Paul BusseyRoyal Institute of British
Architects
Join in on twitter #IIRSMCDM17
The reality of CDM 2015
A practical look at the Principal Designer role
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
The RIBA’s view of the Principal Designers Role
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
The Principal Designer to replicate the Principal Contractor
CDM-C
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
A Designer with Control of the Pre-Construction Phase
• Not a person but a corporate function- ( could be a one man company)
• A designer with appropriate SKE and organisational capability as determined by
their professional body eg. ICE, RICS,I StructE, CIBSE, CIAT, RIBA, etc
• Must plan, manage and monitor the pre-construction phase AND coordinate
matters relating to H&S during the pre-construction phase……..
• Take account of the General Principles of Prevention ( sfarp) which provide a
framework for consideration of potential risks ie. A qualified NOT absolute duty
• On domestic projects the PD role is NO DIFFERENT to commercial projects
except the client duties may be deemed to the PC or PD. ( App. 6 L 153).
• This additional PD function needs resourcing and therefore additional fees. (This
is an area of some ambiguity,domestically, and to be raised with the HSE)
The Principal Designer – Must be:-
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
DIOHAS @ RIBA
Mission StatementAIMS
➢understanding of proportionate and
practicable health and safety issues
amongst construction designers.
➢Provide health and safety information
and procedures to encourage the growth
of a safer industry.
➢To achieve this through
•Education
•Understanding
•Clear Communications
➢Provide a national standing of
architectural and building design related
health and safety issues.
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
What should a Principal
Designer really do!
Design out all risk?
But this has generally been
done at early concept stages
or
Help to MANAGE Design Risk?
But how???
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
Risk Identification, Evaluation, Reduction &
Communication Process by Workstages
Client & Lead Designer
+ Principal Designer
+ Designers & Specialists
Contractor / Worker/ FM
Strategic Definition and Brief
ConceptDesign
DetailedDesign
Procurement Tender
Construction Planning
+ Principal Contractor & subcontractors
Construction &Handover
Project CDM Strategy & Site Risks
Pre-constructionInformation(Initial Design Risks) Pre-construction
Information(Developed Design Risks)
Construction Phase Plan & Site Risks
Significant Risk /Benefit Tolerability
Commercial Decisions VE
Stage
0-1
Stage
2 -3Stage
3-4
Stage
3-4Stage
4-5
Stage
6-7
H&S File & Maintenance Risks
RIBA Work Stages
Ris
k T
ole
rability
BUT HOW?
Contractor/Engineering Hazard Log
A B C D E G I J K L M N O P
Status
L S R L S R
Active/
Closed
S.1 S01 piers C,M,D TAN
(Jacobs)
Working in proximity to live
traffic
4 5 20 S01 crosses several major roads and
impossible to configure within alignment
constraints to avoid constructing near live
traffic. Risk cannot be eliminated or
significantly reduced. Position piers as far
away from live traffic as possible. Single span
3 5 15 Note on drawing - method statement required
to cover particular issues relating to the
complexity of the existing slip roads and
A282 underneath and requirements for
temporary road closures for pier construction.
Tim Nicholson 17/05/06 & 21/05/06 Active M Bell Works to be carried out with lane
closures in accordance with Costain TM
phases. Provide proteced safety zone
with barriers
S.2 S01 Working in A2 c.r.
adjacent to live traffic
C,M,D TAN
(Jacobs)
Working in proximity to live
traffic
4 5 20 S01 crosses several major roads and
impossible to configure within alignment
constraints to avoid constructing near live
traffic. Cannot be eliminated and therefore no
mitigation available to designer.
4 5 20 Note on drawing - method statement required
to address the particular difficulty of working
in an island site
Tim Nicholson 17/05/06 & 21/05/06 Active M Bell Works to be carried out with lane
closures in accordance with Costain TM
phases. Provide proteced safety zone
with barriers
S.3 Pier bearing installation,
maintenance &
replacement (S01, S04,
S10(N) & S10(S)
M TAN
(Jacobs)
Working in proximity to live
traffic. Working at height
5 5 25 Design as integral bridges without bearings
considered but structure too long for this. No
alternative mitigation available to designer in
this respect.
5 5 25 Note on drawing - method statement required
addressing handling and installing of heavy
components at height with restrictive
clearances. Log in H&S file.
Tim Nicholson 17/05/06 & 25/05/06 Residual risks
to be noted in H&S plan - barrriesrs
& TM required
Active M Bell Provide protected safety zone with tvcbs
to mitigate traffic risk.
S.4 Inspecting joints and
bearings at abutments
(S01, S04, S10(N) &
S10(S)
M TAN
(Jacobs)
Working at height. 3 5 15 Provide enclosed abutment galleries 2 2 4 RRR <6 - no further action required Tim Nicholson 17/05/06 & 21/05/06 Closed M Bell
S.5 Painting of steelwork
(S01, S04, S10(N) &
S10(S)
C,M TAN
(Jacobs)
Working at height. 3 5 15 Use weathering steel 1 5 5 RRR <6 - no further action required Tim Nicholson 17/05/06 & 21/05/06 Closed M Bell
S.6 Concrete impregnation C TAN
(Jacobs)
Use of potentially toxic
substance (silane)
4 2 8 Apply for Departure from Standards to use
less toxic substance (Pavix) or to use
concrete additive.
