Date post: | 18-Nov-2014 |
Category: |
Business |
Upload: | osum-oil-sands-corp |
View: | 14,233 times |
Download: | 0 times |
We are unlocking Canada’s unrealized bitumen resource potential.
The time is right.
Steve Spence, President and CEOTD Securities Unconventional Energy ConferenceJuly 6, 2011
1
Disclaimer
Forward Looking Statements
This presentation contains statements that may constitute "forward-looking statements” within the meaning of applicable securities legislation. These statements include, among others, statements regarding business strategy, beliefs, plans, goals, objectives, assumptions or statements about future events or performance. By their nature, forward looking statements are subject to numerous risks and uncertainties, some of which are beyond the Corporation's control, including the impact of general economic conditions, industry conditions, volatility of commodity prices, currency "uctuations, environmental risks, competition from other industry participants, lack of availability of quali#ed personnel or management, stock market volatility and ability to access suf#cient capital from internal and external sources. Readers are cautioned that the assumptions used in the preparation of such information, although considered reasonable at the time of preparation, may prove to be incorrect and, as such, undue reliance should not be placed on forward looking statements. Actual results, performance or achievement could differ materially from those expressed in, or implied by any forward looking statements in this presentation, and accordingly, no assurance can be given that any of the events anticipated by the forward looking statements will transpire or occur, or if any of them do so, what bene#ts the Corporation will derive therefrom.
The Corporation disclaims any intention or obligation to update or revise any forward looking statements, whether as a result of new information, future events or otherwise.
Reserves and Resources
The reserve and resource estimates herein were extracted from reports prepared by GLJ, an independent professional petroleum engineering #rm, in accordance with Canadian Securities Administrators’ National Instrument 51-101 (NI 51-101) and the Canadian Oil and Gas Evaluation Handbook. Under NI 51-101, proved reserves are those reserves which can be estimated with a high degree of certainty to be recoverable. It is 90 percent likely that actual remaining quantities will exceed estimated proved reserves. Probable reserves are those additional reserves that are less certain to be recovered than proved reserves. It is equally likely that the actual remaining quantities recovered will be greater or less than the sum of proved plus probable reserves. Possible reserves are those additional reserves that are less certain to be recovered than probable reserves. There is only a 10 percent probability that the quantities actually recovered will equal or exceed the sum of proved plus probable plus possible reserves. Contingent Resources are those quantities of petroleum estimated, as of a given date, to be potentially recoverable from known accumulations using established technology or technology under development, but which are not currently considered to be commercially recoverable due to one or more contingencies. Contingencies may include factors such as economic, legal, environmental, political, and regulatory matters, or a lack of markets. Contingent Resources are further classi#ed in accordance with the level of certainty associated with the estimates and may be subclassi#ed based on project maturity and/or characterized by their economic status. Resource estimates are described as follows: Best Estimate –This is considered to be the best estimate of the quantity that will actually be recovered from the accumulation. If probabilistic methods are used, there should be at least a 50 percent probability (P50) that the quantities actually recovered will equal or exceed the best estimate.; High Estimate – This is considered to be an optimistic estimate of the quantity that will actually be recovered. It is unlikely that the actual remaining quantities recovered will exceed the high estimate. If probabilistic methods are used, there should be at least a 10 percent probability (P10) that the quantities actually recovered will equal or exceed the high estimate. Low Estimate– this is considered to be a conservative estimate of the quantity that will actually be recovered from the accumulation. If probabilistic methods were used, the term re"ects a P90 con#dence level.
Unless otherwise stated, all !gures presented in Canadian Dollars.
ALL REFERENCES TO THE FEBRUARY 2011 GLJ ASSESSMENT REFLECT THE JANUARY 2011 GLJ ASSESSMENT FOR THE COMPANY'S RESERVE AND RESOURCE BASE AT THAT DATE, PLUS A FEBRUARY 2011 GLJ ASSESSMENT OF A PROPERTY ACQUIRED BY OSUM IN FEBRUARY 2011 - ALL USING THE GLJ JANUARY 2011 PRICE FORECAST.
