OPERATION AND MAINTENANCE
MANUAL FOR
1st & 2nd STAGE 3 PHASE SEPARATOR
Petrodar Order No. : 11057-31100132-MQ01-020
Equipment Tag No. : 1V, 2V, 3V, 4V-8301
LEPS Doc No. : LEPS-20071005-O&M
Higleig Doc No. : PDOC-236207-VD-MEC-075
Issue and Revision Record
016-03-
09Submitted for Approval LEPS LEPS
Rev
No.Date Description
Prepared by
Supplier
Reviewed by
Supplier
Approved by HDC
Owner : EPCC Contractor : Supplier / Sub-Contractor :Document No: LEPS-20071005-O&M
Petrodar Operating Company
Moleeta FPF Oil Development Project
Petrodar Operating Company Limited
Higleig Petroleum Services & Inv. Co. Ltd.
LAKSEL EPS Technologies Pte Ltd
INDEX
1.0 SAFETY
1.1 Safety when Entering the separator1.2 Safety when filling the vessel with Oil1.3 Safety when Emptying the Vessel
2.0 EQUIPMENT DESCRIPTION
2.1 Internals2.2 Weir plates2.3 Baffle2.4 Vortex Breaker2.5 De-sanding Line and Nozzles2.6 Heating Coil
3.0 START-UP PREPARATION
3.1 Vessel and Internals3.2 Pipe Works3.3 Instruments3.4 Electricity
4.0 START-UP PROCEDURE
4.1 Filling with Crude4.2 Adjustment of Interface Level4.3 Oil Level
5.0 NORMAL OPERATION
5.1 Normal Operating and Maintenance Instructions
6.0 SYMPTOMS OF FAULTY SEPARATOR OPERATION
7.0 SHUT DOWN PROCEDURE(Normal and Emergency)
7.1 Shut down7.2 Emptying the Plant
8.0 ELECTRICAL MAINTENANCE
8.1 High Voltage Electrical Failure
Document No: LEPS-20071005-O&M
9.0 DESIGN AND PERFORMANCE DATA
9.1 Design9.2 Description9.3 Performance9.4 Hazards9.5 Information Sources
10.0 STORAGE AND HANDLING
11.0 OPERATION
11.1 Basic Principles of Operation11.2 Slugging Conditions11.3 Emergency Levels11.4 Fault Conditions
12.0 MAINTENANCE
12.1 Recommended schedule of Maintenance12.2 Maintenance Requirements12.3 Vessel
13.0 ANNEXURES
13.1 Process and Instrumentation diagram13.2 General Arrangement Plan13.3 Instrument Schedule13.4 Correction for Buoyancy type Level Gauge
Document No: LEPS-20071005-O&M
PRE START-UP CHECKS OF FOR THREE PHASE SEPARATOR
NOTE – Read this instruction completely prior to introducing Crude Oil in the Separator. Contact your Laksel Representative for start-up assistance.
WARNING Perform all of the following steps in order to ensure personnel safety and equipment protection.
Preliminary Inspection
Perform the following preliminary inspection before putting the Separator online
Isolate all power sources to the Instruments and Controls to be certain that no short circuit takes place
Bypass all interlocks to the Separator
Recheck/correct the Separator and piping installation
Ensure that all the external/internal bolts are fully tightened as per the required torque range. Make sure all the Baffle plate, Weir plate, Vortex breaker are in order and in place. Looseness and misalignment during transportation should corrected during inspection
Make certain that all piping are securely connected and properly supported
Inspect all Separator control components (control valves, flow metering devices, check valves, strainers, gauges, etc.) to make certain that these components are correctly oriented in the piping scheme in order to achieve the proper direction of flow and functional operation
Inspect the Separator inlet to make certain that the inlet screen and clean-out connections have been properly made and are free of tools, equipment and debris
Fully open the inlet and discharge line manual valves of the Separators
Open the Valves in the drain lines
All the instruments and the valves which are damaged during the transportation are replaced with the new items are rectified with the spares
All the pipe lines are cleaned and flushed with the water to remove all the loose items , dust and other matters
Document No: LEPS-20071005-O&M
1.0 SAFETY
SAFETY RULES AND RECOMMENDATIONS APPLICABLE ON SITE WILL
BE APPLIED DURING ERECTION, NORMAL OPERATION AND
MAINTENANCE WORKS ON UNITS.
