1 Addendum No. 02 TO: PLANS AND SPECIFICATIONS FOR: Upgrades to Air Distribution System Missouri State Capitol Building Jefferson City, MO Project No: O2016-01 Bid Opening Date: Unchanged: 1:30 PM, Thursday, January 28, 2021 BIDDERS ARE HEREBY INFORMED THAT THE CONSTRUCTION PLANS AND/OR SPECIFICATIONS ARE MODIFIED AS FOLLOWS: 1. SPECIFICATIONS: A. Section 230923 – Direct Digital Control (DDC) System i. ADD “Setra” to the list of acceptable manufacturers for Pressure Transmitters/Transducers (Hydronic) listed in Paragraph 2.21.D.1 ii. MODIFY Paragraph 2.21.D.2.a to read as follows: The transmitter shall be smart microprocessor based electronics Pressure Sensor: Industrial grade “Smart” microprocessor based electronics “hockey puck” type with accuracy of +/- 0.25% of full scale or better, plated steel body, .25” NPT process connection, 316 stainless steel measuring cell with silicon oil fill fluid. Minimum temperature rating shall be that of 353 deg. F (125 psig saturated steam). Units shall be rated for a minimum of 150% full-scale overpressure and shall be suitable for an operating static pressure of 200 PSIG. Provide with connection fittings. Sensor control signal output shall be 4-20mA. Housing shall be NEMA 4X epoxy- polyester coated cast aluminum threaded connection head, screwed access cover with o-ring and ½” NPT electrical connection. iii. ADD “Schneider” to the list of acceptable Actuator manufacturers listed in Paragraph 2.24.A B. Section 233113 – Metal Ducts i. MODIFY Paragraph 3.6.D.1 to read as follows: All ductwork that is existing to remain located in the following House Hearing Rooms shall be cleaned: Hearing Room 1 (B25), Hearing Room 2 (B30), Hearing Room 3 (B28), Hearing Room 4 (B37), Hearing Room 5 (B17), Hearing Room 6 (B18), Hearing Room 7 (B24).
Transcript
Page 1: O2016-01 Addendum 02

1

Addendum No. 02 TO: PLANS AND SPECIFICATIONS FOR:

Upgrades to Air Distribution System Missouri State Capitol Building Jefferson City, MO

Project No: O2016-01

Bid Opening Date: Unchanged: 1:30 PM, Thursday, January 28, 2021

BIDDERS ARE HEREBY INFORMED THAT THE CONSTRUCTION PLANS AND/OR SPECIFICATIONS ARE MODIFIED AS FOLLOWS:

1. SPECIFICATIONS:

A. Section 230923 – Direct Digital Control (DDC) System

i. ADD “Setra” to the list of acceptable manufacturers for Pressure

Transmitters/Transducers (Hydronic) listed in Paragraph 2.21.D.1

ii. MODIFY Paragraph 2.21.D.2.a to read as follows:

The transmitter shall be smart microprocessor based electronics Pressure Sensor: Industrial grade “Smart” microprocessor based electronics “hockey puck” type with accuracy of +/- 0.25% of full scale or better, plated steel body, .25” NPT process connection, 316 stainless steel measuring cell with silicon oil fill fluid. Minimum temperature rating shall be that of 353 deg. F (125 psig saturated steam). Units shall be rated for a minimum of 150% full-scale overpressure and shall be suitable for an operating static pressure of 200 PSIG. Provide with connection fittings. Sensor control signal output shall be 4-20mA. Housing shall be NEMA 4X epoxy-polyester coated cast aluminum threaded connection head, screwed access cover with o-ring and ½” NPT electrical connection.

iii. ADD “Schneider” to the list of acceptable Actuator manufacturers listed in

Paragraph 2.24.A

B. Section 233113 – Metal Ducts

i. MODIFY Paragraph 3.6.D.1 to read as follows: All ductwork that is existing to remain located in the following House Hearing Rooms shall be cleaned: Hearing Room 1 (B25), Hearing Room 2 (B30), Hearing Room 3 (B28), Hearing Room 4 (B37), Hearing Room 5 (B17), Hearing Room 6 (B18), Hearing Room 7 (B24).

