OVERVIEW PROCESS OF DEVELOPING HOUSING SCHEME BY FEDERAL/STATE
SUBSIDIARY / GOVERNMENT LINK COMPANIES.
OBJECTIVES
• A brief overview the process Housing Development from Initial to
Completion Stage (from Land acquisition to delivery of Titles)
• The process will touch on land matters, planning and submission
process to related authorities at National, State level and local council
level; which includes process of subdivision of land and building
• Reference will be made to codes such as National Land Code (Act 56 of
1965), Town and Country Planning 1976 (Act 172), Housing
Development (Control & Licensing) Act 1966 (Act 118) and Regulations;
and other related Acts and regulations.
• The process will be further be illustrate through case studies in different
states and with different government agencies.
Development Process in relations to Architect’s Basic Services
FEDERAL/STATE GOVERNMENT LINK COMPANIES
SAMPLE FEDERAL/STATE GOVERNMENT SUBSIDIARY / LINK COMPANIES
Sample only
State
Government
Agency
Federal Government
Agencies / Government
Link Companies
• Pr1ma
• Syarikat Perumahan
Negara
• Syarikat Perumahan
Kakitangan
Kerajaan (SPPK)
• Syarikat Perumahan
Negara Berhad
(SPNB)
• Felda
• Kelantan Selatan
Development
Authority (Kesedar)
Federal
Government
Pahang
• Pr1ma Pahang
• KPKT - PPR Selangor
• PKNS
• Kumpulan Hartanah
Selangor
• Permodalan Negeri
Selangor Berhad (PNSB)
Kelantan
• PKINK
• PMBK Development SB
Government Link Companies / Agencies
• Act to achieve Government targets, especially
affordable homes.
• As a means to generate income to Government
SAMPLE FEDERAL/STATE GOVERNMENT SUBSIDIARY / LINK COMPANIES
Abbreviation
• KM – Kebenaran Merancang (Planning Approval
/ Permission) as prescribed under section 21,
Act 172 (Town Country Planning Act)
• Layout Plan –Plan indicating proposed
development components as part of Planning
Approval ) as prescribed under section 21, Act
172 (Town Country Planning Act)
• LCP (Laporan Cadangan Pemajuan) a
comprehensive report indicating proposed
development as part of Planning Approval ) as
prescribed under section 21, Act 172 (Town
Country Planning Act)
• R&D – Road and drainage plan, prepared by
Civil and Structural engineer indicating proposed
development road and drainage infrastructure
• RC Plan – Reinforced Concrete drawings
prepared by Structural Engineer indicating
proposed structural system for building and
loading calculation.
• Water Rect – External Water Reticulation
drawing and calculation prepared by Sivil
engineer indicating proposed external water
supply system
• ESCP – Proposed Erosion and Sediment
Control Plan prepared by Sivil Engineer
• TNB – Tenaga Nasional Berhad
• SKMM – Suruhanjaya Komunikasi dan
Multimedia
• TIA – Traffic Impact Assessment.
Proposed study of traffic and solution
prepared by a Traffic Consultant.
Abbreviation
• RSA – Road Safety Audit. Assessment and audit
to the Traffic Impact Assessment.
• SIA – Social Impact Assessment. A report and
study on impact of social to immediate site and
vicinity
• Pre-Comp. Pre Computation drawing prepared
by Land Surveyor indicating alienated land as
per approved KM Layout Plan
• BP – Building Plan approval. Construction
permit application and approval as prescribed
under section 70, Act 133 (Street, Drainage and
Building Act) & Uniform Building By Law 1984
• CCC – Certificate of Completion and
Compliance indicating building is fit for
occupation as prescribed under section 70, Act
133 (Street, Drainage and Building Act) &
Uniform Building By Law 1984