2
3
SCALE AND UPSIDE THROUGH AN UNMATCHED POSITION
• Early mover in the largest undeveloped oil field in the world
• 170,000 net acres of contiguous land in the heart of the trend
• 3,154 million barrels of contingent recoverable resource (1)
• 300,000+ bbl/day net production potential
• Commercial performance demonstration underway in next generation SAGD pilot (40% WI)
• First commercial project application submitted
Impressive growth potential with a solid foundation.
(1) GLJ February 2011
4
UNDERPINNED BY A SOLID FOUNDATION
• 45,000 bbl/d Taiga Project
• 359 million barrels of 2P reserves (1)
• Regulatory approval anticipated in 2011 / early 2012
Impressive growth potential with a solid foundation.
SCALE AND UPSIDE THROUGH AN UNMATCHED POSITION
• Early mover in the largest undeveloped oil field in the world
• 170,000 net acres of contiguous land in the heart of the trend
• 3,154 million barrels of contingent recoverable resource (1)
• 300,000+ bbl/day net production potential
• Commercial performance demonstration underway in next generation SAGD pilot (40% WI)
• First commercial project application submitted
(1) GLJ February 2011
We have the team to back upour assets.
We have the team to back up our assets.Osum is now comprised of over 50 oil sands professionals with hands on experience in all aspects of major thermal projects, from modeling reservoirs to building and operating steam facilities, and doing it all with care for people and the environment. Our people are highly skilled, passionate and motivated to unlock value.
Osum Pie Charts DATA
Years (%) Sta! (%)Projects 260 years (29%) 13 (28%)Operations 175 years (19%) 8 (17%)Geoscience 135 years (15%) 8 (17%)Finance & Commercial 80 years (9%) 5 (10%)Reservoir 80 years (9%) 4 (8%)HSE 65 years (7%) 3 (6%)Public & 49 years (6%) 3 (6%)"" Investor RelationsHR 49 years (6%) 2 (4%)
TOTAL 893 years (100%) 46 sta!
ProjectsOperations
Thermal developments in which our team members have experience
Geoscience Osum projects
Additional Landmarks
Finance & CommercialReservoirHSEPublic & Investor RelationsHR
–Osum projects–Thermal developments in which our team members have experience
SaleskiCarbonates
Peace River
Firebag
Long Lake
Fort McMurray
Leismer
Christina Lake
Foster Creek
North Tangleflags
Primrose
Wolf Lake
Orion
Taiga ProjectCold Lake
Calgary
Edmonton
Tucker
IOL Cold Lake
TARGETED APPROACH
• Laterally and vertically continuous reservoirs
• Close to existing infrastructure
• Developable using proven thermal technology
• Opportunities enhanced with technological innovation
QUALITY TEAM
• Deep understanding of the resource base
• Richly experienced project team
5
LeaseAcquisition
DelineationCore Well& Seismic
ProjectDe!nition &
InitialContingent
ResourceBooking
Piloting RegulatoryApplication
& InitialConversion
of Resourcesto Reserves
Engineering& Commercial
Preparation
RegulatoryApplication
Approval
Construction Production
$9,113,000,000
$1,796,000,000
SALESKI CARBONATE PROJECTS / UNRISKED NPV(1)
TAIGA PROJECT / UNRISKED NPV(2)
Net interest in JV portion of carbonate projects($3,473,000,000)
100% portion of carbonate projects($5,640,000,000)
(1) Best Estimate Contingent Recoverable Resources, 10% pre tax (GLJ Feb 2011)(2) 2P Reserves plus Best Estimate Contingent Recoverable Resources, 10% pre tax (GLJ Feb 2011)
For Illustrative Purposes6
PORTFOLIO VALUE - BEST ESTIMATE UNRISKED
FINANCIAL HIGHLIGHTS
• $540MM of capital raised to date
• 83.2MM basic (96.9MM fully diluted) shares outstanding
• $196MM working capital (including $60MM of callable common share purchase warrants) as at March 31, 2011
• Sophisticated equity investors
‣ Warburg Pincus
‣ Blackstone Capital Partners
‣ Korea Investment Corporation
‣ Goldman Sachs
‣ Camcor Partners
Estimated remaining funding(Year End 2011)
Depicts estimated utilized and remaining funding as a portion of approximately $196 MM in Q1 2011 working capital at year end 2011.