Page 2: O2016-01 Addendum 02

2

C. Section 262923.13 – Variable-Frequency Motor Controllers, 480-Volt Input

i. ADD new Paragraph 1.3 A as follows:

A. Section 033053 – Miscellaneous Cast-In-Place Concrete

B. CHANGE Paragraphs 1.3 A through J to B through K, respectively.

ii. MODIFY Paragraph 2.6 A as follows:

A. ADD Paragraph 4 as follows: 4. IEC contactors, electronic bypass controls and use of less

than three NEMA contactors for the bypass will not be accepted.

iii. MODIFY Paragraph 2.7 B as follows:

B. ADD the following to the end of Paragraph B:

The maximum size of the enclosure for the 50hp building chilled water pumps shall be 36”Wx24”Dx84”H.

iv. ADD new Paragraph 3.2 C as follows:

C. Control equipment having an enclosure that is greater than or equal to 72” in height shall have all four corners of the base of the enclosure bolted to a concrete housekeeping pad meeting the requirements of Section 033053 – Miscellaneous Cast-In-Place Concrete.

2. PLANS:

A. Sheet G-003 – HOUSE HEARING ROOM PHASING PLAN

i. ADD Notes to maintain access through the west entrance and through the

single door between Room B3 and B2 for the duration of the project, see plans for locations.

ii. Refer to revised Sheet G-003, attached.

B. Sheet GD-101 – BASEMENT RC AND FP DEMOLITION PLAN – QUADRANT A

i. ADD Keyed Note 6 calling for demolition of a portion of the existing soffit in Hearing Room 6.

ii. ADD Keyed Notes 1 and 2 to the corridor South of Hearing Room 4 to call for selective demolition in that area.

iii. Refer to revised Sheet GD-101, attached.

C. Sheet GD-102 – BASEMENT RC AND FP DEMOLITION PLAN – QUADRANT B

Page 3: O2016-01 Addendum 02

3

i. ADD Keyed Notes 1 and 2 to the corridor South of Hearing Room 4 to call for selective demolition in that area.

ii. Refer to revised Sheet GD-102, attached.

D. Sheet G-101 – BASEMENT RC AND FP PLAN – QUADRANT A

i. ADD Keyed Note 6 calling for replacement of a portion of the existing soffit in Hearing Room 6.

ii. ADD Keyed Notes 1 and 2 to the corridor South of Hearing Room 4 to call for reinstallation of the ceiling and ceiling mounted devices in that area.

iii. Refer to revised Sheet G-101, attached.

E. Sheet G-102 – BASEMENT RC AND FP PLAN – QUADRANT B

i. ADD Keyed Notes 1 and 2 to the corridor South of Hearing Room 4 to call for reinstallation of the ceiling and ceiling mounted devices in that area.

ii. Refer to revised Sheet G-102, attached.

F. Sheet MD-101 – BASEMENT FLOOR DEMOLITION PLAN – QUADRANT A

i. MODIFY Keyed Note 22 to clarify that the existing steam risers remain.

ii. ADD Keyed Note 23 to disconnect and abandon existing chilled water piping serving AHU-B17.

iii. Refer to revised Sheet MD-101, attached.

G. Sheet MD-104 – BASEMENT FLOOR DEMOLITION PLAN – QUADRANT D

i. ADD Keyed Note 23 to disconnect and abandon existing chilled water

piping serving AHU-B17.

ii. Refer to revised Sheet MD-104, attached.

H. Sheet MD-401 – ENLARGED MECHANICAL ROOM DEMOLITION PLANS

i. MODIFY note to clarify that the 12” storm drain piping near AHU-301 is existing to remain and is routed approximately 66” A.F.F.

ii. Refer to revised Sheet MD-401, attached.

I. Sheet M-101 – BASEMENT FLOOR RENOVATION PLAN – QUADRANT A

i. ADD Fire Dampers at new duct penetrations between garage and adjacent occupied spaces.

ii. ADD Keyed Note 22 to describe new duct penetration through floor slab and call for a fire damper at the floor penetration.

Page 4: O2016-01 Addendum 02

4

iii. Refer to revised Sheet M-101, attached.

J. Sheet M-103 – BASEMENT FLOOR RENOVATION PLAN – QUADRANT C

i. MODIFY Keyed Note 1 to agree with the BAS Coordination Schedule and

clarify that FCU-BC01 and FCU-BC02 are receiving new control valves but are not being integrated into the BAS.

ii. MODIFY VB02-05 equipment tag to clarify VAV Box number.

iii. Refer to revised Sheet M-103, attached.

K. Sheet M-104 – BASEMENT FLOOR RENOVATION PLAN – QUADRANT D

i. ADD Fire Dampers at new duct penetrations between garage and adjacent occupied spaces.

ii. Refer to revised Sheet M-104, attached.

L. Sheet M-403 – ENLARGED MECHANICAL ROOM RENOVATION PLAN

i. MODIFY Keyed Notes to show all of Keyed Note 8, which had been previously cut off and was not visible.

ii. ADD Detailed Elevation Views of the AHU-216 ductwork to clarify the ductwork configuration.

iii. MODIFY AHU-216 Plan View and Elevation View details to clarify cold

deck and neutral deck supply air connection locations.

iv. Refer to revised Sheet M-403, attached.

