Date post: | 21-Apr-2015 |
Category: |
Documents |
Upload: | mohammad-abu-radi |
View: | 42 times |
Download: | 4 times |
Cost Risk Analysis(CRA)(CRA)
Pedram DaneshmandAssociate DirectorAssociate Director
Blue Visions Management Pty LtdJan 2011
Slide 1 of 18
Content
Project Cost ManagementProject Cost ManagementRisk & OpportunitiesProject Risk ManagementCost Risk Analysis (CRA)y ( )Simulation Results ReviewCRA Fi l R tCRA Final ReportIntegrated Schedule/Cost Risk Analysis
Slide 2 of 18
P j t C t M tProject Cost ManagementOverview
Every project must be managed against a budget;Every project must be managed against a budget;
Project cost controls has been around a long time;
Project Managers should liaise the budget between the client and the project team; and
More concern about how much than how long.
Project Cost Management includes the processes required that the project can be completed within
Slide 3 of 18
the approved budget (PMBOK, 2004).
P j t C t M tProject Cost ManagementProcess
Cost Estimating – developing an approximation ofCost Estimating developing an approximation of the costs of the resources needed to complete project activitiesproject activities.
Cost Budgeting – aggregating the estimated costs of individual activities or work packages toof individual activities or work packages to establish a cost baseline.
f fCost Control – influencing the factors that create cost variances and controlling changes to the
b dproject budget. (PMBOK, 2004)
Slide 4 of 18
C t E ti tiCost EstimatingTools and Techniques
Analogous EstimatingAnalogous Estimating
Determine Resource Cost Rates
Bottom‐up Estimating
Parametric Estimating
Project Management Software
Vendor Bid AnalysisVendor Bid Analysis
Reserve Analysis
f lCost of Quality
Slide 5 of 18
C t E ti ti Cost Estimating Inputs
Estimators develop the project estimate by using:Estimators develop the project estimate by using:Available organisational process assets;
Available quantities resources and productivity rates;Available quantities, resources and productivity rates;
Available work/scope statements;
Work Breakdown Structure (WBS) andWork Breakdown Structure (WBS); and
Other assumptions/documents e.g. PMP, etc.
All these add uncertainties to the estimate and reduce the confidence level. What about risks and
Slide 6 of 18
opportunities in the total project cost?
C t E ti tiCost EstimatingOutputs
The outputs of Cost Estimating process are:The outputs of Cost Estimating process are:(Deterministic) Activity Cost Estimate;
(Deterministic) Total Project Cost;(Deterministic) Total Project Cost;
(Deterministic) Cost Model Data
(Deterministic) Cost Baseline(Deterministic) Cost Baseline
(Deterministic) Resource Requirements
With all these uncertainties in the inputs and the possible risks and opportunities in the estimate, the
i i h fid i hi i ?
Slide 7 of 18
question is, how confident we are in this estimate?
C t E ti tiCost EstimatingProject Management Software
Software like cost estimating softwareSoftware, like cost estimating software applications, computerised spreadsheets, and simulations and statistical tools are widely used tosimulations and statistical tools are widely used to assist with cost estimating.
To have a realistic estimate, Cost Estimating process should be improved by using Cost Risk Analysis (CRA). In other words Project Cost Management and Project
Slide 8 of 18
In other words Project Cost Management and Project Risk Management need to be integrated!
C t E ti tiCost EstimatingRisks & Opportunities
Every estimate has uncertainties/assumptions.Every estimate has uncertainties/assumptions.
Every project has risks and opportunities.Eff jEffect on project(positive or negative)
Time
ScopeCostQuality
So, Risks and Opportunities should be managed effectively to minimize the surprises!!
Slide 9 of 18
Q y
P j t Ri k M t Project Risk Management Process
AS/NZS ISO 31000:2009
SULT
W
Establish ContextA
ND
CO
NS
D R
EVIE
W
Identify Risks
SME
NT
NIC
ATE
A
ITO
R A
ND
Analyse Risks
E l Ri k SK A
SS
ES
S
CO
MM
UN
MO
NEvaluate Risks
Treat RisksR
IS
Slide 10 of 18
P j t Ri k M tProject Risk ManagementRisk Assessment
Risk Assessment includeRisk Assessment includeRisk Identification (both Uncertainties and Events)
Risk AnalysisRisk AnalysisQualitative
Quantitative (Cost Risk Analysis or CRA)Quantitative (Cost Risk Analysis or CRA)
Risk Evaluation
The goal is to have a better understanding of risks/ opportunities and their overall impact on total project cost This will bridges the gap between
Slide 11 of 18
project cost. This will bridges the gap between traditional cost estimating and the REAL project.
