+ All Categories
Home > Documents > Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety...

Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety...

Date post: 04-Oct-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
80
Office of the City Manager 2180 Milvia Street, Berkeley, CA 94704 ● Tel: (510) 981-7000 ● TDD: (510) 981-6903 ● Fax: (510) 981-7099 E-mail: [email protected] Website: http://www.CityofBerkeley.info/Manager CONSENT CALENDAR December 15, 2015 To: Honorable Mayor and Members of the City Council From: Dee Williams-Ridley, Interim City Manager Submitted by: Phillip Harrington, Acting Director, Public Works Subject: Shattuck Reconfiguration and Pedestrian Safety Project Update RECOMMENDATION Accept the progress report for the 35% design concept for the Shattuck Reconfiguration and Pedestrian Safety Project. SUMMARY This report provides an update on the design of the Shattuck Reconfiguration and Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended to improve pedestrian and bicycle safety, reduce unnecessary delays for northbound traffic (including transit vehicles) and enhance the quality of public spaces in the Downtown core. The 2012 Downtown Area Plan (DAP) included conceptual drawings for the project, 1 and the Downtown Streets and Open Space Improvement Plan (SOSIP), which Council unanimously adopted on January 29, 2013 (Resolution 66,000-N.S.), lists the project as a Tier I priority. 2 The project’s construction funds are programmed for fiscal year 2016-17, which means design work and environmental clearance, including Caltrans studies and reviews, must be completed by September 2016. Construction is anticipated to begin in spring 2017 and conclude by December 2017. Detailed design and engineering work on the project began March 2015 and has progressed to the 35% level (see Figure 1 and Attachments 1 and 2). Key elements of the current design are as follows (see Background section for further discussion): Convert the west (southbound) leg of Shattuck Avenue (“Shattuck West”) between University Avenue and Center Street into a two-way, four-lane street. 1 See DAP, Policy AC-1.1(e), p. AC-9 (available online at: http://www.ci.berkeley.ca.us/uploadedFiles/Planning_and_Development/Level_3_-_DAP/FINAL_x- DAP%20document_120329.pdf) 2 See SOSIP, pp. 18, 27-31, and 35 (provided in Attachment 5, or available online at: http://www.cityofberkeley.info/uploadedFiles/Planning_and_Development/Level_3_- _DAP/2013%20SOSIP.pdf).
Transcript
Page 1: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Office of the City Manager

2180 Milvia Street, Berkeley, CA 94704 ● Tel: (510) 981-7000 ● TDD: (510) 981-6903 ● Fax: (510) 981-7099 E-mail: [email protected] Website: http://www.CityofBerkeley.info/Manager

CONSENT CALENDAR December 15, 2015

To: Honorable Mayor and Members of the City Council

From: Dee Williams-Ridley, Interim City Manager

Submitted by: Phillip Harrington, Acting Director, Public Works

Subject: Shattuck Reconfiguration and Pedestrian Safety Project Update

RECOMMENDATION Accept the progress report for the 35% design concept for the Shattuck Reconfiguration and Pedestrian Safety Project.

SUMMARY This report provides an update on the design of the Shattuck Reconfiguration and Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended to improve pedestrian and bicycle safety, reduce unnecessary delays for northbound traffic (including transit vehicles) and enhance the quality of public spaces in the Downtown core. The 2012 Downtown Area Plan (DAP) included conceptual drawings for the project,1 and the Downtown Streets and Open Space Improvement Plan (SOSIP), which Council unanimously adopted on January 29, 2013 (Resolution 66,000-N.S.), lists the project as a Tier I priority.2

The project’s construction funds are programmed for fiscal year 2016-17, which means design work and environmental clearance, including Caltrans studies and reviews, must be completed by September 2016. Construction is anticipated to begin in spring 2017 and conclude by December 2017. Detailed design and engineering work on the project began March 2015 and has progressed to the 35% level (see Figure 1 and Attachments 1 and 2).

Key elements of the current design are as follows (see Background section for further discussion):

Convert the west (southbound) leg of Shattuck Avenue (“Shattuck West”) between University Avenue and Center Street into a two-way, four-lane street.

1 See DAP, Policy AC-1.1(e), p. AC-9 (available online at: http://www.ci.berkeley.ca.us/uploadedFiles/Planning_and_Development/Level_3_-_DAP/FINAL_x-DAP%20document_120329.pdf) 2 See SOSIP, pp. 18, 27-31, and 35 (provided in Attachment 5, or available online at: http://www.cityofberkeley.info/uploadedFiles/Planning_and_Development/Level_3_-_DAP/2013%20SOSIP.pdf).

rthomsen
Typewritten Text
15
Page 2: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Shattuck Reconfiguration and Pedestrian Safety Project Update CONSENT CALENDAR December 15, 2015

Reconfigure the Shattuck West/University intersection to reduce volume of westbound right turns onto Shattuck which conflict with pedestrian movement. By relocating traffic movement to a northbound through movement, this will reduce conflict with pedestrians.

Maintain the east (northbound) leg of Shattuck (“Shattuck East”) as a one-way street, but narrow to two lanes with bulb-outs for enhanced pedestrian crossings.

Provide angle parking on Shattuck East to maintain as much on-street parking in the project area as possible. The current design results in a net loss of five on-street parking spaces.

Route vehicles turning (left or right) onto University to Shattuck East, to maintain adequate sidewalk width and parking on Shattuck West between Addison Street and University.

Prohibit left turns in both directions from Shattuck West at Addison and Center; prohibit northbound left turns from Shattuck West at University, because there is insufficient space for a left turn lane.

Widen sidewalk and create a “transit plaza” on the east side of Shattuck between Center and Allston, with design treatments similar to the BART Plaza; relocate AC Transit stop from in front of Bank of America, to the south end of this block in front of Target. This will provide access to Shattuck West for northbound buses and facilitate pedestrian transfers between BART and bus lines.

Construct a raised intersection at Shattuck East and Center to improve pedestrian access between UC Berkeley and the BART Plaza, and calm northbound traffic entering Shattuck East.

Public engagement has been a high priority throughout the design process. An open house held June 9th to present initial plans and obtain public input was attended by approximately 50 people. Beginning in early October, staff has conducted an online survey which has at this writing received over 1,200 responses. These survey results demonstrate strong support for the main elements of the project and are summarized in Attachment 3. A complete list of project public meetings and media coverage is provided in Attachment 4.

On October 15, 2015, the Transportation Commission received public testimony on the project and voted 6-0-2-13 to recommend Council support the current 35% design plan with the following changes:

Seek to provide three parallel parking spaces on the east side of Shattuck West between Center and Addison Streets.

Use raised planters rather than in-ground planters for landscaping.

Seek functional art or café seating to activate sidewalk area on east side of Shattuck West between Center and Addison Streets.

3 Aye: Gerhardstein, Ghosh, Howe, Humbert, Lathbury, Zander; No: None; Absent: Hauser, Thomas; Recused: Bruzzone

Page 3: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Shattuck Reconfiguration and Pedestrian Safety Project Update CONSENT CALENDAR December 15, 2015

Maximize bicycle facilities and routes.

Avoid fixed non-removable seating (e.g. concrete seat walls).

Consider renaming the Center Street Garage to reflect access from Addison Street (e.g. “Addison-Center Garage”)

Configure traffic signal at Shattuck East and University Avenue to enhance pedestrian travel along University

Prohibit right turns from westbound University to northbound Shattuck.

Implement the left turn prohibitions in the current design, but evaluate after project completion.

As noted earlier, conceptual drawings for the project are included in the adopted DAP and SOSIP. CEQA clearance for the project occurred as part of the DAP EIR. Because staff has now developed more detailed, engineering-level plans which include minor changes from the earlier conceptual drawings, staff is preparing an addendum to the DAP EIR to document the current plans’ consistency with the certified EIR. In addition, federal law requires Section 106 cultural resource analysis for the project (due to use of federal funding). This report is intended to obtain Council direction regarding the preferred project design for the purpose of conducting CEQA and Section 106 review. Council review at this stage is also prudent to ensure the final plans reflect Council’s wishes and to avoid changes later in the design process.

FISCAL IMPACTS OF RECOMMENDATION The project is funded by federal grants with local matching funds, as detailed in the following chart and the grant funding agreement approved by the Council on June 25, 2013.4 It should be noted that the final project cost cannot be determined until construction bids are received; this is anticipated to occur in March 2017.

Fund Name Fund Code Amount Measure B Local Streets & Roads ................................... 391 ........................... $116,389 Measure B Bike and Pedestrian ....................................... 392 ............................. $22,510 Measure F County Vehicle Reg. Fees.............................. 397 ........................... $418,566 Measure BB Local Streets & Roads ................................. 406 ........................... $230,000 UC LRDP Settlement ....................................................... 489 ........................... $320,000 MTC OBAG Grant 614 $2,777,000 Total $4,113,265

4 Council report available online at: http://www.cityofberkeley.info/Clerk/City_Council/2013/06Jun/Documents/2013-06-25_Item_30_Grant_Funding_Agreement_for_MTC.aspx

Page 4: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Shattuck Reconfiguration and Pedestrian Safety Project Update CONSENT CALENDAR December 15, 2015

Figure 1. Proposed Plan (see Attachment 1 for striping plan)

Page 5: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Shattuck Reconfiguration and Pedestrian Safety Project Update CONSENT CALENDAR December 15, 2015

CURRENT SITUATION AND ITS EFFECTS DAP and SOSIP recommend the reconfiguration of Shattuck Avenue between Center Street and University Avenue. Based on the concept-level plans in SOSIP (see Attachment 5), in 2013 the City applied for and received a $2.8 million project grant from the Alameda County Transportation Commission (through the One Bay Area Grant program).

The current configuration of this two-block portion of Shattuck is a “couplet,” where the street divides into two one-way segments, with northbound traffic on the east segment and southbound traffic on the west segment. Because the east segment ends at University, northbound traffic must turn left (westbound) onto University for ½-block, and then turn right (northbound) back onto Shattuck to proceed north of University. This configuration, combined with the high volume of traffic and pedestrians, contributes to high auto/pedestrian conflict and high collision rates at the University/Shattuck intersection. For this reason, the City’s Pedestrian Master Plan identifies the Shattuck/University intersection as High Priority Pedestrian Project #2 (see Attachment 6).

DAP and SOSIP recommend the existing Shattuck couplet be redesigned so as a result: the west side will operate as a two-way street; the east side will have angle parking, lower traffic volumes in the near term and pedestrian-oriented enhancements (e.g. a “plaza or slow street”) in the long term. Current plans (see Figure 1 and Attachments 1 and 2) implement the basic near-term concept described in DAP and SOSIP, but with some of the long-term pedestrian enhancements.

BACKGROUND The following discussion covers several key issues encountered during the design and outreach process.

Left Turns onto University One of the most significant design issues for the project has been how to efficiently handle northbound left turns on University Avenue without sacrificing pedestrian comfort and good urban design. The SOSIP includes two alternatives for handling these turns in the near-term scenario (see Attachment 5, Figure d.19): (1) allow left turns onto University from both sides of the couplet, with a dedicated turn lane on the west side; and (2) allow left turns onto University only from the east side, with signage between Center and Allston indicating the route for vehicles turning onto University. While the SOSIP subcommittee preferred the first option, SOSIP Policy 1.7 acknowledges the need for further evaluation, and that there are several key tradeoffs between the two options.5 As detailed design work on the project began, the design

5 SOSIP Policy 1.7: “A left turn lane from the west side of Shattuck Square to University Avenue is preferred because it is easy to understand -- but a left-turn lane in this location would result in narrow lane

Page 6: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Shattuck Reconfiguration and Pedestrian Safety Project Update CONSENT CALENDAR December 15, 2015

team investigated both options closely. After laying out the geometry of the first option (see Figure 2), it became clear this option includes several major drawbacks:

Sidewalks at the southwest and southeast corners of Shattuck West and University would be reduced to about 10 feet with no bulb-outs.6 This width would be far less than the 20 to 25 feet provided at the south end of this block (at Addison), and generally not adequate for pedestrian comfort at a busy Downtown intersection. Furthermore, existing sidewalk on both sides of the street would be reduced for most of the block, whereas the other option requires only the removal of the bulb-outs on the east side of the block at University and Addison.

Parking would be removed from both sides of Shattuck West, while the second option requires parking to be removed only from the east side of Shattuck West.

Figure 2. Issues with Left Turns from Shattuck West to University

widths, reduced crosswalk curb extensions, and elimination of parking spaces on west Shattuck Square. If lane widths are found to be insufficient, consider routing westbound traffic along the east side of Shattuck Square. To do this, northbound motorists who want to travel west on University would have to be guided by signs before they reach Shattuck Square.” 6 Figure 2 shows sidewalk widths of 11 feet, but these would have to be reduced in order to provide 11-foot traffic lanes rather than the 10-foot lanes shown in the figure. 10-foot lanes are not advisable given the large volumes of trucks and buses on this roadway.

Page 7: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Shattuck Reconfiguration and Pedestrian Safety Project Update CONSENT CALENDAR December 15, 2015

The pedestrian crossing distance across Shattuck West at University would be 55 feet (five lanes) with no median or bulb-outs, effectively one of the widest crossings in the City. In the second option, this distance would be 44 feet with a bulb-out on the southwest corner.

The second option, while less direct for drivers turning left onto University, would generally be more consistent with the SOSIP’s overall direction to enhance the pedestrian realm, and would be more responsive to stakeholder concerns regarding loss of on-street parking. Furthermore, staff believes the inconvenience to drivers turning left onto University would be minimal given the widespread use of GPS navigation devices and apps, as well as the wayfinding signage that would be placed near Shattuck and Allston. Based on these considerations, staff recommends the second option. Left Turn Prohibitions at Center and Addison As noted earlier, the project would prohibit left turns in both directions from Shattuck West to Addison and Center. Left turns would also be prohibited from Shattuck East to Center. These prohibitions are necessary to prevent left-turning vehicles from blocking through traffic due to lack of space for left turn lanes, and from conflicting with pedestrians in the crosswalk as turning drivers focus instead on finding gaps in oncoming traffic. Additionally, at Center Street there are sight distance issues because of the curve on Shattuck and the lack of queueing space between the east and west legs of Shattuck. Attachment 7 provides further details on these issues and discusses how access will be maintained to destinations on Addison and Center Streets. On-Street Parking Supply As mentioned earlier, the current design results in a net loss of five on-street parking spaces within the project area. Figure 3 shows the number of parking spaces being added or removed on each block. In order to accommodate four traffic lanes on Shattuck West, it is necessary to remove the 15 parking spaces along the east side of Shattuck West. The loss of these spaces would be largely offset by angle parking on Shattuck East. The design team investigated several options to maintain the parking spaces on Shattuck West, including having only one northbound lane, and having parking spaces recessed into the existing sidewalk between street trees. However, these options had significant problems: the single northbound lane would cause excessive congestion at Shattuck and University (see Attachment 8, p. 14, Alternative 4), and the recessed parking option would substantially increase the project cost and narrow the sidewalks on both sides of Shattuck West between Addison and University, without increasing the total parking on that block (see Attachment 9).

Page 8: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Shattuck Reconfiguration and Pedestrian Safety Project Update CONSENT CALENDAR December 15, 2015

Given that 270 public parking spaces are being added in the immediate vicinity at the Center Street Garage, and because the goBerkeley program has been demonstrated to effectively manage on-street parking supply in the Downtown, staff believes the loss of five on-street parking spaces is acceptable and consistent with SOSIP Policy 1.18 (regarding no net loss of parking until implementation of goBerkeley).7 Figure 3. Parking Supply in Project Area

7 SOSIP Policy 1.18 (Net Zero Parking Strategy): “On-street parking that is lost because of street and

open space improvements should be replaced by an equal number of new nearby on-street parking spaces. There should be no net loss of parking until parking & transportation demand management programs [i.e., goBerkeley] are implemented [italics added for emphasis] and attain a target of one vacant on-street parking space per block face (about one vacant space for every ten spaces) during peak demand under typical conditions.”

