+ All Categories
Home > Business > Paul Ticher Project Management Presentation

Paul Ticher Project Management Presentation

Date post: 06-Sep-2014
Category:
Upload: samuel90
View: 572 times
Download: 1 times
Share this document with a friend
Description:
 
Popular Tags:
32
Richard Collings: Database Workshop Project Management 16 th May 2006 Sue Fidler, CTO Charity Technology Trust Phone: 0845 456 1823 Email: [email protected] Richard Collings, Consultant Phone: 020 8880 0188 Email: [email protected]
Transcript
Page 1: Paul Ticher Project Management Presentation

Richard Collings: Database Workshop

Project Management

16th May 2006

Sue Fidler, CTOCharity Technology TrustPhone: 0845 456 1823Email: [email protected]

Richard Collings, ConsultantPhone: 020 8880 0188Email: [email protected]

Page 2: Paul Ticher Project Management Presentation

2

Approach – Project Management Question Time

• Project health check

• Introductions

– Who you are

– Your current/planned project

– Problem/question that you have a the moment OR Issue you want to talk about

• Identify issues, prioritise and discuss

• Further material on

– Why projects go wrong

– Effect of budget on functionality, timescale and risk

– Project management approaches

Page 3: Paul Ticher Project Management Presentation

Politics

Multiple parties involved, some actively hostile; no decision making process in place

Multiple parties involved, some apathetic; no/weak decision making process in place

Multiple parties involved, mostly keen; acceptable decision making process in place

Multiple parties; single decision maker but poor understanding

Multiple parties; single decision maker with good understanding

Singe party involved, single decision maker with good understanding

User/management involvement

Users hostile and not involved; dictatorial management with poor understanding

Management delegated to ‘wrong’ users

Users neutral but very limited involvement; very limited management engagement

Users and management keen but do not have time to get effectively involved

Single good user actively involved, consults with others; management effectively involved

Good representative users freed up for project, effective participants; management fully engaged

Understanding of problem/business change

Nobody has thought about the business change needed

Complex change required and not understood; change to be forced through by new system

Complex change required but being done separately from system development

Complex change required; no piloting but effective business change planning being undertaken

Simple system with small business change involved; some planning done

System and business changes already effectively piloted; change programme worked out

Timescale/budget

Big bang roll out; fixed functionality; impossible timescale; insufficient budget

Big bang roll out; fixed functionality; impossible timescale; large budget

Big bang roll out; fixed functionality; acceptable timescale and budget

Big bang rollout; functionality; timescale flexible; budget fixed

Staged rollout possible; functionality flexible; tight, fixed budget and timescale

Project being staged/piloted; functionality flexible; budget and timescale fixed but adequate

Supplier/Technology

New unknown supplier using new technology for first time in new application area

New unknown supplier using new technology for first time in known (to them) application area

Previously used supplier, experienced in application area, working with new technology

Previously used supplier in new application area using known technology

Referenced supplier with substantial experience of technology and application area

Previously used supplier with substantial experience of technology and application area

Stability of requirement/ Previous experience

Requirement likely to change; have not implemented similar project (nor has supplier); big bang rollout

Requirement stable; have not implemented similar project (nor has supplier); big bang rollout

Requirement likely to change; have not implemented similar project (nor has supplier); staging possible

Requirement stable; have not implemented similar project (nor has supplier); staging possible

Requirement likely to change; but similar to previous projects (us and supplier); staging possible

Stable requirement; similar to previous projects (us and supplier)

Data migration

Large amounts of complex data to migrate; have not thought about how to do

Large amounts of complex data to migrate; some initial investigation done

No data to migrate/ load (are you sure?)

Large amounts of complex data to migrate; detailed planning done but no trials

Small amount of data to migrate/load; plan in place

Data transfer/data take on extensively trialled already

Project Health Check © Richard Collings ([email protected])

Page 4: Paul Ticher Project Management Presentation

Politics

Multiple parties involved, some actively hostile; no decision making process in place

Multiple parties involved, some apathetic; no/weak decision making process in place

Multiple parties involved, mostly keen; acceptable decision making process in place

