Performance networks Highways and Street Lighting - How are we performing? Thursday 7 June 2018 Debbie Johns, Head of Performance Networks
Transcript
Page 1: Performance networks - apse

Performance networks

Highways and Street Lighting - How are we performing?

Thursday 7 June 2018

Debbie Johns, Head of Performance Networks

Page 2: Performance networks - apse

Performance management

Recommendation 26 – Performance management framework

A performance management framework should be developed that is clear and accessible to stakeholders as appropriate and supports the asset management strategy

Recommendation 27 – Performance monitoring

The performance of the Asset Management Framework should be monitored and reported. It should be reviewed regularly by senior decision makers and when appropriate, improvement actions should be taken.

Page 3: Performance networks - apse

www.apse.org.uk

Performance networks

• The largest public sector benchmarking service in the UK • 185 UK local authorities registered • 20th year of data collection • 15 service areas • Developed and reviewed by practitioners • Confidentiality and terms of membership • Range of cost, quality, productivity and outcome measures • Like-for-like comparisons through profiling • Independently validated • Flexibility in comparisons • Robust data validation processes including parameters, exclusion reports as well as practitioner checks and an audit process • Partnership working with SCOTS and CSS Wales • Asset management approach to performance measurement (2009) • Carriageways, footways, winter maintenance, street furniture, traffic management systems, road drainage, gullies, street lighting and bridges & structures

Page 4: Performance networks - apse

www.apse.org.uk

Types of analysis

Page 5: Performance networks - apse

www.apse.org.uk

Page 6: Performance networks - apse

www.apse.org.uk

Performance awards

(Best Practice and Improvement Awards)

Page 7: Performance networks - apse

www.apse.org.uk

Page 8: Performance networks - apse

www.apse.org.uk

12-13 13-14 14-15 15-16 16-17 PI 03a 87.26% 90.25% 87.46% 89.25% 91.26% PI 45a 84.76% 86.45% 85.75% 91.75% 88.20%

84.00%

86.00%

88.00%

90.00%

92.00%

94.00%

PI 03a Percentage of damaged roads made safe in target times (2012-17) PI 45a Percentage of damaged footways made safe in target times (2012-17)

Performance trends

Page 9: Performance networks - apse

www.apse.org.uk

4.28% 4.10% 3.76% 3.36% 3.52%

14.29%

9.83% 10.31%

6.85% 6.24%

0.00%

5.00%

10.00%

15.00%

20.00%

25.00%

30.00%

35.00%

12-13 13-14 14-15 15-16 16-17

Condition of roads PI 02b principal - England/Wales

PI 02c non principal- England/Wales

PI 02b PI 02c

Page 10: Performance networks - apse

www.apse.org.uk

0.48

0.33

0.35

0.37 0.37

0.30

0.34

0.38

0.42

0.46

0.50

12-13 13-14 14-15 15-16 16-17

PI 28 Number of Cat 1 defects per Km of maintained road

Page 11: Performance networks - apse

www.apse.org.uk

80%

83%

86%

89%

92%

95%

98%

12-13 13-14 14-15 15-16 16-17

PI 39a Percentage of safety inspections completed on time (carriageways) PI 46a Percentage of safety inspections completed on time (footways)

PI 39a Average PI 46a Average

Page 12: Performance networks - apse

www.apse.org.uk

10.73%

-0.38%

-4.37%

-13.13%

-12.93%

-20.00%

-15.00%

-10.00%

-5.00%

0.00%

5.00%

10.00%

15.00%

12-13 13-14 14-15 15-16 16-17

Aver

age

% c

hang

e

PI 31 Percentage change in the number of 3rd party claims in last 3 years compared to the previous 3 years

Page 13: Performance networks - apse

www.apse.org.uk

£0

£200

£400

£600

£800

£1,000

£1,200

£1,400

12-13 13-14 14-15 15-16 16-17

PI 43 Total cost for carriageway winter maintenance treatment over entire winter period divided by the total carriageway network length

PI 50 Total cost for footway winter maintenance treatment over the entire winter period divided by the total footway net

PI 43 Average PI 50 Average

Page 14: Performance networks - apse

www.apse.org.uk

68.76%

69.82% 70.40% 71.07%

73.90%

68%

69%

70%

71%

72%

73%

74%

75%

12-13 13-14 14-15 15-16 16-17

PI 16 percentage of maintenance expenditure planned/proactive

Average Linear (Average)

Page 15: Performance networks - apse

www.apse.org.uk

Emerging changes to approaches in service management How has the budget for the highways service changed from 2016-17 to 2017-18?

Page 16: Performance networks - apse

www.apse.org.uk

To what extent will your 2017/18 budget for highways maintenance meet the need to fill potholes and resurface where necessary?

Page 17: Performance networks - apse

www.apse.org.uk

Do you currently sell your services to organisations external to the council?