• APDL – Advertising Permit and Developer’s
License. Sales permit and Housing Development
License as prescribed in Housing Development
(Control and Licensing) Act 1966 (Act 118)
• LPHS – Lembaga Perumahan dan Hartanah
Selangor
• SPC – State Planning Committee
• MMKN – Majlis Mesyuarat Kerajaan Negeri
SDBA 1974 (133)
UBBL 1984
PART II
STREET
SEC 4-48
PART III
DRAIN
SEC 50-
69
PART IV
BACKLANE
SEC 65-69
PART V
BUILDING
SEC 70-90
PART VI
MISCELLANEOUS
SEC 91- 132
PART II
SUBMISSION PLAN FOR
APPROVAL
BYLAW 3-29
Salient points
SEC 70NOTICE NEW
BUILDING
SEC 70AEARTHWORK
SEC 70BORDER TO
REVIEW SAFETY
SEC 70CREVOCATION
OF PLAN
SEC 70DINSPECTION OF
BUILDING
SEC 71PENALTY FAILURE
BUILDING/ EARTHWORK
SEC 70 (2)PSP TO SUBMIT
TO LA
SEC70(9A)STRUCTURE SUBMISSION
SEC70(11A)RENOVATION
SEC 70 (12)MISUE OF BUILDING
SEC 70(14)DON’T SUBMIT
- 20 TIMES
SEC 70(20-25)RELATING TO
CCC AND OFFENSE
SEC 80MOVABLE
SHED
PART I
PRELIMINARY
SEC 1-3PART III
SPACE, LIGHT
&VENTILATION
BYLAW 30-47
PART IV
TEMPORARY WORKS
BYLAW 48-52
PART VIII
FIRE ALARM,
DETECTION, FIRE
FIGHTING
BYLAW 225-253
PART VII
FIRE REQUIREMENT
BYLAW 133- 224
PART VI
CONSTRUCTION
REQUIREMENT
BYLAW 81-132
PART V
STRUCTURAL
REQUIREMENT
BYLAW 53-80
SEC 82HOARDING
SEC 85APERIIODIC
INSPECTION
PART VII
BY-LAWS
SEC 133
PART IX
MISC
TCPA
1976
(172)
PART IV
PLANNING
CONTROL
SEC 20A DUTY TO CONSULT
SEC 21 SUBMISSION OF PLANNING
SEC 21A LCPSEC 21B LAYOUT PLANSEC 21C QUALIFIED PERSON
NLC
1965
(56)
S.52 – LAND USES. 124 -CONVERSIONS.124A -CONVERSION & SUBDIVISIONS. 135-139 -SUBDIVISIONS.140-145 -PARTITIONS.146 -150 -AMALGAMATIONS. 195 - SURRENDER S.203 & S.204A - SURRENDER & REALIENATION
BL3 SUBMISSION OF PLANS FOR APPROVAL BL : 6,8,9,10,15,16, 29 ( SUBMISSION REQUIREMENT) BL 5: THE SUPERVISION OF WORKS CARRIED BY PSP/SPBL 7: WITHDRAWAL OR CHANGE OF QUALIFIED PERSONBL 19,20,21 ( TEMPORARY WORKS)22. NOTICE COMMENCEMENT WORK (BORANG B)BL 25 : G1-21 FORMS & CERTIFICATE OF COMPLETION AND COMPLIANCE REQUIREMENTSBL 25A: FORM F-CERTIFICATE OF COMPLETION AND COMPLIANCEBL 27(1): F1 FORM (PARTIAL CCC)BL 27(2): FULL CCC AFTER PARTIAL COMPLETED
COMMENCEMEN
T OF WORKDEPOSIT CCCPRE CONSULTATION
CONSIDERATION
FOR
DEVELOPMENT
Collation of
information from
technical agencies
Water, Electric,
Telecomunications,
Land
Deposit CCC
to LA,
Developer ,
LAM
INTERIM
INSPECTION
Submission to OSC
for propose
development
KM / BP/ Structure/
Engineering/
Earthwork/
Infrastructure/
Landscape
• Borang B
• PDC 6,
MSIG Vol II
• Borang
JKJ103,
• Sijil tanah
• etc
Final Inspection I
PBAN, TNB & PBT/JKR
Permohonan Sambungan
komunikasi.
Final Inspection II JPBM,
DOSH, APP
(IWK/MAJAARI)
Interim
Inspection
TNB,
BOMBA,
PBAN,
IWK, DOSH
dan
JKR/PBT.
FINAL
INSPECTION
Process OSC 3.0
LGA 1976 (171)
PART Xiii BY LAWS102 General Powers to Make By
Law
General Overview of Development Process
GENERAL PROCESS OF DEVELOPING HOUSING SCHEME
PENINSULAR MALAYSIA SUMMARY DEVELOPMENT PERMIT PROCESS
COMMENCEMENT
OF WORKDEPOSIT CCC
PRE
CONSULTATION
CONSIDERATION
FOR DEVELOPMENT
Collation of information
from technical agencies
Water, Electric,
Telecomunications,
Land
Deposit CCC to
LA, Developer ,
LAM
FORM F
FORM G1-G21
CLEARANCE
LETTER
INTERIM
INSPECTION
Submission to OSC for
propose development
KM / BP/ Structure/
Engineering/ Earthwork/
Infrastructure/ Landscape
FORM A : Submission
BP/ Structure
• FORM B
• PDC 6,
MSIG Vol
II
• Borang
JKJ103,
• Sijil tanah
• etc
Final Inspection I
PBAN, TNB & PBT/JKR
Permohonan Sambungan
komunikasi.
Final Inspection II JPBM,
DOSH, APP (IWK/MAJAARI)
Interim
Inspection
TNB,
BOMBA,
PBAN, IWK,
DOSH dan
JKR/PBT.
