no current

    through them. They are used to isolate a part of a circuit, a machine, a part of an overhead-line

    or an underground line for the operating staff to access it without any danger.The opening of the

    line isolator or busbar section isolator is necessary for the safety but it is not enough. Grounding

    must be done at the upstream sector and the downstream sector on the device which they want to

    intervene.

    Fuses

    The fuses can interrupt automatically a circuit with an overcurrent flowing in it for a fixedtime.The current interrupting is got by the fusion of an electrical conductor which is graded.They

    are mainly used to protect against the short-circuits. They limit the peak value of the faultcurrent.

    In three-phase electric power, they only eliminate the phases where the fault current is

    flowing,which is a risk for the devices and the people.

    Circuit Breaker

    A high voltage circuit breaker is capable of making, carrying and breaking currents under the

    rated voltage (the maximal voltage of the power system which it is protecting) :Under normal

  • 8/3/2019 Ntpc Deposit

    50/64

    circuit conditions, for example to connect or disconnect a line in a power system; Under specifiedabnormal circuit conditions especially to eliminate a short circuit. From its characteristics, a

    circuit breaker is the protection device essential for a high voltage power system, because it is theonly one able to interrupt a short circuit current and so to avoid the others devices to be damaged

    by this short circuit.

    To operate on long lines, the circuit breakers are equipped with a closing resistor to limit the

    overvoltages.

    DIRECT ON LINE STARTERA direct on line starter, often abbreviated DOL starter, is a widely-used starting method of

    electric motors.There are many types of motor starters, the simplest of which is the DOL starter.A motor starter is an electrical/electronic circuit composed of electro-mechanical and electronic

    devices which are employed to start and stop an electric motor. Regardless of the motor type(AC or DC), the types of starters differ depending on the method of starting the motor. A DOL

    starter connects the motor terminals directly to the power supply. Hence, the motor is subjectedto the full voltage of the power supply. Consequently, high starting current flows through the

    motor. This type of starting is suitable for small motors below 5 hp (3.75 kW). Reduced-voltagestarters are employed with motors above 5 hp.

    Internal View of a Direct On Line Starter

    Major ComponentsThere are four major components of a Direct On Line Starter. They are given as follows:

    1. Switch2. Fuse

    3. Conductor (Electromagnetic)4. Thermal Overload Relay (Heat & Temperature)

    According to our desire and use of work, we can use auxiliary components in a DOL Starter.

    Motor Direction ReversalChanging the direction of a 3-Phase Squirrel-Cage Motor requires swapping any two phases.

  • 8/3/2019 Ntpc Deposit

    51/64

    Module II

    EMD II

    Generator

    Protection

    Transformer

  • 8/3/2019 Ntpc Deposit

    52/64

    GENERATORSThe basic function of the generator is to convert mechanical power, delivered from the shaft of

    the turbine, into electrical power. Therefore a generator is actually a rotating mechanical energy

    converter. The mechanical energy from the turbine is converted by means of a rotating magnetic

    field produced by direct current in the copper winding of the rotor or field, which generates

    three-phase alternating currents and voltages in the copper winding of the stator (armature). The

    stator winding is connected to terminals, which are in turn connected to the power system for

    delivery of the output power to the system.

    The class of generator under consideration is steam turbine-driven generators, commonly calledturbo generators.The generators particular to this category are of the two- and four-pole design

    employing round-rotors.At Badarpur Thermal Power Station 3000 rpm, 50 Hz generators areused of capacities 210 MW and 95 MW.

    As the system load demands more active power from the generator, more steam (or fuel in acombustion turbine) needs to be admitted to the turbine to increase power output. Hence more

    energy is transmitted to the generator from the turbine, in the form of a torque.The higher the power output, the higher the torque between turbine and generator.The power output of the

    generator generally follows the load demand from the system.Therefore the voltages and currentsin the generator are continually changing based on the load demand. The generator design must

    be able to cope with large and fast load changes, which show up inside the machine as changes in

    mechanical forces and temperatures. The design must therefore incorporate electrical current-

    carrying materials (i.e., copper), magnetic flux-carrying materials (i.e., highly permeable steels),

    insulating materials (i.e., organic), structural members (i.e., steel and organic), and cooling media

    (i.e., gases and liquids), all working together under the operating conditions of a turbo generator.

    Since the turbo generator is a synchronous machine, it operates at one very specific speed to

    produce a constant system frequency of 50 Hz, depending on the frequency of the grid to which it

    is connected. As a synchronous machine, a turbine generator employs a steady magnetic flux

    passing radially across an air gap that exists between the rotor and the stator.This flux pattern

    rotates

    with the rotor, as it spins at its synchronous speed. The rotating magnetic field moves past athree-phase symmetrically distributed winding installed in the stator core, generating an

    alternating voltage in the stator winding. The voltage waveform created in each of the threephases of the stator winding is very nearly sinusoidal. The output of the stator winding is the

    three-phase power, delivered to the power system at the voltage generated in the statorwinding.In addition to the normal flux distribution in the main body of the generator, there are

    stray fluxes at the extreme ends of the generator that create fringing flux patterns and induce

    stray losses in the generator. The stray fluxes must be accounted for in the overall design.

    Generators are made up of two basic members, the stator and the rotor, but the stator and rotor

    are each constructed from numerous parts themselves. Rotors are the high-speed rotating member

    of the two, and they undergo severe dynamic mechanical loading as well as the electromagnetic

    and thermal loads.