7
#1 RANKED PRE-PRODUCTION OIL SANDS COMPANY IN 2P RESERVES
#3 RANKED PRE-PRODUCTION OIL SANDS COMPANY IN 2P RESERVES PLUS BEST ESTIMATE CONTINGENT RECOVERABLE RESOURCES
8
Source: Credit Suisse
OsumIn ProductionPre-Production
0
750
1500
2250
3000
Sun
cor
CO
S
MEG
Cen
ovus
OPTI
Con
nach
er
Osu
m
Ath
abas
caIv
anho
e
STP
Pet
roba
nkSun
shin
e
Laric
ina
AO
S
Sliv
erbi
rch
Par
amou
ntB
lack
pear
l
BQ
I
7,170
359 MMbbls
28,039
0
2500
5000
7500
10000
Sun
cor
Ath
abas
caC
enov
us
MEG
Laric
ina
CO
S
Osu
m
OPTI
Sun
shin
eSliv
erbi
rch
STP
Con
nach
erPet
roba
nkPar
amou
ntB
lack
pear
lIv
anho
e
AO
S
BQ
I
3,617 MMbbls
MAJOR RESOURCE BASE
• Independent engineering appraisal (1) (2) (3)
RESERVES359 MMbbl Proved plus Probable (2P)533 MMbbl Proved plus Probable plus Possible (3P)
RESOURCES711 MMbbl Low Estimate Contingent3,258 MMbbl Best Estimate Contingent5,503 MMbbl High Estimate Contingent
• Total production potential in excess of 350,000 bopd
(1) Net working interest.(2) Based on February 2011 GLJ assessment.(3) Refer to “Reserves and Resources” on Disclaimer slide.
0
1
2
3
4
June 2007 January 2008 January 2009 January 2010 January 2011 February 2011
GLJ Proved Plus Probable ResourcesGLJ Best Estimate Contingent Recoverable Resources
Billio
ns
of
Barr
els
GROWTH OF RESERVES AND RECOVERABLE RESOURCES
9
0
15
30
45
60
75
90
105
120
January 2007 January 2008 January 2009 January 2010 January 2011 February 2011
Net Working Capital (including dilutive proceeds)10% BT NAV of GLJ Proved Plus Probable Reserves10% BT NAV of GLJ Best Estimate Contingent Recoverable Resources Financing Valuation Per Share (based on last #nancing)
Equity placement
Net
Ass
et
Valu
e (
10%
BT
) /
Fu
lly D
ilu
ted
Sh
are
($
)
NET ASSET VALUE PER SHARE GROWTH
$13/share(Nov, 2010)
$10.50/share(Aug, 2008)
$8.11/share(Jul, 2007)
Date of GLJ Assessment
10
WE HAVE PLACED OURSELVES AT THE FOREFRONT OF A MASSIVE OPPORTUNITY
• Osum dominates the southern portion of the main trend which is closest to infrastructure
• Osum holds over 11 billion barrels of bitumen in the Grosmont and an estimated net 3.2 billion barrels of contingent recoverable resources (1) (2)
• Osum’s projects will provide the first commercial bitumen to market from the Grosmont.
(1) GLJ Best Estimate Contingent Recoverable Resources as of February 2011.
