Schedule Risk Analysisy(SRA)
Pedram DaneshmandAssociate Director
Blue Visions Management Pty Ltd
Slide 1 of 18
Content
Project Time ManagementProject Time ManagementRisk & OpportunitiesProject Risk ManagementSchedule Risk AnalysisyResults ReviewA ti PlAction Plan
Slide 2 of 18
P j t Ti M tProject Time ManagementHistory
Every project must be managed against a schedule;Every project must be managed against a schedule;
Project Scheduling has been around a long time;
Scheduling is one of the most widely practiced project management disciplines (Archibald and Villoria 1967).
Project Time Management includes the processes required to accomplish timely completion of the
Slide 3 of 18
project (PMBOK, 2004).
P j t Ti M tProject Time ManagementProcess
Activity DefinitionActivity Definition
Activity Sequencing (logic)
Activity Resource Estimating
Activity Duration Estimating
Schedule Development
Schedule ControlSchedule Control(PMBOK, 2004)
Slide 4 of 18
P j t Ti M tProject Time ManagementSchedule Development
The Schedule Development process includesThe Schedule Development process includes selecting a scheduling Method, scheduling Tool, incorporating project specific data within thatincorporating project specific data within that scheduling tool to develop project specific schedule Model and generating Project ScheduleModel, and generating Project Schedule.
(PMI‐PS for Scheduling, 2007)
Slide 5 of 18
S h d l D l tSchedule DevelopmentMethods
Logic‐based Scheduling Methods (LSM)Logic‐based Scheduling Methods (LSM)Deterministic Techniques
E g Critical Path Method (CPM) Resource Optimisation CriticalE.g. Critical Path Method (CPM), Resource Optimisation, CriticalChain Method (CCM), etc.
Stochastic TechniquesE.g. Probabilistic Evaluation and Review Technique (PERT), PNET,Monte Carlo Simulation (MCS), etc.
( )Repetitive Scheduling Methods (RSM)Line of Balance (LOB)
Flowline Method
Slide 6 of 18
S h d l D l t Schedule Development Inputs
Planners develop the project schedule by using:Planners develop the project schedule by using:Available templates;
Available quantities resources and productivity rates;Available quantities, resources and productivity rates;
Available work/scope statements;
Available construction logic andAvailable construction logic; and
Other assumptions/documents e.g. calendars, PMP, etc.
All these add uncertainties to schedule and reduce the confidence level. What about risks and
Slide 7 of 18
opportunities in the schedule?
S h d l D l t Schedule Development Outputs
The outputs of Schedule Development process are:The outputs of Schedule Development process are:(Deterministic) Project Schedule;
(Deterministic) Schedule Model Data(Deterministic) Schedule Model Data
(Deterministic) Schedule Baseline
(Deterministic) Resource Requirements(Deterministic) Resource Requirements
With all those uncertainties in the inputs and the possible risks and opportunities in the schedule, the
i i h fid i hi h d l ?
Slide 8 of 18
question is, how confident we are in this schedule?
S h d l D l t Schedule Development Major Challenges
Uncertainties due to assumptions;Uncertainties due to assumptions;
Logic, constraints, resources, calendars and activity durations are not always clear and agreeddurations are not always clear and agreed;
What‐If Scenarios; and
Risks and Opportunities
To have a realistic schedule, Schedule Development process should be improved by using Schedule Risk Analysis In other words Project Time Management
Slide 9 of 18
Analysis. In other words Project Time Management and Project Risk Management need to be integrated!
S h d l D l tSchedule DevelopmentRisks & Opportunities
Every schedule has uncertainties/assumptions.Every schedule has uncertainties/assumptions.
Every schedule has risks and opportunities.Eff jEffect on project(positive or negative)
Time
ScopeCostQuality
So, Risks and Opportunities should be managed effectively to minimize the surprises!!