All procedures indicated in this manual that could be in contradiction with applicable safety
rules on site, will be modified to meet site requirements
In any case, if several safety rules govern the same application, the most constraining ones
will be applied
1.1 Safety when entering the separator
When entering the separator the safety rules applicable to process vessel should be
followed. As example some of these rules are listed here under:
Authorization permit to enter the vessel should be delivered by the relevant
authority
All vessel flanges connected with process lines should be blinded
Vessel must be free of oil, water gas or dirt
An explosivity test must be carried out in all accessible parts of the vessel internal
Internal temperature must be acceptable
Natural or mechanical ventilation should be sufficient to permit work inside the
vessel without risk
Etc
1.2 Safety when entering the vessel with oil
In order to avoid the information of explosive mixture, the vessel should be totally
purged from air before charging with hydrocarbons
This purging can be done using nitrogen or other inert gas which is not harmful if
released to atmosphere
1.3 Safety when emptying the vessel
In order to avoid formation of explosive atmosphere when emptying the vessel , it is
absolutely imperative to replace pumped put product by inert gas(ex. Nitrogen) or
water under low pressure(<15psig)
Document No: LEPS-20071005-O&M
Special care will be taken also to avoid any vacuum in each vessel compartment
during pumping out.
2.0 EQUIPMENT DESCRIPTION
2.1 I nternals
Separators are horizontally mounted on a skid. The separator is divided in to two
compartments be a weir plate. i.e the water side and the oil side. Internals consist of
weir plate, baffles, vortex breaker and diverter. Internals are of SS316 and are bolted
to the vessel with fittings which are SA516Gr.70
2.2 Weir Plate
Crude and water mixture enters to the left side of weir. The interface is controlled and
not allowed to rise above the height of the weir. This weir keeps the separated water
in left compartment. During low production rates the oil will overflow to the oil
compartment over the weir. During high production rates the oil level will be above
the weir and both compartments will be flooded with oil
The height of weir plate is adjustable. For the first stage, 3 levels (1585,
1905&2105mm) of adjustability is possible and for second stage, 2 levels (xxxx). Weir
should be fixed to the flat bars on vessel shell through neoprene rubber. Neoprene
rubber is also used to seal the bolt holes
2.3 Baffle
Baffle plates are fitted on the water side to enhance separation. Inlet crude oil mixture
enters the separator on the left side of the baffle and has to pass through the baffles
to get transferred to the right side of the baffle. All the baffle through the baffle plates
except the bottom plate can be unbolted and removed through the manholes for the
1st stage and second stage
2.4 Vortex Breaker
Vortex breaker is placed at the outlet of both crude oil and produced water. It helps to
break the vortex formation on the outflow
Document No: LEPS-20071005-O&M
2.5 Desanding Line and nozzles
Inlet crude mix brings with it sand particles, which get settles in the vessel. Desanding
needs to be done to remove the accumulated sand in the vessel. Frequency of
desanding operation depends on the sand content in a given crude mix. De-sanding
water is circulated through the desanding line and it is sprayed on the accumulated
sand at the bottom of the vessel through the spray nozzles, which are fitted to the
desanding pipes. Desanding line is of SS316 Material
2.6 Heating Coil
In order to maintain a temperature of 50 degrees C in the separator at all times, even
while it is not in operation, hot oil is circulated through the heating coils. Inlet hot oil
temperature is 250ºC
3.0 START – UP PREPARATION
* IMPORTANT NOTE : BEFORE STARTING ANY OPERATION, PLEASE REFER TO CHAPTER 1.0. “SAFETY”.
