+ All Categories
Home > Documents > Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4,...

Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4,...

Date post: 21-Jun-2020
Category:
Upload: others
View: 6 times
Download: 0 times
Share this document with a friend
48
Nuclear Metals, Inc. Superfund Site Site Presentation September 4, 2013
Transcript
Page 1: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Nuclear Metals, Inc. Superfund Site

Site Presentation

September 4, 2013

Page 2: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Presentation Outline • Background

• Current Work

• NTCRA Overview

• Remedial Investigation (RI) / Feasibility Study (FS)

– RI / Risk Assessment Results

– FS Outline

– Soil / Sediment Remedial Alternatives

– Groundwater Remedial Alternatives

– Vapor Intrusion Remedial Alternatives

Page 3: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

r-1 . • .·

~~ ..

·~-~

Sphagnum Bog

Site Location – 2229 Main Street, Concord, MA

Old Landfill

Area

Page 4: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •
Page 5: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

History of Nuclear Metals, Inc. Site • 46-acre site is bordered by light commercial properties and

Main Street (MA Route 62) to the north, residential properties to the north-east and east, and woodlands and commercial industrial properties to the west and south

• Nuclear Metals, Inc. (NMI) purchased undeveloped property in 1957 and built original facility buildings in 1958.

• Owners/Operators: – 1958 – 1972: Textron Inc. and Whittaker Corp. sequentially

own NMI, which performed specialty metals research and development, primarily for US AEC and DOD. Licensed since 1958 to possess low-level radioactive substances (uranium and thorium)

– 1972: Employees purchase company and incorporate as NMI – expand work to include production of depleted uranium (DU) penetrators under contract with US Army

Page 6: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

History of Nuclear Metals, Inc. Site (continued)

– 1997: NMI changes name to Starmet Corporation. Starmet stops DU penetrator production and focusses on other manufacturing (metal powders, beryllium-aluminum alloys) through several affiliated businesses located on the property.

• Radioactive materials license altered to “possess only” in 2003.

• Starmet and affiliated businesses abandon Site in November 2011.

Page 7: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Regulatory History • March 1980 – chlorinated solvents found in NMI production

well during sampling by MADEQE (predecessor to current MassDEP), triggering further studies at site.

• 1980 – 1998 – variety of site environmental studies conducted on behalf of NMI and NRC

• 1997 – Starmet, with funding from US Army, excavates approximately 8,000 yards3 of uranium hydroxide sludge and soils from “Holding Basin” (HB) for off-site disposal.

• July 2000: EPA proposes NMI Site for inclusion on the National Priorities List (NPL)

• June 2001: NMI Site listed on the NPL • April 2002 – April 2003 – EPA conducts Time-Critical Removal

Action (TCRA) to install temporary caps on HB and “Old Landfill Area”

Page 8: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Regulatory History (continued)

• June 2003 – EPA, Respondents (Textron and Whittaker), and Settling Federal Agencies (SFAs) (US Army and DOE) enter into Administrative Order by Consent (AOC) to complete Remedial Investigation / Feasibility Study (RI/FS). AOC also provides for preparation of an Engineering Evaluation / Cost Analysis (EE/CA), if requested by EPA.

• 2004 – MassDEP and US Army enter into agreement to remove approximately 3,800 drums of uranium hexafluoride and other wastes from the site. With US Army funding, MassDEP performs drum removal from September 2005 – March 2007.

• June 2007 – a small fire in scrap metal turnings occurs at the site. Concord Fire Department requests EPA perform second TCRA to remove hazardous materials from site; and that a Fire Hazards Analysis (FHA) be performed to evaluate fire risk posed by buildings.

Page 9: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Regulatory History (continued) • December 2007 – EPA signs Approval Memorandum for EE/CA

to evaluate alternatives to address buildings and contents. • January 2008 – September 2008 – EPA performs second TCRA to

remove hazardous substances that posed threat of fire orexplosion.

• February 2008 – EPA issues EE/CA completed by Respondents. • September 2008 – EPA issues Action Memorandum for Non-

Time-Critical Removal Action (NTCRA) to remove buildingcontents and demolish buildings, with off-site disposal ofmaterials. EPA starts negotiations with Respondents and SFAsto implement / fund NTCRA.

• August 2009 – Respondents complete Fire Hazards Analysis. • August 2011 – Settlement Agreement for NTCRA becomes

effective. NTCRA Trust funding of $70 MM follows effective date.

Page 10: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Current Site Activities Remedial Investigation / Feasibility Study (RI/FS)

• Initiated in 2004

• Evaluation of nature and extent of contamination, risks to human health and the environment, and options and costs to address unacceptable risks.

• “Everything outside the buildings.”

Non-Time-Critical Removal Action (NTCRA)

• Initiated in 2011.

• Maintenance, then progressive removal of buildings contents and demolition of buildings, with capping of foundations.

Page 11: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

NTCRA Project Scope • Monitoring, access controls and site security

• Building stabilization, removal and disposal of hazardous and flammable and combustible materials

• Removal and disposal of asbestos, universal waste, and building contents

• Demolish ~180,000 feet2 of buildings down to slabs

• Fill voids and place a temporary cap over foundation.