Slide 10 of 18
Q y
P j t Ri k M t Project Risk Management Process
AS/NZS ISO 31000:2009
SULT
W
Establish ContextA
ND
CO
NS
D R
EVIE
W
Identify Risks
SME
NT
NIC
ATE
A
ITO
R A
ND
Analyse Risks
E l Ri k SK A
SS
ES
S
CO
MM
UN
MO
NEvaluate Risks
Treat RisksR
IS
Slide 11 of 18
P j t Ri k M tProject Risk ManagementRisk Assessment
Risk Assessment includeRisk Assessment includeRisk Identification (both Uncertainties and Events)
Risk AnalysisRisk AnalysisQualitative
Quantitative (Schedule Risk Analysis or SRA)Quantitative (Schedule Risk Analysis or SRA)
Risk Evaluation
The goal is to have a better understanding of risks / opportunities and their overall impact on project completion date This will bridges the gap between
Slide 12 of 18
completion date. This will bridges the gap between traditional CPM schedule and the REAL project.
P j t Ri k M tProject Risk ManagementRisk Analysis
Risk Analysis is the process to comprehend theRisk Analysis is the process to comprehend the nature of risks (or opportunities) and to determine the level of risks (or opportunities) in the schedulethe level of risks (or opportunities) in the schedule
Risk analysis provides the basis for risk evaluation anddecisions about risk treatment; anddecisions about risk treatment; and
Risk Analysis includes risk estimation.
By Schedule Risk Analysis (SRA), we model the risks and opportunities (uncertainties and events) within the complexity of the interrelationships between
Slide 13 of 18
the complexity of the interrelationships between the various tasks of the schedule.
S h d l Ri k A l iSchedule Risk Analysis(SRA)
SRA is a probabilistic analysis to quantify theSRA is a probabilistic analysis to quantify the impacts to a project, program or portfolio as a result of carrying uncertainties and/or risks andresult of carrying uncertainties and/or risks and opportunities or to simulate the possible what‐if scenariosscenarios.
Relying on a accurate most likely schedule as a base, SRA takes the project time management to h l l f d fid
Slide 14 of 18
the next level of accuracy and confidence.
S h d l Ri k A l iSchedule Risk AnalysisOverview
Available data gatheringAvailable data gathering
Schedule Review
Technical Research
Risks & Opportunities RegisterBoth Uncertainties and Events
Schedule Risk ModelSchedule Risk Model
Simulation
Res lts and Disc ssionsResults and Discussions
Slide 15 of 18
S h d l Ri k A l i Schedule Risk Analysis Data Gathering
Required information for a SRARequired information for a SRAWell‐developed project scope;
Quality estimate excluding contingency and escalation;Quality estimate excluding contingency and escalation;
Schedule reflecting the estimate;
Risk management policy/processes in your organisationRisk management policy/processes in your organisation;
Risk checklist presenting typical risks and opportunities;
Ri k & O t iti T l tRisk & Opportunities Template;
Schedule Risk Templates/Models; and
S l f h d d iSample report of the process and recommendations.
Slide 16 of 18
S h d l Ri k A l i Schedule Risk Analysis Schedule Review
How to review the deterministic schedule?How to review the deterministic schedule?Validation of all quantities (most likely);
Validation of all productivity rates (most likely);Validation of all productivity rates (most likely);
Validation of all durations (most likely);
Minimum number of constraintsMinimum number of constraints;
Complete logic network;
R bl d ti f t k dReasonable duration for tasks; and
Reasonable Critical Path.
Slide 17 of 18
SRA S h d l R iSRA – Schedule ReviewSample Report
Confidential
Slide 18 of 20
S h d l Ri k A l i Schedule Risk Analysis Technical Research
When the team is confident that the projectWhen the team is confident that the project deterministic schedule reflects the most likely case, the technical research can beginthe technical research can begin.
Historical data research
InterviewsInterviews
Internet searches, etc.
Issues may include items such as site access, Environmental Approvals, inclement weather, construction productivity concerns construction
Slide 19 of 18
construction productivity concerns, construction modifications, equipment and material deliver, etc.