P j t Ri k M tProject Risk ManagementRisk Analysis
Risk Analysis is the process to comprehend theRisk Analysis is the process to comprehend the nature of risks (or opportunities) and to determine the level of risks (or opportunities) in the schedulethe level of risks (or opportunities) in the schedule
Risk analysis provides the basis for risk evaluation anddecisions about risk treatment; anddecisions about risk treatment; and
Risk Analysis includes risk estimation.
By Cost Risk Analysis (CRA), we model the risks and opportunities (uncertainties and events) within the complexity of the interrelationships between the
Slide 12 of 18
complexity of the interrelationships between the various elements of the estimate.
C t Ri k A l iCost Risk Analysis(CRA)
CRA is a probabilistic analysis to quantify theCRA is a probabilistic analysis to quantify the impacts to a project, program or portfolio total cost as a result of carrying uncertainties and/or risksas a result of carrying uncertainties and/or risks and opportunities or to simulate the possible what‐if scenariosif scenarios.
Relying on a accurate most likely estimate as a base, CRA takes the project cost estimating to the
l l f d fid
Slide 13 of 18
next level of accuracy and confidence.
C t Ri k A l i (CRA)Cost Risk Analysis (CRA)Objectives
What is the project’s most likely cost?What is the project s most likely cost?
How likely is the baseline estimate to be overrun?
/Where are the risks/opportunities and the impacts (negative/positive) in this project?
How much contingency does project need?
Relying on a accurate most likely estimate as a base, CRA takes the project cost management to h l l f d fid
Slide 14 of 18
the next level of accuracy and confidence.
C t Ri k A l i (CRA)Cost Risk Analysis (CRA)Overview
Available data gatheringAvailable data gathering
Estimate Review
Technical Research
Risks & Opportunities RegisterBoth Uncertainties and Events
Cost Risk ModelCost Risk Model
Simulation
Res lts and Disc ssionsResults and Discussions
Slide 15 of 18
C t Ri k A l i (CRA)Cost Risk Analysis (CRA)Process - sample
Slide 16 of 18
C t Ri k A l i (CRA) Cost Risk Analysis (CRA) Data Gathering
Required information for a CRARequired information for a CRAWell‐developed project scope;
Quality estimate excluding contingency and escalation;Quality estimate excluding contingency and escalation;
Schedule reflecting the estimate;
Risk management policy/processes in your organisationRisk management policy/processes in your organisation;
Risk checklist presenting typical risks and opportunities;
Ri k & O t iti T l tRisk & Opportunities Template;
Cost Risk Templates/Models; and
S l f h d d iSample report of the process and recommendations.
Slide 17 of 18
C t Ri k A l i (CRA) Cost Risk Analysis (CRA) Estimate Review
How to review the deterministic estimate?How to review the deterministic estimate?Validation of all quantities (most likely);
Validation of all resource cost rates (most likely);Validation of all resource cost rates (most likely);
Validation of all durations (most likely);
Minimum number of constraintsMinimum number of constraints;
Work Statements;
C t tContract;
Reasonable duration for tasks; and
R bl C i i l P hReasonable Critical Path.
Slide 18 of 18
CRA E ti t R iCRA – Estimate ReviewSample Estimate
Slide 19 of 20
C t Ri k A l i (CRA) Cost Risk Analysis (CRA) Technical Research
When the team is confident that the projectWhen the team is confident that the project deterministic estimate reflects the most likely case, the technical research can beginthe technical research can begin.
Historical data research
InterviewsInterviews
Internet searches, etc.
Issues may include items such as geotechnical assumptions, Environmental Approvals, material prices inclement weather productivity concerns
Slide 20 of 18
prices, inclement weather, productivity concerns, existing services, contaminated material, etc.
C t Ri k A l i (CRA) Cost Risk Analysis (CRA) Risk Register
The Technical Research will enable the scheduleThe Technical Research will enable the schedulerisk analyst to complete the Risk Register file:
The identified risks & opportunitiesThe identified risks & opportunities
Likelihood of the identified risks and opportunities
Impacted activitiesImpacted activities
Schedule and/or Cost Impact/s
S h d l d/ C t V i tiSchedule and/or Cost Variations
Correlation of risks and opportunities to one another
N t tNotes, etc.
Slide 21 of 18
C t Ri k A l i (CRA) Cost Risk Analysis (CRA) Risk Register - sample
Slide 22 of 18
CRA Ri k R i tCRA – Risk RegisterQuality Check
Major risks and opportunities been identified;Major risks and opportunities been identified;
The likelihood and impacts been assessed;
Risk Matrix aligned with the company’s risk management policy;
Impacts checked against the allocated calendars;
Correlations between risks been identified;;
Stage the opportunities if required; and
Duplications are minimised and addressedDuplications are minimised and addressed.