3.1 Vessel and Internals
Ensure the condition of the pressure vessel and the internals.
Check the maximum allowable working pressure and the operating temperature,
which are marked on the name plate of the vessel.
3.2 Pipe Works
Ensure all pipe work is correctly installed
3.3 Instruments
Check all instruments for correct function
Check all relief/safety system for correct operation
Check all control valves and associate system for correct function including
“failure” modes.
3.4 Electricity
All electrical part should be carefully checked – wiring of all elements should be checked
as well as their satisfactory connection, Earthling circuit should be checked
Document No: LEPS-20071005-O&M
4.0 START UP PROCEDURE
(See chapter 1.0 “SAFETY”)
4.1 Charging with Hydrocarbon
*IMPORTANT NOTE:
Before charging with hydrocarbon, the vessel should be completely free of air. This
purge should be done with nitrogen or any other insert gas not harmful to the
atmosphere. Check that all valves. Drains vents sample are closed and their caps are
installed. When the level of oil is between the low level and high level, then reset the
low and high alarm of the interface by pressing the reset push button on the control
panel.
4.2 Adjustment of Interface Level
Follow the development of the interface level by using the level gauge on the
standpipe. When the set supper level is reached, the control valves opens in
accordance with the controller signal and allows produce water to flow out of vessel.
The preferred settings at design production rates for First Stage Separator are as
follows:
Interface Liquid Level: ILHH
ILH
ILL
ILLL
Document No: LEPS-20071005-O&M
Preferred setting for Second Stage Separator is:
Interface Liquid Level: ILHH
ILH
ILL
ILLL
Control valves operation taken place such that the interface layer stays between ILH and ILL
additional low level and high level cut offs are provided between ILH and ILL.
Check alarm and trip circuit for high and low levels by stimulating abnormal level conditions.
4.3 Oil Level
Oil levels are maintained on the basis of following oil level settings.
The preferred settings at designed production rates are as follows:
Liquid Level in Separator: LHH
LH
LL
LLL
Preferred settings for 2nd stage are
Liquid Level in Separator: LHH
LH
LL
LLL
Levels are controlled between LH and LL. Additional cut offs are provided at LHH and
LLL.
Check alarm and trip circuits for high and low level by stimulating abnormal level
condition.
5.0 NORMAL OPERATION
5.1 Normal Operation and Maintenances Instructions (See Chapter 1.0 SAFETY”)
Document No: LEPS-20071005-O&M
5.1.1 Operation Data Sheet
If required a daily operating data sheet will be issued. This data sheet
allows all essential parameters that allow operation and control of the
plant.
5.1.2 Preparation for the Inspection of the Vessel
When a vessel inspection is foreseen, the following recommendation
should be applied
Stop the plant
Check that there is no voltage on the Power unit
Drain the vessel according to Chapter 9.2
Isolate the vessel by placing blind flanges on all the inlet and outlet
nozzles.
Open both manholes and top vent of vessel.
Vent the vessel with low pressure steam if available (Lower than 3
bar) for 274 hours.
Connect a stripped cable to an earthling pad or to vessel wall, then
connect it to the electrode. No spark or presence of current should be
detected.
Clean the internal walls of vessel with pressurized water, hot if
available.
Before entering the vessel ensure that the temperature has dropped
sufficiently to allow entry and that any harmful or flammable gas has
been purged.
5.1.3 Maintenance and trouble – shooting
The separator until offers high operating reliability because all parts of the units:
vessel and internal (baffles, weir, etc ) piping etc…static elements .It trouble on the
treating operations occurs, then refer to chapter 8.0
All items of equipments (Instruments, vessels, power units, piping etc) should be kept
in good condition and clean (free of rust) they should be checked regularly for good
operation and sealing.
If a part or equipment appears to be faulty or out of order, then refer to the trouble –
shooting guide in the manufacturer’s manuals
Document No: LEPS-20071005-O&M
It is recommended that when the vessel is opened or maintenances internal
distribution and collection pipe work together with the electrode s grids and the vessel
shell are inspected for signs of erosion and/or corrosion.