Page 18: Performance networks - apse

www.apse.org.uk

Has the severe weather over the past 3 years led to any of the following (you may answer more than one)

Page 19: Performance networks - apse

www.apse.org.uk

Have you recently taken a more aggressive approach to defending claims?

Page 20: Performance networks - apse

www.apse.org.uk

When do you estimate the existing damage to roads in your council area will be repaired to an acceptable standard by?

Page 21: Performance networks - apse

www.apse.org.uk

• External Income Streams

• Asset Management

• Air Quality

• Sustainable drainage

• Collaboration with other authorities

• Town Centre Regeneration

• Charging for Specialist Knowledge

• Housing and Industrial Development sites

• Surface Dressing Road Network

• Design and Build using Section 278 and 38

Where do you see growth areas for the service over the next 12 months?

Page 22: Performance networks - apse

www.apse.org.uk

• Pothole Repairs

• Structural Highway Maintenance

• Long Term Maintenance

• Cyclic & Routine Maintenance

• Carriageway Surfacing

• Road Reconstruction

• Major Resurfacing

• Street Light Maintenance

• Winter Service

Where do you see areas where work may decrease over the next 12 months?

Page 23: Performance networks - apse

www.apse.org.uk

What do the public think?

Page 24: Performance networks - apse

www.apse.org.uk

Page 25: Performance networks - apse

www.apse.org.uk

Page 26: Performance networks - apse

www.apse.org.uk

Page 27: Performance networks - apse

www.apse.org.uk

Page 28: Performance networks - apse

www.apse.org.uk

Page 29: Performance networks - apse

www.apse.org.uk

Page 30: Performance networks - apse

Our survey said

• Roads maintenance and winter maintenance given comparatively lower satisfaction ratings but are rated high for new government spending, obviously seen as a priority

• The public have seen a decline in local services but..

• Don't fully relate that easily to central government cuts ‘Its the council’

• Public are starting to see the impact of austerity

• APSE will continue to provide intelligence on front line services

Page 31: Performance networks - apse

APSE / DMG project

• 21 English Councils

• Benchmarking between county councils and others (3 years) through DMG – Dorset CC were administering this

• APSE managing the project

• Steve Berry, DfT:

"Effective Benchmarking is a key component in any performance management framework and the Department has been following the Direct Management Group's initiative with interest. We fully support this proposed alignment with APSE's Performance Networks and believe this will ensure members will be able to demonstrate best practice in accordance with the local highways maintenance Incentive Fund self-assessment principles."

Page 32: Performance networks - apse

APSE / DMG project

Reduced set of data collection and indicators:

– Asset condition

– Maintenance costs

– Third party claims

– Defects completed within timescale

– Street lighting

– Winter maintenance

– Bridges / structures

Page 33: Performance networks - apse

What’s included in the project?

– Performance at a Glance

– PI standings

– Performance reports

– Direction of travel

– Case studies

– Infographics

Page 34: Performance networks - apse

www.apse.org.uk

Contact details

Debbie Johns, Head of Performance Networks

Email: [email protected]

Mobile: 07834 334193

Association for Public Service Excellence 2nd floor Washbrook House, Lancastrian Office Centre, Talbot Road,

Old Trafford, Manchester M32 0FP. telephone: 0161 772 1810

fax: 0161 772 1811 web:www.apse.org.uk

Page 35: Performance networks - apse

Bob Fenwick Group Leader Highways Maintenance Swansea Council

1

Page 36: Performance networks - apse

Best in Uk? • Welsh Asset

Management Project • Innovation approach by

the council • Swansea Pothole Project

2

Page 37: Performance networks - apse

Welsh Asset Management Project

Real Benefits Tools

Valuation tool kit Standardised Spreadsheets Methods of visual inspection with training

Agreed Standards

Standardised documents Safety Intervention levels

State of the Nation Report on Highways Asset

Management

3

Page 38: Performance networks - apse

Examples Asset Management Policy Statement Asset Management Plan (Standard Template) Annual Status and Options Report Asset Valuation Report Data Management Plan 5 Year Forward Works programme Performance Indicator Returns Road Maintenance Manual Agreed Method for Visual Inspection Welsh FNS All Wales Safety Intervention Levels Looking at Agreeing a national approach to the new Code of

Practice

4

Page 39: Performance networks - apse

Swansea Council Innovation

Council Innovation Officer and “Sustainable Swansea” Corporate Stuff

System thinking Blue Sky thinking Deep Ocean thinking

Listening and trying things out

Drop in session for all staff to unload Meeting to discuss the outcomes – all invited Prioritise Trying things out

5

Page 40: Performance networks - apse

Swansea Council Innovation Our “Driving Forward” Programme PATCH Safety Inspections Pot Hole initiative Notices Internal drain cameras Gulley Work schedules

Still to be looked at Street works and internal noticing Apprentice Positions Prioritisation Scoring for schemes.