FINAL
INSPECTION
Certify
FORM
G1-G21
By
stages
CONSTRUCTION PERIOD
DLP
Submit Sifus to
PTG & Submit
Schedule Parcel
to COB for
stratified sales
After BP
All schedule
DLP 24
Months
Delivery of Vacant
Possession
Schedule G & I -
Within 24 Month
Schedule H & J –
Within 36 Month
Third Schedule: Progress Billing
Schedule G
Individual
Title
Stage billing
Schedule H
Strata
Title
Stage
billing
Schedule I
Individual
Title
Built then sell
10:90
Schedule J
Strata
Title
Built then sell
10:90
Apply Developer
license & Open
Accounts
Apply Advertising
Permit to
commence sales
Submit Propose
Strata Plan to
JUPEM at G12
and obtain CPSP
Obtain Permit
And
commence
sale
Submit to Land
Office
VP &
issuance
Strata Title
Establish
MC
SMA
2013
Super structure
stage
CONSTRUCTION PERMIT PROCESS
HOUSING DEVELOPMENT PERMIT PROCESS
STRATA TITLES PROCESS
Housing Development Process
Completion
Commencement
workKMBP
Titles
CCC
/ VPAPDL
Sales
Housing Development Process
Completion
Commencement
workKMBP
Titles
CCC
/ VPAPDL
Sales
Planning Approval
Housing Development Process
Completion
Commencement
workKMBP
Titles
CCC
/ VPAPDL
Sales
Planning Approval Construction
Permit
Housing Development Process
Completion
Commencement
workKMBP
Titles
CCC
/ VPAPDL
Sales
Construction and
Completion
Planning Approval Construction
Permit
Housing Development Process
Completion
Commencement
workKMBP
Titles
CCC
/ VPAPDL
Sales
Construction and
Completion
Planning Approval Construction
Permit
Planner
Developer
Architect
Housing Development Process
Planner
Completion
Commencement
work
Endorsed
KM
BP
Developer
Titles
Architect
CCC
APDL VPSales
KM Submission
Construction and
Completion
Planning Approval Construction
Permit
Housing Development Process
Land
Surveyor
Planner
Completion
Commencement
work
Endorsed
KM
BP
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Titles
Architect
CCC
APDL VPSales
KM Submission
Construction and
Completion
Planning Approval Construction
Permit
Sample of OSC flowchart
Sample of OSC flowchart with related Acts and Codes
LANDED
GENERAL PROCESS OF DEVELOPING HOUSING SCHEME
LANDED Housing Development Process
Land
Surveyor
Planner
Completion
Commencement
work
Endorsed
KM
BP
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Acquire B1 / Titles
Architect
CCC
APDL VPSales
KM Submission
Planning Approval
LANDED Housing Development Process
Land
Surveyor
Planner
Completion
Commencement
work
Endorsed
KM
BP
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Acquire B1 / Titles
Architect
CCC
APDL VPSales
KM Submission
LANDED Housing Development Process
Land
Surveyor
Planner
Completion
Commencement
work
Endorsed
KM
BP
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Acquire B1 / Titles
TNB, SKMM
Water
Architect
CCC
APDL VPSales
KM Submission
LANDED Housing Development Process
Land
Surveyor
Planner
Completion
Commencement
work
Endorsed
KM
BP
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Acquire B1 / TitlesSurvey
plan
TNB, SKMM
Water
Architect Development Cost
CCC
APDL VPSales
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
LANDED Housing Development Process
Land
Surveyor
Planner
Completion
Commencement
work
Endorsed
KM
BP
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Acquire B1 / TitlesSurvey
plan
TNB, SKMM
Water
Architect
Premium
ISF
Development Cost
CCC
APDL VPSales
3 – 6 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
LANDED Housing Development Process
Land
Surveyor
Planner
Completion
Commencement
work
Endorsed
KM
BP
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Acquire B1 / TitlesSurvey
plan
TNB, SKMM
Water
Architect
Premium
ISF
Development Cost
CCC
APDL VP
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
Sales
3 – 6 months 3 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
LANDED Housing Development Process
Land
Surveyor
Planner
Completion
Commencement
work
Endorsed
KM
BP
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Acquire B1 / TitlesSurvey
plan
TNB, SKMM
Water
Architect
S&P
Account, Price, BrochurePremium
ISF
Development Cost
CCC
APDL VP
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba Stage Cert
Sales
18 months3 – 6 months 3 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
LANDED Housing Development Process
Land
Surveyor
Planner
Completion
Commencement
work
Endorsed
KM
BP
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Telco, Street lighting
Land Office
Acquire B1 / Titles
Landscape
Survey plan
R&D
TNB, SKMM
Water
Architect
S&P
Account, Price, BrochurePremium
ISF
Development CostG8,12
CCC
APDL VP
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
CCC / VP
TNB
Water, Sewer
1st Stage Inspection
Stage Cert
G21
G2
G5-7, 9-11, 16, 18, 20
G1, 3-4, 13-15, 17, 19
Form F
Sales
Building, Bomba
18 months3 – 6 months 3 months3 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
2nd Stage Inspection
G Forms
STRATA
GENERAL PROCESS OF DEVELOPING HOUSING SCHEME
Sample of Strata Application Flowchart
Sample of Strata Application Flowchart
STRATA Housing Development Process
CompletionCommencement
workCCC
APDL VPSales
Land
Surveyor