(2) Refer to “Reserves and Resources” in disclaimer
Pay Thickness Map Source: ERCB , 2010
newly acquired leases
11
⤶
N
SALESKI JVSALESKI EAST 100%
SALESKI WEST 100%LIEGE 100%
NEW LANDS – ACQUIRED JUNE 2011
Previous Wells3-D Seismic Area
2011 Winter DrillingJV Pilot 70 – 120
60 – 7050 – 6040 – 50
30 – 4020 – 3010 – 201.5 – 10
Grosmont erosional edgeRivers
Bitumen Pay Thickness (m)
KM YC
4
sg
PROJECT: 2836327 Saleski Map Updates FILE NAME: 2836327 Saleski Map Updates.indd SIZE: 8.5”x5” FINISHED SIZE: 8.5” x 5” BLEED SIZE: n/a
2836327 Saleski Map Updates.indd 2 05/07/11 5:34 PM
Grosmont:406 Bln BOIP
THE GROSMONT CARBONATES
2008 2011 2015 to 2018
Grosmont Fundamentals Verify and Prove Application
Field Test of Cold Solvent (complete)
Laboratory Test (complete)
Analysis of Past Field Tests (complete)
Analog Studies (ongoing)
Modelling Studies for Pilot and Commercial Prediction (ongoing)
Access JIP & Public Data (ongoing)
Field Pilot Construction (underway)
Pilot Test or Demonstration
Operation Experience
Verify Predictive Models
Commercial Assessment
Studies on Alternative Recovery Process
Delineation and Mapping
Commercial Development
Optimization
KM YC
4
ds
PROJECT: 2835764 Investor Book FILE NAME: 2835764 Investor Pocket Book FLAT SIZE: 17” x 5” FINISHED SIZE: 8.5” x 5” BLEED SIZE: 0.125”
KM YC
4
ds
PROJECT: 2835764 Investor Book FILE NAME: 2835764 Investor Pocket Book FLAT SIZE: 17” x 5” FINISHED SIZE: 8.5” x 5” BLEED SIZE: 0.125”
SALESKI SAGD PILOT
Initial cold solvent pilot tests complete
Bitumen mobilized and produced in the field
JV SAGD construction near completion
JV Pilot operations to begin by year end
Amendment to include solvents approved
TECHNICAL PATH AT SALESKI
39
2008 - 2010 2011+ 2012+
Commercial
(complete)
• Bolster Resource Holdings
The Path to Realizing Full Value
• Field Test of Cold Solvent
• Laboratory Tests
• Analysis of Past Field Tests
• Analog Studies
• Modelling Studies for Pilot and Commercial Production
• Access JIP & Public Data
• Field Pilot Construction
• Pilot Test
• Operation Experience
• Verify Predictive Models
• Commercial Assessment & Preparation - JV & 100%
• Studies on Next Generation Recovery Processes
• Delineation and Mapping
• Bolster Resource Holdings
• Commercial Development
• Optimization
12
• v
NEXT GENERATION SAGD PILOT UNDERWAY
Based on initial assessments of JV pilot data, several factors critical to successful SAGD start-up are evident. Oil is being produced at relatively low temperatures and there is evidence of a strong pressure response between the injector and producer wells, both of which are indicative of effective vertical permeability.
13
Osum’s carbonate holdings are underpinned by the Taiga Project, offering a clear path to near-term commercial production and cash "ow.
14
• v
PROPOSED PAD L AYOUT AND PL ANT LOCATION A number of measures have been proposed to the facility’s design to reduce impacts on the surrounding areas as much as possible. For example, by “doubling up” and in some cases “tripling up” on infrastructure associated with each well pad, Osum has been able to reduce the total number of proposed pads for the project from 63 to 36. In addition, we have attempted to follow existing cleared Rights of Way (ROWs) as much as possible. Pipelines and roads have been minimized as a consequence of these two design practices, resulting in an approximate net reduction of 25% to surface disturbance. Osum’s team has endeavored to achieve balance in the proposed layout, positioning well pads for optimized oil recovery while minimizing proximity to water bodies and wetlands.
A progressive reclamation plan has also been included in the Taiga Project application to reduce the impact of the project at any one time. What this means is that not everything will happen at once. By the time the last succession of well pads are being constructed, many of the first wells drilled for the project will already have been abandoned with the reclamation process underway.