6

Page 41: Performance networks - apse

Swansea’s 48 hour pot hole pledge

7

Second best roads in Wales but very poorly perceived

Head in sand or tackle Pot Hole initiative Extra Funding to tackle perception

Page 42: Performance networks - apse

Swansea’s 48 hour pot hole pledge

8

Not related to safety Explain some exceptions. Heavy marketing Social media Every report with email

address gets a response with photograph of before and after or an explanation

Work statistics published online

Page 43: Performance networks - apse

Swansea’s 48 hour pot hole pledge

9

Very Wary -Backlash 6000 first year Customer satisfaction up 30% Social Media satisfaction Compliments rather than

complaints Support from politicians Additional real work done Some preventative works A means to an end

Page 44: Performance networks - apse

Thank You

10

Take Praise were you can get it we don’t often deserve the criticism we get Public don’t understand what we do so get them on board. All the weapons available

Page 45: Performance networks - apse

Implementation of the Code of Practice for Well Managed Highway

Infrastructure

Page 46: Performance networks - apse

Introduction

Liz Kirkham • Managed Gloucestershire’s bridges 2001 - 2014

• Member of COP Steering Group

• Chair of ADEPT National Bridges Group and UK Bridges Board

• Network Manager

Page 47: Performance networks - apse

Intentions behind review

• Identify gaps and omissions

• Remove “common” threads to volume 1 (overarching)

• Electronic – not hard copy, so can be edited, and also contains links to other standards and documents

• Emphasis on risk based decision making

Page 48: Performance networks - apse
Page 49: Performance networks - apse

Implementation in Gloucestershire

Split recommendations into Themes

Linked to Self Assessment Questions where applicable

Allocated themes to members of Highway Management Team

Gap Analysis and action plans for each theme

Page 50: Performance networks - apse

Themes Policy & Strategy Framework

Network & Hierarchy

Asset Management Risk based approach

Resilience Performance/ Benchmarking

Environment/ Sustainability

Scott Tompkins Liz Kirkham Liz Kirkham Martyn Midgley Jenny Goodson Mark Darlow-Joy Kath Haworth

Self assessment Questions

Q1,6,7, 17, 18, 22 Q4, 5, 20, Q8 Q9-11 Q2, 3, 12-16, 19, 21

COP

reco

mm

enda

tion

s

1 - Use of Code 6 - Integrated network 10 – Asset Data 7 - Risk based approach 20 – Resilient Network 4 - Engage with stakeholders

32 - Carbon

2 - AM Framework 9 – Network Inventory 11 – AM Systems 8 - Information to support RBA

21 – Climate Change Adaptation

5 - Consistency with neighbours

33 – Sustainability with character

3 - AM Policy & Strategy 12 – Network Hierarchy 13 – Whole Life / designing for maintenance

14 – risk management 22 – Drainage Maintenance

26 – Performance Management Framework

34 – Heritage Assets

15 – Competencies & Training

17 – Condition surveys 28 – Financial Plans 16 - Inspections 23 – Civil Emergencies & Severe Weather plans

27 – Performance Monitoring

35 – Environmental Impact, Nature Conservation and Biodiversity

30 – Cross Asset Priorities

29 – Lifecycle Plans 18 – Management system and claims

24 – Communication (plans for emergencies)

36 – Minimising Clutter

31 – Works Programming

19 – Defect repair 25 – Learning from Events

Section headings in asset specific parts of COP

Legal Framework Condition & Investigatory Levels

Asset Management Information

Inspection, Assessment & recording

Winter Service Service Agreements

Rele

vant

to

Highways Highways Highways Highways Highways Street lighting

Structures Structures Structures Structures

Street Lighting Street Lighting Street Lighting Street Lighting

Section headings in asset specific parts of COP

Programming & Priorities

Rele

vant

to

Abnormal Loads Highways Road/Rail incursion Critical Infrastructure

Structures

Street Lighting

Page 51: Performance networks - apse
Page 52: Performance networks - apse

Governance

• Political process to adopt new Code

• Key decision (affecting all electoral divisions)

• Amendments to existing policy statement

Gloucestershire County Council will manage the local highway asset in line with the Highways Asset Management Framework and other guidance or policies such as the Code of Practice for Well Managed Highway Infrastructure

Page 53: Performance networks - apse

RECOMMENDATION 6 – AN INTEGRATED NETWORK

The highway network should be considered as an integrated set of assets when developing highway infrastructure policies.

GCC Approach

• Through Asset Management Group

New Code Recommendations

Page 54: Performance networks - apse

RECOMMENDATION 7 – RISK BASED APPROACH

A risk based approach should be adopted for all aspects of highway infrastructure maintenance, including setting levels of service, inspections, responses, resilience, priorities and programmes.