Slide 23 of 18
CRA C t Ri k M d lCRA - Cost Risk ModelUncertainties & Events
Developing the Cost Risk Model involves modellingDeveloping the Cost Risk Model involves modelling the potential impacts and the likelihood of the risks and opportunities on the project and then applyingand opportunities on the project and then applying those to the schedule.
Two aspects of the risks and opportunities shouldTwo aspects of the risks and opportunities should be modelled within the schedule:
E i U i i (O i i i M Lik l dEstimate Uncertainties (Optimistic, Most Likely and Pessimistic)
Events including probabilistic branching (probability andEvents including probabilistic branching (probability and the impacts)
Slide 24 of 18
CRA C t Ri k M d lCRA - Cost Risk ModelTypes of Cost Uncertainty
Fixed Costs (e g from $5 000 to $7 000) – alsoFixed Costs (e.g. from $5,000 to $7,000) also spending distribution (uniform, normal, start or end) is importantend) is important.
Resource Rate uncertainty (e.g. $500/day to $700/day)$700/day)
Resource Allocations uncertainty (e.g. from 2 )decorator crews to 5 decorator crews)
Time Dependent Costs (e.g. from 4 days to 10 days)
Slide 25 of 18
CRA C t Ri k M d lCRA – Cost Risk ModelProbability Distributions
Probability Distribution is a way to indicate theProbability Distribution is a way to indicate the likelihood of values between the optimistic and pessimistic valuespessimistic values.
Probability Distribution can be:U if (fl )Uniform (flat),
Normal (bell shaped),
( k b ll h )Beta (skinny bell shaped),
Triangle (pyramid shaped), or
Customised (user defined).
Slide 26 of 18
CRA C t Ri k M d lCRA – Cost Risk ModelProbability Distributions
Slide 27 of 18
CRA C t Ri k M d lCRA – Cost Risk ModelSpecial Conditions
Special conditions which needs extra attention:Special conditions which needs extra attention:Probabilistic Branching – which considers the situation where the outcome of an event can cause in two orwhere the outcome of an event can cause in two or multiple possible courses of activities.
Correlation between risksPositive Correlation: occurs when one risk goes higher, so must the other.
Negative or Adverse Correlation: occurs when one risk increases, the other must decrease.
Inclement Weather or other external influencesInclement Weather or other external influences
Slide 28 of 18
CRA C t Ri k M d lCRA – Cost Risk ModelInclement Weather
Inclement Weather can be a significant factor in aInclement Weather can be a significant factor in a project schedule and cost. Very often there is good data available but understanding the impact on thedata available but understanding the impact on the schedule is challenging.
A proper modelling will allow the team to defineA proper modelling will allow the team to define risk assessment criteria for inclement weather conditions in the schedule and include theseconditions in the schedule, and include these uncertain weather conditions in the risk analysis.
Slide 29 of 18
CRA C t Ri k M d lCRA – Cost Risk ModelInclement Weather
There are two distinct ways of defining inclementThere are two distinct ways of defining inclement weather events:
Event with results in an uncertain number of nonEvent with results in an uncertain number of non working days scattered throughout a period, e.g. rain or snow.
Event with results in a single block of non working time with a probability of occurrence, e.g. chance of a hurricane in a period.
Slide 30 of 18
C t Ri k A l i (CRA) Cost Risk Analysis (CRA) Simulation Methods
The CRA performs multiple simulations of theThe CRA performs multiple simulations of the project using random samplings of the relevant risks and opportunities considering their probabilityrisks and opportunities considering their probability and impact.
Two popular methodsTwo popular methods:Monte Carlo Simulation (MCS) – faster method but has a larger possibility of sampling errorlarger possibility of sampling error
Latin Hypercube Sampling (LHS) – slower method but less sampling errorsless sampling errors
Slide 31 of 18
C t Ri k A l i (CRA) Cost Risk Analysis (CRA) Simulation Process
Analysis does the simulation through multipleAnalysis does the simulation through multiple samplings or iterations.
Each iteration is picking one sample point fromEach iteration is picking one sample point from each activity and calculating the total project cost.
User defines the number of iteration (e.g. 1000, 5000, etc) depending on the complexity of the project and its risk model.
Slide 32 of 18
C t Ri k A l i (CRA) Cost Risk Analysis (CRA) Simulation Tools
Main tools been widely used for simulation are:Main tools been widely used for simulation are:@Risk
Primavera Risk Analysis (previously known asPrimavera Risk Analysis (previously known as Pertmaster)
@Risk for Project@Risk for Project
Crystal Ball
Slide 33 of 18
C t Ri k A l i (CRA) Cost Risk Analysis (CRA) Simulation Reports
Main reports been widely produced by CRA are:Main reports been widely produced by CRA are:Schedule Check Report (if integrated with schedule)
Total Project Contingency Analysis: against the mostTotal Project Contingency Analysis: against the most likely estimate in $.