Planner
Endorsed
KM
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Architect
KM Submission
BP
Strata
Title
Planning Approval
STRATA Housing Development Process
CompletionCommencement
workCCC
APDL VPSales
Land
Surveyor
Planner
Endorsed
KM
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Architect
KM Submission
BP
Strata
Title
STRATA Housing Development Process
CompletionCommencement
workCCC
APDL VPSales
Land
Surveyor
Planner
Endorsed
KM
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
TNB, SKMM
Water
Architect
KM Submission
BP
Strata
Title
STRATA Housing Development Process
CompletionCommencement
workCCC
APDL VPSales
Land
Surveyor
Planner
Endorsed
KM
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Survey plan
TNB, SKMM
Water
Architect Development Cost
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
BP
Strata
Title
STRATA Housing Development Process
CompletionCommencement
workCCC
APDL VPSales
Land
Surveyor
Planner
Endorsed
KM
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Survey plan
TNB, SKMM
Water
Architect
Premium
ISF
Development Cost
3 – 6 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
BP
Strata
Title
STRATA Housing Development Process
CompletionCommencement
workCCC
APDL VPSales
3 months
Land
Surveyor
Planner
Endorsed
KM
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Survey plan
TNB, SKMM
Water
Architect
Premium
ISF
Development Cost
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
3 – 6 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
BP
Strata
Title
STRATA Housing Development Process
CompletionCommencement
work
S&P
Account, Price, Brochure
CCC
APDL VPSales
SIFUS SOP
3 months
Land
Surveyor
Planner
Endorsed
KM
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Survey plan
TNB, SKMM
Water
Architect
Premium
ISF
Development Cost
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
3 – 6 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
BP
Strata
Title
STRATA Housing Development Process
CompletionCommencement
work
CPSP
S&P
Account, Price, Brochure
CCC
APDL VP
Stage Cert
Sales
SIFUS SOP PSP - SSS
24-30 months3 months
Land
Surveyor
Planner
Endorsed
KM
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Survey plan
TNB, SKMM
Water
Architect
Premium
ISF
Development Cost
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
3 – 6 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
BP
Strata
Title
STRATA Housing Development Process
CompletionCommencement
work
Telco, Street lighting
Landscape
CPSP
R&D
S&P
Account, Price, Brochure
CCC
APDL VP
2nd Stage
Inspection
TNB
Water, Sewer
1st Stage
Inspection
Stage Cert
G21
G5-7, 9-11, 16, 18, 20
G1, 3-4, 13-15, 17, 19
Form F
Sales
Building, Bomba
SIFUS SOP PSP - SSS G2
24-30 months 3-6 months3 months
G8,12
Land
Surveyor
Planner
Endorsed
KM
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Survey plan
TNB, SKMM
Water
Architect
Premium
ISF
Development Cost
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
3 – 6 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
CCC / VP
1st Stage Inspection
2nd Stage Inspection
G Forms
BP
Strata
Title
SAMPLE 1 : LANDED HOUSING SCHEME IN SELANGOR
OVERVIEW PROCESS OF DEVELOPING HOUSING SCHEME BY FEDERAL/STATE
GOVERNMENT SUBSIDIARY / LINK COMPANIES
SAMPLE 1 : LANDED HOUSING SCHEME IN
SELANGOR
CLIENT Shah Alam Properties (SAP)
subsidiary of KHSB
A Units 91 UNITS DOUBLE STOREY
TERRACE HOUSE (RUMAH
SELANGORKU-JENIS D)
B Location Kuala Selangor
C Site Condition Flat (Direct to Main Road, No
Infra/ utilities reserve)
D Size & Lot LOT NO. PT 620 AND PT 621
(4.6 ACRES)
E Land Matter Alienated Land with Titles
Category : Building (Housing)
Non Malay Reserve
F Planning Matter Zoning Housing (Apartment)
to Housing (Landed)
G Additional
Authorities
Requirement
None
H Target /
Marketing
Rumah Selangorku Jenis D
I Implementation Conventional Contract
SAMPLE 1 : LANDED HOUSING SCHEME IN
SELANGOR
overview process of developing housing scheme
SAMPLE 1 : LANDED HOUSING SCHEME IN
SELANGOR
overview process of developing housing scheme
SAMPLE 1 : LANDED HOUSING SCHEME IN
SELANGOR
CLIENT Shah Alam Properties (SAP)
subsidiary of KHSB
A Units 91 UNITS DOUBLE STOREY
TERRACE HOUSE (RUMAH
SELANGORKU-JENIS D)
B Location Kuala Selangor
C Site Condition Flat (Direct to Main Road, No
Infra/ utilities reserve)
D Size & Lot LOT NO. PT 620 AND PT 621
(4.6 ACRES)
E Land Matter Alienated Land with Titles
Category : Building (Housing)
Non Malay Reserve
F Planning Matter Zoning Housing (Apartment)
to Housing (Landed)
G Additional
Authorities
Requirement
None
H Target /
Marketing
Rumah Selangorku Jenis D
I Implementation Conventional Contract
SAMPLE 1 : LANDED HOUSING SCHEME IN
SELANGOR
overview process of developing housing scheme
SAMPLE 1 : LANDED HOUSING SCHEME IN
SELANGOR
overview process of developing housing scheme
ZON 3
ZON 1
ZON 2
PROSES OSC (RUMAH SELANGORKU)Pemaju telah mengetahui tanah yanghendak dibuat pembangunan.1
Pemaju datang / dapatkan ulasandaripada LPHS untuk menentukanjenis dan keperluan RUMAHSELANGORKU yang akan dibina.(Khidmat Rundingan).