5.1.4 Power and control Panel
Equipment on the control panel such as relays, contactors, voltmeter, ammeter and
push buttons will be checked and maintained regularly.
6.0 SYMPTOMS OF FAULTY SEPARATOR OPERATION
*NOTE: Before adjustment in the plant, check that operating conditions are in conformity with required specifications.
FAULT PRIMARY CAUSE SECONDARY CAUSE REMEDY1 High oil ppm in
produce water outlet
A Ineffective separation
B Level setting of interface level not effective
a. Control valve defective
b. Connection fault at LTc. Fault in DCS signals
Leakage through Baffle PlatedHigher production rates over the design rates
Reduce production to design limits
Low operating temperatureHigh viscosity
2 High water ppm in oil outlet
A Leakage through weir plates
a. Bolts on weir loose/gasket not defective
Check and tighten
B Level setting of interface level not effective
a. Control valve defective
b. Connection fault at LTc. Fault in DCS signals
Leakage through Baffle platesHigher production over the design rates
Reduce production to design limits
Low operating temperatureHigh viscosity
Document No: LEPS-20071005-O&M
3 Sand content high in outlet water
A Sand accumulation too high
a. Carry out desanding operation
B a.4 No outflow in
outflow linesNo gas content b. Use inert gas
c.
5 Improper functioning of vortex meter
C a.
b.
6 Improper functioning of PD meter
A
B
7.0 SHUT DOWN PROCEDURE (NORMAL AND EMERGENCY)
(Before any operation, please refer to chapter 1.0. “Safety”)
7.1 Shut Down
The following procedure should be followed
Close all manual valves Stop the oil pumps Close isolation valves of unit Stop electrical feed of heat tracing lines
* REMARKS:
When the vessels are to be taken out of service the drain lines and any compartments
should be blown down to remove all the material that has been collected.
Vessels to be fully vented before man ways are released and purged with nitrogen.
Gas masks to be worn when entering the vessel until it is certain that all happens and
compartment are clear of gas and free of hazardous contaminates.
7.2 Emptying the Plant
When it is necessary to completely empty the vessel, apply the following procedure Close the inlet valves of Crude Drain the oil and the water As soon as the draining is complete Carry out Desanding operation and flush
out sand Open both manholes Place blind flanges or spectacles on at each nozzle connected to pipe work.
Document No: LEPS-20071005-O&M
7.2.1 IMPORTANT NOTES:
During the operation it is absolutely imperative to replace the pumped-out product by
inset gas (e.g. Nitrogen) or water under low pressure
Air must never enter the emptying vessel in order to avoid an explosive mixture
8.0 ELECTRICAL MAINTENANCE
9.0 DESIGN AND PERFORMANCE DATA
9.1 DESIGN 1st STAGE SEPARATOR
MANUFACTURER
PROCESS DATA (DESIGN BASIS FOR EACH SEPARATOR IS 75% OF GROSS TRAIN THROUGHOUT
INLET CONDITION TO 1ST STAGE SEPARATOR TAG NO: 1V/2V/3V/4V-8301 ARE AS FLOWS (EACH)
DESCRIPTION UNIT DESIGN OUTLET FLOW
FIRST YEAR (MAX OIL)LATER YEARS