7 8 9 10 11 12
131415161718
19 20 21 22 23 24
252627282930
31 32 33 34 35 36
10 11 12
131415
22 23 24
252627
34 35 36
123456
7 8 9 10 11 12
131415161718
19 20 21 22 23 24
252627282930
31 32 33 34 35 36
123
10 11 12
131415
22 23 24
252627
34 35 36
I.R . 149c
P rovinc ia l P ark
´
R2W4
T65
T66
Current Proposed CPF Taiga Pads First Phase Pads Source Water Wells Salt Cavern and Disposal Pad Borrow Pit First Phase Pipeline and Road SAGD Pipeline and Road
CSS Pipeline and Road Source Water Pipeline and Road Other Existing Pipelines CPF Access Road Borrow Pit Access Road Major Roads Other Existing Roads Provincial Park
TAIGA PROJECT FACIL IT IES PL AN
THE TAIGA PROJECT 45,000 bbl/day, 2 phase development
15
• v
2014 TAIGA COMMERCIAL PRODUCTION TARGET
The Taiga Project: Development Timeline
2008 2009 2010 2011 2012 2013 2014 2015 2016
Public Consultation Process
Delineation Drilling & Seismic Acquisition
Geosciences, Reservoirs and DBM Development
Environmental Impact Assessment
Project Disclosure / Regulatory Application
Regulatory Review & Approval
Engineering
Procurement
Wells Drilling / Facilities / Pipelines
Construction Phase 1
First Oil Phase 1
Construction Phase 2
First Oil Phase 2
THE TAIGA PROJECT: DEVELOPMENT TIMELINE
16
• v
17
CONSTRUCTION OPERATIONS
20212020201920182017201620152014201320122011
SALESKI JV COMMERICALEXPANSION
SALESKI JV COMMERICALPHASE 2
SALESKI WEST COMMERICALPHASE 1
LIEGE COMMERCIALPHASE 1
SALESKI EAST COMMERCIALPHASE 1
SALESKI JV COMMERICALPHASE 1
TAIGAPHASE 2
TAIGAPHASE 1
TOTAL CUMMULATIVEDAILY CAPACITY(bbls/d)
SALESKI JV PILOTOPERATIONS
Corporate Projects: Development Timeline
149,00085,00070,00060,00050,00028,00028,000
24,000
40,000
15,000
10,000
10,000
22,000
5,000
23,000
Saleski development timeline & capacity per GLJ Feb 2011Taiga development timeline & capacity per management view.
x
•v
CORPOR ATE NET PRODUCTION PROFILE
Production Potential in Excess of 350,000 Barrels per Day
Raw
Bitu
mem
Rat
e (b
bl/d
)
Taiga Project Saleski JV Saleski East Liege Saleski West
GLJ Reserves/Resource Report (February 2011), 2P Reserves plus Best Estimate Contingent Recoverable Resources.Refer to “Reserves and Resources” inside front cover. 9
18
COLD LAKE
• 359 MMbbls of 2P reserves (1)
• 104 MMbbls additional recoverable (2)
• Taiga leases fully delineated
• Commercial project approval targeted mid-2011
GROSMONT
• 3.2 Billion barrels recoverable resources (2)
• JV pilot operationsunderway sinceDecember 2010
• JV commercialdemonstrationprojectdelineation(seismic and wells)completed and 1stphase commercialapplication !led
• Funded through all key corporate milestones
through 2011(3)(4)
• Investors includeworld class equityproviders
• The right matrix of capabilities and experience
(See osumcorp.com/team for executive and management
bios).
(1) GLJ, January 2011(2) GLJ Best Estimate Contingent Recoverable Resources, February 2011(3) Inclusive of callable common share purchase warrants(4) Based on current capital cost estimates and scheduling.Refer to “Reserves and Resources”, disclaimer.
19
The Means The TeamThe PrizeThe Solid Base
OSUM OIL SANDS CORP.Suite 1900, 255 – 5th Avenue SWBow Valley Square 3Calgary, Alberta, Canada T2P 3G6(403) 283-3224
www.osumcorp.com
The time is right.
20