S h d l Ri k A l i Schedule Risk Analysis Risk Register
The Technical Research will enable the scheduleThe Technical Research will enable the schedulerisk analyst to complete the Risk Register file:
The identified risks & opportunitiesThe identified risks & opportunities
Likelihood of the identified risks and opportunities
Impacted activitiesImpacted activities
Schedule and/or Cost Impact/s
S h d l d/ C t V i tiSchedule and/or Cost Variations
Correlation of risks and opportunities to one another
N t tNotes, etc.
Slide 20 of 18
S h d l Ri k A l i Schedule Risk Analysis Risk Register (Sample)
Confidential
Slide 21 of 18
SRA Ri k R i t (S l )SRA – Risk Register (Sample)Rain details
Slide 22 of 18
SRA Ri k R i tSRA – Risk RegisterQuality Check
Major risks and opportunities been identified;Major risks and opportunities been identified;
The likelihood and impacts been assessed;
Risk Matrix aligned with the company’s risk management policy;
Impacts checked against the allocated calendars;
Correlations between risks been identified;;
Stage the opportunities if required; and
Duplications are minimised and addressedDuplications are minimised and addressed.
Slide 23 of 18
SRA S h d l Ri k M d lSRA – Schedule Risk ModelUncertainties & Events
Developing the Schedule Risk Model involvesDeveloping the Schedule Risk Model involves modelling the potential impacts and the likelihood of the risks and opportunities on the project andof the risks and opportunities on the project and then applying those to the schedule.
Two aspects of the risks and opportunities shouldTwo aspects of the risks and opportunities should be modelled within the schedule:
E i U i i (O i i i M Lik l dEstimate Uncertainties (Optimistic, Most Likely and Pessimistic)
Events including probabilistic branching (probability andEvents including probabilistic branching (probability and the impacts)
Slide 24 of 18
SRA S h d l Ri k M d lSRA – Schedule Risk ModelProbability Distributions
Probability Distribution is a way to indicate theProbability Distribution is a way to indicate the likelihood of values between the optimistic and pessimistic valuespessimistic values.
Probability Distribution can be:U if (fl )Uniform (flat),
Normal (bell shaped),
( k b ll h )Beta (skinny bell shaped),
Triangle (pyramid shaped), or
Customised (user defined).
Slide 25 of 18
SRA S h d l Ri k M d lSRA – Schedule Risk ModelProbability Distributions
Slide 26 of 18
SRA S h d l Ri k M d lSRA – Schedule Risk ModelSpecial Conditions
Special conditions which needs extra attention:Special conditions which needs extra attention:Probabilistic Branching – which considers the situation where the outcome of an event can cause in two orwhere the outcome of an event can cause in two or multiple possible courses of activities.
Correlation between risksPositive Correlation: occurs when one risk goes higher, so must the other.
Negative or Adverse Correlation: occurs when one risk increases, the other must decrease.
Inclement Weather or other external influencesInclement Weather or other external influences
Slide 27 of 18
SRA S h d l Ri k M d lSRA – Schedule Risk ModelInclement Weather
Inclement Weather can be a significant factor in aInclement Weather can be a significant factor in a project schedule. Very often there is good data available but understanding the impact on theavailable but understanding the impact on the schedule is challenging.
A proper modelling will allow the team to defineA proper modelling will allow the team to define risk assessment criteria for inclement weather conditions in the schedule and include theseconditions in the schedule, and include these uncertain weather conditions in the risk analysis.
Slide 28 of 18
SRA S h d l Ri k M d lSRA – Schedule Risk ModelInclement Weather
There are two distinct ways of defining inclementThere are two distinct ways of defining inclement weather events:
Event with results in an uncertain number of nonEvent with results in an uncertain number of non working days scattered throughout a period, e.g. rain or snow.
Event with results in a single block of non working time with a probability of occurrence, e.g. chance of a hurricane in a period.
Slide 29 of 18
S h d l Ri k A l i Schedule Risk Analysis Simulation Methods
The SRA performs multiple simulations of theThe SRA performs multiple simulations of the project using random samplings of the relevant risks and opportunities considering their probabilityrisks and opportunities considering their probability and impact.