(MAX Gross Liquid)TOTAL FLOW Kg/hr 161200.9 163337OIL (REFER PRODUCT SPEC.) Kg/hr 76980 30780WATER Kg/hr 83520 132300GAS Kg/hr 700.9 257TEMPERATURE °C 50 50PRESSURE kpag 800 800DENSITY OF OIL EMULSION Kg/m3 943.7 943.5DENSITY WATER Kg/m3 988.4 988.5VISCOSITY OF OIL EMULSION cP 1687 1709VISCOSITY OF WATER cP 0.5417 0.5431
PRODUCT SPECIFICATION1. Liquid particles of sizes 150pm and above shall be removed from outlet gas(100% REMOVAL)2. Oil Retention time shall be 10 minutes (minimum)3. water retention time shall be 10 minutes (minimum)4. water cut in outlet oil stream shall be less than 30% v/v/
Design Codes ASME VIII DIV 1 U-STAMP
FLUID Oil, water & GasSWEET SERVICE
Document No: LEPS-20071005-O&M
OPERATING TEMPERATURE AND PRESSURE
INTERNAL 850 kPag @ 50 °C
EXTERNAL - kPag @ - °C
DESIGN TEMPERATURE AND PRESSURE
INTERNAL 1380 & FULL Vacuum kPag @ 125 °C
EXTERNAL - kPag @ - °C
MAWP 1425.75 kPag @ °C
MINIMUM DESIGN METAL TEMPERATURE
PWHT REASON IF REQD., AS PER CODE
RADIOGRAPHY JOINT EFF: SHELL 100% HEAD 100%
HYDROTEST 1794 kPag Horizontal position
WIND VELOCITY 135 km/h EARTHQUAKE ZONE UBC1, Z=0.075
CAPACITY 91.82 m3
INSULATION 38mm THICK Hot, As per PDOC-SP-MEC-014
REMARKS APPLICABLE PDOC SPECIFICATION: PDOC-SP-MEC-020
Document No: LEPS-20071005-O&M
MATERIALSSHELL TYPE Cylindrical Shell ASME MATERIAL SA 516 Gr 70 DESIGN THICK Mm 18.54 CORROSION ALL. Mm 3 MILL TOLERANCE Mm 0.3TOTAL THICK Mm 18.54NOMINAL THICK Mm 19.06HEADTYPE 2.1 SE ASME MATERIAL SA 516 Gr 70 DESIGN THICK Mm 18.75 CORROSION ALL. Mm 3 MILL TOLERANCE Mm 0.3
TOTAL THICK Mm 18.75NOMINAL THICK Mm 22.23SADDLE PLATES / WRAPPER PLATE
SA 36 / SA516 GR 70
TRAYS NOSUPPORT INT SA 516 GR 70 EXT SA 516 GR 70 / SA 36BOLTS INT SA 193 GR B7M EXT SA 193 GR B7NUTS INT SA 194 GR2HM EXT SA 194 GR 2HFLANGES SA 105 NNOZZLE -NECKS SA 106 GR BGASKETS SPIRAL WOUND SS 304VESSEL TRIMHEATING COIL SS 316LINTERNALS SS 316 L
DESIGN 2ND STAGE SEPARATOR
MANUFACTURER
PROCESS DATA (DESIGN BASIS FOR EACH SEPARATOR IS 75% OF GROSS TRAIN THROUGHOUT
INLET CONDITION TO 2ND STAGE SEPARATOR TAG NO: 1V/2V/3V/4V-8302 ARE AS FLOWS (EACH)
DESCRIPTION UNIT DESIGN OUTLET FLOW
FIRST YEAR (MAX OIL)LATER YEAR
(MAX Gross Liquid)TOTAL FLOW Kg/hr 112816 45111.1OIL (REFER PRODUCT SPEC.) Kg/hr 76630 30650WATER Kg/hr 35720 14290GAS Kg/hr 466 171.1TEMPERATURE °C 105 105
Document No: LEPS-20071005-O&M
PRESSURE kpag 400 400DENSITY OF OIL EMULSION Kg/m3 887.4 877.2DENSITY WATER Kg/m3 944 944VISCOSITY OF OIL EMULSION cP 93.7 93.39VISCOSITY OF WATER cP 0.2653 0.2652
PRODUCT SPECIFICATION1. Liquid particles of sizes 150pm and above shall be removed from outlet gas(100% REMOVAL)2. Oil Retention time shall be 10 minutes (minimum)3. water retention time shall be 10 minutes (minimum)4. water cut in outlet oil stream shall be less than 30% v/v/
Design Codes ASME VIII DIV 1 U-STAMP
FLUID Oil, water & Gas
SWEET SERVICE
OPERATATING TEMPERATURE AND PRESSURE
INTERNAL 300 kPag @ 105 °C
EXTERNAL - kPag @ - °C
DESIGN TEMPERATURE AND PRESSURE
INTERNAL 1380 & FULL Vacuum kPag @ 125 °C
EXTERNAL - kPag @ - °C
MAWP 1425.75 kPag @ °C
PWHT REASON IF REQD., AS PER CODE