    These components are very carefully designed for high-stress operation. The stator isstationary,as the term suggests, but it also sees significant dynamic forces in terms of vibrationand torsional loads, as well as the electromagnetic, thermal, and high-voltage loading. The most

    critical component of the stator is arguably the stator winding because it is a very high cost itemand it must be designed to handle all of the harsh effects described above. Most stator problems

    occur with the winding.STATOR

    The stator winding is made up of insulated copper conductor bars that are distributed around the

    inside diameter of the stator core, in equally spaced slots in the core to ensure symmetrical flux

  • 8/3/2019 Ntpc Deposit

    53/64

    linkage with the field produced by the rotor. Each slot contains two conductor bars, one on top ofthe other. These are generally referred to as top and bottom bars. Top bars are the ones nearest

    the slot opening (just under the wedge) and the bottom bars are the ones at the slot bottom. Thecore area between slots is generally called a core tooth.

    The stator winding is then divided into three phases, which are almost always wye

    connected.Wye connection is done to allow a neural grounding point and for relay protection of

    the winding. The three phases are connected to create symmetry between them in the 360 degreearc of the stator. The distribution of the winding is done in such a way as to produce a 120

    0

    difference in voltage peaks from one phase to the other, hence the term three-phase

    voltage. The parallels in all of the phases are essentially equal on average, in their performance

    in the machine. Therefore, they each seeequal voltage and current, magnitudes and phase

    angles, when averaged over one alternating cycle.

    The stator bars in any particular phase group are arranged such that there are parallel paths,which

    overlap between top and bottom bars.

    Stator

    The pitch is the number slots that the stator bars have to reach in the stator bore arc, separatingthe two bars to be connected. This is always less than 180 degrees.

    The distribution factor is used to minimize the harmonic content of the generated voltage.The currents normally flowing in large turbo generators can be in the order of thousands of

    amperes. Due to the very high currents, the conductor bars in a turbo generator have a large

    cross-sectional area. In addition they are usually one single turn per bar. These stator orconductor bars are also very rigid and do not bend unless significant force is exerted on them.

    ROTOR

    The rotor winding is installed in the slots machined in the forging main body and is distributed

    symmetrically around the rotor between the poles. The winding itself is made up of many turnsof copper to form the entire series connected winding. All of the turns associated with a single

    slot are generally called a coil. The coils are wound into the winding slots in the forging,

  • 8/3/2019 Ntpc Deposit

    54/64

    Rotor

    concentrically in corresponding positions on opposite sides of a pole. In addition almost all large

    turbo generators have directly cooled copper windings by air or hydrogen cooling gas.Cooling

    passages are provided within the conductors themselves to eliminate the temperature drop acrossthe ground insulation and preserve the life of the insulation material.In an axially cooled

    winding, the gas passes through axial passages in the conductors, being fed from both ends, andexhausted to the air gap at the axial center of the rotor. The winding is held in place in the slots

    by wedges, in a similar manner as the stator windings.

    The difference is that the rotor winding loading on the wedges is far greater due to centrifugalforces at speed. The wedges therefore are subjected to a tremendous static load from these forcesand bending stresses because of the rotation effects.

    As in the rotor slots, the copper turns in the end-winding must be isolated from one another so

    that they do not touch and create shorts between turns. Therefore packing and blocking are used

    to keep the coils separated, and in their relative position as the rotor winding expands from

    thermal effects during operation.

    The A.C. Generator or alternator is based upon the principle of electromagnetic induction and

    consists generally of a stationary part called stator and a rotating part called rotor. The stator housed

    the armature windings. The rotor houses the field windings. D.C. voltage is applied to the field

    windings through slip rings. When the rotor is rotated, the lines of magnetic flux (viz magnetic field)

    cut through the stator windings. This induces an electromagnetic force (e.m.f.) in the stator windings.The magnitude of this e.m.f. is given by the following expression.

    E = 4.44 /O FN volts

    0 = Strength of magnetic field in Webers.

    F = Frequency in cycles per second or Hertz.

    N = Number of turns in a coil of stator winding

    F = Frequency = Pn/120

  • 8/3/2019 Ntpc Deposit

    55/64

    Where P = Number of poles

    n = revolutions per second of rotor.

    From the expression it is clear that for the same frequency, number of poles increases with decrease

    in speed and vice versa. Therefore, low speed hydro turbine drives generators have 14 to 20 poles

    where as high speed steam turbine driven generators have generally 2 poles. Pole rotors are used inlow speed generators, because the cost advantage as well as easier construction.

    BEARINGS

    All turbo generators require bearings to rotate freely with minimal friction and vibration. The

    main rotor body must be supported by a bearing at each end of the generator for this purpose.

    This ensures that the excitation end of the rotor shaft does not create a wobble that transmits

    through the shaft and stimulates excessive vibration in the overall generator rotor

    or the turbo generator line.

    AUXILIARY SYSTEMS

    All large generators require auxiliary systems to handle such things as lubricating oil for the rotor

    bearings, hydrogen cooling apparatus, hydrogen sealing oil, de-mineralized water for stator

    winding cooling, and excitation systems for field-current application. Not all generators require

    all these systems and the requirement depends on the size and nature of the machine.

    There are five major auxiliary systems that may be used in a generator. They are given asfollows:

    1. Lubricating Oil System2. Hydrogen Cooling System

    3. Seal Oil System

    4. Stator Cooling Water System5. Excitation SystemEach system has numerous variations to accommodate the hundreds of different generator

    configurations that may be found in operation. But regardless of the generator design and which

    variation of a system is in use, they all individually have the same basic function .

    1. Lubricating Oil System

    The lube-oil system provides oil for all of the turbine and generator bearings as well as being the

    source of seal oil for the seal-oil system.

  • 8/3/2019 Ntpc Deposit

    56/64

    Lubricating Oil System Layout

    The main oil t


Recommended