• Dispose of debris off-site at appropriately licensed facilities

• Post-removal site control (security, monitoring)

Page 12: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

NTCRA Project Timeline • NTCRA Trust funded September 2011

• Last Starmet tenant abandoned Site November 2, 2011

• NTCRA Work Plans submitted January 2012, approved September 2012.

• Phase 1 Construction Submittal provided to EPA July 2012, approved March 2013.

• As of August 2013, more than 2,210,560 pounds of waste shipped off-site. Buildings significantly empty.

• NTCRA work on track to be completed by Fall 2014

Page 13: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

inc.

Starmet Facility Buildings

Page 14: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Anticipated Schedule to Complete RI/FS • Prepare revised FS Report (completed August 2013 –

under EPA review)

• EPA submits prospective remedy to NRRB (October2013)

• EPA prepares responses to NRRB comments, revised FS(if needed)

• EPA prepares “Proposed Plan” that identifies overallremedy

• EPA issues Proposed Plan for comment in early 2014

• Meeting on Proposed Plan (early 2014)

• EPA issues “Record of Decision” that sets forth required remedy for Site. (early 2014)

Page 15: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

--,_ . /

() '\ --~

!:!./

I ~ $ .t.

• \

) • • • • • • '$~ • • • •

• • Legend • • I

Site Boundary s Sphagnum lJ1 • aog

• .,,.

ll ' ' AOI Outlines

~ Test Pit

Soil Boring

Surface Soil

Sediment

Surface Water

Staff Gauge ~ • Waterloo Profi • A0116

suRFAce sor.s

• • • • It • -6

• • •

• • ·"· i/

RI Sampling Locations

Page 16: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

sz de maximis, inc.

RI Off-Property Sampling Locations

Page 17: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Remedial Investigation / Risk Assessments Results • Surface soil and subsurface soil exceeding acceptable risk levels

limited to certain areas within Site boundary. DU and PCBs primary drivers for risk.

• Sediment exceeding acceptable risk levels limitedrained to SW portion of bog and cooling water pond. PCBs primary drivers for risk.

• Groundwater contamination exceeding acceptable risk levels exists on-site and in defined area off-site. DU, VOCs and 1,4-dioxane primary drivers for risk.

• DU in overburden groundwater continues to migrate from Holding Basin. Modeling suggests that DU plume > MCLs will migrate off-site within 100 years if no remedial actions performed.

Page 18: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Section 1 –

Section 2 –

Section 3 –

Section 4 –

Section 5 –

Section 6 -

Section 7 -

FS Outline Introduction, background, nature and extent ofcontamination, risk assessment results

ARARs, RAOs, GRAs, PRGs, areas and volumes of media, ID and screening of technology types

ID and screening of technologies and processoptions

Detailed and comparative analysis of soil andsediment remedial alternatives

Groundwater technologies summary

Detailed and comparative analysis of groundwaterremedial alternatives

Detailed and comparative analysis of vapor intrusionremedial alternatives

Page 19: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Preliminary Remediation Goals (PRGs)

PRGs developed in accordance with EPA’s “RAGS Part B” guidance, process detailed in FS Appendix B.

• Soil PRGs developed for PAHs, PCBs, As, U, and Th.

– As and Th PRGs based on background levels.

– PRGs for U (2.3 mg/kg) and PCBs (1 mg/kg) will control scope of soil remediation.

• Sediment PRGs developed for PCBs, Cu, Pb and Hg using ecological risk.

– PRG for PCBs (1 mg/kg) will control scope of sediment remediation in pond and bog.

• Groundwater PRGs based on Federal and State MCLs for VOCs, SVOCs, and metals.

– PRGs for TCE, VC, U and 1,4-dioxane will control extent and duration of groundwater remediation.

Page 20: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Soil and Sediment Remedial Alternatives

SS-1 No Action

SS-2 Excavation of Non-Holding Basin Soils and Sediments and Unsaturated Soils at Holding Basin, In-Situ Stabilization of Saturated Soils below Holding Basin, On-Site Consolidation of All Soils and Sediments and Site Restoration

SS-3 Excavation of Non-Holding Basin Soils and Sediments (On and Off-Site Disposal), In-Situ Stabilization of Unsaturated and Saturated Soils at Holding Basin, Low-Permeability Sub-Grade Cap at Holding Basin, and Site Restoration

Page 21: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Soil and Sediment Remedial Alternatives (continued)

SS-4 Excavation of Non-Holding Basin Soils and Sediments and Off-Site Disposal, Containment and Stabilization of Holding Basin, Low-Permeability Sub-Grade Cap at Holding Basin, and Site Restoration

SS-5 Excavation of Non-Holding Basin Soils and Sediments and Unsaturated Zone Soils at Holding Basin (Off-Site Disposal), In-Situ Stabilization of Saturated Soils beneath Holding Basin, Low-Permeability Sub-Grade Cap at Holding Basin, and Site Restoration

Page 22: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Note on Soils / Sediments Remedial Alternatives

• All soils/sediment options include excavation of approximately 77,000 yards3 of materials > PRGs. This volume includes building slabs and sub-slab soil. Excavation areas and depths illustrated on figure (next page).