Sensitivity Analysis Report (or Key Risk Drivers): theSensitivity Analysis Report (or Key Risk Drivers): the areas of greatest concerns in order of criticality.
The next slides are presenting results from cost model simulations run by using @ Risk software.
Slide 34 of 18
model simulations run by using @ Risk software.
C t Ri k A l i (CRA)Cost Risk Analysis (CRA)Probability Density - sample
Confidential
Slide 35 of 18
C t Ri k A l i (CRA)Cost Risk Analysis (CRA)Sensitivity Analysis - sample
Confidential
Slide 36 of 18
C t Ri k A l i (CRA)Cost Risk Analysis (CRA)Detailed Report - sample
Confidential
Confidential
Slide 37 of 18
C t Ri k A l i (CRA) Cost Risk Analysis (CRA) Detailed Report - sample
Slide 38 of 18
C t Ri k A l i (CRA)Cost Risk Analysis (CRA)Detailed Report - sample
Slide 39 of 18
C t Ri k A l i (CRA)Cost Risk Analysis (CRA)Results Quality Check
After initial model a quality check is required forAfter initial model, a quality check is required forreasonableness of the simulation results.
The calculation of the contingency should beThe calculation of the contingency should bechecked against the project risk register, availableknowledge scope and estimate quality etcknowledge, scope and estimate quality, etc.
Sensitivity Report should be checked for the orderf fof high risk events and out of expected order.
Slide 40 of 18
C t Ri k A l i (CRA)Cost Risk Analysis (CRA)Common mistakes
Errors within the scope development;Errors within the scope development;
Risks/opportunities correlations not considered;
/Similar risks/opportunities cause double up;
Distribution curves not evaluated right; and
Simulation problems within the model.
Because of all these reasons, it is normal to review/run the risk model several times before a confidence level
Slide 41 of 18
is achieved for the available data within the risk model.
C t Ri k A l i (CRA) Cost Risk Analysis (CRA) Action Plan
The accuracy of the CRA outcomes should beThe accuracy of the CRA outcomes should be improved through a number of iterations of this processprocess.
Based on the initial results, the team should:R i th i k i t d k difi ti h iReview the risk register and make modifications where require;
Make changes to the risk model accordingly;
Run the simulation again and repeat the process to achieve theRun the simulation again and repeat the process to achieve the most cost‐effective risk mitigation plan;
Finalise the Risk Action Plan as well as the Contingency Plan; and
Communicate this schedule with the team and then monitor it.
Slide 42 of 18
C t Ri k A l i (CRA) Cost Risk Analysis (CRA) Final CRA Report
The Final CRA Report should include:The Final CRA Report should include:Project information including the scope;
Executive summary;Executive summary;
Report purpose, scope and background;
CRA methodology including software and teamCRA methodology including software and team;
Assumptions and market research;
Fi l Ri k/O t it R i tFinal Risk/Opportunity Register;
CRA Simulation Results, results and findings; and
Mi i i d i i lMitigation recommendations, contingency plan, etc.
Slide 43 of 18
Wh t i t?What is next?Schedule/Cost Risk Analysis
For big projects because of the reasons below anFor big projects, because of the reasons below, an integration of Schedule & Cost & Risk is required:
Schedule Cost and Risk are related;Schedule, Cost and Risk are related;
Time Dependent Costs;
Correlations between risks and opportunities; andCorrelations between risks and opportunities; and
One Schedule / Cost Risk Model for the project.
In other words Project Cost Management, Project Time Management and Project Risk Management
d b i d! !
Slide 44 of 18
need to be integrated! !
About the Author
Pedram Daneshmand Associate DirectorPedram Daneshmand, Associate Director
Blue Visions ManagementPedram is a civil engineer with over 15 years experience in the construction industry He isPedram is a civil engineer with over 15 years experience in the construction industry. He ishighly skilled and technically proficient in many aspects of construction includingProgramming, Programme Performance Measurement, Quantitative Risk Analysis,Contract Management, Schedule Risk Analysis (SRA), Cost Risk Analysis (CRA), ProjectMonitoring & Controls (PMC) Systems, Earned Value Performance Measurementtechnique (EVPM) and POW (Program of Work) Planning & Controls.
As an industry innovation award winner for his programming and risk analysis skills,Pedram is currently an Associate Director with Blue Visions Management leading a teamof planning and controls professionals within the infrastructure sector. With more than 15articles in the professional conferences/journals he is been regularly invited to thearticles in the professional conferences/journals, he is been regularly invited to thetechnical presentations as one of the industry leaders in his field.
Slide 45 of 18