Multiple parties; single decision maker but poor understanding

Multiple parties; single decision maker with good understanding

Singe party involved, single decision maker with good understanding

User/management involvement

Users hostile and not involved; dictatorial management with poor understanding

Management delegated to ‘wrong’ users

Users neutral but very limited involvement; very limited management engagement

Users and management keen but do not have time to get effectively involved

Single good user actively involved, consults with others; management effectively involved

Good representative users freed up for project, effective participants; management fully engaged

Understanding of problem/business change

Nobody has thought about the business change needed

Complex change required and not understood; change to be forced through by new system

Complex change required but being done separately from system development

Complex change required; no piloting but effective business change planning being undertaken

Simple system with small business change involved; some planning done

System and business changes already effectively piloted; change programme worked out

Timescale/budget

Big bang roll out; fixed functionality; impossible timescale; insufficient budget

Big bang roll out; fixed functionality; impossible timescale; large budget

Big bang roll out; fixed functionality; acceptable timescale and budget

Big bang rollout; functionality; timescale flexible; budget fixed

Staged rollout possible; functionality flexible; tight, fixed budget and timescale

Project being staged/piloted; functionality flexible; budget and timescale fixed but adequate

Supplier/Technology

New unknown supplier using new technology for first time in new application area

New unknown supplier using new technology for first time in known (to them) application area

Previously used supplier, experienced in application area, working with new technology

Previously used supplier in new application area using known technology

Referenced supplier with substantial experience of technology and application area

Previously used supplier with substantial experience of technology and application area

Stability of requirement/ Previous experience

Requirement likely to change; have not implemented similar project (nor has supplier); big bang rollout

Requirement stable; have not implemented similar project (nor has supplier); big bang rollout

Requirement likely to change; have not implemented similar project (nor has supplier); staging possible

Requirement stable; have not implemented similar project (nor has supplier); staging possible

Requirement likely to change; but similar to previous projects (us and supplier); staging possible

Stable requirement; similar to previous projects (us and supplier)

Data migration

Large amounts of complex data to migrate; have not thought about how to do

Large amounts of complex data to migrate; some initial investigation done

No data to migrate/ load (are you sure?)

Large amounts of complex data to migrate; detailed planning done but no trials

Small amount of data to migrate/load; plan in place

Data transfer/data take on extensively trialled already

Project Health Check © Richard Collings ([email protected])

Page 5: Paul Ticher Project Management Presentation

5

Introduction

• Who you are

– Your current planned project

– What you would like to get out of the session

– Problem/question that you have a the moment OR Issue you want to talk about

• Further material on

– Why projects go wrong

– Effect of budget on functionality, timescale and risk

– Project management approaches

Page 6: Paul Ticher Project Management Presentation

6

London Ambulance Service

• Ridiculously short timescales

• Belief that system could solve major organisational problems

• Fear based culture

• Insufficient budget

• No engagement with staff

• Lack of management understanding

• Responsibilities not defined

• Lack of project management experience

• No independent review

• Poor risk management

• Inexperienced supplier

• New/unproven technology

• Inadequate/non-existent testing & QA

• Poor system performance

• Poor change control

• No contingency planning/fall back options

• No/poor training

• Staff hostility

Page 7: Paul Ticher Project Management Presentation

7

Other things that can go wrong

• Insufficient buy-in from management

• Organisational politics

• Conflicting requirements

• Untested ideas

• Changing business environment

• Poor choice of package

• Over complicated design

• Unusable system

• Wrong users involved

• Interface problems

• Technically driven project

• Insufficient attention to data take on

• Transferring poor data from existing systems

• Supplier overcommitted

• Supplier goes bust

• Users not committed

Page 8: Paul Ticher Project Management Presentation

8

Reasons projects fail (1 of 2)

The Chaos Report, Standish Group, 1995Survey of 365 IT Managers

Page 9: Paul Ticher Project Management Presentation

9

Reasons why projects fail (2 of 2)