• Differences between alternatives are: 1) whether materials are consolidated on-site (SS-2) or disposed off-site (SS-3, SS-4, and SS-5); and 2) how HB is managed.

• HB is source of overburden groundwater DU. Complete excavation of ~95,000 yards3 of HB material containing ~10,000 kg of DU eliminated in FS screening (>$117,000,000 and significant risk to implement).

• HB alternatives need to be effective for at least 200 years (goal is 1,000 years) to meet ARARs from NRC (10 CFR Part 40).

Page 23: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Figure 2.5.2 Excavation Areas with Drains and utilities

X 1111: ~

\l.1clcor ~/:XII<: ::llo

P.l.f~ :IO!I,D.i!U ar:l

8 :;~:" tu 1 Exuvation Depth (ft) .g', :; ~~:(•:lb - J: "'" • !,dtr:t:. 1 • I (l Sli'l :IE~ ll <:lith tlun - I'~~ ill ~a& t:J 1.L l·l.LJ Jl. ·,•er: - • ())Ciht '•'A'IIEI r- ~ (1 :H1 5f ~r-'E ~ t'ctatiE'I'IJI!Er:'L.l.lh'l'l'e C: Ul·UJ 3ll ~UIIlk1~Hd8 t)llrE'tiE • '1.(1·6.0 a :ledr: v.-·hdE - S.iflbr, II Ul · l::l.lJ ~ ·1oor:'il1n - Nf~ht:n'l • HI ·n1 ¢ -"fr·ad - li1 ~:-:1 1i·llu•':llllh!J\'I:I1:1 ~ .. I ~ l.tiL• .lnErn:l>'seiedor $/) VMtH - r)lt'rE'C1)1'r[tH CJ ~C'>E) ~~~~.~di!Or~:3 1:::> :; .rfall l.hlu 1 .,.., ArNNam• a \'<4\'$ ~r:et)JIY.I~rl :6 .l.llc::::.; ~ (OOI.-,Wf«>t~E:UrtE -.Cr:l

CJ u:n br ll'i:J(.,,,~;.·I,..·I~' c:J ~~~ ~~~:~rr ~ ... ·n~l'tl~o)~

t-l1ll ~·uP;).'Ifll 'I ro·aho)l '1

1?2 lUI)'

~ddms .,.. .. ,...,,.:l<.nerr' "n

It~ ltli/Xf!Jtis, {/J(.

Soil and Sediments Exceeding PRGs (Areas and Depths)

Page 24: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

11<':1•"t\l ~.sit! ... --D •<> • (.=J Con~CIIJ:!!llion hO.il)' m

.SS2 ·Oil·Site consolidatiOn F;,clltrpo F9uibil ity Stuct:t

Hut~· Ue!~~ tl<... C>•oc' N/,

"""' ''~! let' ...... ·­,.., .. '''"' ... '' NJJ<.~o(~ 650 600

;, ~!.s:ll!:.\lh:Svrf;.~ <I J.a~b J!t0H•

if"MGf'tO.I!te-U~

)r.lin-.)1'(-ct~rc:mrr.vitr

~n· t H(;Wf ( l'.oiUU':•:ttl(.,;Ttll'l"li:f,orw.

"':liS"(l'lt.let~: O~t.inttor :Z4-aiiY

G;,;\<!Mfr\JG~Oil~~

;,"(\;!\ '•l:ontlf19 /~!jN!g~l('

550 500 450

Stratified Drift

400 350 300 250 200

:"•m•<~!lrr+'i:tr P :tr. !fo'Pf'fkr,")I,...-!HI";ofll:il! f.' ;)bk..t;.;> "ry(J't •)W'1

r.omiJ -ICPE\~''IJ.II,"t!('.,,.II'W'II'I;r.~ttP :,.:'0.\j ltlhr.U:.\..lll)' l!l"<:r KoLL"

- 20

- 0.0

- -20

- -10

- -60

- -80

- -11XI

150 100 80 0 I'WJ-KI'h J t41 --l.'of•lt

tfddrns ~.~~!~ --------------------------------------------------------------------------------------------------------------------

LEGEND Zone 1 -Uranium >30 mg/kg in vadose Zone Soils Zone 2 -Uranium >30 mg/kg in Saturated Zone Soils

Jgj Building to be demolished

..X.. Ground··IJater

Distance units depicted are feet 1ft)

SS2- Consolidation Facility Elevation View Feasibility Study

Nuclear M&tals Inc., Concord, MA

\l;:tn': Fi•J4 ~ - ~_(:F _pmilc: ;t.tlo;-. rd(.tt;!~tl$ . .:.. . h·:· : .. ~::;..(.l'i-•1

=-t•j: ;t he•: :~·ltJ7

~t ... f::!!~.;o.•; I>)'. · ... · •• :

Figure 4.3.2

·~!:!.~ ')I·' -;.·or III:.H·,r \ 8:. =•JI '1H :A;·()

SS-2 Excavation of Non-HB Soils and Sediments and Unsaturated Soils at HB, In-Situ Stabilization of Saturated Soils below HB, On-

Site Consolidation and Site Restoration

Page 25: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

SS-2 - Scope Summary • Construct ~2.5 acre on-site consolidation area, partially co-located on HB.