4 1 4 RRR <6 - no further action required Tim Nicholson 17/05/06 & 21/05/06 Closed M Bell
S.7 Parapet installation
(S01, S04, S10(N) &
S10(S)
C TAN
(Jacobs)
Working at height, debris falls 3 5 15 No mitigation available to designer at
installation stage.
3 5 15 Note on drawing - method statement required
to address the particular dufficulty of providing
temporary edge protection while installing the
permanent edge protection at the same
location. Log in H&S file - maintenance
wpork on the outside of the parpap
Tim Nicholson 17/05/06 & 21/05/06 Active M Bell Cantilever formwork left in position until
parapet installation complete
S.7a Parapet maintenance
(S01, S04, S10(N) &
S10(S)
M TAN
(Jacobs)
Working at height, debris falls 3 5 15 Use aluminium parapet to minimise
maintenance
1 5 5 RRR <6 - no further action required. Tim Nicholson 17/05/06 & 31/05/06 Residual risks
to be noted in H&S plan
Closed M Bell
S.8 Placing deck formwork
(S01, S04, S10(N) &
S10(S)
C TAN
(Jacobs)
Working at height. 5 5 25 No mitigation available to designer. 3 5 15 Note on drawing - method statement
required. Consider placing deck formwork at
ground level and lifting into place with beams.
Otherwise special precautions e.g.netting,
harnesses, will be required to ensure safety of
operatives while working on bare st
Tim Nicholson 17/05/06 & 21/05/06 Active M Bell Permanent formwork placed where
possible at ground level and lifted into
place with main steel.
S.9 Placing deck formwork
(S01, S04, S10(N) &
S10(S)
C TAN
(Jacobs)
Debris falling onto motorway
and construction site.
5 5 25 No mitigation available to designer 3 5 15 Note on drawing - method statement required
- see above - but addressing containment of
materials by use of netting or similar.
Tim Nicholson 17/05/06 & 21/05/06 Active M Bell Any formwork erected at height to be
carried out wijt lane closures in place or
area beneath enclosed
S.10 Site splicing of steelwork
(S01, S04, S10(N) &
S10(S)
C TAN
(Jacobs)
Working at height. 3 5 15 Minimise number of splice positions. 2 5 10 Note on drawing - method statement required
to address handling of heavy components at
height.
Tim Nicholson 17/05/06 & 21/05/06 Active M Bell All work at height to be carried out wijt
lane closures in place or area beneath
enclosed
PART B - TRANSFER OF INFORMATION
Initial Risk
Rating
Residual
Risk Rating
Action by Designer to
Eliminate/Reduce Risk Rating
CDM Design Hazard Log: Project 'X'
PART C - CONTRACTOR IMPLEMENTATION
Au
tho
r -
Nam
e &
Co
mp
an
y
PART A - HAZARD ELIMINATION/REDUCTION
Information provided about the
residual hazards -
Drawing/Document
STRUCTURES
External Review
of Control
Measures? Y/N
(by whom)Control Measures required
Control Measures
identified in:
Construction
Manager
responsible -
NamePh
as
e Designer/Constructor
Discussion Date &
CommentsRef
Specific
Location/Activity
Design Manager
responsible - NamePotential Hazards
F H
Is it this?
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
Simple Register with risk identification, actions, ownership and timings
Or this?
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
Designer Guidance –
Symbols for Design Drawings
Identifying hazards that cannot be mitigated
Identifying compulsory actions to avoid risks
Identifying actions that should be prohibited
Identifying significant safety information to pass on
Or this ?
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
Contractor Guidance – Site Drawing
Safety Symbols & Signage
Are these needed for architectural design
drawings?
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
Site Analysis – Underground
Services for Initial Design and
Construction Phase
Underground
electrical cables
Subscan Survey -hazards identified with symbols
Choke Points
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
Site Contamination - Asbestos Survey
Information on design drawings
.
Survey drawings to be used for asbestos survey
Areas of asbestos and not surveyed identified
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
Detailed Design- Significant
Risks “only” Identified with
Symbols
Significant risks “only” identified on drawings
Key and symbols identify
significant risks
Other symbols used for significant risks only
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
Guidance- Design to avoid
silica and dust creation and
exposure by detailing
Avoid
“Notched”
block details
Avoid unnecessary or excessive cutting
But how do you add this?
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
Guidance- Design to
avoid silica and dust
creation and exposure
generic trade risks, by
specification?
Or this?
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
Contract Stage Design – Riser Ducts
Large duct at party wall, fall risk highlighted
1. Sleeved services 2. Large metal mesh
3.Small metal mesh prevents falls in open areas
Or this?
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
Detailed /Contract Design –
Heavy Masonry Units
Weight of units significant
Traditional attitudes Mechanised approach
Or this?
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
Roped Access- To unusual
structuresThe HSE’s description of Roped
Access
Terminal 5
Heathrow
Spinnaker
Tower
Roped access IRATA
guidelines
Or this?
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
A simple “Architectural Project” Risk Register to record
“ Significant Risks” only
AHMM Architects, RIBA, IIRSM
Demystifying the Principal Designer Role
Architectural Design sets the level of
construction risk that is acceptable to the
project team taking all other factors into
consideration
only the “significant design and site risks”
need special identification for contractors.
Contractors need to then deal with the
construction stage risk management
associated with these “significant risks”
in addition to their normal site and trade risk
management issues.