2
LPHS keluarkan surat ulasanmengenai jenis dan peratusanpenyediaan Rumah Selangorku
3
RUMAH
LANDED Housing Development Process
Land
Surveyor
Planner
Completion
Commencement
work
Endorsed
KM
BP
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Telco, Street lighting
Land Office
Acquire B1 / Titles
Landscape
Survey plan
R&D
TNB, SKMM
Water
Architect
S&P
Account, Price, BrochurePremium
ISF
Development CostG8,12
CCC
APDL VP
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
CCC / VP
TNB
Water, Sewer
1st Stage Inspection
Stage Cert
G21
G2
G5-7, 9-11, 16, 18, 20
G1, 3-4, 13-15, 17, 19
Form F
Sales
Building, Bomba
18 months3 – 6 months 3 months3 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
2nd Stage Inspection
G Forms
SAMPLE 1 : LANDED HOUSING SCHEME IN
SELANGOR
CLIENT Shah Alam Properties (SAP)
subsidiary of KHSB
A Units 91 UNITS DOUBLE STOREY
TERRACE HOUSE (RUMAH
SELANGORKU-JENIS D)
B Location Kuala Selangor
C Site Condition Flat (Direct to Main Road, No
Infra/ utilities reserve)
D Size & Lot LOT NO. PT 620 AND PT 621
(4.6 ACRES)
E Land Matter Alienated Land with Titles
Category : Building (Housing)
Non Malay Reserve
F Planning Matter Zoning Housing (Apartment)
to Housing (Landed)
G Additional
Authorities
Requirement
None
H Target /
Marketing
Rumah Selangorku Jenis D
I Implementation Conventional Contract
LANDED Housing Development Process
Land
Surveyor
Planner
Completion
Commencement
work
Endorsed
KM
BP
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Telco, Street lighting
Land Office
Acquire B1 / Titles
Landscape
Survey plan
R&D
TNB, SKMM
Water
Architect
S&P
Account, Price, BrochurePremium
ISF
Development CostG8,12
CCC
APDL VP
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
CCC / VP
TNB
Water, Sewer
1st Stage Inspection
Stage Cert
G21
G2
G5-7, 9-11, 16, 18, 20
G1, 3-4, 13-15, 17, 19
Form F
Sales
Building, Bomba
18 months3 – 6 months 3 months3 months
Pre-Comp
KM Submission
LPHS
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
2nd Stage Inspection
G Forms
TIA, RSA, SIA
Layout Plan
MMKN
3 – 6 months
Layout Plan LCP
MMKN
LPHS Name list
LANDED Housing Development Process
Land
Surveyor
Planner
Completion
Commencement
work
Endorsed
KM
BP
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Telco, Street lighting
Land Office
Acquire B1 / Titles
Landscape
Survey plan
R&D
TNB, SKMM
Water
Architect
S&P
Account, Price, BrochurePremium
ISF
Development CostG8,12
CCC
APDL VP
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
CCC / VP
TNB
Water, Sewer
1st Stage Inspection
Stage Cert
G21
G2
G5-7, 9-11, 16, 18, 20
G1, 3-4, 13-15, 17, 19
Form F
Sales
Building, Bomba
18 months3 – 6 months 3 months3 months
Pre-Comp
KM Submission
LPHS
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
2nd Stage Inspection
G Forms
TIA, RSA, SIA
Layout Plan
MMKN
3 – 6 months
Layout Plan LCP
MMKN
LPHS Name list
SAMPLE 2 : LANDED HOUSING SCHEME IN KELANTAN
OVERVIEW PROCESS OF DEVELOPING HOUSING SCHEME BY FEDERAL/STATE
GOVERNMENT LINK COMPANIES
SAMPLE 2 : LANDED HOUSING SCHEME IN
KELANTAN
CLIENT PMBK Development Sdn Bhd
A Units 121 units Rumah Mampu
Milik Kelantan (Teres), 150
units Mix Terrace, Semi D,
Bungalows, 116 Shop Lots &
Other Infrastructure
B Location Gua Musang
C Site Condition Undulating with mix Category
1-3
D Size & Lot 63 Acres (No Lot No)
E Land Matter (Government Land) No Titles
F Planning Matter No Zoning
G Additional
Authorities
Requirement
TIA, RSA, EIA
H Target /
Marketing
Rumah Mampu Milik & Market
I Implementation Design & Build
SAMPLE 2 : LANDED HOUSING SCHEME IN
KELANTAN
overview process of developing housing scheme
SAMPLE 2 : LANDED HOUSING SCHEME IN
KELANTAN
overview process of developing housing scheme
SAMPLE 2 : LANDED HOUSING SCHEME IN
KELANTAN
CLIENT PMBK Development Sdn Bhd
A Units 121 units Rumah Mampu
Milik Kelantan (Teres), 150
units Mix Terrace, Semi D,
Bungalows, 116 Shop Lots &
Other Infrastructure
B Location Gua Musang
C Site Condition Undulating with mix
Category 1-3
D Size & Lot 63 Acres (No Lot No)
E Land Matter (Government Land) No Titles
F Planning Matter No Zoning
G Additional
Authorities
Requirement
TIA, RSA, EIA
H Target /
Marketing
Rumah Mampu Milik &
Market
I Implementation Design & Build
SAMPLE 2 : LANDED HOUSING SCHEME IN
KELANTAN
overview process of developing housing scheme
Kerajaan Negeri mensasarkan pembinaan
rumah mampu milik sebanyak 5000 unit
dalam tempoh 5 tahun (2013-2018) melalui
3 kaedah;
i. Kerajaan bina sendiri di atas tanah milik
kerajaan,
ii. Usahasama agensi kerajaan/ swasta di
atas tanah kerajaan/ agensi kerajaan, dan
iii. Projek swasta di atas tanah milik
swasta.