RADIOGRAPHY JOINT EFF: SHELL 100% HEAD 100%
HYDROTEST 1794 kPag Horizontal position
WIND VELOCITY 135 km/h EARTHQUAKE ZONE UBC1, Z=0.075
CAPACITY 77 m3
INSULATION 38mm Hot, As per PDOC-SP-MEC-014
REMARKS APPLICABLE PDOC SPECIFICATION : PDOC-SP-MEC-020
Document No: LEPS-20071005-O&M
MATERIALSSHELL TYPE Cylindrical Shell ASME MATERIAL SA 516 Gr 70 DESIGN THICK Mm 18.56 CORROSION ALL. Mm 3 MILL TOLERANCE Mm 0.3TOTAL THICK Mm 18.56NOMINAL THICK Mm 19.05HEADTYPE 2.1 SE ASME MATERIAL SA 516 Gr 70 DESIGN THICK Mm 18.43 CORROSION ALL. Mm 3 MILL TOLERANCE Mm 0.3TOTAL THICK Mm 18.43NOMINAL THICK Mm 22.23SADDLE PLATES / WRAPPER PLATE
SA 36 / SA516 GR 70
TRAYS NOSUPPORT INT SA 516 GR 70 EXT SA 516 GR 70 / SA 36BOLTS INT SA 193 GR B7M EXT SA 193 GR B7NUTS INT SA 194 GR2HM EXT SA 194 GR 2HFLANGES SA 105 NNOZZLE -NECKS SA 106 GR BGASKETS SPIRAL WOUND SS 304VESSEL TRIMHEATING COIL SS 316LINTERNALS SS 316 L
9.2 Description
See General arrangement plan
9.3 Performance
The PPM of oil in water at the outlet meet shall be less than 2000 ppm Liquid particles of size 150 microns and above shall be removed from the outlet
gas (100% removal).. Oil retention time shall be minimum of 10 minutes Water retention time shall be minimum of 10 minutes Water cut in oil stream shall be less than 10% v/v
9.4 Hazards
This separator contains hot, high-pressure H/C fluids. Observe statuary regulations for operating vessel. Do not enter vessel until it has been purged and spaded-off. Do not operate vessel outside of design conditions. Do not subject to surges/slugs outside of design conditions.
Document No: LEPS-20071005-O&M
9.5 Information Sources
Address queries on separator performance (not vessel) to :
Hup Seng offshore and Engineering Pte Ltd152 Gul Circle, Jurong, SingaporeTel +65 68614449
10.0 STORAGE AND HANDLING
11.0 OPERATION
The separators are in the form of horizontal pressure vessels fitted with internals to effect separation of oil, water and gas.
11.1 Basic Principles of Operation
Three phase crude oil consisting of oil, associated gas and water enters the separator at the inlet nozzle.
It first encounters a diverter, where the bulk separation of liquid and gas takes place. The mixture then passes through the perforated baffle plate which causes it to calm down and aid oil water separation. After the baffle plate major separation of oil and water takes place and two separate layers of oil and gas are established. The required residence time is available to the mixture which causes the oil particles to rise upwards from the water phase and water particles to move downwards from the oil phase.
After separation the water flows out through the produce water outlet line. The control valve on this line is regulated so as to maintain a level of interface lower than the weir level. As the level of oil exceeds the weir level, the excess oil flows over the weir to the right side in the oil zone. At normal production rates the oil level would be above the weir height. The separated oil then flows out through the oil outlet.