Off-site reuse of clean soils excavated to create area. • Excavate and place ~77,000 yards3 of site soils and sediments into

consolidation area (off-site disposal of TSCA materials, if any). Backfill excavations with clean soils.

• Holding Basin – Excavate and place ~12,500 yards3 unsaturated zone within consolidation

area (temporary stockpile while saturated HB soils addressed) – In-situ stabilization of saturated soils within the HB using apatite injection – Perform temporary hydraulic containment during HB construction to

control potential for further DU migration • Construct cover on consolidation and restore site. • Perform long-term operations and maintenance (O&M).

Estimated Costs: Capital: $37,586,000 O&M (NPV, 200 years, 7%): $ 7,305,000 Total: $44,891,000

Page 26: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

SS-3 Excavation of Non-HB Soils and Sediments (On and Off-Site Disposal), In-Situ Stabilization of Unsaturated and

Saturated Soils at HB, Low-Permeability Sub-Grade Cap, and Site Restoration

Page 27: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

SS-3 – Scope Summary

• Excavate approximately 77,000 yards3 of site soils and sediments. Dispose off-site. Backfill excavations with clean soil.

• Holding Basin – Perform temporary hydraulic containment during HB construction

to control potential for further DU migration – In-situ stabilize unsaturated and saturated HB soils using cement

based solidification. – Off-site dispose of ~13,000 yards3 of spoils resulting from HB

stabilization process. – Install low-permeability below grade cap stabilized HB – Backfill remaining HB basin to bring it to grade.

• Restore site. • Perform long-term O&M.

Estimated Costs: Capital: $107,636,000 O&M (NPV, 200 years, 7%): $ 7,305,000 Total: $114,941,000

Page 28: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

l.~tlO

,h, !;) j:-o .. •(ll)~ ~lkl·~~e•'lkJ "'l! l:'ii!'J 1!\ovn

c:J")o·

... -I'll ~~:~=';i!,.--~,:~~~

ss.a • V• rttcM Dan'• I Y\'a ll •M Cap f (\"l$11)111()' 611J{tf

~§A~4~~~~~~· ~-...... , ..•

LEGEND

Bldg- c

Stratified Drift

Zone 1 - Uranium > 30 mglkg in Vadose Zone Soils Zone 2 - Uranium > 30 mglkg in SabJrated Zone Soils Zone 3 - Uranium > 30 ugll in Groundwater

181 Building to be demolished .:lL Groundwater

Units depicted are feet (It)

Bldg B-3

-20

-0.0

-40

-60

-80

-100

SS4 -Vertical Barrier Wall Elevation View Feasibility Study

Nuelaar Mat!ls Inc., C<lncard. MA

hJ 0Jn1:: Fi!14 ::. :) .\'RvV pmfh~ L~:.1l~. 1kltir2fJ 1 r~ Auth•:or: ?.~~m~,. 1 >~e. ::L~l r'b . ~~2· ~

Rev ewo?d t·~,: VR

Figure4.3.5

1217EHU'I8 BvdN

OJ QJ

u..

SS-4 Excavation of Non-HB Soils and Sediments and Off-Site Disposal, Containment and Stabilization of HB, Low-

Permeability Sub-Grade Cap, and Site Restoration

Page 29: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

SS-4 - Scope Summary

• Excavate approximately 77,000 yards3 of site soils and sediments. Dispose off-site. Backfill excavations with clean soil.

• Holding Basin – Perform temporary hydraulic containment during HB construction

to control potential for further DU migration – In-situ stabilize unsaturated and saturated HB soils using apatite

injection. – Install vertical containment wall around HB – Install low-permeability below grade cap – Backfill remaining HB basin to bring it to grade.

• Restore site. • Perform long-term O&M.

Estimated Costs: Capital: $77,605,000 O&M (NPV, 200 years, 7%): $ 7,305,000 Total: $84,910,000

Page 30: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

SS-5 Excavation of Non-HB Soils and Sediments and Unsaturated Zone Soils at HB (Off-Site Disposal), In-Situ

Stabilization of Saturated Soils beneath HB, Low-Permeability Sub-Grade Cap, and Site Restoration

Page 31: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

SS-5 – Scope Summary • Excavate approximately 77,000 yards3 of site soils and sediments. Dispose

off-site. Backfill excavations with clean soil. • Holding Basin

– Perform temporary hydraulic containment during HB construction tocontrol potential for further DU migration

– Excavate 12,500 yards3 of unsaturated HB soil. Off-site disposal. – Stabilize saturated HB soils using cement based soil mixing / jet

grouting. – Off-site dispose of ~2,000 yards3 of spoils resulting from HB stabilization

process. – Install low-permeability below grade cap stabilized HB – Backfill remaining HB basin to bring it to grade.

• Restore site. • Perform long-term O&M.