Dasar Perumahan Mampu Milik Negeri
Kelantan yang digubal mensyaratkan bagi
projek perumahan 250 unit ke atas untuk
membina sekurang-kurangnya 30% rumah
mampu milik
LANDED Housing Development Process
Land
Surveyor
Planner
Completion
Commencement
work
Endorsed
KM
BP
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Telco, Street lighting
Land Office
Acquire B1 / Titles
Landscape
Survey plan
R&D
TNB, SKMM
Water
Architect
S&P
Account, Price, BrochurePremium
ISF
Development CostG8,12
CCC
APDL VP
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
CCC / VP
TNB
Water, Sewer
1st Stage Inspection
Stage Cert
G21
G2
G5-7, 9-11, 16, 18, 20
G1, 3-4, 13-15, 17, 19
Form F
Sales
Building, Bomba
18 months3 – 6 months 3 months3 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
2nd Stage Inspection
G Forms
SAMPLE 2 : LANDED HOUSING SCHEME IN
KELANTAN
CLIENT PMBK Development Sdn Bhd
A Units 121 units Rumah Mampu
Milik Kelantan (Teres), 150
units Mix Terrace, Semi D,
Bungalows, 116 Shop Lots &
Other Infrastructure
B Location Gua Musang
C Site Condition Undulating with mix
Category 1-3
D Size & Lot 63 Acres (No Lot No)
E Land Matter (Government Land) No Titles
F Planning Matter No Zoning
G Additional
Authorities
Requirement
TIA, RSA, EIA
H Target /
Marketing
Rumah Mampu Milik &
Market
I Implementation Design & Build
LANDED Housing Development Process
Land
Surveyor
Planner
CompletionCommencement
work
Endorsed
KM
BP
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Telco, Street lighting
Proposed Layout JBPD
Acquire B1 / Titles
Landscape
Proposed Survey plan
R&D
TNB, SKMM
Water
Architect
S&P
Account, Price, BrochurePremium
ISF
Development CostG8,12
CCC
APDL VP
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
CCC / VP
TNB
Water, Sewer
1st Stage Inspection
Stage Cert
G21
G2
G5-7, 9-11, 16, 18, 20
G1, 3-4, 13-15, 17, 19
Form F
Sales
Building, Bomba
18 months3 – 6 months 3 months3 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
2nd Stage Inspection
G Forms
Obtain Letter frm State (Area)
Survey plan
Land Office
EIA
TIA, RSA, SIA
Premium
State Name list
LANDED Housing Development Process
Land
Surveyor
Planner
CompletionCommencement
work
Endorsed
KM
BP
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Telco, Street lighting
Proposed Layout JBPD
Acquire B1 / Titles
Landscape
Proposed Survey plan
R&D
TNB, SKMM
Water
Architect
S&P
Account, Price, BrochurePremium
ISF
Development CostG8,12
CCC
APDL VP
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
CCC / VP
TNB
Water, Sewer
1st Stage Inspection
Stage Cert
G21
G2
G5-7, 9-11, 16, 18, 20
G1, 3-4, 13-15, 17, 19
Form F
Sales
Building, Bomba
18 months3 – 6 months 3 months3 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
2nd Stage Inspection
G Forms
Obtain Letter frm State (Area)
Survey plan
Land Office
EIA
TIA, RSA, SIA
Premium
State Name list
SAMPLE 3 : STRATA HOUSING SCHEME IN JOHOR
OVERVIEW PROCESS OF DEVELOPING HOUSING SCHEME BY FEDERAL/STATE
GOVERNMENT LINK COMPANIES
SAMPLE 3 : STRATA HOUSING SCHEME IN
JOHOR
CLIENT SPNB Aspirasi
A Units 252 units APARTMENTS (52
units RUMAH RAKYAT JOHOR)
B Location Pengerang, Johor
C Site Condition Flat (200 feet from sea shore)
D Size & Lot LOT NO. 1451(4.35 ACRES)
E Land Matter Alienated Land with Titles
Category : Agriculture
F Planning Matter Zoning – Not Specified. Within
Pengerang Development
Coriddor
G Additional
Authorities
Requirement
TIA, RSA, EIA
H Target /
Marketing
Rumah Rakyat Johor, Market
I Implementation Design & Build
SAMPLE 3 : STRATA HOUSING SCHEME IN
JOHOR
overview process of developing housing scheme
Image
SAMPLE 3 : STRATA HOUSING SCHEME IN
JOHOR
overview process of developing housing scheme
SAMPLE 3 : STRATA HOUSING SCHEME IN
JOHOR
CLIENT SPNB Aspirasi
A Units 252 units APARTMENTS (52
units RUMAH RAKYAT
JOHOR)
B Location Pengerang, Johor
C Site Condition Flat (200 feet from sea shore)
D Size & Lot LOT NO. 1451(4.35 ACRES)
E Land Matter Alienated Land with Titles
Category : Agriculture
F Planning Matter Zoning – Not Specified.