Page 9: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Shattuck Reconfiguration and Pedestrian Safety Project Update CONSENT CALENDAR December 15, 2015

Back-in Angle Parking Another significant component of the proposed on-street parking is the use of “back-in” angle parking spaces, where (similar to parallel parking) drivers pass the open space, then put the vehicle in reverse and back into the space. These spaces have been implemented successfully in a number of cities including Sacramento, Chico, Portland, Seattle, Philadelphia, and Washington, D.C. The main advantage of this design is provision of better visibility of oncoming traffic (particularly bicycles) as the driver enters the traffic lane (see Figure 4).8 With traditional “head-in” angle parking, drivers must generally back into the traffic lane without being able to see oncoming traffic, due to the presence of adjacent parked vehicles. In addition, back-in angle parking allows goods to be loaded into a vehicle’s trunk from the sidewalk. Figure 4. Back-in Angle Parking Diagram

For the reasons described above, back-in angle parking has strong support from Berkeley’s cycling community. However, some stakeholders have expressed concern that drivers will not be familiar with the back-in spaces and will not know how to properly use them. Staff’s position is that installation of the back-in spaces carries little risk, because such spaces can be restriped to the traditional head-in design with minimal expense if they are found to be undesirable. In addition, the City could restripe some of its existing angle parking spaces as a back-in space pilot program before implementing it in this project. For further information, see Attachment 10 and the video in Footnote 8.

8 A video explaining the benefits of back-in angled parking is available at: https://www.youtube.com/watch?v=HddkCbsWHlk&feature=youtu.be

Page 10: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Shattuck Reconfiguration and Pedestrian Safety Project Update CONSENT CALENDAR December 15, 2015

Pedestrian “Buffer” along East Side of Shattuck West Removal of the parking spaces along the east side of Shattuck West presents a design challenge. Typically, parking spaces provide a visual and psychological buffer between the sidewalk and moving traffic which increases pedestrian comfort. However, the project team has investigated several options for introducing landscaping elements along the edge of this sidewalk to maintain an adequate buffer, including new street trees, light poles, various types of planters, benches, and bicycle racks. One of the issues still under discussion is whether fixed seating is appropriate given the potential for loitering, panhandling, and other problematic behaviors. Water usage is also being considered. The design team will continue working with adjacent stakeholders and the Downtown Berkeley Association to refine the design of this buffer. Commercial Loading Loading zones in the project area are shown in Attachment 11. The project would remove three existing loading zones, but replace these with other loading zones in the immediate vicinity. Merchants in the project area have expressed concerns that: (1) removal of traffic lanes will cause double-parked delivery vehicles to have a greater impact on congestion; and (2) removal of specific loading zones will adversely impact businesses currently relying on those zones. In response to merchants’ concerns, staff is also investigating additional loading zones to better serve the businesses at the north end of the Shattuck Square block between Shattuck West and Shattuck East, at University. The main options being considered are:

(1) “Bulb-in” loading zone on Shattuck West mid-way between Addison and University. This option would require removal of one street-tree and would reduce the sidewalk width.

(2) Convert a bus stop on University between Shattuck West and Shattuck East to a loading zone. This option would require moving the bus stop east of Shattuck East, or lengthening the stop west of Shattuck West, which would, in either case potentially require removal of several on-street parking spaces.

Transit By removing the need to turn onto University, the project reduces delays for northbound traffic from Allston to University by about 20 percent (25 seconds). This will help improve on-time performance for AC Transit buses passing through the corridor. In addition, as noted earlier, a key element of the project is the creation of a “transit plaza” on the east side of Shattuck between Center and Allston, across from and with design treatments similar to, the BART Plaza. This feature has several important benefits:

Page 11: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Shattuck Reconfiguration and Pedestrian Safety Project Update CONSENT CALENDAR December 15, 2015

Reinforce (visually and functionally) this block of the Downtown as the City’s major transit center.

Allow easier transfers between bus and BART by moving the stop for several AC Transit lines one block closer to the BART entrances, with one less street to cross (Center).

Allow easier transfers between buses by consolidating all north- and westbound buses on the same block.

Enhance the appearance and “sense of place” of the Downtown core by complementing the design features of the BART Plaza (especially trees, lighting, paving, and high-quality bus shelters).9

The design team has coordinated closely with AC Transit, including traffic modeling to maximize on time performance and reliability of buses. As design work proceeds, the team will be investigating the use of queue jump lanes and transit signal priority to further enhance bus operations. ENVIRONMENTAL SUSTAINABILITY This project is intended to make Shattuck Avenue in Downtown Berkeley more accessible for walking, bicycling, and riding transit. The project is thereby expected to support ongoing reduction in the share of Downtown trips made via single occupancy vehicles, thereby reducing vehicle emissions including carbon dioxide and other greenhouse gases. The project is also expected to reduce collisions between motor vehicles and pedestrians and bicyclists.

RATIONALE FOR RECOMMENDATION Staff is requesting Council’s input at this stage of design in order to ensure that the final design reflects Council’s goals and priorities.

ALTERNATIVE ACTIONS CONSIDERED None.

CONTACT PERSON Farid Javandel, Manager, Transportation, Public Works, 981-7061 Aaron Sage, Principal Planner, Transportation, Public Works, 981-6399

9 Some of these enhancements are subject to the City securing required funding. The City has requested funding from the Alameda County Transportation Commission for Downtown transit center improvements as part of the Countywide Transportation Plan.

Page 12: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Shattuck Reconfiguration and Pedestrian Safety Project Update CONSENT CALENDAR December 15, 2015

Attachments: 1. 35% Design Plan (Signage/Striping) 2. 35% Design Plan (Landscaping) 3. Survey Results 4. List of Stakeholder Meetings 5. SOSIP Excerpts 6. Pedestrian Master Plan Excerpts 7. Information on Left Turn Prohibitions 8. Traffic Study 9. “Bulb-In” Parking Option (Shattuck West between Addison and University) 10. Back-in Angle Parking Study 11. Commercial Loading Zones

Page 13: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-03 DRAWINGS\SHEETS\C3.00 SIGN & STRIPING PLAN.DWGNovember 24, 2015JACK MONG

C3.

00

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-03 DRAWINGS\SHEETS\C3.00 SIGN & STRIPING PLAN.DWG

####

####

--

11/2

4/15

--

RA

C

JMJLB

DA

TE

01

23

FOR

RE

DU

CE

D P

LAN

S -

OR

IGIN

AL

SC

ALE

IS IN

INC

HE

S

SU

BM

ITTE

D:

DA

TER

.C.E

.E

XP

.

AP

PR

OV

ED

:

DE

SIG

N

DR

AW

N

CH

EC

K

AS

BU

ILT

DA

TE

BO

OK

VE

RT.

HO

RIZ

.

DE

PA

RTM

EN

T O

F P

UB

LIC

WO

RK

SC

ITY

OF

BE

RK

ELE

Y

REVISIONMARKDATEDESCRIPTION

SH

EE

T

FILE

PLA

N

OF

--

SU

PE

RV

ISIN

G C

IVIL

EN

GIN

EE

R

CIT

Y E

NG

INE

ER

EX

P.

R.C

.E.

DA

TE

SU

RV

EY

PA

RTY

CH

IEF

DE

PIC

TIO

N O

F M

ON

UM

EN

TS:

DA

TEW

ATE

RS

HE

D R

EV

IEW

:

DA

TEP

RO

JEC

T M

AN

AG

ER

:--

2425

77

--

SH

ATT

UC

K R

EC

ON

FIG

UR

ATI

ON

AN

DP

ED

ES

TRIA

N S

AFE

TY P

RO

JEC

T

ww

w.a

rup.

com

Tel (

415)

957

944

5 F

ax (4

15) 9

57 9

096

San

Fra

ncis

co, C

A 9

4105

U

SA

560

Mis

sion

Stre

et, S

uite

700

Aru

p N

orth

Am

eric

a Lt

d.

----

STR

IPIN

G P

LAN

SC

ALE

: 1"=

40'

0

SC

ALE

1" =

40'

2040

8012

0

Atta

chm

ent 1

Page 14: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Sh

att

uck

Re

con

fig

ura

tio

n:

Pro

pose

d Im

prov

emen

t Pla

n

UNIVERSITY AVE

ADDISON ST

CENTER ST

ALLSTON WAY

Ex

isti

ng

Tre

es

Plat

anus

hyb

rida

Pitt

ospo

rum

und

ulat

umAc

er r

ubru

m

Re

mo

ve

d T

ree

Ne

w T

ree

s

Acer

rub

rum

Ole

a eu

ropa

ea ‘S

wan

Hill

SHAT

TUCK

AVE

WES

T

SHAT

TUCK

AVE

WES

T

BAR

T PL

AZA

SHAT

TUCK

AVE

EAS

T

SHAT

TUCK

AVE

EAS

T

LE

GE

ND

Be

nch

Pe

de

str

ian

/Str

ee

t L

igh

t

Pe

rme

ab

le P

av

ing

Sp

eci

al

con

cre

te i

n r

ais

ed

in

ters

ect

ion

Pa

ve

rs

Pla

nti

ng

Bu

ild

ing

En

tra

nce

s

Ga

rba

ge

/Re

cycl

ing

Cu

rbs

ide

Pic

ku

p i

n a

rea

s w

ith

ou

t lo

ad

ing

zon

es

080

4020

Atta

chm

ent 2

Page 15: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Survey Results

Shattuck Reconfiguration and Pedestrian Safety Project Survey Dates: October 8, 2015 – November 1, 2015

Distributed via:

� Berkeley Climate Action Coalition � City of Berkeley Employees � City of Berkeley Website � City staff via intercept surveys on BART Plaza (week of October 19, 2015) � Downtown Berkeley Association � East Bay Bike Coalition � Livable Berkeley � Mailer (to residents/owners within project vicinity) � Press Release/News Articles � Transform � University of California

Total Number of Respondents: 1,245

23%

4%

18%14%

36%

5%

In Downtown, which of these issues is most important to you?

Bicycle Safety

Bus Rider Comfort/Convenience

Confusing Traffic Pattern

Parking Availability

Pedestrian Safety/Comfort

Sidewalk Amenities

Attachment 3

Page 16: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Current Conditions

5%

29%

10%

45%

11%

0

5

10

15

20

25

30

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Is Downtown attractive for pedestrians?

1%

12% 9%

50%

29%

0

50

100

150

200

250

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Is parking convenient Downtown?

3%

51%

6%

36%

5%

0

50

100

150

200

250

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Do you feel safe as a pedestrian?

Page 17: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

38%35%

10%15%

4%

020406080

100120140160

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Is the traffic pattern for northbound traffic on Shattuck confusing?

2%

30%

9%

48%

11%

0

5

10

15

20

25

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Is transit comfortable and reliable?

2%

26%

4%

55%

13%

020406080

100120140160180

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Do you feel safe as a bicyclist?

Page 18: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Shattuck and Center Intersection Improvements

Transit Plaza

22%

48%

14% 14%

2%0

50

100

150

200

250

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Will the proposed design improve pedestrian safety?

26%

45%

6%

15%8%

0

5

10

15

20

25

30

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Will the proposed design improve the pedestrian experience?

18%

27%

32%

20%

2%

0

2

4

6

8

10

12

14

16

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Will the transit plazaimprove transit riders' experiences?

Page 19: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

East Shattuck Avenue Improvements

30%

45%

13% 10%2%

0

50

100

150

200

250

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Will the proposed design improve pedestrian safety?

22%

40%

15%18%

6%

020406080

100120140

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Will the proposed design improve bike safety?

34%

47%

6% 6% 6%

0

5

10

15

20

25

30

35

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Will the proposed design improve the pedestrian experience?

Page 20: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Shattuck and University Intersection Improvements

Landscaping and Sidewalk Amenities

40%

49%

8%2% 1%

0

50

100

150

200

250

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Will the proposed design improve pedestrian safety?

32%

52%

8% 5% 2%0

50

100

150

200

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Will the proposed design improve bike safety?

32%

53%

5% 5% 5%

0

5

10

15

20

25

30

35

40

Strongly Agree

Agree No opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Will the proposed design improve the pedestrian experience?

Page 21: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Parking

One Way to Two Way Conversion of Shattuck

11%

38%

21% 23%

8%

020406080

100120140160

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Does the project, along with expansion of the Center St. Garage, provide adequate parking?

32%

41%

11%16%

0

5

10

15

20

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Will the proposed design improve bus routing?

32%

44%

7%11%

6%

020406080

100120140160180200

Strongly Agree

Agree No Opinion Disagree Strongly Disagree

num

ber o

f res

pons

es

Will the proposed design improve traffic flow?

Page 22: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

AT

TA

CH

ME

NT

4

Lis

t o

f S

tak

eh

old

er

Me

eti

ng

s (

as

of

No

ve

mb

er

10,

20

15

)

Sh

attu

ck R

eco

nfigu

ratio

n a

nd

Pe

de

str

ian

Safe

ty P

roje

ct

Date

Pe

rso

ns A

tte

nd

ing

P

urp

ose

of

Me

eti

ng

/ T

op

ics

Dis

cu

sse

d

Au

gu

st

20

14

(va

rio

us d

ate

s)

Sh

attu

ck A

ve

nu

e m

erc

ha

nts

S

taff

co

nd

ucte

d o

ne

-on

-on

e

me

etin

gs w

ith

me

rchan

ts t

o

pre

se

nt co

nce

ptu

al d

raw

ings,

dis

cuss p

roje

ct

go

als

, a

nd

o

bta

in in

pu

t on

loa

din

g z

on

es,

pa

rkin

g a

nd o

the

r con

ce

rns.

4/2

1/1

5

Au

ste

ne

Ha

ll, P

iQ C

afé

, 91

Sha

ttu

ck S

q.

Tim

Ha

nse

n, P

iQ C

afé

, 9

1 S

hatt

uck S

q.

Tom

Hun

t, P

iQ C

afé

, 91

Sha

ttu

ck S

q.

Pre

se

nta

tio

n o

f in

itia

l pro

ject

dra

win

gs;

dis

cussio

n o

f p

ark

ing,

loa

din

g,

sid

ew

alk

co

mfo

rt a

nd

oth

er

issue

s.

4/2

1/1

5 (

ph

on

e c

all)

Jo

hn

Pa

luksa

, C

om

al re

sta

ura

nt,

202

0 S

ha

ttuck

Va

rio

us issue

s in

clu

din

g:

ove

rall

pu

rpo

se

of

pro

ject,

le

ve

l o

f o

utr

ea

ch

co

ndu

cte

d,

imp

acts

to

lo

ad

ing a

ctivitie

s,

rem

ova

l of

pa

rkin

g a

nd

bu

lbou

ts

4/2

7/1

5

Ste

ph

en N

ew

ho

use

, A

C T

ran

sit

AC

Tra

nsit c

ircu

lation

issu

es

an

d s

top lo

ca

tion

s

4/3

0/1

5

Po

lly A

rmstr

on

g,

Be

rkele

y C

ha

mb

er

of

Com

me

rce

S

hifra

de

Be

ned

ictis-K

essn

er,

Dow

nto

wn

Be

rke

ley A

sso

cia

tion

A

uste

ne

Ha

ll, P

iQ C

afé

, 91

Sha

ttu

ck S

q.

Tod

d H

en

ry,

UC

Be

rkele

y

Dia

na

Hsu

, T

err

an

om

ics

Bo

b L

yce

tte

, 2

151

Sh

att

uck (

pro

pe

rty o

wn

er)

K

irste

n M

acD

on

ald

, B

erk

ele

y C

ha

mb

er

of

Com

me

rce

Walk

ing t

ou

r of

pro

ject a

rea

w

ith

ke

y D

ow

nto

wn

sta

ke

ho

lde

rs to

dis

cu

ss

exis

ting c

on

ditio

ns a

nd p

roje

ct

go

als

.