Estimated Costs: Capital: $105,820,000 O&M (NPV, 200 years, 7%): $ 7,305,000 Total: $113,125,000

Page 32: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Groundwater Remedial Alternatives

GW-1 – No Action

GW-2 – Institutional Controls and Long-Term Monitoring

GW-3 – Institutional Controls, Hydraulic Containment (DU and 1,4-Dioxane in Overburden, U in Bedrock), and MNA (VOCs in Overburden and Bedrock)

GW-4 - Institutional Controls, Hydraulic Containment (1,4-Dioxane in Overburden), In-Situ Treatment (DU in Overburden), Long-Term Monitoring (U in Bedrock), and MNA (VOCs in Overburden and Bedrock)

Page 33: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Notes on Groundwater Remedial Alternatives

• Analysis of approaches to specific contaminants and units (e.g., DU in overburden, U in bedrock, VOCs and 1,4-dioxane in overburden and bedrock) assessed separately in FS Section 5.

• Alternatives combined into “unified” groundwater alternatives in FS Section 6.

• Groundwater alternatives assume HB “source control” implemented under soil/sediment alternatives, so consider alternatives to control further DU migration and restore to ARARs.

• No “sources” of VOCs and 1,4-dioxane or U in bedrock identified during RI, so groundwater alternatives consider migration control and restoration to ARARs.

Page 34: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

··:vi · ·~s :sc:

'?.'ttl =x).c.l

1 \11:0• •~<o;

;

/

/ //

I I

/ /

,/ /

/

./

i /

' ' · \, ......

>'X· ~{\)-) "' .... ., Ul,ti/

\.' 1\

:i

•. ....,.Y. II ~~ ,,,,.,

...... __ _

/

'•,---:::-.~~-·•'A .... -·

a.tw-WlO.l!lv.l ~.·:... ~ ..... ~'(~ 3t4)

\.'ll• '))7 M.>4)

1~ l.t;(Yl '.,•";) !A~ .,,y.. ~'JI)

~· ,!1 :llllM ~.'). 1 !,'1))

$'ll l~

..;.l'!~ .j,'(~ 2:)Xl I~ IA:IO•~

~.\'(' ~,'(i

'"' u:<P 1~>:'·1

llll f l

-SG.J ..

__. PZ·RI-D02 t :._ - PZ-RI-S02

'

.

Legend r:o.nb!ilt,: '•'.\:.•1

Pi" ;:;;oroo,l .. o

eun 3:~u\l.: Ct:111ne..wnM f'tn'11l!ll) l~::~htlll

n ~~UF~'O; 'A'ct:t.-.1~

- &uofkt ·A'~I.ef •. " " V'¥· io; -:• MC.bv~~"o: ·~·•;;• ~"iS!; l.lil'tJ

_ C>t<:fJ SEct en;.,.;;

- c ·.:.u&;ctr.nc ..::· = :::::; =~: :~.::::·;:::;::,(~::~:'::~ It N~\'C•: - Groo.·"'d·:nter 'lo'"'d r«::on

-t~! L\ll 'liJII\ . '•b:~t i< II<:O:I! . Cot!:~,;)$

· - · ~~ ... . .. ;,. · .... .,.. • ,~~~ r. ~·-

Nlo\ Vr.a 111.1m ~;.o~.t,; r<n~ , ... ..,..

}itj \:

u.oo 111.0

Total Uranium Concentraticns.in . Overt>ufden Gfoundwater Neaf Hold•ng Bastn

Histotical Data through Octobet 2012 ····:;:-.·,':,\'~;;;;:.·:~!! ••

Geosyntect> consulta1Us

~ Jc nKI.Timi.,·, ilu-•

1.4.2

Area of Depleted Uranium in Overburden Groundwater > PRG

Page 35: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

.,, VOC a nd 1 . .4-0 ioxane P lume Areas in

Overburden and Bedrock Groundwater Most Recent Data through October 2012

~luc;!11&r t-41:tllfli! Su~81iun:J Site Ccr.ccrct ··.1.ns.:ch :~ se::r:s

- Y-•Ie maximiJ·, lll('.

Figure

1.4.3

Areas of Groundwater with VOCs and 1,4-Dioxane > PRGs

Page 36: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

' ~ J. ··:. ...... · 'lot'·'~"

- e-..n .... ........ .

0 6>) 12::1 J.t()

I> Geosyntec consultant~

8 greater than

y Figure de ma..\·lmlt , bt.c.

JUL '2013 1.4.4

Locations and Which VOCs and 1,4-Dioxane > PRGs

Page 37: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

- .. ____ ..._... -~- ./ .. •( ''

.rl

\ ' ' "·

f ~· P1-111-DM

' ..,,,,u.:~n ; .

IIA II •

' . . . . '

Tulal tfr<tnium C Bf!:drock cnuc:~Hfr<ttinns in

Histodcal oaU.: tJ .rotmdwater \Judo~M MNa~~~•gb OC'tobe( 2012

<;onr.ord ~I · 111~rfuncl ~il <' ' · as~nchu:sctts

GeosyntecC> 0€ MA.XIMIS, INC.

consultants

Jllt.V-2<1 13

Uranium in Bedrock Groundwater > PRG

Page 38: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

GW-2 – Scope Summary

• Implement institutional controls to prohibit use of on-and off-property groundwater > PRGs

• Annual monitoring of 35 wells for first 30 years, and then every 5 years from year 31 – 200.