Within Pengerang
Development Coriddor
G Additional
Authorities
Requirement
TIA, RSA, EIA
H Target /
Marketing
Rumah Rakyat Johor, Market
I Implementation Design & Build
SAMPLE 3 : STRATA HOUSING SCHEME IN
JOHOR
overview process of developing housing scheme
Dasar Perumahan Rakyat Johor
- Allocation of 20% from Total
no of Units in the area
outside Iskandar
Development / Nusajaya and
40% within Iskandar
Development / Nusajaya
STRATA Housing Development Process
CompletionCommencement
work
Telco, Street lighting
Landscape
CPSP
R&D
S&P
Account, Price, Brochure
CCC
APDL VP
2nd Stage
Inspection
TNB
Water, Sewer
1st Stage
Inspection
Stage Cert
G21
G5-7, 9-11, 16, 18, 20
G1, 3-4, 13-15, 17, 19
Form F
Sales
Building, Bomba
SIFUS SOP PSP - SSS G2
24-30 months 3-6 months3 months
G8,12
Land
Surveyor
Planner
Endorsed
KM
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Survey plan
TNB, SKMM
Water
Architect
Premium
ISF
Development Cost
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
3 – 6 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
CCC / VP
1st Stage Inspection
2nd Stage Inspection
G Forms
BP
Strata
Title
SAMPLE 3 : STRATA HOUSING SCHEME IN
JOHOR
CLIENT SPNB Aspirasi
A Units 252 units APARTMENTS (52
units RUMAH RAKYAT
JOHOR)
B Location Pengerang, Johor
C Site Condition Flat (200 feet from sea shore)
D Size & Lot LOT NO. 1451(4.35 ACRES)
E Land Matter Alienated Land with Titles
Category : Agriculture
F Planning Matter Zoning – Not Specified.
Within Pengerang
Development Coriddor
G Additional
Authorities
Requirement
TIA, RSA, EIA
H Target /
Marketing
Rumah Rakyat Johor, Market
I Implementation Design & Build
STRATA Housing Development Process
CompletionCommencement
work
Telco, Street lighting
Landscape
CPSP
R&D
S&P
Account, Price, Brochure
CCC
APDL VP
2nd Stage
Inspection
TNB
Water, Sewer
1st Stage
Inspection
Stage Cert
G21
G5-7, 9-11, 16, 18, 20
G1, 3-4, 13-15, 17, 19
Form F
Sales
Building, Bomba
SIFUS SOP PSP - SSS G2
24-30 months 3-6 months3 months
G8,12
Land
Surveyor
Planner
Endorsed
KM
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Survey plan
TNB, SKMM
Water
Architect
Premium
ISF
Development Cost
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
6 – 12 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
CCC / VP
1st Stage Inspection
2nd Stage Inspection
G Forms
BP
Strata
Title
EIA
TIA, RSA, SIA
State Planning Commitee
JBPD
State Name list
STRATA Housing Development Process
CompletionCommencement
work
Telco, Street lighting
Landscape
CPSP
R&D
S&P
Account, Price, Brochure
CCC
APDL VP
2nd Stage
Inspection
TNB
Water, Sewer
1st Stage
Inspection
Stage Cert
G21
G5-7, 9-11, 16, 18, 20
G1, 3-4, 13-15, 17, 19
Form F
Sales
Building, Bomba
SIFUS SOP PSP - SSS G2
24-30 months 3-6 months3 months
G8,12
Land
Surveyor
Planner
Endorsed
KM
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Survey plan
TNB, SKMM
Water
Architect
Premium
ISF
Development Cost
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
6 – 12 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
CCC / VP
1st Stage Inspection
2nd Stage Inspection
G Forms
BP
Strata
Title
EIA
TIA, RSA, SIA
State Planning Commitee
JBPD
State Name list
SAMPLE 4 : STRATA HOUSING SCHEME IN PAHANG
OVERVIEW PROCESS OF DEVELOPING HOUSING SCHEME BY FEDERAL/STATE
GOVERNMENT LINK COMPANIES
SAMPLE 4 : STRATA HOUSING SCHEME IN
PAHANG
CLIENT SPNB Idaman
A Units 1126 units of Apartments
B Location Tanah Rata, Cameron Highland
C Site Condition Undulating Category 2-4
Slopes
D Size & Lot Lot Simpanan Melayu Tanah
Rata (PW 3298)
E Land Matter No Title, Government Malay
Reserve Land
F Planning Matter Zoning Housing
G Additional
Authorities
Requirement
TIA, RSA, EIA (Geotech,
Geoterrain)
H Target /
Marketing
Rumah Rakyat
I Implementation Conventional Contract
SAMPLE 4 : STRATA HOUSING SCHEME IN
PAHANG
overview process of developing housing scheme
SAMPLE 4 : STRATA HOUSING SCHEME IN
PAHANG
overview process of developing housing scheme
SAMPLE 4 : STRATA HOUSING SCHEME IN
PAHANG
overview process of developing housing scheme
Need to comply Dasar Perumahan
Rakyat Pahang ?