Page 23: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Date

Pe

rso

ns A

tte

nd

ing

P

urp

ose

of

Me

eti

ng

/ T

op

ics

Dis

cu

sse

d

Mik

a M

iya

sa

to,

AC

Tra

nsit

Ito

Rip

ste

en,

13

3-1

39

Be

rkele

y S

q.

(pro

pe

rty o

wn

er)

T

on

y R

ossm

an

, R

ossm

an &

Moo

re (

atto

rne

ys),

20

14

Sh

attu

ck

Se

an S

late

r, E

LS

Arc

hite

ctu

re, 2

04

0 A

dd

iso

n

Ma

tt T

ae

cke

r, T

ae

cke

r P

lan

nin

g &

De

sig

n,

214

0 S

ha

ttu

ck

5/4

/15

Au

ste

ne

Ha

ll, P

iQ C

afé

, 91

Sha

ttu

ck S

q.

Jo

hn

Ca

ne

r, D

ow

nto

wn B

erk

ele

y A

sso

cia

tion

T

od

d H

en

ry,

UC

Be

rkele

y

Tom

Hun

t, P

iQ C

afé

, 91

Sha

ttu

ck S

q.

Tiffa

ny P

oo

raia

h,

Rossm

an &

Moo

re (

atto

rne

ys),

20

14

Sh

attu

ck

Ton

y R

ossm

an,

Rossm

an &

Moo

re (

atto

rne

ys),

20

14

Sh

attu

ck

Ma

tt T

ae

cke

r, T

ae

cke

r P

lan

nin

g &

De

sig

n,

214

0 S

ha

ttu

ck

(re

pre

se

ntin

g p

rop

osed

hote

l at

21

29

Sha

ttuck)

Me

etin

g w

ith

ke

y D

ow

nto

wn

sta

ke

ho

lde

rs to

dis

cu

ss p

roje

ct

go

als

, p

resen

t in

itia

l d

raw

ings

an

d o

bta

in inp

ut.

5/2

9/1

5

Tia

n F

en

g,

BA

RT

S

teph

en N

ew

ho

use

, A

C T

ran

sit

Sco

tt S

mith

, B

AR

T

Coo

rdin

atio

n w

ith

BA

RT

Pla

za

d

esig

n;

AC

Tra

nsit c

ircu

lation

an

d s

top d

esig

n.

6/9

/15

Se

e a

tta

ch

ed

lis

t.

Com

mu

nity o

pe

n h

ou

se

to

p

rese

nt in

itia

l d

raw

ings,

dis

cuss p

roje

ct

go

als

, a

nd

o

bta

in in

pu

t.

6/2

3/1

5

Tim

Ha

nse

n,

PiQ

Café

, 9

1 S

hatt

uck S

q.

Au

ste

ne

Ha

ll, P

iQ C

afé

, 91

Sha

ttu

ck S

q.

Se

e p

revio

us m

ee

tin

g w

ith

PiQ

o

n 4

/21.

6/2

5/1

5

Dow

nto

wn

Be

rkele

y A

sso

cia

tion B

oa

rd m

em

be

rs

Jo

hn

Go

rdon

, D

ow

nto

wn

pro

pe

rty o

wn

er

an

d c

om

me

rcia

l re

al

esta

te b

roke

r

Dis

cu

ssio

n o

f Jo

hn

Gord

on

’s

co

nce

rns r

ega

rdin

g th

e p

roje

ct

(e.g

., r

em

ova

l of

pa

rkin

g a

nd

b

ulb

ou

ts,

righ

t tu

rns o

nto

A

dd

ison

, o

ve

rall

pu

rpose

of

pro

ject)

6/2

9/1

5

Sh

ifra

de

Be

ned

ictis-K

essn

er,

Dow

nto

wn

Be

rke

ley A

sso

cia

tio

n

O

nlin

e s

urv

ey f

orm

at

Page 24: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Date

Pe

rso

ns A

tte

nd

ing

P

urp

ose

of

Me

eti

ng

/ T

op

ics

Dis

cu

sse

d

7/2

1/1

5

Tom

Ho

lste

in,

Ca

ltra

ns

Nam

Ngu

ye

n,

Caltra

ns

Fie

ld r

evie

w m

ee

tin

g w

ith

C

altra

ns s

taff

to

dis

cuss

requ

ire

d e

nviro

nm

en

tal

stu

die

s.

7/2

3/1

5

Je

nn

ife

r L

ovvo

rn,

Civ

ic A

rts C

om

mis

sio

n m

em

be

r Ju

lia R

ob

ert

so

n, C

ivic

Art

s C

om

mis

sio

n m

em

be

r Jo

hn

To

ki, a

rtis

t

Relo

ca

tio

n o

f scu

lptu

re a

t so

uth

ea

st co

rne

r of

Sha

ttu

ck

West a

nd

Add

ison

.

8/7

/15

Jo

hn

Ca

ne

r, D

ow

nto

wn B

erk

ele

y A

sso

cia

tion

S

ea

tin

g/lan

dscap

ing o

ptio

ns

for

Sha

ttu

ck W

est.

8/2

7/1

5

Dow

nto

wn

Be

rkele

y A

sso

cia

tion B

oa

rd m

em

be

rs

Pre

se

nta

tio

n o

f cu

rre

nt d

esig

n,

dis

cussio

n o

f le

ft t

urn

p

roh

ibitio

ns,

ga

rage

/the

ate

r a

cce

ss,

se

atin

g,

an

d o

the

r is

sue

s.

9/1

0/1

5

Jo

hn

Ca

ne

r, D

ow

nto

wn B

erk

ele

y A

sso

cia

tion

D

aw

n F

eh

r, 2

151

Sh

attu

ck (

pro

pe

rty o

wn

er)

M

ia G

ittlen

, 2

13

2-6

8 C

en

ter

(pro

pe

rty o

wn

er)

B

ob

Lyce

tte

, 2

151

Sh

att

uck (

pro

pe

rty o

wn

er)

R

ep

rese

nta

tive

s o

f B

erk

ele

y C

en

tra

l b

uild

ing (

20

55

Ce

nte

r)

Pre

se

nta

tio

n o

f cu

rre

nt d

esig

n,

dis

cussio

n o

f le

ft t

urn

p

roh

ibitio

ns,

acce

ss to

20

00

b

lock o

f C

en

ter,

an

d o

the

r is

sue

s.

9/2

1/1

5

Mia

Gittlen

, 2

13

2-6

8 C

en

ter

(pro

pe

rty o

wn

er)

T

od

d H

en

ry,

UC

Be

rkele

y

Em

ily M

art

hin

se

n,

UC

Be

rkele

y

La

wre

nce

Rin

de

r, B

erk

ele

y A

rt M

use

um

M

att

Ta

ecke

r, T

ae

cke

r P

lan

nin

g &

De

sig

n,

214

0 S

ha

ttu

ck

(re

pre

se

ntin

g p

rop

osed

hote

l at

21

29

Sha

ttuck)

Pre

se

nta

tio

n o

f cu

rre

nt d

esig

n,

dis

cu

ssio

n o

f le

ft t

urn

p

roh

ibitio

ns,

acce

ss to

21

00

b

lock o

f C

en

ter,

an

d o

the

r is

sue

s.

9/2

1/1

5

Wil

Bu

ller,

AC

Tra

nsit

Ste

ph

en N

ew

ho

use

, A

C T

ran

sit

Pre

se

nta

tio

n o

f tr

aff

ic

sim

ula

tion

an

d d

iscussio

n o

f p

ote

ntia

l im

pa

cts

to b

us

pe

rfo

rma

nce

fro

m o

ther

traff

ic.

9/2

9/1

5

Jo

hn

Ca

ne

r, D

ow

nto

wn B

erk

ele

y A

sso

cia

tion

D

BA

re

qu

ests

fo

r p

roje

ct.

Page 25: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Date

Pe

rso

ns A

tte

nd

ing

P

urp

ose

of

Me

eti

ng

/ T

op

ics

Dis

cu

sse

d

10

/7/1

5

Mia

Gittlen

, 2

13

2-6

8 C

en

ter

(pro

pe

rty o

wn

er)

S

oh

eyl M

od

are

ssi, 2

132

-68

Cen

ter

(pro

pe

rty o

wn

er)

A

cce

ss t

o 2

10

0 b

lock o

f C

en

ter.

10

/9/1

5

Chu

ck S

iege

l, B

erk

ele

y C

lima

te A

ctio

n C

oa

litio

n

Coo

rdin

atio

n w

ith

Un

ivers

ity

Ave

. im

pro

ve

men

ts f

rom

S

OS

IP.

10

/15

/15

Jo

hn

Ca

ne

r, D

ow

nto

wn B

erk

ele

y A

sso

cia

tion

T

im H

an

se

n, P

iQ C

afé

, 9

1 S

hatt

uck S

q.

Tom

Hun

t, P

iQ C

afé

, 91

Sha

ttu

ck S

q.

Mic

ha

el M

aff

ia, 4

8 S

hatt

uck S

q.

(pro

pe

rty o

wne

r)

Tod

d O

live

r, 4

8 S

ha

ttuck S

q.

(pro

pe

rty o

wn

er)

Lo

ad

ing z

on

es,

left

tu

rn

pro

hib

itio

ns,

lan

dscap

ing,

se

atin

g,

bik

e r

acks.

10

/20

/15

Sa

rah

Be

rnha

rd,

JR

DV

Arc

hite

cts

, O

akla

nd

M

att

Ta

ecke

r, T

ae

cke

r P

lan

nin

g &

De

sig

n,

214

0 S

ha

ttu

ck

(bo

th r

ep

resen

tin

g p

rop

osed

hote

l at

21

29 S

ha

ttu

ck)

Coo

rdin

atio

n w

ith

pro

po

se

d

ho

tel a

t 2

129

Sh

attu

ck.

11

/10

/15

Jo

hn

Ca

ne

r, D

ow

nto

wn B

erk

ele

y A

sso

cia

tion

A

uste

ne

Ha

ll, P

iQ C

afé

, 91

Sha

ttu

ck S

q.

Mic

ha

el M

aff

ia, 4

8 S

hatt

uck S

q.

(pro

pe

rty o

wne

r)

Tod

d O

live

r, 4

8 S

ha

ttuck S

q.

(pro

pe

rty o

wn

er)

D

avid

Sh

am

sza

d, 6

4 S

ha

ttu

ck S

q.

(pro

pe

rty o

wn

er)

Lo

ad

ing z

on

es

Page 26: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended
Page 27: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended
Page 28: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended
Page 29: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended
Page 30: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Maj

or P

roje

cts

18

f.Lo

cate

impr

ovem

ents

adj

acen

t to

deve

lop-

men

t pro

ject

s to

hel

p fu

nd th

ese

impr

ove-

men

ts,

and

take

adv

anta

ge o

f sy

nerg

ies

betw

een

deve

lopm

ent a

nd p

ublic

impr

ove-

men

ts.

g.In

the

near

term

, rep

lace

on-

stre

et p

ark-

ing

that

wou

ld b

e lo

st w

ith p

ublic

impr

ove-

men

ts w

ith a

dditi

onal

nea

rby

on-s

tree

tpa

rkin

g.

h.Fu

nd m

ultip

le p

roje

cts.

Avo

id u

sing

lim

ited

fund

s on

a s

ingl

e pr

ojec

t.

Usi

ng t

hese

crit

eria

, th

e fo

llow

ing

proj

ects

ha

ve b

een

iden

tifi e

d as

fund

ing

prio

ritie

s. N

ote

how

ever

that

thes

e pr

iorit

ies

do n

ot p

recl

ude

the

City

from

mov

ing

forw

ard

on o

ther

SO

SIP

pr

ojec

ts if

opp

ortu

nitie

s fo

r gra

nts

or d

evel

oper

co

ntrib

utio

ns e

mer

ge.

Hig

hest

Prio

ritie

s (T

ier I

)

a.C

ente

r S

tree

t P

laza

Pha

se 1

. C

ente

rSt

reet

offe

rs a

uni

que

oppo

rtuni

ty to

cre

ate

a pu

blic

gat

herin

g sp

ace

activ

ated

by

high

pede

stria

n vo

lum

es, e

xist

ing

com

mer

cial

uses

, and

the

futu

re B

erke

ley

Art

Mus

e-um

/ Pa

cifi c

Film

Arc

hive

. P

hase

1 w

ill b

eco

nstru

cted

on

the

east

end

of t

he b

lock

,ab

ove

whe

re a

cces

s to

the

Ban

k of

Am

er-

ica

park

ing

lot

need

s to

be

mai

ntai

ned.

Gre

en in

frast

ruct

ure

feat

ures

, suc

h as

per

-m

eabl

e pa

ving

and

rai

n ga

rden

s (b

io-r

e-te

ntio

n ba

sins

), co

uld

be in

corp

orat

ed in

toP

hase

1 to

dem

onst

rate

gre

en in

frast

ruc-

ture

and

mak

e a

uniq

ue d

estin

atio

n. W

hile

a w

ater

feat

ure

that

ref

ers

to S

traw

berr

yC

reek

app

ears

to b

e te

chni

cally

infe

asib

lein

Pha

se 1

, pip

ing

mig

ht b

e pu

t in

plac

ebe

low

Pha

se 1

impr

ovem

ents

to a

void

ex-

cava

tion

and

addi

tiona

l cos

ts la

ter.

b.S

hattu

ck S

quar

e an

d U

nive

rsity

Ave

nue

Gat

eway

. R

econ

fi gur

e S

hattu

ck to

mak

etra

ffi c

oper

ate

two-

way

on

the

wes

t sid

e of

Shat

tuck

Squ

are

and

prov

ide

addi

tiona

l on-

stre

et p

arki

ng o

n th

e ea

ster

n le

g of

Sha

t-tu

ck.

This

impr

ovem

ent w

ill he

lp im

plem

ent

the

Pla

n’s

zero

-net

par

king

stra

tegy

and

shou

ld b

e pr

eced

e ot

her

impr

ovem

ents

ifpo

ssib

le.

Esta

blis

h a

trans

it ce

nter

on

the

east

sid

e of

Sha

ttuck

Squ

are

if it

is d

eter

-m

ined

tha

t th

is is

the

pre

ferr

ed lo

catio

nD

ownt

own.

On

Uni

vers

ity A

venu

e be

twee

nS

hattu

ck a

nd O

xfor

d, tr

avel

lane

s ca

n be

elim

inat

ed to

allo

w w

ider

sid

ewal

ks a

nd a

d-di

tiona

l lan

dsca

ping

and

oth

er a

men

ities

.O

ne a

ltern

ativ

e w

ould

als

o in

crea

se o

n-st

reet

par

king

.

c.S

treet

Tre

es.

The

City

sho

uld

mak

e th

epl

antin

g of

stre

et tr

ees

a ne

ar-te

rm p

riorit

y,w

ith a

goa

l of p

lant

ing

500

new

tree

s w

ithin

ten

year

s in

loca

tions

whe

re “

maj

or p

roj-

ects

” are

not

ant

icip

ated

. (Se

e Po

licy

5.1)

Hig

h Pr

iorit

ies

(Tie

r II)

a.A

llsto

n-K

ittre

dge

Park

Blo

ck a

nd e

ast e

ndof

Uni

vers

ity A

venu

e. T

hese

pro

ject

s w

illsu

ppor

t co

mm

erci

al r

evita

lizat

ion

alon

gD

ownt

own’

s pr

inci

pal

com

mer

cial

cor

ri-do

rs b

y ad

ding

act

ivity

and

new

syn

ergi

esw

ith e

xist

ing

uses

(e.g

. cin

emas

) an

d fu

-tu

re u

ses.

a.H

ears

t Ave

nue

/ Ohl

one

Gre

enw

ay P

hase

1.G

reen

way

impr

ovem

ents

will

pro

vide

cont

inuo

us b

icyc

le la

nes

from

MLK

to th

eU

C c

ampu

s.