• Provides for Five-Year Reviews to assess protectiveness.

Estimated Costs: Capital: $ 793,000 O&M (NPV, 200 years, 7%): $1,724,000 Total: $2,517,000

Page 39: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

.... Pfo;'IQ$.${'1 i;ft~ t:ti(;n 1.',~1 in e~ro~k (~.4.(li¢y~nP}

~ t"ropo:.cd E.:dro:t:JOn '/,\aU 1n o-.. erbl r.:a-o (1..4-0Joxane)

~ M~n· toting Wei

+ Piezo""netEr

:;J:_ ~ \\~etla"'C8 !'.u-flccM'o\'Mi ft'

C] Sit<o Bo~m;bJ)· t l PIIIII :

.. y ... ;-~ · I / \_ .......

-- E,:,;irn;r;E'd 1-!yo:lr.;.vlic CCil)11lr~ Zt>~ in 0'-''Jibl• <iw.f'l (1 4-0iQ".<''n~j - - 1, 4-Di!)xAn"' .;t..'l-."1".;. .,~..!;o;?h11"'tT~ O~P Drioki"!) '•'i~'to;ir (;,,a,~·i~ in 0\·~rb•.• r.C~;;r.

--':::.:1ma:e:1 H)ldr<~uhc (; <~ ~:ure L.or.:e (0..1 - 0\'l."fburden) -··-· 1.4-0I))hlne aoo .. e t.4-:~ssachuens OSf' Dnntc r.g 'i'itltEr Gu~.1re In I:!Edroctc

-- ~e.<:(m~:e!l Hy·cr~uUe C3~~ur~ Zor-e In e :d•<:el< (' ,4·0leX~n~! -- U!'>'nlum ,b,.,~lh~ .,~t:L(:>30 1JgiL~

- .:e.:ima;e:l H1draulic C.;,p:ureo Zor "e in 9~d-c:ck. (e.e~r«k Urariurr: • •• Ce;~letEd Uranium Jbo~·e tM r\~CL i>30 Jlgi'l }

~ Hokting Ba91r $c;l•c:e Comrol Are;.:;;

I, Th• '\Nt>olo•d"'"l ',.,. , ,._.,. ;, dooj<IM·"'I '"""'"'" ;,. ,,.,..,,!""'"""'' ,.,,,. ~"'"" ~" 2 . li-e ~V'..tl~lcd<:~pt~ott> Zotlt' fotutll!! Ill') nl:!oc-"Jn:o."t ~:.:;Jfi'C'ro

HI !II"'" ,1-:1 <:n ,. h~..,,., ""I>'".; "'' <<I fl .n 1'2, >< 1~-<h:o ..a::<>,,.,.,..,,;,;,,. d :; 1 tl>:l ~v . .,,,.~"'" ;Mitlo tli t7S 11>•u<l :o p ' "" " l!oioll""" " " ' 4~ i, M.:O PI}Ui1U»9flldcnt ofC.OC-9, .:o h)l31.:.ule(I0 1:111'Cti.il~· d 49 ft,'~.:oy.o p1Ufi'>C'o'.oodth<i1i1; 1~ llfl J ~ p\_rne l~id."l"'t!'.'. oi l£ t .

3.11 ~· il'v-.itl.III:\I(';.V,Ill~t .:vt¢ r,u , 4., Tt ll h$JI"'I~C~f"t!J"IJ 'ro<> lntU,_ 1\<,"1)

:>. lt~l:cab~m: ::1 CCI<"'Yr.•ane~:

!oaW'J un ;.o, h,Ut;.\\Jivg•ado:r lvl ) ,!)11, :.oltto.!r;u.~li;~••d.l;ti\•t:r U d.-l 1\.\bt. a ~~~""'M,il'l o:fJOO B :..tiS :.• ~..,,,"' n Oo.:•/~,_..,. ..,1 SOn_

N

t

GW-3: Institutional Conttols, Hold ing Basin Source Control, Hydraulic Containment

IOU, UROCK, 1,4-Dioxono) and MNA jVOCs)

Nuclear Metal!:> Superfund Site Conco:d. l\·1assachusetts

!!""-~;:===:!'----~htl 20.:> 1CO 2Coa

Geosyntec I> collSultants

____;g._ tl~ nm:dmi.V1 inc.

Figure

6.3. 1

GW-3 – Institutional Controls, Hydraulic Containment (DU and 1,4-Dioxane in Overburden, U in Bedrock), and MNA

(VOCs in Overburden and Bedrock)

Page 40: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

GW-3 – Scope Summary

• Implement institutional controls to prohibit use of on-and off-property groundwater > PRGs

• Annual monitoring of 50 wells for first 30 years, and then 40 wells every 5 years from year 31 – 200.

• Extraction of groundwater and ex-situ treatment to control DU in overburden, U in bedrock, and VOCs and 1,4-dioxane in overburden and bedrock – assumed to operate for 30 years

• Provides for Five-Year Reviews to assess protectiveness.