Two popular methodsTwo popular methods:Monte Carlo Simulation (MCS) – faster method but has a larger possibility of sampling errorlarger possibility of sampling error
Latin Hypercube Sampling (LHS) – slower method but less sampling errorsless sampling errors
Slide 30 of 18
S h d l Ri k A l i Schedule Risk Analysis Simulation Process
Analysis does the simulation through multipleAnalysis does the simulation through multiple samplings or iterations.
Each iteration is picking one sample point fromEach iteration is picking one sample point from each activity and calculating the project outcome.
User defines the number of iteration (e.g. 1000, 5000, etc) depending on the complexity of the project and its risk model.
Slide 31 of 18
S h d l Ri k A l i Schedule Risk Analysis Simulation Tools
Main tools been widely used for simulation are:Main tools been widely used for simulation are:Primavera Risk Analysis (previously known as Pertmaster)Pertmaster)
@Risk for Project
Crystal BallCrystal Ball
The next slides are presenting results from simulations by using Primavera Risk Analysis.
Slide 32 of 18
simulations by using Primavera Risk Analysis.
S h d l Ri k A l i Schedule Risk Analysis Sample Programme
Confidential
Confidential
Slide 33 of 18
S h d l Ri k A l i Schedule Risk Analysis Finish Date Histogram
Confidential
Slide 34 of 18
S h d l Ri k A l i Schedule Risk Analysis Histogram & Statistics
Confidential
Slide 35 of 18
S h d l Ri k A l i Schedule Risk Analysis Criticality Index Tornado
Confidential The Criticality Index of an e ca y de o aactivity is the proportion of the iterations in which the activity was critical Usuallyactivity was critical. Usually more attention will be given to the activities with Criticality Index of more thanCriticality Index of more than 50%.
Slide 36 of 18
S h d l Ri k A l i Schedule Risk Analysis Criticality Path Report
The Criticality Path Report Confidentialhighlights the path through the project containing the tasks with the highest gCriticality Index values.
Percent Criticality is thePercent Criticality is the probability that an activity will be on the critical path; this indicates the relativethis indicates the relative importance of the activity to other activities in the
Slide 37 of 18
programme.
S h d l Ri k A l i Schedule Risk Analysis Criticality Distribution Profile
Confidential Criticality Distribution Profile plots the spread of Criticality Index in a project which gives an indication of the number and threat of near to critical path.
A high percentage (more than 40%) indicates a relatively tight programmetight programme.
Slide 38 of 18
S h d l Ri k A l i Schedule Risk Analysis Action Plan
The accuracy of the SRA outcomes should beThe accuracy of the SRA outcomes should be improved through a number of iterations of this processprocess.
Based on the initial results, the team should:R i th i k i t d k difi ti h iReview the risk register and make modifications where require;
Make changes to the risk model accordingly;
Run the simulation again and repeat the process to achieve theRun the simulation again and repeat the process to achieve the most cost‐effective risk mitigation plan;
Finalise the Risk Action Plan as well as the Contingency Plan; and
Communicate this schedule with the team and then monitor it.
Slide 39 of 18
About the Author
Pedram Daneshmand Associate DirectorPedram Daneshmand, Associate Director
Blue Visions ManagementPedram is a civil engineer with over 15 years experience in the construction industry He isPedram is a civil engineer with over 15 years experience in the construction industry. He ishighly skilled and technically proficient in many aspects of construction includingProgramming, Programme Performance Measurement, Quantitative Risk Analysis,Contract Management, Schedule Risk Analysis (SRA), Cost Risk Analysis (CRA), ProjectMonitoring & Controls (PMC) Systems, Earned Value Performance Measurementtechnique (EVPM) and POW (Program of Work) Planning & Controls.
As an industry innovation award winner for his programming and risk analysis skills,Pedram is currently an Associate Director with Blue Visions Management leading a teamof planning and controls professionals within the infrastructure sector. With more than 15articles in the professional conferences/journals he is been regularly invited to thearticles in the professional conferences/journals, he is been regularly invited to thetechnical presentations as one of the industry leaders in his field.
Slide 40 of 18