To a

void

con

stru

ctio

n co

n-fli

cts

whe

n U

C d

evel

ops

belo

w W

alnu

t,im

prov

emen

ts s

houl

d fi r

st b

e m

ade

to th

eW

alnu

t int

erse

ctio

n an

d ab

ove.

Dia

gona

lpa

rkin

g m

ight

be

prov

ided

on

Hea

rst i

n th

ene

ar-te

rm n

ear S

hattu

ck.

Atta

chm

ent 5

Page 31: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Maj

or P

roje

cts

27Figu

re d

.16.

Wes

t si

de o

f S

hatt

uck

Squa

re.

Six

traf

fi c la

nes

have

pas

sed

alon

g S

hattu

ck S

quar

e, w

ith th

ree

lane

s ru

nnin

g al

ong

the

wes

t sid

e of

the

Squ

are

(fi rs

t sec

tion

abov

e). A

naly

sis

indi

cate

s th

at fo

ur la

nes

are

suffi

cien

t. B

y m

ovin

g al

l fou

r lan

es to

the

wes

t sid

e of

Sha

ttuck

S

quar

e (s

econ

d se

ctio

n be

low

), th

e ea

st

side

of S

hattu

ck S

quar

e w

ill b

e av

aila

ble

for

mor

e pa

rkin

g (in

the

near

term

) an

d m

ore

pede

stria

n am

eniti

es (

in th

e lo

ng

term

). R

econ

fi gur

ing

traffi

c sh

ould

als

o in

crea

se s

afet

y an

d re

duce

con

gest

ion

at th

e U

nive

rsity

-Sha

ttuck

inte

rsec

tion.

N

arro

w T

raffi

c La

nes

Del

iver

ies/

Acc

ess

Lane P

oten

tial

Hot

el

Plaz

a or

Sl

ow S

tree

t

Plaz

a +

Pot

entia

l Tra

nsit

Cen

ter

(Lon

g te

rm)

SHAT

TUC

K A

V. (

East

Sid

e)

UNIVERSITY AVENUE

SHAT

TUC

K A

V.

(Wes

t Si

de)

SHAT

TUC

K A

VEN

UE

BA

RT

SHA

TTU

CK

SQ

UA

RE

BER

KEL

EY S

QU

AR

E

b.

Est

ablis

h a

gree

n vi

sual

con

nect

ion

be-

twee

n C

ivic

Cen

ter P

ark

and

Cen

ter S

treet

Pl

aza

(and

the

UC

Cam

pus

and

Stra

wbe

rry

Cre

ek b

eyon

d), w

hile

sim

ulta

neou

sly

mai

n-ta

inin

g sa

fety

for b

icyc

lists

and

enh

anci

ng

safe

ty fo

r pe

dest

rians

. Ev

alua

te a

ltern

a-tiv

es fo

r acc

ompl

ishi

ng th

ese

prin

cipa

l ob-

ject

ives

. Sp

ecifi

cally

, con

side

r the

rela

tive

safe

ty a

nd p

erfo

rman

ce o

f:

• ke

epin

g C

ente

r as

pre

sent

ly c

onfig

ured

w

ith b

icyc

le la

nes

and

park

ing

on b

oth

sides

;

• cr

eatin

g a

land

scap

ed g

reen

way

by

elim

-in

atin

g pa

rkin

g on

the

nort

h si

de o

f the

st

reet

(but

kee

ping

bic

ycle

lane

s); o

r

• cr

eatin

g a

land

scap

ed g

reen

way

and

“s

hare

d st

reet

” whe

re m

otor

ists

, bic

yclis

ts

and

pede

stria

ns c

an m

ix w

hile

mai

ntai

n-in

g or

impr

ovin

g sa

fety

– e

ven

with

the

rem

oval

of b

icyc

le la

nes.

c.

Use

lan

dsca

ping

and

ped

estri

an-s

cale

d lig

htin

g to

est

ablis

h th

e G

reen

way

. P

lant

m

ore

stre

et tr

ees,

and

con

side

r cre

atin

g a

land

scap

ed “

bio-

swal

e” to

cap

ture

run

-off

from

Cen

ter

Stre

et, t

he S

hattu

ck S

quar

e ar

ea, a

nd p

oten

tially

incl

udin

g ru

noff

from

ab

uttin

g bu

ildin

gs.

Con

side

r the

pot

entia

l sw

ale

in th

e co

ntex

t of o

ther

nee

ds, i

nclu

d-in

g bi

cycl

e sa

fety

and

par

king

. Rem

oval

of

bicy

cle

lane

s on

Cen

ter S

treet

sho

uld

only

be

pur

sued

if it

will

not d

ecre

ase

safe

ty fo

r bi

cycl

ists

and

ped

estri

ans.

d.

If a

swal

e ca

n be

acc

omm

odat

ed, p

lace

it

alon

g th

e no

rth s

ide

of C

ente

r to

take

max

i-m

um a

dvan

tage

of

suns

hine

and

avo

id

Figu

re d

.17.

Shat

tuck

Squ

are

- Lon

g Te

rm.

Ove

r the

long

term

, the

eas

t sid

e of

Sha

ttuck

an

d B

erke

ley

squa

res

can

be p

edes

trian

ized

. Tra

nsit

oper

atio

ns a

nd im

prov

emen

ts c

ould

be

inco

rpor

ated

.

����

���

���

Page 32: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Maj

or P

roje

cts

28

confl

icts

with

pas

seng

ers

bein

g dr

oppe

d of

f at B

CC

, Con

side

r wid

enin

g th

e si

dew

alk

on th

e so

uth

side

of t

he s

treet

bec

ause

of

heav

y pe

dest

rian

activ

ity, a

nd u

se th

is w

id-

enin

g as

an

oppo

rtuni

ty to

pla

nt a

dditi

onal

st

reet

tree

s.

e.

Use

che

ck d

ams

with

sw

ales

to s

low

wat

er

whe

n th

e sw

ale

fi lls

and

to c

reat

e ca

scad

-in

g po

ols

durin

g he

avy

rain

s. C

onsi

der h

ow

to in

clud

e ac

cess

ible

edu

catio

nal a

nd re

c-re

atio

nal o

ppor

tuni

ties.

f. C

onsi

der c

urb

exte

nsio

ns in

fron

t of t

he e

n-tra

nce

to B

erke

ley

City

Col

lege

and

whe

re

the

mid

bloc

k pa

ssag

e to

Add

ison

mee

ts

Cen

ter S

treet

.

g.

Mai

ntai

n fe

atur

es th

at a

re c

onsi

sten

t with

th

e de

sign

of t

he C

ente

r Stre

et P

laza

(be-

twee

n O

xfor

d an

d Sh

attu

ck).

h.

Pro

vide

for

taxi

sta

nd n

ear

BA

RT

as p

art

of th

e C

ente

r Stre

et G

reen

way

des

ign

pro-

cess

Cen

ter S

tree

t Gre

enw

ay (C

ivic

Cen

ter P

ark)

.C

ivic

Cen

ter P

ark

gets

con

side

rabl

e us

e, s

uch

as d

urin

g S

atur

day

Farm

ers

Mar

kets

, bu

t its

pr

oxim

ity to

Dow

ntow

n’s

hear

t is

diffi

cult

to p

er-

ceiv

e. T

he P

ark

also

offe

rs a

uni

que

oppo

rtu-

nity

to d

aylig

ht S

traw

berr

y C

reek

, as

the

Cre

ek

runs

bel

ow th

e Pa

rk.

In a

dditi

on, g

over

nmen

t se

rvic

es, t

he Y

MC

A’s

Teen

Cen

ter,

and

the

Vet-

eran

s M

useu

m m

ight

be

supp

orte

d by

pub

lic

impr

ovem

ents

.

a.

Use

tree

s, la

ndsc

apin

g an

d ot

her f

eatu

res

to m

aint

ain

desi

gn c

onsi

sten

cy w

ith C

ente

r S

treet

Pla

za a

nd th

e po

rtion

of G

reen

way

ab

ove

Milv

ia, w

hile

als

o co

mpl

emen

ting

the

char

acte

r of t

he C

ivic

Cen

ter H

isto

ric D

is-

trict

.

b.

Con

side

r the

feas

ibilit

y of

day

light

ing

Stra

w-

berr

y C

reek

as

an u

rban

am

enity

and

for

ecol

ogic

al b

enefi

ts.

c.

Con

tinue

to

seek

fun

ding

to

rest

ore

the

foun

tain

in C

ivic

Cen

ter P

ark,

and

pro

vide

fo

r its

on-

goin

g m

aint

enan

ce.

d.

Con

side

r w

ays

to s

uppo

rt a

butti

ng u

ses

and

the

Sat

urda

y Fa

rmer

s M

arke

t thr

ough

pu

blic

impr

ovem

ents

.

e.

Con

side

r cis

tern

s to

sto

re a

nd re

use

rain

-w

ater

.

Polic

y 1.

7, S

hatt

uck

Squa

re &

Uni

vers

ity

Aven

ue (F

igur

es d

.14-

d.19

). P

rese

ntly

traf

fi c

alon

g S

hattu

ck S

quar

e ru

ns n

orth

on

its e

ast

side

and

sou

th o

n its

wes

t sid

e.3

This

con

fi gur

a-tio

n m

akes

nor

thbo

und

traffi

c fo

llow

an

S-c

urve

at

it m

oves

from

Sha

ttuck

Squ

are’

s ea

st s

ide

to S

hattu

ck A

venu

e no

rth o

f Uni

vers

ity. T

raffi

c vo

lum

es a

nd s

peed

s al

ong

this

S-c

urve

mov

e-m

ent h

ave

cont

ribut

ed to

hig

h pe

dest

rian

colli

-si

on ra

tes

at th

e U

nive

rsity

-Sha

ttuck

inte

rsec

-tio

n. T

wo-

way

traf

fi c is

pro

pose

d on

the

wes

t si

de to

add

ress

this

issu

e, a

nd to

incr

ease

traf

fi c

capa

city

at t

he U

nive

rsity

-Sha

ttuck

inte

rsec

tion.

Two-

way

traf

fi c o

n th

e w

est s

ide

also

mak

es

the

east

sid

e av

aila

ble

for m

ore

park

ing

in th

e ne

ar t

erm

and

mor

e pe

dest

rian

amen

ities

in

the

long

term

. In

addi

tion,

AC

Tra

nsit

cons

ider

s th

e ea

st s

ide

of B

erke

ley

Squ

are

as a

pot

entia

l ne

ar te

rm lo

catio

n fo

r a n

ew “t

rans

it ce

nter

.”

Figu

re d

.18.

Eas

t si

de o

f S

hatt

uck

Squa

re.

By

rout

ing

thro

ugh

traffi

c on

th

e w

est

side

of

Sha

ttuck

Squ

are,

52

feet

of

asph

alt

devo

ted

to t

he a

utom

o-bi

le (p

hoto

& 1

st s

ectio

n ab

ove)

cou

ld b

e tra

nsfo

rmed

into

a p

laza

or “

slow

stre

et,”

whi

ch m

ight

als

o be

the

loca

tion

for a

new

D

ownt

own

Tran

sit C

ente

r (2n

d se

ctio

n).

3W

hile

the

“w

ests

ide

of S

hattu

ck S

quar

e” is

act

ually

nam

ed

“Ber

kele

y S

quar

e,” m

ost r

eade

rs w

ill fi

nd th

e ea

stsi

de/ w

ests

ide

nom

encl

atur

e ea

sier

to u

nder

stan

d.

����

���

���

Page 33: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

12’14.5’

WB

WB

WB

WB

BA

RT

ALT

ERN

ATIV

E R

OU

TEFO

R W

ESTB

OU

ND

WES

TBO

UN

DTU

RN

NET

GA

IN: +

19 S

PAC

ES

NET

GA

IN: +

28 S

PAC

ES

BA

RT

PAR

KIN

G S

TREE

T

Curb

Exte

nsio

n

PREF

ERRE

D LO

CATI

ON

FOR

WES

T BO

UND

TURN

TO

UNI

VERS

ITY

New

Cur

bN

ew P

edes

trian

Ref

uge

PAR

KIN

G IM

PAC

TS

PAR

KIN

G +

TR

AN

SIT

(FU

TUR

E PL

AZA

)C

UR

B E

XTEN

SIO

N

WES

TBO

UN

DSI

GN

UNIVERSITY AVE

Bus

Sto

p

Bus

Sto

p

Bus

Sto

p

CENTER ST

University Ave

Shat

tuck

Ave

Addison St

Center St

Allston St

New

Bum

p-O

ut(O

ptio

nal)

Alte

rnat

ive

with

Lef

t Tur

n at

Sha

ttuck

& U

nive

rsity

--Pr

efer

red

by s

ubco

mm

ittee

.

Alte

rnat

ive

with

Wes

tbou

nd T

urns

from

Eas

t Sha

ttuck

Squ

are

Maj

or P

roje

cts

29

Figu

re d

.19.

Shat

tuck

Squ

are

- Nea

r-Ter

m.

Mak

ing

traffi

c tw

o-w

ay

on th

e w

est s

ide

of S

hattu

ck S

quar

e w

ill c

reat

e op

port

uniti

es o

n th

e ea

st s

ide

to b

oost

par

king

in th

e ne

ar te

rm –

and

cre

ate

a pl

aza

or s

low

st

reet

in th

e lo

ng te

rm (s

ee F

igur

ed.

17).

����

���

���

Page 34: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Maj

or P

roje

cts

30

Des

ign

obje

ctiv

es fo

r Sha

ttuck

Squ

are

incl

ude

the

follo

win

g, s

ubje

ct t

o en

viro

nmen

tal a

nd

traffi

c an

alys

is:

a.

Rec

onfi g

ure

auto

mob

ile tr

affi c

on

Shat

tuck

S

quar

e, s

o th

at th

e w

est s

ide

of S

hattu

ck

Squ

are

acco

mm

odat

es t

wo-

way

thro

ugh

traf

fic,

and

the

east

sid

e of

Sha

ttuck

S

quar

e ca

n be

com

e a

slow

stre

et fo

r loc

al

traffi

c, a

slo

w s

treet

whe

re o

nly

buse

s ar

e al

low

ed, o

r a p

laza

with

out t

raffi

c.

b.

Eval

uate

the

best

con

fi gur

atio

n fo

r rou

ting

traffi

c th

at is

goi

ng n

orth

on

Sha

ttuck

and

th

en w

est o

n U

nive

rsity

. A

left

turn

lane

fro

m th

e w

est s

ide

of S

hattu

ck S

quar

e to

U

nive

rsity

Ave

nue

is p

refe

rred

bec

ause

it

is e

asy

to u

nder

stan

d --

but

a le

ft-tu

rn la

ne

in th

is lo

catio

n w

ould

resu

lt in

nar

row

lane

w

idth

s, re

duce

d cr

ossw

alk

curb

ext

ensi

ons,

an

d el

imin

atio

n of

par

king

spa

ces

on w

est

Shat

tuck

Squ

are.

If

lane

wid

ths

are

foun

d to

be

insu

ffi ci

ent,

cons

ider

rou

ting

wes

t-bo

und

traffi

c al

ong

the

east

sid

e of

Sha

t-tu

ck S

quar

e. T

o do

this

, nor

thbo

und

mot

or-

ists

who

wan

t to

trave

l wes

t on

Uni

vers

ity

wou

ld h

ave

to b

e gu

ided

by

sign

s be

fore

th

ey re

ach

Shat

tuck

Squ

are.

c.

If th

e ea

st s

ide

of S

hattu

ck S

quar

e is

not

ne

eded

for r

egul

ar tr

affi c

, con

side

r est

ab-

lishi

ng a

“tra

nsit

plaz

a” li

mite

d to

ped

es-

trian

s, b

icyc

lists

, and

bus

es.