Estimated Costs: Capital: $ 4,258,000 O&M (NPV, 200 years, 7%): $13,597,000 Total: $17,855,000

Page 41: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

' ' i /

'~ // I /i

; .'! ' /;

;/// lil .~ I I

~~;:-!' ';

Legend

1\1 ~ro~-:~d !::)(IJ'~~~•c:r Wtll •n etft~ek -::rop~e.ed Rto~chto zone Mon~·•na iN~ 1

1'\i Pro;:·::MKI CttT~irw ~\f'tll l i n 0\-.rbl.ldt!tn • ~rop:.>l!IIJ<i Mttd '~ h j101cl.i:m Point (Ap 11li l"'}

-4~ .. ~-<.lol !';11 .. 10:1

to: (\'o;i~ung \Nell n orop:>:;cd M~d-.s l njc<:tnn Po1nt (Zero ¥\11erl !f-;»n iZVH)

+ ?!c:z::11nott:f

\. r .. --. • .-1},

,/SF'~N+-: ,/ "'•

- - 1 ,4·DI0)(3M: 3tove M:lt~:~ehuett"! OEP onnklng V'b:~r Gutd&!lnt ' " o·..-e~·een

- · - · 1 ,4•DiOI<I'tr!~ :tl:r.r.tl$ 1.1<tu~chu"i1~ OCP Olinkin:J '<"i'.&:4H G~•ide:ti ntt h 1.'1-ttdnH.:k.

- - Ur.Jntum ;:bt:~ve lh: 1.1CL P·3J 11; ILj

'.\'e'; ll:-~n dt~ --(~::tht:"t !t'ld H~·d·mt16 \;;1p lu1r! 7an~ in ~::tmr:k ( 1 , 4·1)iol(~ne) ~Holding f!:,~in t:1m1~ C-m11ml AIM

CJ SvM~:e- '."hter - S~t!"'l:it!d Hyd~W~ C:!I):1UI'e ZOI'I~ li"l 0\.'e:I'OUI'den (1,4-l.'i~X;)ne.) D Sil~ 8 <Hit)1.3r>J tllltll'l: 1, n. iiW11otW ; -..:ul o$.W111 (o;f lhlt 1 <H)~'«fl" '-""rluUtmWIIItwo~~-..l tW~I lt~AtMIJ;on 1:1\ot tf"VIIIU.~r-~hll 6,(o $1\ll "l, l'=I'~Uillo •rtltlfiJ.;;SIIUil 11'11: ~ (),0 I' , lli. l-~t.ho~li;~l.'flilll.t~tl'f v i ot .~II.\J<'I)' ;, l"b1t:l <>~t;illl ot~:-il 11111t.l11 J.• ~m" !h~··lltot¥ d 50fl. 2.lt(.· il~..tlill.:d ·:..V.IIf<'!O~ f<• tllc l\·n 1.4-.C\:<OIIlt b..~llXkwdl~o~~l'll:Y.. .:Oil ~lr;:.:~onr,)lccf ;a,:~o:u·~):ly ( 0,(;. 911"!· h~dt>'l 01 h)•dr.wlc,grOidi:nl olO.C~ llyC:r;,u!Ocontb:b•r t.i -::.22 11.\:J.t)' ~ ph~•::".~otlhcf-420\Md o11pl ~~ llli:~rc--...-. d26 fl. 0.11-.o lee~.,ew. ef «ol'l'o«r,Jt~Ce> linee, lr¢.."11m«tbult-.~.~., ~ o1~·~e ine \'mll:l te eclo::od .t; -in~ romdbld~iQ, , ~ . Tt .- ll:l)r¥1 IWII r.~n·cn~u. 1110\' l ,.t.Otlfi(A .. .,_ fiiJmM0-1!~"• r-n~UI IITIIun;;m~ r.llrtr(.

'f/ ;\ ~­v··~, ·' ·.

'. cs·,::::\ '.)J·o···· \ ' • ¢ ' • ..

\

GW-4: lnstituti on31 Contmls, Holding Basin Source Control, Hydraulic Containment

(1 ,4-Dioxano}, ln-Situ Trnatmont {DUJ, Long-Term Monitoring (UROCK} and MNA (VOCs}

NIXIe~r Me~J'$ Sup~rttln¢ tilt~ fil.lSS3ChUS~1;!'o

~ .. ~~==~ ........ ~.~~ :.<"::<! ltl ) 1!))

Geosyntec~> consultants

~ de ma.timis. inc

Figure

6.4.1

GW-4 - Institutional Controls, Hydraulic Containment (1,4-Dioxane in Overburden), In-Situ Treatment (DU in Overburden), Long-Term Monitoring

(U in Bedrock), and MNA (VOCs in Overburden and Bedrock)

Page 42: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

GW-4 – Scope Summary

• Implement institutional controls to prohibit use of on-and off-property groundwater > PRGs

• Semi-annual monitoring of 40 wells for first 8 years, and then 35 wells annually from year 9 – 30, then 45 wells once every 5 years from year 31 – 200.