M. Sheet M-405 – ENLARGED MECHANICAL ROOM RENOVATION PLAN

i. MODIFY AHU-303 Plan View and Elevation View details to correct the locations of the access doors and coil connections.

ii. Refer to revised Sheet M-405, attached.

N. Sheet M-406 – ENLARGED MECHANICAL ROOM RENOVATION PLAN

i. ADD Fire Dampers at new duct penetrations between garage and adjacent occupied spaces.

ii. Refer to revised Sheet M-406, attached.

O. Sheet M-502 – DETAILS

i. ADD Fire Damper and duct boot details.

ii. Refer to revised Sheet M-502, attached.

Page 5: O2016-01 Addendum 02

5

P. Sheet M-602 - SCHEDULES

i. MODIFY Control Valve Schedule to indicate that CV-FCU-BC02-HC shall

be a 3-way valve.

ii. MODIFY VAV Box Schedule to clarify the tag for VAV Box VB02-05, which was previously not numbered.

iii. Refer to revised Sheet M-602, attached.

Q. Sheet ED-101 – ELECTRICAL DEMOLITION – BASEMENT FLOOR QUADRANT A

i. ADD Key Note 8 to relocate existing emergency lighting unit and remove existing u-channel support stand for existing VFDs.

ii. Refer to revised Sheet ED-101, attached.

R. Sheet E-101 – POWER PLAN – BASEMENT FLOOR QUADRANT A

i. MODIFY Key Note 1 to reference Specification Section 033053 for concrete housekeeping pad construction.

ii. MODIFY Key Note 3 to change from mounting the new VFDs to a U-channel support stand to mounting them on a concrete housekeeping pad per Specification Section 033053

iii. Refer to revised Sheet E-101, attached.

S. Sheet E-110 – POWER PLAN – 5TH FLOOR – NORTH

i. ADD 120VAC, 1-Phase branch circuit for new Schneider Electric

Struxureware BAS control panel that is to be installed by the Controls Contractor.

ii. ADD Key Notes 2 and 3 related to the addition of the 120VAC power circuit for the new BAS control panel.

iii. Refer to revised Sheet E-110, attached.

3. GENERAL:

(none)

4. ATTACHMENTS:

A. Revised Sheet G-003, dated 1/21/2021 B. Revised Sheet GD-101, dated 1/21/2021 C. Revised Sheet GD-102, dated 1/21/2021 D. Revised Sheet G-101, dated 1/21/2021 E. Revised Sheet G-102, dated 1/21/2021

Page 6: O2016-01 Addendum 02

6

F. Revised Sheet MD-101, dated 1/21/2021 G. Revised Sheet MD-104, dated 1/21/2021 H. Revised Sheet MD-401, dated 1/21/2021 I. Revised Sheet M-101, dated 1/21/2021 J. Revised Sheet M-103, dated 1/21/2021 K. Revised Sheet M-104, dated 1/21/2021 L. Revised Sheet M-403, dated 1/21/2021 M. Revised Sheet M-405, dated 1/21/2021 N. Revised Sheet M-406, dated 1/21/2021 O. Revised Sheet M-502, dated 1/21/2021 P. Revised Sheet M-602, dated 1/21/2021 Q. Revised Sheet ED-101, dated 1/21/2021 R. Revised Sheet E-101, dated 1/21/2021 S. Revised Sheet E-110, dated 1/21/2021

END OF ADDENDUM 02

Page 7: O2016-01 Addendum 02
Page 8: O2016-01 Addendum 02
Page 9: O2016-01 Addendum 02
Page 10: O2016-01 Addendum 02
Page 11: O2016-01 Addendum 02
Page 12: O2016-01 Addendum 02
Page 13: O2016-01 Addendum 02
Page 14: O2016-01 Addendum 02
Page 15: O2016-01 Addendum 02
Page 16: O2016-01 Addendum 02
Page 17: O2016-01 Addendum 02
Page 18: O2016-01 Addendum 02
Page 19: O2016-01 Addendum 02
Page 20: O2016-01 Addendum 02
Page 21: O2016-01 Addendum 02
Page 22: O2016-01 Addendum 02
Page 23: O2016-01 Addendum 02

ED-101

ELECTRICALDEMOLITION -BASEMENT FLOORQUADRANT A BASEMENT FLOOR ELECTRICAL DEMOLITION PLAN - QUADRANT A

SHEET 68 OF 103

BDFBDFMNS

O2016-01-0001- 05001ED-101.dwg

ISSUE DATE:

SHEET NUMBER:

SITE #

CHECKED BY:DRAWN BY:

DESIGNED BY:

DATE:REVISION:

ASSET #

PROJECT #

SHEET TITLE:

REVISION:DATE:

REVISION:DATE:

CAD DWG FILE:

STATE OF MISSOURIMICHAEL L. PARSON,GOVERNOR

OFFICE OF ADMINISTRATIONDIVISION OF FACILITIESMANAGEMENT,DESIGN AND CONSTRUCTION

O2016-0110013101001040

MISSOURI CAPITOL BUILDINGUPGRADES TO THE AIRDISTRIBUTION SYSTEM

JEFFERSON CITY, MISSOURI

1736 West Park Center Drive, Suite 204 St. Louis, MO 63026 ● 636-600-1551

ROGERS-SCHMIDTENGINEERING CO., P.C.

CONSULTING ENGINEERS

MO Certificate of Authority No. 000408

12/10/2020

BERNHARD TME ENGINEERING622 Emerson Road, Suite 250St. Louis, MO 63141 ● 314-727-8760MO Certificate of Authority No. 2009021478

BARRY D. FREINERRegistered Professional Engineer

MO # E-24220Expires 12-31-2022

12/10/2020

ADDENDUM 2 01-21-2021

Page 24: O2016-01 Addendum 02

E-101

POWER PLAN -BASEMENT FLOOR -QUADRANT A

BASEMENT FLOOR ELECTRICAL POWER PLAN - QUADRANT A

SHEET 78 OF 103

BDFBDFMNS

O2016-01-0001- 05001E-101.dwg

ISSUE DATE:

SHEET NUMBER:

SITE #

CHECKED BY:DRAWN BY:

DESIGNED BY:

DATE:REVISION:

ASSET #

PROJECT #

SHEET TITLE:

REVISION:DATE:

REVISION:DATE:

CAD DWG FILE:

STATE OF MISSOURIMICHAEL L. PARSON,GOVERNOR

OFFICE OF ADMINISTRATIONDIVISION OF FACILITIESMANAGEMENT,DESIGN AND CONSTRUCTION

O2016-0110013101001040

MISSOURI CAPITOL BUILDINGUPGRADES TO THE AIRDISTRIBUTION SYSTEM

JEFFERSON CITY, MISSOURI

1736 West Park Center Drive, Suite 204 St. Louis, MO 63026 ● 636-600-1551

ROGERS-SCHMIDTENGINEERING CO., P.C.

CONSULTING ENGINEERS

MO Certificate of Authority No. 000408

12/10/2020

BERNHARD TME ENGINEERING622 Emerson Road, Suite 250St. Louis, MO 63141 ● 314-727-8760MO Certificate of Authority No. 2009021478

BARRY D. FREINERRegistered Professional Engineer

MO # E-24220Expires 12-31-2022

12/10/2020

ADDENDUM 2 01-21-2021

Page 25: O2016-01 Addendum 02

POWER PLAN -5TH FLOOR - NORTH

E-110SHEET 87 OF 103

O2016-01-0001-05001-E-110.DWGMNSBDFBDF

FIFTH FLOOR ELECTRICAL POWER PLAN - NORTH

ISSUE DATE:

SHEET NUMBER:

SITE #

CHECKED BY:DRAWN BY:

DESIGNED BY:

DATE:REVISION:

ASSET #

PROJECT #

SHEET TITLE:

REVISION:DATE:

REVISION:DATE:

CAD DWG FILE:

STATE OF MISSOURIMICHAEL L. PARSON,GOVERNOR

OFFICE OF ADMINISTRATIONDIVISION OF FACILITIESMANAGEMENT,DESIGN AND CONSTRUCTION

O2016-0110013101001040

MISSOURI CAPITOL BUILDINGUPGRADES TO THE AIRDISTRIBUTION SYSTEM

JEFFERSON CITY, MISSOURI

1736 West Park Center Drive, Suite 204 St. Louis, MO 63026 ● 636-600-1551

ROGERS-SCHMIDTENGINEERING CO., P.C.

CONSULTING ENGINEERS

MO Certificate of Authority No. 000408

12/10/2020

BERNHARD TME ENGINEERING622 Emerson Road, Suite 250St. Louis, MO 63141 ● 314-727-8760MO Certificate of Authority No. 2009021478

BARRY D. FREINERRegistered Professional Engineer

MO # E-24220Expires 12-31-2022

12/10/2020

ADDENDUM 2 01-21-2021