The

trans

it pl

aza

– in

com

bina

tion

with

oth

er b

us

faci

litie

s al

ong

Sha

ttuck

bet

wee

n A

ddi-

son

& A

llsto

n –

coul

d es

tabl

ish

a m

ore

func

tiona

l “tra

nsit

cent

er”

with

in D

own-

tow

n. W

hile

Sha

ttuck

and

the

east

sid

e of

Sha

ttuck

Squ

are

may

be

wel

l sui

ted

to s

erve

mul

tiple

bus

line

s, b

us la

yove

rs

shou

ld b

e av

oide

d.

The

City

sho

uld

wor

k w

ith A

C T

rans

it to

iden

tify

suita

ble

layo

ver

loca

tions

in o

r ne

ar D

ownt

own.

Th

is a

rea

shou

ld b

e de

sign

ed a

s an

invi

t-in

g, p

edes

trian

-frie

ndly

pla

ce w

ith n

ega-

tive

impa

cts

from

bus

es m

itiga

ted

to th

e ex

tent

pos

sibl

e.

d.

In t

he n

ear-

term

, us

e th

e ea

st s

ide

of

Sha

ttuck

Ave

nue

for

addi

tiona

l par

king

to

hel

p of

fset

on-

stre

et p

arki

ng th

at m

ay

be lo

st b

ecau

se o

f nea

r-ter

m S

OS

IP im

-pr

ovem

ents

. N

ear-

term

impr

ovem

ents

sh

ould

als

o co

nsid

er c

urb

exte

nsio

ns

on th

e so

uthe

ast c

orne

r of t

he S

hattu

ck-

Cen

ter

inte

rsec

tion

and

the

nort

heas

t co

rner

of t

he S

hattu

ck-U

nive

rsity

inte

r-se

ctio

n.

e.

Con

side

r cr

eatin

g a

new

ent

ranc

e to

BA

RT

on th

e ea

st s

ide

of S

hattu

ck to

pro

-vi

de im

med

iate

and

uni

nter

rupt

ed p

edes

-tri

an a

cces

s to

the

Cen

ter

Stre

et P

laza

an

d th

e ea

st s

ide

of S

hattu

ck S

quar

e.

����

���

���

Page 35: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

BA

RTBB

ALLSTON WAY

CEN

TER

STR

EET

PLA

ZA

SHA

TTU

CK

SQ

.

BA

RT

PLA

ZA

CENTER ST

ADDISON ST

UNIVERSITY AVE.

BERKELEY WAY

HEARST AVE.

SHAT

TUC

K SQ

. (W

est

Sid

e)

SHAT

TUC

K SQ

. (E

ast

Sid

e)

ASH

ATTU

CK S

QU

ARE

IM

PRO

VEM

ENTS

Maj

or P

roje

cts

31Figu

re d

.20.

Shat

tuck

Ave

nue

Nor

th

of A

llst

on I

mpr

ovem

ents

: C

en-

ter

Str

eet

Gre

enw

ay/

Pla

za,

Sha

ttuck

S

quar

e Im

prov

emen

ts,

Uni

vers

ity A

v-en

ue.

����

���

���

Page 36: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

TREE

GUA

RD

EXIS

TING

TRE

E

PARK

ING

AIS

LE

EXIS

TING

CUR

B

8’ E

XPAN

DED

WID

E R

OO

TIN

G A

REA

TRAV

EL L

ANE

5’ W

IDE

RAIS

EDBI

KELA

NE

EDGE OF REMOVED CURB

EXIS

TIN

G R

OO

TIN

G A

REA

Maj

or P

roje

cts

35

Rec

onfi g

urin

g Sh

attu

ck S

quar

e w

ill re

quire

the

real

ignm

ent o

f bus

rout

es.

AC T

rans

it an

d sh

ut-

tle b

us o

pera

tors

sho

uld

be e

ngag

ed a

s de

sign

de

velo

pmen

t co

mm

ence

s to

det

erm

ine

how

co

nven

ient

, rel

iabl

e, a

nd re

ason

ably

fast

tran

sit

serv

ice

shou

ld b

e m

aint

aine

d.

Uni

vers

ity A

venu

e. T

he e

ast e

nd o

f Uni

vers

ity

Aven

ue h

as th

e po

tent

ial t

o be

com

e a

reco

g-ni

zabl

e “g

atew

ay” a

ccen

tuat

ing

one’

s ar

rival

to

the

Dow

ntow

n an

d U

nive

rsity

. S

idew

alk

wid

-en

ing

and

othe

r maj

or im

prov

emen

ts a

re p

os-

sibl

e. F

rom

Sha

ttuck

Squ

are

to O

xfor

d S

treet

, U

nive

rsity

Ave

nue

has

rela

tivel

y lo

w tr

affi c

vol

-um

es s

o tw

o tra

vel l

anes

can

be

elim

inat

ed.

This

pro

ject

are

a is

als

o no

tabl

e in

tha

t it

is

lined

by

maj

or d

evel

opm

ent a

nd h

isto

ric re

ha-

bilit

atio

n op

portu

nitie

s th

at w

ould

ben

efi t

from

an

d ad

d pe

dest

rian

activ

ity to

stre

etsc

ape

en-

hanc

emen

ts.

Figu

re d

.26.

Sha

ttuc

k A

venu

e. B

ike

lane

s ar

e pr

opos

ed o

n S

hattu

ck (

phot

o &

1st

sec

tion)

. W

here

par

king

acc

ess

lane

s ar

e m

aint

aine

d, b

ike

lane

s w

ould

ru

n ju

st o

utsi

de o

f tra

ffi c

thro

ugh

lane

s (2

nd s

ectio

n).

Des

ign

obje

ctiv

es in

clud

e:

a.

Wid

en s

idew

alks

, inc

reas

e tre

es a

nd la

nd-

scap

ing,

and

add

gre

en in

frast

ruct

ure

(like

bi

o-re

tent

ion

“rain

gar

dens

”) by

elim

inat

ing

unne

cess

ary

traffi

c la

nes.

b.

Con

side

r us

ing

diag

onal

par

king

to

in-

crea

se th

e su

pply

of o

n-st

reet

par

king

.

c.

Mai

ntai

n 20

-feet

cle

ar fo

r em

erge

ncy

ve-

hicl

es, s

uch

as b

y: e

limin

atin

g th

e m

edia

n,

usin

g an

acc

epta

ble

mou

ntab

le c

urb

alon

g th

e m

edia

n, o

r by

wid

enin

g on

ly th

e no

rth

side

and

kee

ping

two

lane

s of

eas

tbou

nd

traffi

c.

d.

Con

side

r th

e cr

eatio

n of

out

door

din

ing,

re

tail

and

info

rmat

ion

kios

ks.

Figu

re d

.27.

Cro

ss S

ectio

n O

f Pot

entia

l Gra

de-S

epar

ated

. Bi

ke L

ane

On

Shat

tuck

Bou

leva

rd.

����

���

���

Page 37: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

6. Recommended Pedestrian Projects

6-18 Final Draft Berkeley Pedestrian Master PlanJanuary 2010

INTERSECTION IMPROVEMENT PROJECT: 2. UNIVERSITY AVENUE AND SHATTUCK AVENUE

Study Area Description The signalized intersection where northbound Shattuck splits from southbound Shattuck at University Avenue lies at the north end of the downtown district of Berkeley. University Avenue is the major east/west street and Shattuck Avenue is the major north/south street in Berkeley and their intersection is very complex, a result of the historic layout of the city as developed around the earlier streetcar system. Shattuck Avenue is split into a north/south couplet that is three lanes in either direction for several blocks between University Avenue and Center Street to the south. This intersection lies at the north end of the couplet, where it is resolved by the northbound Shattuck alignment being incorporated into University Avenue for a short block westward until it turns northward and reunites with southbound Shattuck to become bi-directional. This short block of University Avenue is three lanes wide with the far right lane being a right turn only lane, the middle lane allowing right turns and through movement, and the left lane allowing left turns and through movement. Shattuck Avenue southbound is three lanes in width. Eastbound University Avenue has two lanes for through movement, and both left and right hand pocket lanes, while southbound Shattuck, north of University Avenue, has two through lanes and a right-hand pocket lane. Issues � The Shattuck and University corridors are two of the most heavily congested corridors in Berkeley. � This intersection is the site of the most auto/pedestrian collisions during a recent eight-year period. � There are two right turn lanes proceeding northward from westbound University onto northbound Shattuck. � Left turns are allowed from University onto Shattuck, although there is no dedicated lane from westbound

University onto southbound University.

����������Attachment 6

Page 38: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

6. Recommended Pedestrian Projects

Final Draft Berkeley Pedestrian Master Plan 6-19 January 2010

Proposed Improvements

� If sufficient right-of-way exists, install perpendicular curb ramps with truncated domes at all corners so that ramps face directly into crosswalk. $20,000

� Install advance stop bars on University to discourage encroachment of stopped vehicles into crosswalk and in right-turn-on-red situations. $1,800

� Consider utilization of a “leading pedestrian signal phase” to give pedestrians a “head start” to cross the street before motor vehicles start. (No capital cost)

� Repaint crosswalk striping at each crossing. $2,000 � Consider restricting right turn on red from westbound University traffic to northbound Shattuck in conjunction

with improving intersection operations through signal timing modifications and/or signage. $200 � Install “No U-Turn” sign on west leg of intersection. $200 Cost � $24,200 ($21,000 is accounted for in Citywide projects)

����������

Page 39: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

ATTACHMENT 7 Supplemental Information on Proposed Left Turn Prohibitions

Shattuck Reconfiguration and Pedestrian Safety Project As noted in the staff report, the project would prohibit left turns in both directions from Shattuck West to Addison and Center. Left turns would also be prohibited from Shattuck East to Center. These prohibitions are necessary for the following reasons:

Because of the high pedestrian volumes along Shattuck, right-turning vehicles have less opportunity to turn and frequently block the right lane, temporarily leaving only one lane available in a given direction. Allowing left turns would increase the chances of both lanes being blocked simultaneously, as left-turning vehicles also wait for an opportunity to turn.

Increased congestion as described above would be particularly problematic on northbound Shattuck between Center and Allston, because of the need to provide a clear path for buses pulling out of the stops on that block.

Given the high pedestrian volumes along Shattuck, allowing permitted left turns (where the turning vehicle must yield to oncoming traffic) is not advisable because the driver’s attention is focused primarily on the oncoming traffic, and not on pedestrians who may be crossing to the left. In this situation, drivers frequently make the left turn and then deal with pedestrian cross-traffic, creating safety risks to the pedestrians and blocking oncoming traffic if the vehicle must wait for pedestrians to clear.

At Shattuck West and Center, the curved roadway would make it more difficult for left-turning drivers to see both lanes of oncoming traffic, particularly if another driver is turning left in the opposite direction.

Southbound left turns at Shattuck West and Center, and northbound left turns at Shattuck East and Center, would function poorly because of the limited space for cars to wait between Shattuck West and East. Only one or possibly two cars would be able to turn on each green light, potentially creating a long back-up in the left lane. On Shattuck East the resulting congestion could be particularly severe, as only one through lane is provided. (It should be noted that this problem already occurs at this intersection, with left-turning vehicles stacking up in the left lane.)

Page 40: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Attachment 7

While the potential impacts of allowing left turns are fairly significant, the inconvenience to drivers in the Downtown is expected to be fairly minor. The following table explains how access to key destinations on Center and Addison Streets would be affected by the proposed turn prohibitions. Table 1. Impact of Turn Restrictions on Addison and Center Destinations Destination Location Current

Access Route Affected by Project

Impact of Turn Restriction

Center Street Garage

Entrances on Addison and Center between Shattuck and Milvia

Northbound Shattuck East, left on Center or Addison

(See Figure 1 below.) Access to the Addison St. entrance would be unchanged from the current condition, since northbound left turns would still be allowed from Shattuck East to Addison. Northbound vehicles on Shattuck could access the Center St. entrance by (1) turning left on Addison, then left on Shattuck West and right on Center, or (2) turning left on Allston, then right on Milvia and right on Center.

Addison Street Arts District

Addison between Shattuck and Milvia.

Northbound Shattuck East, left on Addison

Access to destinations in the Arts District (e.g. Berkeley Repertory Theatre, Freight & Salvage) would be unchanged from the current condition, since northbound left turns would still be allowed from Shattuck East to Addison.

Allston Way Garage

Entrances on Allston and Center between Shattuck and Milvia

Northbound Shattuck East, left on Allston or Center

Access to the Allston Way entrance would be unchanged from the current condition. Inbound vehicles that would otherwise use the Center St. entrance would likely shift to the Allston entrance. However, as noted earlier the northbound left turn from Shattuck to Center does not currently function well, so this shift would have other benefits.

Berkeley Art Museum

Center/Oxford (north side of Center)

Southbound Shattuck, left on Center

(See Figure 2 below.) Southbound vehicles on Shattuck cannot turn onto Center. However, because the museum’s drop-off zones will be located on the west side of Oxford and the north side of Center, this will not be the primary access route to the museum, and it will be more convenient for southbound vehicles to turn left at

Page 41: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Attachment 7

Destination Location Current Access Route Affected by Project

Impact of Turn Restriction

University and right at Oxford. Vehicles turning from Shattuck onto Center would have to do a U-turn to access the drop-off zones.

Proposed hotel at 2129 Shattuck

Center/Shattuck (north side of Center)

Southbound Shattuck, left on Center

(See Figure 2 below.) Southbound vehicles on Shattuck cannot turn onto Center. However, because the hotel’s drop-off zone is proposed for the north side of Center, this will not be the primary access route to the hotel, and it will be more convenient for southbound vehicles to turn left at University and right at Oxford. Vehicles turning from Shattuck onto Center would have to do a U-turn to access the drop-off zones.

Center St. restaurants and proposed hotel

2100 block of Center St., south side

Southbound Shattuck, left on Center

(See Figure 3 below.) Southbound vehicles on Shattuck cannot turn onto Center. Alternate routes include (1) making a U-turn at Allston, then turning right on Center; (2) for vehicles using University, turning right on MLK or Milvia, then left on Center; (3) for vehicles using Oxford, proceeding on Oxford to Allston, turning right and then right on Shattuck and right on Center.

Page 42: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Attachment 7

Figure 1. Access to Center St. Garage

Page 43: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Attachment 7

Figure 2. Access to Art Museum and Proposed Hotel (2129 Shattuck)

Page 44: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Attachment 7

Figure 3. Access to 2100 Block of Center, South Side

Page 45: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 1 of 24Arup North America Ltd | F0.3

To Aaron Sage, City of Berkeley DateDecember 1, 2015

Copies Reference number 242577/MVI

From Mike Iswalt File reference 4-05

Subject Shattuck Reconfiguration - Traffic Analysis with Sensitivity Tests

Arup has completed a detailed traffic analysis for the proposed reconfiguration of Shattuck Avenue between University Avenue and Allston Way. The reconfiguration will convert Shattuck to two-way operations between Allston and University. Figure 1 presents the extents of the study area.

Figure 1: Study Area

Attachment 8

Page 46: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 2 of 24Arup North America Ltd | F0.3

This analysis considers the following:

How will various configurations for the two-way segment perform? Are the number of travel lanes and the signal timing/phasing adequate? We have tested four alternatives in this report, including the Downtown Area Plan (DAP) Concept.

How will the Shattuck / University intersection operate given the redistribution of traffic from Shattuck East to the new two-way Shattuck West segment?

How will north and southbound left-turns at Addison Street and Center Street work with the reconfiguration?

Evaluate a series of sensitivity tests to understand how different intersection configurations and signal timing/phasing plans could impact traffic operations and pedestrian access.

Compare the results of the preferred Reconfigure option to previous results from Berkeley Downtown Area Plan (DAP) Program Environmental Impact Report (EIR) Traffic Impact Analysis (IBI Group, January 2009).

