Cost efficient and carbon neutral, ‘Thinking outside the box……’ Kevin Burton Parthenon Data Centres THE NEXT GENERATION OF DATACENTRES SLIDE 1 SLIDE 1 Parthenon Data Centres Director 5 th Data Center Power & Cooling Conference, London 7-8 October , 2010
Transcript
Page 1: Parthenon Broadgroup5thpower&Coolinglondon Ppt

Cost efficient and carbon neutral,‘Thinking outside the box……’Kevin BurtonParthenon Data Centres

THE NEXT GENERATION OF DATACENTRES

SLIDE 1SLIDE 1

Parthenon Data CentresDirector

5th Data Center Power & Cooling Conference, London 7-8 October , 2010

Page 2: Parthenon Broadgroup5thpower&Coolinglondon Ppt

SYMBIOSIS™

SLIDE 2SLIDE 2

Page 3: Parthenon Broadgroup5thpower&Coolinglondon Ppt

Evolution

Generally, this location provided for the following;Huge available power– 240MW, with redundant connection to 150kV

‘Thinking outside the box…..or thinking outside the data center’

SLIDE 3SLIDE 3

Huge available power– 240MW, with redundant connection to 150kV Network, in place ready to use as of 2005.The area has a private power network – 30+ CHP’s providing 135MW to the network, connected in a radial formation.Natural resources - underground water storage and availability of ground , surface and lake water for coolingThe future expansion of the area for SymbiosisExcellent connectivity to Amsterdam Internet Exchange (AMS-IX)Very competitive land prices.

So how will this evolve?Does Symbiosis provide a mutual benefit?How will this location improve our efficiency and PUE?

Page 4: Parthenon Broadgroup5thpower&Coolinglondon Ppt

PARTHENON ONE

Grower40 ha peppers

CHP 3+3 MWe CHP 3+3 MWe

SLIDE 4SLIDE 4

1000meter

Datacenter

10 haNo lighting

10 haNo lighting

10 haNo lighting

10 haLit

New10 ha

New5 ha

CHP 3+3 MWe CHP 3+3 MWe

CHP 3+3 MWe

CHP 3+4 MWe

No CHP No CHP

Page 5: Parthenon Broadgroup5thpower&Coolinglondon Ppt

Heat

CO2

20 kV

Heat/coldParthenon Data Centre

SYMBIOSISTM 2008

SLIDE 5SLIDE 5

Heat

CO2

Heat

CO2

Trafo

150 kV Tennet

Substation20 kV

20 kV

20 kVGroundStorage

Page 6: Parthenon Broadgroup5thpower&Coolinglondon Ppt

Heat/coldParthenon Data Centre

SYMBIOSIS™ 2011

SLIDE 6SLIDE 6

Heat

CO2

Heat

CO2

Trafo

150 kV TennetSubstation20 kV

20 kV

20 kV

Ground storage

Page 7: Parthenon Broadgroup5thpower&Coolinglondon Ppt

Heat/coldGround Storage

Parthenon Data Centre

SYMBIOSIS™ 2015/2017

New 15 hectareNO CHP

Existing 300 hectare

50 GWh 20MW

SLIDE 7SLIDE 7SLIDE 1SLIDE 1

150 kV TennetSubstation(This is a private network)Digester

20 kV

20 kV

100.000 ton

150 GWh

750 GWh 730 GWh30 GWh

1.000 GWh

NaturalVegetationWaste

Heat

CO2

180MW CHP’s

Natural gas

1.900 GWh

50 Gwh to startDigestion process

Wind Farm producing150 GWh

Page 8: Parthenon Broadgroup5thpower&Coolinglondon Ppt

EUE CALCULATION

2008 EUE was a respectable 1.3

We have in 2010 calculated our EUE at 1.14

SLIDE 8SLIDE 8

Combining Electrical, Ventilation and water optimisationinto the equation;EUE Water 1.017EUE Ventilation 1.038EUE Electrical 1.088

Total 1.143

Page 9: Parthenon Broadgroup5thpower&Coolinglondon Ppt

METRICS

New metrics by the Green Grid for energy reuse:

Parthenon One

PUE = 1,14ERF = 0,68

SLIDE 9SLIDE 9

ERF = 0,68RER = 0,40

Page 10: Parthenon Broadgroup5thpower&Coolinglondon Ppt

Inherent low opex cost structureVery large power densityAmple power supply by existing infrastructureSmart power procurement

PARTHENON ONE

SLIDE 10SLIDE 10

Smart power procurementIT energy reuse, ERF = 0,68Proprietary heat exchange processTotal of 30,200 metric tons annual carbon savingsSmart use of CHP units and network as additional back-up power source

An important step into the low carbon economy!