SAMPLE 4 : STRATA HOUSING SCHEME IN
PAHANG
CLIENT SPNB Idaman
A Units 1126 units of Apartments
B Location Tanah Rata, Cameron Highland
C Site Condition Undulating Category 2-4
Slopes
D Size & Lot Lot Simpanan Melayu Tanah
Rata (PW 3298)
E Land Matter No Title, Government Malay
Reserve Land
F Planning Matter Zoning Housing
G Additional
Authorities
Requirement
TIA, RSA, EIA (Geotech,
Geoterrain)
H Target /
Marketing
Rumah Rakyat
I Implementation Conventional Contract
STRATA Housing Development Process
CompletionCommencement
work
Telco, Street lighting
Landscape
CPSP
R&D
S&P
Account, Price, Brochure
CCC
APDL VP
2nd Stage
Inspection
TNB
Water, Sewer
1st Stage
Inspection
Stage Cert
G21
G5-7, 9-11, 16, 18, 20
G1, 3-4, 13-15, 17, 19
Form F
Sales
Building, Bomba
SIFUS SOP PSP - SSS G2
24-30 months 3-6 months3 months
G8,12
Land
Surveyor
Planner
Endorsed
KM
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Survey plan
TNB, SKMM
Water
Architect
Premium
ISF
Development Cost
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
3 – 6 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
CCC / VP
1st Stage Inspection
2nd Stage Inspection
G Forms
BP
Strata
Title
State Name list
STRATA Housing Development Process
CompletionCommencement
work
Telco, Street lighting
Landscape
CPSP
R&D
S&P
Account, Price, Brochure
CCC
APDL VP
2nd Stage
Inspection
TNB
Water, Sewer
1st Stage
Inspection
Stage Cert
G21
G5-7, 9-11, 16, 18, 20
G1, 3-4, 13-15, 17, 19
Form F
Sales
Building, Bomba
SIFUS SOP PSP - SSS G2
24-30 months 3-6 months3 months
G8,12
Land
Surveyor
Planner
Endorsed
KM
Pre Consultation
Developer
C&S
Engineer
M&E
Engineer
Landscape
Architect
Land Office
Survey plan
TNB, SKMM
Water
Architect
Premium
ISF
Development Cost
TNB, Streetlighting, Telco, Internal Water & Sewer
Landscape Plan
RC Plan, R&D, Earthwork, External Sewerage. Water Rect
BP, Bomba
3 – 6 months
Pre-Comp
KM Submission
Layout Plan LCP
TNB, SKMM, Telco
R&D, Earthwork, ESCP, Sewerage. Water
CCC / VP
1st Stage Inspection
2nd Stage Inspection
G Forms
BP
Strata
Title
EIA
TIA, RSA, SIA
Proposed Survey plan
Obtain Letter frm State (Area)
Premium
Proposed Layout
State Name list
overview process of developing housing scheme
• On Client (Government Link Subsidiary / Companies / Agencies)
• The process of developing housing scheme by Government Link
Companies is similar to the process by Private companies
• Payment such as premiums for the GLC may be minimised (nominal)
• Act to achieve Government targets, especially affordable homes.
• The GLCs act as vehicle to facilitate process (expedite certain approvals)
Summary and Conclusion
overview process of developing housing scheme
On Development Process
• Development process is different from a project to another.
• Various factors contributes such as –
1. State guidelines and policies
2. Number of units
3. Geographical and location
4. Site condition and terrain
5. Land Matter – Reserves (e.g. Government, Malay, alienated land,
Titles)
6. Structure and Local Plan
7. Target Market
8. Project Implementation
Summary and Conclusion
The END