The traffic analysis utilizes a Synchro/SimTraffic traffic operations model provided by the City of Berkeley. The model provides information regarding existing peak hour traffic volumes, pedestrian counts, signal timings, etc. Arup has modified the Synchro model and utilized its microscopic simulation “microsimulation” tool SimTraffic to analyze traffic flow, queuing, and delay along the corridor. SimTraffic models individual drivers and how they react to the various elements of the transportation network (roadway geometrics and lane configurations, signal timing/phasing and coordination, other drivers, heavy vehicles such as trucks and buses, etc.). Issues related to transit routing and operations are currently being coordinated with City and AC Transit staff.

1 Background Traffic and Transit Conditions

The DAP EIR provides intersection traffic level-of-service (LOS) for several of the key intersections. Table 1 summarizes the EIR results. Table 1: DAP EIR Intersection LOS Results

AM Peak Hour PM Peak Hour

Intersection Existing 2030 Baseline2030 With

DAP Existing 2030 Baseline 2030 With

DAP1. Shattuck / University B / 14.2 B / 14.8 C / 24.7 B / 15.0 F / 113.2 E / 60.7

2. Shattuck / Center B / 11.2 A / 9.8 B / 18.4 B / 10.1 E / 66.7 F / 106.1

3. Shattuck / Allston B / 10.8 B / 10.2 C / 27.0 B / 13.0 D / 38.0 F / 122.8

Source: Berkeley Downtown Area Plan (DAP) Program EIR (IBI Group, January 2009) The EIR indicates that the intersections function acceptably under existing conditions. However, future PM conditions have several locations that would operate at LOS F.

Page 47: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 3 of 24Arup North America Ltd | F0.3

Figure 2 presents the existing transit routes within the study area.

Currently, 14 AC Transit lines, 3 UC Shuttle lines and 2 Lawrence Berkeley Lab Shuttle lines stop at the bus stop located on Addison Street and Shattuck Ave.

Approximately 62 buses per hour pass through the study area.

About 24 northbound Shattuck buses/shuttles per hour currently make a left turn onto University from Shattuck. Of the 24 buses per hour, 13 make a right turn onto northbound Shattuck, while 11 continue westbound on University.

Approximately 22 buses per hour make a right onto eastbound University from northbound Shattuck.

Figure 2: Existing Transit Routes (PM Peak Hour)

Page 48: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 4 of 24Arup North America Ltd | F0.3

Table 2 presents a summary of the existing headways for transit service in the study area. Figure 3 shows the existing roadway configuration and the location of the transit stops with the number of buses per hour. Table 2: Scheduled Transit Service

Weekdays

Headway in minutes

First Trip 6a–9a 9a–4p 4p–7p buses per

hr

after Last

7p Trip

1 5:30a 15 20 15 4 20 11:30p

1R 6:30a 12 12 12 5 — 6:45p

7 6:00a 40 40 40 2 40 7:45p

12 6:15a 20 30 20 3 30 10:00p

18 6:30a 15–20 15 15 4 20 11:30p

25 7:15a 40 40 40 2 40 7:40p

25 7:15a 40 40

— 2:30p (two trips) (two trips)

49 6:15a 30 30 30 2 — 7:00p

51B 5:30a 10–20 12 10 6 12–20 11:45p

51B* 7:15a 40 20–40 30–40 2 30–40 8:30p

52 6:00a 15–30 35 15 4 30 11:30p

65 6:00a 60 60 60 1 60 8:00p

65* 7:00a 60 60 60 1 60 7:30p

67 6:00a 30–40 40 40 2 — 7:30p

67* — — — — — —

88 5:30a 20 20 20 3 30 9:45p

F 7:00a 30 30 30 2 30 11:45p

FS 6:15a 30–60

— 30–60 2

— 7:00p (four trips) (four trips)

RFS 60 1

604/605 (two trips) - - - - AM

P1 7:00a 30 30 30 2

P2 6:45a 20 20 20 3

H 7:35 30 30 30 2

Berkeley Lawrence Lab Shuttle Routes

Blue 10 14 10 6

Orange 10-15 15 15 4

Page 49: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 5 of 24Arup North America Ltd | F0.3

Figure 3: Existing Roadway Configuration and Transit Stops

Page 50: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 6 of 24Arup North America Ltd | F0.3

2 Traffic Analysis of Reconfiguration Alternatives

Arup has completed an initial assessment of traffic and transit operations for existing conditions and four reconfiguration alternatives. All of the alternatives have the same lane configurations and signal assumptions at Addison, Center, and Allston. The alternatives are summarized below. Figures 4 through 8 present the Synchro inputs for each alternative.

Existing Conditions: The existing conditions analysis includes traffic volumes from 2011 and 2012. The analysis utilizes the City’s Synchro traffic models developed for the Program for Arterial System Synchronization (PASS), which include lane configurations, signal timings, and traffic and pedestrian volumes.

Alternative 1 – DAP Concept (northbound left-turn at Shattuck West): This is the configuration defined in the original Concept Plan. Provide a dedicated left-turn lane from northbound Shattuck West to westbound University with a protected signal phase. Figure 4 shows the lane configurations. Shattuck West has a five-lane cross-section south of University (two northbound travel lanes, two southbound travel lanes, one northbound left-turn lane). The reassignment of traffic away from Shattuck East and University indicates that the dedicated westbound right-turn lane on University approaching Shattuck can be removed, which would narrow westbound University to two lanes (a shared left/through and a shared through/right). The analysis tests this configuration, which would be safer for pedestrians crossing the north leg of the Shattuck / University intersection.

Alternative 2 – Revised Concept with Barrier (northbound left-turn from Shattuck East): Locate the northbound left-turn lane on Shattuck East instead of from Shattuck West, with a barrier on University to channel the left turning traffic to westbound University. Figure 5 shows the lane configurations. This allows the narrowing of Shattuck West south of University from five to four lanes (two travel lanes in each direction). The channelization would prevent vehicles traveling westbound on University to make a left-turn to southbound Shattuck West. This configuration requires that three westbound lanes on University at Shattuck remain (one channelized through lane, one through lane, and one right-turn lane) instead of the two westbound lanes tested in Alternative 1. Two westbound lanes on University at Shattuck West were evaluated (one channelized through, one shared through/right). However, this configuration did not work operationally.

Alternative 3 – Revised Concept-Optimized (Proposed Configuration): Remove the channelization on University to allow for two westbound travel lanes (one shared through/left and one shared through/right). Removing the channel allows for a more efficient use of lane capacity on westbound University at Shattuck West. The westbound right-turn volume from University to Shattuck is low enough to make this configuration work. We also assumed a shared left/through lane on southbound Shattuck at University, which would allow a shorter north crosswalk. Using Shattuck West to travel northbound between would remain a much faster travel option than using Shattuck East and University.

Alternative 4 – Remove One NB Travel Lane on Shattuck West: Remove one northbound travel lane on Shattuck West south of University. This would also allow for a four-lane cross-section on Shattuck West (one northbound travel lane, one northbound left-turn lane, two southbound travel lanes). The remainder of the Alternative 3 assumptions are included in this scenario.

Page 51: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 7 of 24Arup North America Ltd | F0.3

Figure 4: Existing Conditions (2011/2012 PM Peak Hour)

Page 52: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 8 of 24Arup North America Ltd | F0.3

Figure 5: Alternative 1 – DAP Concept

Existing right-turn lane is not required

Dedicated left-turn lane

No left-turns at Center

No left-turns on SB Shattuck at Addison or Center

Left-turn pocket has sufficient capacity

Page 53: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 9 of 24Arup North America Ltd | F0.3

Figure 6: Alternative 2 – Revised Concept with Barrier

Three WB lanes required with the channelization. The channel prevents WB left-turns at University.

No left-turns from northbound Shattuck

No left-turns on SB Shattuck at Addison or Center

Page 54: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 10 of 24Arup North America Ltd | F0.3

Figure 7: Alternative 3 – Revised Concept (Optimized)

Two WB lanes work if there is no channelization because the intersection operates more efficiently. The WB right-turn volume is relatively low. This also allows for WB left-turns from University.

Opportunity to have one receiving lane that opens up to a NB left-turn pocket at University and Addison.

Shared left/through lane on southbound Shattuck.

No left-turns on SB Shattuck at Addison or Center

Page 55: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 11 of 24Arup North America Ltd | F0.3

Figure 8: Alternative 4 - 1 NBT Lane on Shattuck West

One NB travel lane on Shattuck West from Center to University.

No left-turns on SB Shattuck at Addison or Center

Page 56: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 12 of 24Arup North America Ltd | F0.3

The traffic analysis for each alternative utilized the existing PM peak hour Synchro traffic operations models provided by the City and followed these steps:

1. The lane configuration changes for each alternative were coded into Synchro.

2. Left-turns on Shattuck West and East were addressed in the following way:

We have assumed that all left-turns would be prohibited from the proposed two-way Shattuck West at Addison and Center.

For northbound Shattuck, left-turns would be permitted from Shattuck East to Addison (as occurs today). Northbound left-turns would still occur from the dedicated lanes at Allston and University.

For southbound Shattuck, we have assumed that left-turns would occur at the existing pockets at University and Allston.

3. The existing PM peak hour traffic volumes were redistributed in Synchro from the existing one-way circulation pattern to the new two-way pattern, taking into account the reassignment of left-turn volumes described above.

4. Initial signal timing/phasing plans were developed in Synchro at University, Addison, Center, and Allston and assume a cluster phasing.

5. The proposed changes were analyzed with Synchro’s traffic simulation tool, SimTraffic, to measure delay, LOS, and queuing. All results represent the average of five simulation runs.

Note: additional analysis will be required to evaluate a future design year.

Page 57: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 13 of 24Arup North America Ltd | F0.3

The following traffic performance measures were used to evaluate the alternatives:

Intersection PM peak hour LOS and delay. The delay was calculated using SimTraffic, with LOS determined using criteria from the Highway Capacity Manual (HCM, Transportation Research Board, 2010). LOS and delay is only measured for an individual intersection, and does not fully account for the effects of queuing at upstream and downstream locations. Table 3 shows the intersection LOS criteria for signalized intersections.

Table 3: Intersection LOS Criteria

LOS Signalized Intersections

A Delay of 0 to 10 seconds. Most vehicles arrive during the green phase and do not stop at all.

B Delay of 10 to 20 seconds. More vehicles stop than with LOS A, but many drivers still do not have to stop.

C Delay of 20 to 35 seconds. The number of vehicles stopping is significant, although many still pass through without stopping.

D Delay of 35 to 55 seconds. The influence of congestion is noticeable, and most vehicles have to stop.

E Delay of 55 to 80 seconds. Most, if not all, vehicles must stop and drivers consider the delay excessive.

F Delay of more than 80 seconds. Vehicles may wait through more than one cycle to clear the intersection.

“Percent vehicles served” at each intersection. The “percent vehicles served” indicates how much of

the forecasted traffic volume can be served at the intersection during the peak hour. A percent served value higher than 95% is typical. A lower percent served indicates that traffic is delayed at the location, or it is stuck in queue somewhere else in the system.

Travel time and speed on Shattuck West and Shattuck East between Allston and University. The

north and southbound travel time and speed was estimated using SimTraffic and measured from a point north of University (near Delaware) and a point south of Allston (near Durant). For Shattuck East, the path of travel includes the northbound left-turn from Shattuck West to University and the westbound right-turn from University to Shattuck northbound.

Table 4 summarizes the performance measures for each alternative:

Page 58: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 14 of 24Arup North America Ltd | F0.3

Table 4: PM Peak Hour Traffic Analysis Performance Metrics

Intersection Existing Conditions

Alt 1 DAP Concept

Alt 2 Revised

Concept with Barrier

Alt 3 Revised

Concept – Optimized

Alt 4 Remove One NB Travel Lane on

Shattuck West

Intersection LOS and Percent Served

Shattuck West / University (Percent Served)

B / 15 100%

C / 29 100%

B / 15 99%

B / 19 100%

D / 44 98%

Shattuck East / University (Percent Served)

C / 23 100%

A / 3 99%

B / 13 99%

C / 25 99%

E / 79 98%

Shattuck West / Addison (Percent Served)

A / 7 100%

B / 16 99%

B / 13 98%

B / 17 100%

B / 20 98%

Shattuck East / Addison (Percent Served)

B / 8 100%

C / 25 99%

B / 25 98%

C / 24 98%

C / 24 99%

Shattuck West / Center (Percent Served)

B / 10 98%

A / 6 99%

A / 7 98%

A / 7 100%

B / 18 97%

Shattuck East / Center (Percent Served)

B / 14 97%

C / 24 99%

B / 16 99%

B / 16 99%

C / 28 95%

Shattuck / Allston (Percent Served)

B / 15 99%

B / 16 100%

B / 19 98%

B / 19 99%

D / 48 97%

Travel Time and Speed: University to Allston

Shattuck West Travel Time (min:ss) and Speed (mph)

NB SB

n/a 01:35 (14 mph)

02:04 (11 mph)01:38 (14 mph)

01:47 (13 mph)01:39 (14 mph)

01:45 (13 mph) 01:47 (13 mph)

03:25 (7 mph)02:47 (8 mph)

Shattuck East Travel Time (min:ss) and Speed (mph)

NB 02:10 (9 mph) 01:50 (9 mph) 02:06 (8 mph) 02:12 (7 mph)

02:58 (7 mph)

Source: Arup, 2015

Alternates 1, 2, and 3 all operate acceptably from a traffic perspective. Two-way operations on Shattuck

West provide a slightly faster and more direct northbound travel path, which is reflected in the travel time results.

Alternative 3, with one receiving lane on northbound Shattuck East at Center and Addison, as well as the shared left/through configuration at the southbound approach at the University/Shattuck intersection, performs almost as well as Alternative 2. LOS and travel speeds for Alternative 3 are slightly worse than Alternative 2, but the difference is negligible. Alternative 3 is the current preferred option analyzed throughout the remainder of the traffic study.

Alternative 4 performs worse than the other alternatives, as the lane reduction would result in significant queuing on northbound Shattuck West and University between Shattuck East and West. This queuing affects the operations at both Shattuck intersections on University, as the two signals are clustered. The travel times on both Shattuck West and East are significantly slower than Alternatives 1, 2, and 3.

The results indicate that the proposed lane configurations and circulation changes along Shattuck Avenue can be implemented without any adverse impacts on traffic flow.

Page 59: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 15 of 24Arup North America Ltd | F0.3

3 Additional Concepts and Sensitivity Tests

A series of additional concepts and sensitivity tests were evaluated to better understand the impact of higher pedestrian volumes, alternative lane configurations, various signal phasing options, and alternative left-turn treatments. Alternative 3 is used as the basis for all of the sensitivity testing.

ALTERNATIVE CONFIGURATIONS AT ALLSTON AND UNIVERSITY THAT WERE EXPLORED BUT REJECTED

Remove the southbound dedicated left-turn lane from Shattuck to Allston and allow southbound left-turns from a shared left/through lane with permitted left-turns: This would result in one southbound shared left/through lane with permitted left turns and one shared right/through lane at Shattuck/Allston. The analysis indicates that this intersection would operate at LOS F conditions with queues extending along southbound Shattuck back to Center and Addison.

Provide one eastbound through lane at Shattuck West/University: This would result in one eastbound travel lane on University between Shattuck West and Shattuck East, as well as one eastbound left and one eastbound right-turn lane. The analysis indicates that one eastbound through lane on University would result in LOS F conditions with significant queuing.

TEST OF HIGHER PEDESTRIAN VOLUMES

Traffic and pedestrian counts were recently collected by AC Transit at Shattuck West / Addison, Shattuck East / Addison and Shattuck / Center for the Line 51 Service and Reliability Study. Arup has reviewed the counts and identified the following:

The PM peak hour vehicle counts from the Line 51 study are consistent with the volumes used in this Shattuck Reconfiguration traffic analysis. The southbound volumes are higher in the Reconfiguration analysis, but are slightly lower than the Line 51 study in the northbound direction. Overall, the difference is minimal.

The pedestrian volumes at the west leg of both Shattuck West / Addison and Shattuck / Center are much higher in the Line 51 study. The Line 51 counts at the west leg for both intersections are in the 1,100 to 1,200 pedestrians per hour range. The volumes in the Synchro model are in the 300 to 400 pedestrians per hour range. Field observations by City staff support using the higher volume.