• In-situ treatment of overburden DU plume • Monitored Natural Attenuation (MNA) for VOCs in overburden

and bedrock, Long-term Monitoring of U in bedrock • Extraction of groundwater and ex-situ treatment to control 1,4-

dioxane in overburden and bedrock – assumed to operate for 30 years

• Provides for Five-Year Reviews to assess protectiveness. Estimated Costs: Capital: $ 4,939,000 O&M (NPV, 200 years, 7%): $ 6,122,000 Total: $11,061,000

Page 43: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Vapor Intrusion Remedial Alternatives

VI-1 No Action

VI-2 Institutional Controls and Development Restrictions

VI-3 Institutional Controls and Vapor Mitigation

Page 44: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

-+ P1Ctl)ll'¢0CI'

¢> $1t(l(>·(U$1~

• :.t'l,.l: <:l'•~I)Ut..:len StW:i'/•~1

• f~noc:· Onltn.ut-=n &!~pi~ Wl:'l

• r:>m>~~· Bfl:u:d::ll.(lf!!f•'•·

~ Publb\V;~t$.(.1~1(\V.If

V\tl!an(t;

Sllp1c fl$ r.'!i

C t.llti61>0 11' :!11rt

OP.:.tx;.

~s Ex(eedhlQ Vapor ltltrusiot~ Screenillg L~vel-s ett•.··dnn· 0.71 j;~l

• p(;£-~1)~·-

• TOE· ::I Gl l•t?•t

• \'C-01"1-!;i.'L

• \'Ot:r. cletM":!:d ,, "'•'llt:.t-4~1'1 r.nf ;H t«""r.~niMtm~g-<:-!111~1 t>'ll'l :tr.1')hr,'lfr~crh ~l) 1 111~

8t<C':t.c !:e-~!Yt i\4(.X!C~tfll~ ilbtl:.. S~:<.c .. ~l~ ,)~ <te'f~OI!-1 ¥.'.1 ... ' )$/N'(, W,V 6'~ :V:, t":l>l!lOI o~..:~~/;l()I.11Cr.'•IL X l

• :;(( $ (•I •) hu ... JI!'Y j:l;l<' Ult.l t.y ·~,~...,:::,1~ ·t:l~~ 11 <'\1~.11 trd ii'I,' I (O' MII:IkJ :111.11 lj.>'l!ll>Wlot~C 'C ~If,l!h1',;;~,

• \ ' 'f'" '"""''"" t.;,..,.,;,:~ t.. .. .,., ... ,~ ... ; ........ .:..t ........ <l ...... e u. .. er.-. · .. 1nL .,,.t..., .,,,. .. .,; .. ~.11 .,,.. &!,._.»>II 1'•'*!\I-1UIIf look•: ;!l1l \t\,U/1.,...,1'.:/t•~l-l .r.~ i':A: I ' -! fll¥ol /Mt'll :t~lo) 11'1:1•:11 (f: 'fll\o'l lfl rr.ll~l llll\'t.trtv.:t -~~l

Areas Exce.~ding Vapor Intrusion Screening Levels

Nuclear Metals Superlund Site Concord, Massachusetts

Geosyntec C> consultants

-&-dr nurximls. ltu:

O!l.t.UG ::<Ot2

Figure

1.4.S

Areas Exceeding Vapor Intrusion Screening Levels

Page 45: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

VI-2 Institutional Controls and Development Restrictions

Institutional Controls would be implemented to limit construction of new buildings to areas where significant VI is not expected.

Costs: Capital: $ 0 O&M (NPV, 30 years, 7%): $214,000 Total: $214,000

Page 46: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

VI-3 Institutional Controls, Future Investigation and Vapor Mitigation (if needed)

Institutional Controls would be implemented to require that new buildings include vapor mitigation measures in areas where unacceptable VI is possible.

Future Investigation includes new monitoring wells and soil sampling.

Vapor Mitigation would include vapor barrier plus sub-slab venting system – costs assume 10 future residential buildings, each with a 1,600 ft2 footprint

Costs: Capital: $ 403,000 O&M (NPV, 30 years, 7%): $ 944,000 Total: $1,347,000

Page 47: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Note on Costs

FS costs calculated pursuant to EPA’s guidance, which requires use of 7% discount rate for net present worth analysis of long-term O&M costs.

Using current White House OMB discount rate1 of 1.1% increases O&M costs by factor of ~5.9 (i.e., an O&M cost estimated in the FS using 7% discount of $10 million would actually cost $59 million to fund using today’s interest rates)

1 http://www.whitehouse.gov/omb/circulars_a094/a94_appx-c.

Page 48: Nuclear Metals, Inc. Superfund Site Site PresentationSuperfund Site Site Presentation September 4, 2013 Presentation Outline • Background • Current Work • NTCRA Overview •

Noteworthy FS Appendices

Appendix B – PRG calculations

Appendices C, D & E – Soil, Groundwater and VI Cost Estimates

Appendix H – TEDE Evaluations (ResRad & Dose Compliance Calculator)

Appendix I – Institutional Controls Analysis


Recommended