On the left side of weir, the interface level is controlled between two preset alarm levels ie IHL and ILL. A standpipe is fitted in parallel with the separator, capable of reflecting levels in the separator. On this standpipe, there are two float type level transmitters, which transfer the signal to DCS control. DCS controls the interface level by regulating the control valve on the produce water outlet line. Alarms are also signaled at DCS at these levels.
In addition to these, for levels above IHL and below ILL, a level transmitter is fitted to initiate signal at IHH and ILL which cuts off of the inlet and outlet valves. Float type level gauge is fitted on the standpipe to indicate the interface levels.
On the oil side of weir, the oil level is controlled between the two alarm levels ie HL and LL. This control is achieved by regulating the control valve on the oil outlet and on the oil inlet. For levels beyond this range, a level transmitters is provided to initiate signal at HHL and LLL which will valve cut off inlet and outlet valves. Magnetic level gauge is provided to indicate oil levels.
Document No: LEPS-20071005-O&M
All transmitters for interface detection are buoyancy tyope and those for oil level detection are diaphragm type.
11.2 Measuring and Control instruments
Flow indicator: Differential pressure type indicator is provided in the incoming crude oil line, which measures flow with the help of orifice plates.
Vortex Flow Meter: Provided on the produce water outlet line
Differential Pressure Indicator: Differential pressure transmitter and indicator are provided to measure the pressure drop across the strainer on crude oil outlet line.
Temperature Indicator: 2 nos, provided on the vessel
Pressure indicator: To indicate the pressure
Level Indicators: Fitted on the vessel to measure interface level and il level.
11.3 Control Valves
PV Valve on the Gas lineESDV : On crude inletLevel Control Valves;1 on Custody oil outlet1 on produce water outlet
11.4 Fault conditions
Provided the separators are operated within the design criteria specified in section 1.3, no faults should occur. The main ways to identify failure are:
- Excessive oil carryout in produce water downstream- Increase in normal operating pressure drop across the separators.
Because of the nature of the separators it would be impractical to mention all the possibilities which could cause the above, but in the event of any of the above occurring, this is to be reported immediately to HSOEPL with the process flow particulars as specified in section 1.3.
Trouble Shooting Guide
FAULT PROBABLE CAUSE1 Excessive pressure drop across
separatorBlockage in separator/internals damaged.Open separator and investigate.
2 Separator operating at incorrect levels Instrument/control valve fault : consult suppliers product data
3 Incorrect separation efficiencies Check 1 & 2 and also check process conditions are as stated in this manual
Document No: LEPS-20071005-O&M
12.0 MAINTENANCE
12.1 Recommended Schedule of maintenance
All internals should be visually inspected every 8 weeks, unless in operation the separator fails to meet the required duty and process specification for the gas and liquid streams.
12.2 Maintenance Requirements
Internals, Routine Maintenance
The horizontal separators comprise internal baffles that have to be regularly maintained during the life of the vessels. The internals are listed in the description section of this manual and the following activities should be carried out as per recommended schedule:
1) Internals should be visually inspected for signs of cracking, erosion, damage etc., and repaired as necessary.
2) Check all internals are free of dirt, debris, blockages etc., ensure they are free of tar build-up etc.
3) Check all items show no signs of damage from erosion, surges etc., check weirs and sound.
4) Check all bolting is tight and fitted with second nut (lock nut).
5) Carry out re-certification inspection of pressure vessels in accordance with manufacturer’s instructions/statuary requirements.
If it is necessary to remove the internals from the vessels follow the reversed procedures outlined in section 3.3.
12.2.1 Vessel As required by pressure vessel code, carry out periodic re-certification requirements.Check for:
Cracking of attachment welds to shells Erosion of vessel shells at areas around inlet/outlet nozzles Corrosion around drain connections and instrumentation connections Clogging, plugging of instrumentation connections Pitting or scuffing of any gasketed faces
Always use gaskets when re-making nozzle/manway flange connections.
Document No: LEPS-20071005-O&M