The pedestrian volumes at Shattuck East / Addison are approximately the same between the two studies.

To evaluate the potential impact of higher pedestrian volumes on traffic operations, we conducted a sensitivity test using the Alternative 3 Synchro/SimTraffic model described above with the higher pedestrian volumes at Shattuck West / Addison and Shattuck West / Center. We also optimized the cycle lengths and signal timings to improve north and southbound traffic flow on Shattuck. Table 5 presents the results.

Page 60: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 16 of 24Arup North America Ltd | F0.3

Table 5: Alternative 3 Higher Pedestrian Volume Test

Intersection Alt 3 Revised Concept –

Optimized

Alt 3 Higher Pedestrian

Volumes

Intersection LOS and Percent Served

Shattuck West / University (Percent Served)

B / 19 100%

B / 20 100%

Shattuck East / University (Percent Served)

C / 25 99%

B / 19 99%

Shattuck West / Addison (Percent Served)

B / 17 100%

C / 21 100%

Shattuck East / Addison (Percent Served)

C / 24 98%

C / 21 97%

Shattuck West / Center (Percent Served)

A / 7 100%

B / 16 100%

Shattuck East / Center (Percent Served)

B / 16 99%

B / 19 99%

Shattuck / Allston (Percent Served)

B / 19 99%

C / 24 98%

Travel Time and Speed: University to Allston

Shattuck West Travel Time (min:ss) and Speed (mph)

NB SB

01:45 (13 mph) 01:47 (13 mph)

2:00 (11 mph) 2:23 (10 mph)

Shattuck East Travel Time (min:ss) and Speed (mph)

NB 02:12 (7 mph)

02:49 (6 mph)

Source: Arup, 2015

The higher pedestrian volumes along Shattuck West at Addison and Center result in slightly higher delays and travel times, when compared to the previous analysis results. The average queue measured for the southbound shared through/right-turn lane is 162 feet with a 95th percentile queue of 254 feet. The block length is 280 feet, which should provide sufficient queue storage without spilling back to University.

The reason the higher pedestrian volumes do not have a greater impact is that the southbound right-turn volume (which conflicts with pedestrians crossing at the west leg of these intersections) is very low, in the 50-70 vehicles per hour range. Assuming a 60 second cycle (60 cycles per hour), approximately one to two vehicles would typically be waiting to make a right-turn at the crosswalk each cycle. These vehicles would conflict with approximately 20 pedestrians each cycle. The one to two vehicles making the southbound right-turn will be delayed at the beginning of the signal phase to allow the pedestrians to cross. This will also block southbound traffic and result in the queue reported above. However, towards the end of the phase, as pedestrians have cleared from the crosswalk, there should be enough time to clear the waiting vehicles.

SPLIT PHASE AT UNIVERSITY / SHATTUCK WEST

Arup investigated the possibility of operating a split phase at Shattuck West / University. This would allow northbound left-turns to shift back to Shattuck West from Shattuck East. In a split phasing configuration, northbound Shattuck and southbound Shattuck movements would operate as separate phases. This would allow left turning traffic to operate with no conflicting traffic traveling through the intersection from the opposing approach. West and eastbound University would still operate concurrently as they do today. Split phases

Page 61: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 17 of 24Arup North America Ltd | F0.3

typically work well in situations where opposing approaches at an intersection have substantially different volumes that require different green time splits.

We tested the intersection in Synchro and generated a HCM LOS result and queues. The LOS indicates that a split phase would operate at LOS F conditions with 86.9 seconds of delay. Table 6 summarizes the 50th and 95th percentile queues for each approach.

Table 6: Shattuck West / University Split Phase Test Queueing

Approach 50th Percentile 95th Percentile Exceeds Available Storage

Northbound 245 ft 467 ft Yes

Southbound 210 ft 282 ft No

Eastbound 106 ft 164 ft No

Westbound 360 ft 467 ft Yes Source: Arup, 2015

The results indicate that the northbound and westbound queues could spill back through adjacent intersections, which could result in negative traffic impacts at these other locations.

PEDESTRIAN SCRAMBLE PHASE AT SHATTUCK WEST / UNIVERSITY

We also tested the feasibility of a pedestrian scramble phase at the Shattuck West / University intersection. A scramble is a pedestrian crossing system that stops all vehicular traffic and allows pedestrians to cross an intersection in every direction, including diagonally, at the same time. No vehicles would be able to make a right-turn on red while pedestrians are crossing during the scramble phase. Pedestrians would still be able to cross with their typical phases. Scrambles provide an enhanced crossing environment for pedestrians by improving safety and providing more opportunities and less delay for crossing.

Pedestrian scrambles add an additional phase to the overall traffic signal cycle. The length of the phase is determined by the time required to cross diagonally through the intersection (the longest crossing distance). This crossing time would establish the Flash Don’t Walk (FLDW) time. A shorter initial Walk time is also required.

For this exercise, we measured the distance diagonally across the intersection (100 ft) and determined a time of 29 seconds for the diagonal crossing (includes yellow and red time) assuming a crossing speed of 3.5 feet per second. The diagonal crossing distance is approximately the same between the existing condition and the concept plan.

We evaluated the pedestrian scramble option under existing and Alternative 3 using HCM LOS. The results are summarized below:

Existing PM Peak Hour Conditions: LOS E (70.2 seconds)

Alternative 3 PM Peak Hour Conditions with Scramble: LOS F (108.1 seconds)

Adding the pedestrian scramble phase increases the overall cycle length, which degrades LOS to LOS E/F conditions. The scramble phase makes the signal less efficient and reduces the share of green time allocated to the traffic phases. Given the high traffic volumes, the less efficient signal timing would lead to the degradation in LOS.

Page 62: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 18 of 24Arup North America Ltd | F0.3

DEDICATED WESTBOUND LEFT-TURN POCKET AT SHATTUCK WEST / UNIVERSITY TEST

We evaluated the Shattuck West / University intersection with a dedicated left-turn pocket serving westbound left turns. A westbound left-turn pocket adds additional queue storage and capacity at the intersection and allows for concurrent protected left turn phasing on University with the eastbound left-turns on the opposite side of the intersection. We tested this configuration (left-turn pockets with protected left turn phasing at both University Avenue approaches) with the Alternative 3 traffic model and the results indicate that the intersection would operate at LOS B with 17 seconds of delay, a slight improvement over the baseline Alternative 3 configuration.

REASSIGNING SOUTHBOUND LEFT-TURNS FROM ALLSTON TO KITTREDGE TEST

As part of evaluating a potential bus boarding island on northbound Shattuck at Allston, Arup evaluated the feasibility of removing southbound left-turns (and the left-turn pocket) at Allston and reassigning the left-turns to Kittredge. The southbound left-turn pocket at Kittredge is only 60 ft, enough room for approximately two vehicles. The PM peak hour traffic counts indicate that the reassignment is relatively small. There are only 24 southbound left-turns at Kittredge and 76 left-turns at Allston.

Similar to the other tests, we used Synchro to calculate the HCM LOS and southbound left-turn (SBL) queues at Kittredge before and after the reassignment of the left-turn traffic from Allston. The results are presented below:

Existing PM Peak Hour Conditions: LOS B (16.5 seconds)

o SBL 50th percentile queue of 7 ft

o SBL 95th percentile queue of 23 ft

Alternative 3 PM Peak Hour Conditions with Reassignment: LOS C (24.9 seconds)

o SBL 50th percentile queue of 60 ft

o SBL 95th percentile queue of 118 ft

The results indicate that reassigning the left-turns to Kittredge will cause LOS and delay to degrade slightly. However, the queuing information indicates that a few vehicles will routinely spill out of the short turn pocket at Kittredge and block through traffic on Shattuck.

To increase our level of confidence in the results, we also tested the network using SimTraffic to verify that the operations would work and that the queuing at the southbound left-turn would not exceed the available capacity of the turn pocket. The SimTraffic test is consistent with the HCM findings, as it indicates LOS C with 32 seconds of delay and a 98 ft average queue and a 138 ft average queue.

The issue of queues blocking through traffic on southbound Shattuck does not appear to be an issue for overall traffic intersection and corridor operations, but it could result in unsafe driving behavior as vehicles change lanes to avoid the queue. Protected / permitted phasing would likely not provide much help because the short length of the turn pocket would only allow a few cars to utilize the protected left-turn phase. Protected/permitted phasing can result in the “yellow trap” issue where vehicles making a permitted left-turn, seeing that their light is turning yellow, believe that oncoming traffic also has a yellow and turn in front of oncoming vehicles. There are also potential pedestrian safety issues, where pedestrians trying to cross the street are unaccustomed to left turning vehicles.

Page 63: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 19 of 24Arup North America Ltd | F0.3

PROVIDING GAPS FOR BUSES EXITING BART TO NORTHBOUND SHATTUCK

There is a concern that buses stopping at the BART station on northbound Shattuck between Allston and Center will have a difficult time exiting the bus stop and pulling back out into traffic. Safely merging back into traffic requires the following:

1. The curbside lane needs to be clear of vehicle queues from a downstream red signal at Center.

2. There must be adequate gaps in the traffic stream along Shattuck for buses to pull out into moving traffic.

The SimTraffic analysis indicates that the 95th percentile queues caused by the red signals at Center are less than 100 feet with the maximum observed queue as 169 feet. The length of the block is 270 feet, with the bus stop for northbound buses on the southern half of the block.

A series of changes to the traffic signal timings, coordination offsets, and pedestrian crossing times could all help to generate artificial gaps in traffic. Adding leading pedestrian intervals (LPI) of three to five seconds for the Shattuck crosswalks would also provide additional gaps for buses trying to exit the bus stop, as well as provide an additional measure of safety.

EXPANDED NETWORK

Arup expanded the network to address concerns regarding how the Shattuck Reconfiguration (Alternative 3) and the left-turn prohibitions on Shattuck would reassign traffic to the east-west cross-streets. The reassignment of traffic has the potential to impact Milvia and Oxford. We used our Synchro/SimTraffic models of the study area and added in the intersections on Milvia and Oxford using the City’s existing PM peak hour Synchro network. Figure 9 presents the expanded study area network.

Page 64: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 20 of 24Arup North America Ltd | F0.3

Figure 9: Expanded Study Area Network (Alternative 3 with Milvia and Oxford Streets added)

For the reconfiguration scenario, we reassigned the traffic volumes using the same methodology described above and balanced the traffic volumes between adjacent intersections. We accounted for the Center Street garage in the balancing and assumed a small increase in the number of trips associated with the future expansion of the garage. Data provided by the City indicates that the existing garage typically generates the following entering and exiting volumes for a midweek day (Tuesday-Thursday) from 5-6 PM (the peak hour for the traffic analysis):

Enter = 76 vehicles per hour (5-6 PM) Exit = 114 vehicle per hour (5-6 PM)

The 5-6 and 6-7 PM hours have approximately the same entering and exit volumes and represent the peak hours of the day. The Center Street garage replacement will increase the parking supply from 420 to 710 spaces, a 69 percent increase. The increase in the number of trips associated with the expansion of the garage is still relatively minor

Stop signs are shown

Page 65: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 21 of 24Arup North America Ltd | F0.3

(130 total entering/existing) when compared to the overall traffic volumes on the adjacent streets. Applying the growth rate to the entering and exit volumes yields the following garage volumes:

Entering (projected) = 128 vehicles per hour (5-6 PM) (+52 vehicles over existing) Exiting (projected) = 192 vehicles per hour (6-6 PM) (+78 vehicles over existing)

These volumes were added to the background traffic and used to estimate the LOS. Table 7 provides the results of the HCM LOS analysis. We did not use SimTraffic to simulate the larger network. (Note: the City’s original Synchro model and the DAP did not include three unsignalized intersections. These were added in to the analysis). We obtained the existing conditions LOS from the DAP (for the available intersections) and tested the Shattuck Reconfiguration using the Alternative 3 Synchro model. We used 2009 volumes from the DAP and the assumptions described above to test the impacts of the reconfiguration. LOS for unsignalized intersections is reported for the stop controlled approach. For the Oxford / Allston intersection, this is the eastbound approach on Allston. Table 7: Expanded Network Intersection LOS

Intersection Existing PM Existing with Reconfiguration (Alternative 3)

Milvia / University B / 12 B / 16

Milvia / Addison (all-way stop) n/a C / 16

Milvia / Center B / 12 B / 16

Milvia / Allston C / 21 C / 21

Oxford / University C / 21 C / 28

Oxford / Addison (side-street stop) Not analyzed in the DAP EIR B / 11 (EB approach)

Oxford / Center B / 11 B / 11

Oxford / Allston (side-street stop) F / 120 (EB Approach) F / > 180 (EB Approach)

F / > 113 with additional EB turn lane – this mitigates the impact

Notes: For unsignalized (side-street stop controlled) intersections, the LOS and delay is reported for the stop controlled movement (the EB approach from Addison and Allston). The overall intersection LOS is also reported. Source: Arup, 2015

The DAP EIR identified that Oxford / Allston currently operates at LOS F (120 seconds of delay to the eastbound Allston approach) under Existing PM peak hour conditions. The analysis presented in Table 7 indicates that the redistribution of traffic associated with the reconfiguration and the left-turn prohibitions on Shattuck would reassign trips to Allston and exacerbate the LOS F conditions at the intersection (180 seconds of delay to the eastbound Allston approach). This degradation in LOS would be considered a traffic impact using the City’s impact analysis guidelines. The Allston approach at Oxford consists of a single travel lane, which does not provide enough capacity. To mitigate this traffic impact, the delay at the Allston approach under the Reconfiguration scenario (180 seconds of delay) would need to be reduced to a level equal or better to the Existing PM peak hour result (120 seconds of delay).

Page 66: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 22 of 24Arup North America Ltd | F0.3

The DAP EIR identifies a future “cumulative” traffic impact at Oxford / Allston and recommends a mitigation measure that incorporates restriping eastbound Allston with one left and one right-turn lane as well as including a traffic signal. The restriping can be accommodated by removing one or two on-street parking spaces on Allston and is sufficient to mitigate the traffic impact. With the additional lane, the delay at the Allston approach improves to 113 seconds of delay, which is an improvement over the 120 seconds of delay under Existing conditions. This improvement would successfully mitigate the impact. The traffic signal is not required at this time as the restriping is sufficient.

4 Impact Analysis

We have compared the intersection LOS for the Shattuck Reconfiguration (Alternative 3) scenario to the traffic impact analysis results presented in the DAP EIR under Existing and 2030 Conditions. The Shattuck West / Addison intersection is not included because it was not included in the DAP EIR. This analysis utilizes HCM LOS and the same EIR volumes for both scenarios (applying similar redistribution assumptions) to allow for a direct comparison between the scenarios. The only significant changes between the current Reconfiguration design (Alternative 3) and what was analyzed in the DAP EIR are:

The northbound left-turn at Shattuck West / University has been relocated to Shattuck East / University o The northbound left-turn traffic using Shattuck East is now reassigned to the westbound through

movement at Shattuck West

The number of lanes and the lane configurations at Shattuck West / University have changed o The northbound approach has one through lane and one shared through/right-turn lane o The removal of the dedicated westbound right-turn lane o A shared southbound left/through lane

No left-turns from Shattuck West to Center

Table 8 presents the Existing Conditions comparison and Table 9 presents the 2030 Conditions comparison. Table 8: Existing with Reconfiguration HCM LOS Comparison

AM Peak Hour PM Peak Hour

Intersection Existing

Existing With Reconfiguration (Alternative 3) Existing

Existing With Reconfiguration (Alternative 3)

1. Shattuck / University B / 14.2 B / 18.8 B / 15.0 B / 18.9

2. Shattuck / Center B / 11.2 A / 9.8 B / 10.1 A / 8.4

3. Shattuck / Allston B / 10.8 B / 13.9 B / 13.0 B / 16.3

Source: Berkeley Downtown Area Plan (DAP) Program EIR (IBI Group, January 2009); Arup 2015

The Existing with Reconfiguration HCM results indicate that the conversion of Shattuck to two-way operations would not result in any significant change to traffic LOS when compared to the DAP EIR. The results indicate that the minor changes associated with the lane configurations and traffic assignments would not have a significant impact to traffic under the Existing With Reconfiguration scenario.