OASIG study, 199545 ‘experts’ in academia and consultancy

Page 10: Paul Ticher Project Management Presentation

10

Approaches to project management

• Traditional approach

– ‘Waterfall’ based

– Large amount of documentation/formal procedures

– PRINCE2

– Tends to be used on larger projects – particularly in government

• Agile approach

– AKA: Lightweight, RAD, DSDM, eXtreme Programming (XP), RUP, SCRUM

– Iterative approach

– Timeboxed development

– Delivery in small stages

– Focus on user engagement

– Small teams

Page 11: Paul Ticher Project Management Presentation

11

Budget vs Functionality, Risk and TimescaleF

unct

iona

lity

Tim

esca

le/R

isk

Budget

Page 12: Paul Ticher Project Management Presentation

12

Waterfall approach

Requirements capture

Analysis and design

Implement and module test

Integrate and test

Deploy

Freeze requirements

Freeze design

Page 13: Paul Ticher Project Management Presentation

13

PRINCE2 - Background

• Process based approach to project management

• Commissioned by CCTA (now OGC) – launched 1996

• Developed from PRINCE (1989) which was based on PROMPTII (1975)

• Mandated for government projects

• Widely used in private sector

• Certifications

– Foundation

– Practitioner

Page 14: Paul Ticher Project Management Presentation

14

PRINCE2 - Elements

• Processes

– Activities to be carried out during project

• Components

– Things generated/used by processes

• Techniques

– Used throughout the approach

• Roles

• Plans

Page 15: Paul Ticher Project Management Presentation

15

PRINCE2 – Processes

Directing a ProjectDirecting a Project

PlanningPlanning

Starting up a project

Starting up a project

Initiating a project

Initiating a project

Controlling a stage

Controlling a stage

Managing product delivery

Managing product delivery

Managing stage

boundaries

Managing stage

boundaries

Closing a project

Closing a project

Managing Successful Projects with Prince2, Pg12

Page 16: Paul Ticher Project Management Presentation

16

PRINCE2 - Components

• Business case

• Organisation

• Plans

• Controls

• Management of risk

• Quality in a project environment

• Configuration management

• Change control

Page 17: Paul Ticher Project Management Presentation

17

PRINCE2 - Techniques

• Product based planning

• Change control

• Quality reviews

Page 18: Paul Ticher Project Management Presentation

18

PRINCE2: Good things (1 of 5)

• Business case

– Contains: Reasons, Options considered; Benefits; Risks; Costs and Timescales; Investment appraisal

– Sensitivity analysis: Good, Average, Poor

– Need to (continue to) make sure that system is going to deliver a cost effective solution

• Project Board

– Consists of:• Executive: representing the Business: does the project meet the needs of the business overall• Senior user: representing the Users: will the project deliver a useable result (‘fit for purpose’)• Senior supplier: representing the Supplier(s): responsible for delivery of system• Project assurance: see below

– Need to make sure that above three constituencies are adequately represented

– Meets periodically review progress/risks/issues

Page 19: Paul Ticher Project Management Presentation

19

PRINCE2: Good things (2 of 5)

• Project manager (personal view)

– Understands business and technology

– Good communication skills

– Experienced

– Good communication skills

– Efficient and well organised

– Driven

– Good at delegating

• Project assurance

– Independent assessment of the project

– Understands business and technology

– Experienced

Page 20: Paul Ticher Project Management Presentation

20

PRINCE2: Good things (3 of 5)

• Project initiation document

– What, why, who, how and when

– Project definition: Objectives, Approach, Scope, Deliverables, Exclusions, Constraints, Interfaces, Assumptions

– Project organisation structure: Team structure, Job descriptions

– Communication plan

– Quality plan

– Project controls

– Initial Business case

– Initial Project plan

– Initial Risk log

Page 21: Paul Ticher Project Management Presentation

21

PRINCE: Good things (4 of 5)

• Stage boundaries

– Set points at which to review previous stage – confirm viability of project

– Review business case

– Plan next stage

• Risk Log

– Risk log:• Risk Description• Impact• Likelihood• Mitigation: Prevent, Reduce, Transfer, Accept, Provide contingency• Status• Outstanding actions

– Brainstorm

– Periodic reviews (eg Stage boundaries)

Page 22: Paul Ticher Project Management Presentation

22

PRINCE: Good things (5 of 5)

• Issue Log

– Issues: Request for change; Off-specification; Question; Statement of concern

– Capture:• Description• Priority• Impact analysis• Decision

Page 23: Paul Ticher Project Management Presentation

23

PRINCE2: Weaknesses

• Bureaucratic/labour intensive

• Focus on project management process; not on project itself

• Focus on deliverables rather than on delivering business benefit

• Focus on wrong things

– What needs to be done rather than how should we do this?