Page 67: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 23 of 24Arup North America Ltd | F0.3

Table 9: 2030 with Reconfiguration HCM LOS Comparison

AM Peak Hour PM Peak Hour

Intersection 2030

Baseline 2030 With

DAP

2030 With Reconfiguration

(Alt 3) 2030

Baseline 2030 With

DAP

2030 With Reconfiguration

(Alt 3)

1. Shattuck / University

B / 14.8 C / 24.7 C / 28.3 F / 113.2 E / 60.7 E / 66.0

2. Shattuck / Center A / 9.8 B / 18.4 B / 15.2 E / 66.7 F / 106.1 F / 105.1

3. Shattuck / Allston B / 10.2 C / 27.0 C / 29.4 D / 38.0 F / 122.8 E / 71.7

Source: Berkeley Downtown Area Plan (DAP) Program EIR (IBI Group, January 2009); Arup 2015

The 2030 with Reconfiguration HCM results indicate a slight increase in delay but no change in LOS compared to the 2030 results from the DAP EIR. The results indicate that the minor changes associated with the lane configurations and traffic assignments would not have cause a significant impact to traffic under the 2030 With Reconfiguration scenario.

Page 68: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Memorandum

J:\S-F\240000\242577-00\4 INTERNAL PROJECT DATA\4-05 REPORTS & NARRATIVES\INITIAL TRAFFIC ANALYSIS\2015 11 30 TRAFFIC STUDY\2015 12 01 TRAFFIC ANALYSIS.DOCX

Page 24 of 24Arup North America Ltd | F0.3

ATTACHMENTS

Page 69: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

A

1

BC

DE

FG

HI

JK

LM

NO

PQ

2 3 4 5 6 7 8 9 10

Sta

mp

Clie

ntJo

b Ti

tleD

raw

ing

Title

Key

Pla

n

Job

No

Che

cked

By

File

Nam

e

Dra

win

g N

o

Sca

le

Dra

win

g S

tatu

s

Dra

wn

By

NO

.R

EV

ISIO

ND

ATE

ww

w.a

rup.

com

Tel (

415)

957

944

5 F

ax (4

15) 9

57 9

096

San

Fra

ncis

co, C

A 9

4105

U

SA

560

Mis

sion

Stre

et, S

uite

700

Aru

p N

orth

Am

eric

a Lt

d.

C

SK

-C-0

6-P

AR

KIN

G B

AY

BE

TWE

EN

AD

DIS

ON

AN

D U

NIV

EC

ITY

OF

BE

RK

ELE

YS

HA

TTU

CK

AV

EN

UE

RE

CO

NFI

GU

RA

TIO

N A

ND

PE

DE

STR

IAN

SA

FETY

PR

OJE

CT

242577

24x3

6

BE

TWE

EN

UN

IVE

RS

ITY

AV

EN

UE

AN

D C

EN

TER

STR

EE

T

BU

LB-IN

CO

NFI

GU

RA

TIO

NP

RE

LIM

INA

RY

PA

RK

ING

LA

YO

UT

1" =

20'

A. C

AN

NO

N

J. M

ON

G

0'40

'20

'20

'

GR

AP

HIC

SC

ALE

N

AS

HA

TTU

CK

SE

CTI

ON

NO

T TO

SC

ALE

BS

HA

TTU

CK

SE

CTI

ON

NO

T TO

SC

ALE

NO

TE:

1.E

XIS

TIN

G U

TILI

TIE

S S

HO

WN

AR

E F

OR

RE

FER

EN

CE

ON

LY A

ND

HA

D N

OT

BE

EN

FIE

LD V

ER

IFIE

D.

2.U

TILI

TIE

S C

ALL

OU

T IN

TH

E D

RA

WIN

GS

AR

E A

SS

UM

ED

TO

BE

RE

LOC

ATE

D F

OR

BU

LB-IN

PA

RK

ING

OP

TIO

N.

����

���

���

Atta

chm

ent 9

Page 70: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Back-in/Head-out Angle Parking

Nelson\Nygaard Consulting Associates 785 Market Street, Suite 1300

San Francisco, CA 94103

January 2005

Attachment 10

Page 71: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

B a c k - i n / H e a d - o u t A n g l e P a r k i n g

Page i • Nelson\Nygaard Consulting Associates

Table of Contents PAGE

Introduction .....................................................................................................................1

Some examples.................................................................................................................1

Advantages.......................................................................................................................4 Bicyclists.......................................................................................................................4 Visibility........................................................................................................................5 Steep terrain..................................................................................................................5 Disabled parking...........................................................................................................5 Safety ............................................................................................................................6

Cities using back-in/head-out angle parking......................................................................6

Typical dimensions...........................................................................................................7

References........................................................................................................................8 Appendix A Nawn, J.A. (2003) Central Business District Back In Angle Parking. PE

Reporter, November/December Issue, P. 11-13.

Appendix B City Of Pottstown (2001) Proposed High-Street Traffic Calming Plan.

Appendix C City Of Vancouver (2004) Angle Back In Parking Striping.

Appendix D City Of Seattle (2005) Angle Back In Parking Dimensions.

Table of Figures PAGE

Figure 1 Back-in/Head-out parking in Tucson, AZ........................................................2 Figure 2 With back-in angle parking you can load your car on the curb, rather than in

the street (Vancouver, WA). ...........................................................................2 Figure 3 An ‘eye-to-eye’ line of sight between parker and approaching road-user

(Vancouver, WA). ..........................................................................................3 Figure 4 The parker’s view of the on-coming traffic (Vancouver, WA). ........................3 Figure 5 A traffic sign showing the three steps of back-in angle parking, in Kelowna,

BC, Canada. ..................................................................................................4 Figure 6 A disabled parking stall located right next to the pedestrian crossing and the

curb ramp......................................................................................................5 Figure 7 Cities using back-in/head-out angle parking. ..................................................6 Figure 8 Cross-section of a roadway accommodating both bike lanes and back-in/head-

out angle parking...........................................................................................7

Page 72: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

B a c k - i n / H e a d - o u t A n g l e P a r k i n g

Page 1 • Nelson\Nygaard Consulting Associates

Introduction In recent years the use of back-in/head-out angle parking has increased steadily in cities across North America. There are several reasons for this development. Kulash and Lockwood (2003) state that:

“Back-in/head-out diagonal parking is superior to conventional head-in/back-out diagonal parking. Both types of diagonal parking have common dimensions, but the back-in/head-out is superior for safety reasons due to better visibility when leaving. This is particularly important on busy streets or where drivers find their views blocked by large vehicles, tinted windows, etc., in adjacent vehicles in the case of head-in/back-out angled parking. In other words, drivers do not back blindly into an active traffic lane. The back-in maneuver is simpler than a parallel parking maneuver. Furthermore, with back-in/head-out parking, the open doors of the vehicle block pedestrian access to the travel lane and guide pedestrians to the sidewalk, which is a safety benefit, particularly for children. Further, back-in/head-out parking puts most cargo loading (into trunks, tailgates) on the curb, rather than in the street.”

The growing presence on American streets of sport utility vehicles (SUVs), with their bulky rear ends and (frequently) tinted windows may have spurred the trend toward back-in/head-out angle parking: when using conventional angle parking, drivers increasingly find themselves beside an SUV, with more difficult sightlines.

This report briefly discusses the design and benefits of back-in/head-out angle parking and shows where the design has already been implemented.

Some examples In Tucson, AZ, two blocks of reverse diagonal parking have been installed along the University Boulevard Bikeway (see Figure 1), which leads into the west entrance of the University of Arizona (~36,000 students). In the two years of reverse diagonal parking, there have been no accidents along the segment, despite the large number of cyclists using the bikeway.

Figures 2-4 illustrate some of the benefits of back-in/head-out angle parking. In Figure 2 the driver is able access her trunk from the curb rather than from the street. Figures 3 and 4 show that the driver can have eye contact with oncoming traffic, in this case a bicyclist.

Figure 5 shows typical signage used to introduce drivers to back-in/head-out angle parking. For more examples on back-in/head-out angle parking, see Appendices A and B.

Page 73: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

B a c k - i n / H e a d - o u t A n g l e P a r k i n g

Page 2 • Nelson\Nygaard Consulting Associates

Figure 1 Back-in/Head-out parking in Tucson, AZ.

Source: T. Boulanger, Transportation Services, City of Vancouver, WA.

Figure 2 With back-in angle parking you can load your car on the curb, rather than in the street (Vancouver, WA).

Source: T. Boulanger, Transportation Services, City of Vancouver, WA.

Page 74: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

B a c k - i n / H e a d - o u t A n g l e P a r k i n g

Page 3 • Nelson\Nygaard Consulting Associates

Figure 3 An ‘eye-to-eye’ line of sight between parker and approaching road-user (Vancouver, WA).

Source: T. Boulanger, Transportation Services, City of Vancouver, WA.

Figure 4 The parker’s view of the on-coming traffic (Vancouver, WA).

Source: T. Boulanger, Transportation Services, City of Vancouver, WA.

Page 75: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

B a c k - i n / H e a d - o u t A n g l e P a r k i n g

Page 4 • Nelson\Nygaard Consulting Associates

Figure 5 A traffic sign showing the three steps of back-in angle parking, in Kelowna, BC, Canada.

Source: City of Kelowna, British Columbia, Canada.

Advantages Back-in/head-out angle parking is similar to both parallel and standard angle parking. As with parallel parking, the driver enters the stall by stopping and backing, but need not maneuver the front of the vehicle against the curb. When leaving the stall, the driver can simply pull out of the stall, and has a better view of the oncoming traffic.

Bicyclists This type of parking provides a safer environment for bicyclists using the roadways. The driver is able to see the cyclist easily when exiting the stall. Several cities where back-in angle parking has been implemented have seen a reduction in number of accidents compared to the number of accidents at regular parallel parking schemes. Matt Zoll at

Page 76: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

B a c k - i n / H e a d - o u t A n g l e P a r k i n g

Page 5 • Nelson\Nygaard Consulting Associates

Tucson-Pima County Bicycle Advisory Committee says that after implementing the back-in/head-out angle parking scheme in Tucson they “went from an average of 3-4 bike/car accidents per month to no reported accidents for 4 years following implementation.”

Visibility In contrast to standard angle parking the visibility while exiting a back-in/head-out angle parking into traffic is much improved. When the driver is backing up (into the stall), the driver is in control of his lane: traffic behind either waits, or changes lanes.

Steep terrain Back-in angle parking can also be useful on steep terrain: if used on the correct side of the street, it causes drivers to automatically curb their wheels, which in turn prevents runaway autos. Used on the wrong side of a steep street, however, it is likely to cause more runaways.

Disabled parking In Pottstown, PE, a 13-foot wide handicap accessible stall has been incorporated into the angle parking as the last space, intersection nearside, of each block. This places each disabled parking stall close to the existing curb ramps, and allows the wheelchair-using drivers to unload out of the way of traffic (see Figure 6). By contrast, the street’s previous parallel parking arrangement could not be safely used for disabled parking, and conventional angle parking raised safety concerns for the street’s proposed bicycle lanes.

Figure 6 A disabled parking stall located right next to the pedestrian crossing and the curb ramp.

Back-in angle parking stalls

Page 77: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

B a c k - i n / H e a d - o u t A n g l e P a r k i n g

Page 6 • Nelson\Nygaard Consulting Associates

Safety As SLCTrans (2004) states, “one of the most common causes of accidents is people backing out of standard angled parking without being able to see on-coming traffic. Reverse angled parking removes this difficulty.” It also improves safety for cyclists, and for loading/and unloading the trunk of the car. Similarly, the Urban Transportation Monitor’s recent article on back-in angle parking reported reduced accidents and benefits for bicyclists in several communities. In all, back-in/head-out angle parking is a good choice when compared to conventional head-in angle/back-out parking and parallel parking.

Cities using back-in/head-out angle parking The list of cities in North America that use back-in/head-out angle parking is growing. Figure 7 lists some of these communities.

Figure 7 Cities using back-in/head-out angle parking.

City Source Arlington, VI Dan Burden Walkable Communities, Inc. Birmingham, AL Russ Soyring City of Traverse City, MI Burnaby, Canada Dan Burden Walkable Communities, Inc. Charlotte, NC Dan Burden Walkable Communities, Inc. Chico, CA Patrick Siegman Nelson\Nygaard Everett, WA Michael M. Moule Livable Streets, Inc Honolulu, HI Dan Burden Walkable Communities, Inc. Indianapolis, IN Michael M. Moule Livable Streets, Inc Knoxville, TN Michael M. Moule Livable Streets, Inc Marquette, MI Russ Soyring City of Traverse City, MI Montreal, Canada Michael M. Moule Livable Streets, Inc New York, NY Dan Burden Walkable Communities, Inc. Olympia, WA Dan Burden Walkable Communities, Inc. Plattsburgh, NY Dan Burden Walkable Communities, Inc. Portland, OR Michael M. Moule Livable Streets, Inc Pottstown, PA Michael M. Moule Livable Streets, Inc Salem, OR Todd Boulanger City of Vancouver, WA Salt Lake City, UT Dan Burden Walkable Communities, Inc. San Francisco, CA Michael M. Moule Livable Streets, Inc Seattle, WA Dan Burden Walkable Communities, Inc. Tacoma, WA Dan Burden Walkable Communities, Inc. Tucson, AZ Michael M. Moule Livable Streets, Inc Vancouver, WA Todd Boulanger City of Vancouver, WA Ventura, CA Todd Boulanger City of Vancouver, WA Washington, DC Dan Burden Walkable Communities, Inc. Wilmington, DE Michael M. Moule Livable Streets, Inc

Page 78: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

B a c k - i n / H e a d - o u t A n g l e P a r k i n g

Page 7 • Nelson\Nygaard Consulting Associates

Typical dimensions Particularly when accommodating bike lanes within the roadway, back-in/head-out angle parking is useful. Figure 8 shows the cross-section of such a roadway in Pottstown, PA. Appendix C and D shows Vancouver’s, WA, and Seattle’s, WA, choices of dimensions for this type of parking.

Figure 8 Cross-section of a roadway accommodating both bike lanes and back-in/head-out angle parking.

Source: City of Pottstown (2001) Proposed High Street Traffic Calming Plan.

Page 79: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

B a c k - i n / H e a d - o u t A n g l e P a r k i n g

Page 8 • Nelson\Nygaard Consulting Associates

References City of Pottstown (2001) Proposed High Street Traffic Calming Plan.

City of Pottstown (2004) Back In Angle as a Way to Improve Pedestrian Circulation in the Central Business District High Street, Pottstown Borough, Montgomery County, Pennsylvania, USA.

City of Vancouver, WA (2004) Angle Back In Parking Striping. Standard Plan Number T29-62.

Kulash, W. M. and Lockwood, I.M. (2003) Time-saver Standards for Urban Design, 7.2—5, McGraw-Hill Professional, New York, New York.

Nawn, J. (2003) Central Business District Back In Angle Parking. November/December PE Reporter, pages 11-13.

SLCTrans, Salt Lake City, UT (2004) Back-in or Reverse Angle Parking - FAQ. http://www.slcgov.com/transportation/Aboutus/FAQ.htm.

Urban Transportation Monitor. Back-in Angle Parking. June 11, 2004, page 1.

Page 80: Pedestrian Safety Project (“Shattuck Reconfiguration”) · 12/15/2015  · Pedestrian Safety Project (“Shattuck Reconfiguration”). This federally funded project is intended

Atta

chm

ent 1

1


Recommended