– Focus on paper rather than on actual deliverables

– Concerned with protecting one’s ‘rear end’ rather than on getting the job done

• Still dependent on the skills and knowledge of the individuals

• Delivers false sense of security

• Assumes that you know what you are doing

Page 24: Paul Ticher Project Management Presentation

24

PRINCE2: Resources

• Books

– Managing Successful Projects with PRINCE2, OGC, 2002

• Websites

– http://www.prince2.org.uk/

– http://www.btt-research.com/prince_2_project_failures.htm

Page 25: Paul Ticher Project Management Presentation

25

Agile - background

• Originated in mid/late 1980s

– Response to ‘big’ methodologies (SSADM, Information Engineering)

– Spiral (Boehm, 1986); Evo Development (Gilb, 1988), RAD (Martin, 1991)

• Mid 1990s

– DSDM – UK based initiative

• Late 1990s/Early 2000s

– Object community

– eXteme Programming (Beck/Cunningham – 1999)

– Agile Software Development (Alastair Cockburn – 2002)

– Scrum (Jeff Sutherland, 1993; Ken Schwaber, 2004)

– RUP/EUP (Jacobson 1988; Ambler 2000-2002)

Page 26: Paul Ticher Project Management Presentation

26

Agile - overview

“Manifesto for Agile Software Development

We are uncovering better ways of developing software by doing it and helping others do it. Through this work we have come to value:

• Individuals and interactions over processes and tools

• Working software over comprehensive documentation

• Customer collaboration over contract negotiation

• Responding to change over following a plan

That is, while there is value in the items on the right, we value the items on the left more.”

Agile Manifesto, 2001

Page 27: Paul Ticher Project Management Presentation

27

Agile: Approach/Good things (1 of 3)

• Iterative

– high benefit/low cost first

– focus on high risk areas

• Short development phases

– 1 week - 2 months

– Timeboxing

– Descope to deliver on time

– Deliver real working systems

• Face to face communication

– Small teams

– Pair programming

– ‘Onsite user’

Page 28: Paul Ticher Project Management Presentation

28

Agile: Approach/Good things (2 of 3)

• Keep it simple

– Focus on immediate requirements

– Don’t overcomplicate

– ‘Refactor’ where necessary

• Focus on business benefit

– Be clear why you are doing something

– Try and measure benefits

• Lightweight documentation

– Minimal specifications/documentation

– No modelling (or throw away)

– System/code is the documentation

Page 29: Paul Ticher Project Management Presentation

29

Agile: Approach/Good things (3 of 3)

• Testing driven

– Prepare tests before starting to code

– Test all the time (every build?)

– Automated testing

• ‘Human approach’ to system development

– Reasonable working hours

– Build team spirit

– Open/honest approach

– Accept people make mistakes

Page 30: Paul Ticher Project Management Presentation

30

Agile: Weaknesses

• Works best on projects where

– Requirements are uncertain

– Better to have something sooner with some certainty

• Less good on

– Replacement/Big bang projects

– Projects with known requirements

• Problems with passing risk onto supplier (fixed price contracts)

– ‘House with no roof’

• Issues with

– Stability

– ‘Project memory’

• Need a risk taking culture

– Works less well where there is a blame culture

Page 31: Paul Ticher Project Management Presentation

31

Agile: Sources

• Books

– Agile Software Development, Alistair Cockburn, 2002

– DSDM, The Method in Practice, Jennifer Stapleton, 1997

– Principles of Software Engineering Management, Tom Gilb, 1998

– eXtreme Programming explained, Kent Beck, 2000

– Agile Project Management with Scrum, Ken Schwaber, 2004

• Websites

– http://xprogramming.com/

– http://www.extremeprogramming.org/

– http://www.gilb.com/

– http://www.dsdm.org/

– http://www.enterpriseunifiedprocess.com/

Page 32: Paul Ticher Project Management Presentation

32

Contact details

• Richard Collings

– IS Strategy, Requirements preparation, Supplier Evaluation, Contract Negotiation

– User engagement facilitator, Acceptance Test planning, design and execution

– Project planning, project mentoring, project review

– email: [email protected]

– phone: 020 8888 0188

• Sue Fidler

– IS Strategy, Requirements preparation, Supplier Evaluation, Contract Negotiation

– Solution provision

– email: [email protected]

– phone: 0845 456 1823


Recommended