New Code Recommendations

Page 55: Performance networks - apse

GCC Approach - Risk

6 different recommendations

Asset/data driven

Policies and Levels of Service

Inspections, maintenance and claims management

Page 56: Performance networks - apse

GCC Approach

Changing from reliance on specific guidance to a risk-based approach is not a huge step for Gloucestershire

Higher Risk Appetite than many authorities and moved away from the “prescribed” Inspection regime to a risk based approach.

• Structures inspections 2003

• Safety inspections 2006

Page 57: Performance networks - apse

Asset by Asset approach

We are in the process of reviewing on an asset by asset approach:

• What do we know

• What are the risks

• How do we maintain

Page 58: Performance networks - apse

Consider for each asset

Why do we maintain it? How important is it?

How many people use it?

If not maintained, is the risk significant

What data do we have?

What activities need to be carried out to manage the risks

What annual/cyclical works are carried out?

Is there targeted maintenance, or just reactive?

What inspections are carried out?

How is the work/programme prioritised?

How is this reported?

What comms do we carry out?

Page 59: Performance networks - apse

Evidence Check list

Generated through CIPFA/HAMP workshops

• Formally approved policy

• How service levels are based on local needs/priorities

• The approach is risk based, and risk managed

• Who takes the (risk based) decisions

• Skills and competencies

• Services are monitored and recorded

Page 60: Performance networks - apse

RECOMMENDATION 12 – NETWORK HIERARCHY

A network hierarchy, or a series of related hierarchies, should be defined which include all elements of the highway network, including carriageways, footways, cycle routes, structures, lighting and rights of way. The hierarchy should take into account current and expected use, resilience, and local economic and social factors such as industry, schools, hospitals and similar, as well as the desirability of continuity and of a consistent approach for walking and cycling.

New Code Recommendations

Page 61: Performance networks - apse

Carriageway Hierarchy

• Developed by South West Asset Management Group

• Very similar to old COP hierarchy but with more “lower” hierarchy bands

• 11 bands in total

• Adopted by most authorities in South West

Page 62: Performance networks - apse

Safety Inspection Policy

• No changes to intervention levels

• Urgent/non-urgent rather than Category 1/Category 2

Feature Description Inspection Frequency Roads Hierarchy 2-4

Hierarchy 5-6 Hierarchy 7-11

1 month 3 month

12 month

Footways Town Centre Secondary

Link Local Access

1 month 3 month 6 month 12 month

Cycle Cw/Fw Remote Cycle

As cw/fw 6 months

1 year

Page 63: Performance networks - apse

Implementation for Structures

Previous Code Recommendations

Located through the document, with 1 or 2 for each chapter.

• Employ suitably qualified and experienced personnel

• Follow asset management principals

• Have an inspection regime

• Assess/review/maintain your structures

Rec 15 Rec 2 & 3

Rec 16 & 17

Rec 19 & 31

Page 64: Performance networks - apse

Structures Risk Based Inspection Policy General inspections are carried out every two years, in line with

DMRB standards. Gloucestershire has taken a risk based approach to determining

the “level” and interval of any other inspections.

Page 65: Performance networks - apse

Structures Hierarchy

Page 66: Performance networks - apse

RECOMMENDATION 15 – COMPETENCIES & TRAINING

The appropriate competencies for all staff should be identified. Training should be provided where necessary for directly employed staff, and contractors should ensure that they provide evidence of the appropriate competencies for their staff.

New Code Recommendations

Page 67: Performance networks - apse

Competence & Training

Gloucestershire have a Competence framework for all staff.

Asset Management Certification.

BICs Qualification encouraged (will be required in next contract)

Page 68: Performance networks - apse

RECOMMENDATION 19 – DEFECT REPAIR

A risk based defect repair regime should be developed and implemented for all highway assets.

RECOMMENDATION 31 – WORKS PROGRAMMING

A prioritised forward works programme for a rolling period of 3 to 5 years should be developed and updated regularly.

New Code Recommendations

Page 69: Performance networks - apse

Risk Based Prioritisation & Value Management review and prioritise works as a team through value management processes and /or workshops

This is known in Gloucestershire as ‘Structure Top Trumps’ Prioritisation criteria in TAMP • Safety & Functionality • Benefits & dis-benefits • Socio-economic and environmental

Page 70: Performance networks - apse

Implementation for Structures

Part C – Structures

• Legal Framework

• Asset Management Information

• Asset Condition and Investigatory Levels

• Inspection, Assessment and Recording

• Programming and Priorities

• “should …”

Page 71: Performance networks - apse

Gaps • Basic inventory data for all retaining walls (Rec.9)

• Increased liaison with highway safety inspectors; (C.5.2.8)

• The need to undertake inspections after extreme events (C5.2.18)

• Improvements to GCC Scour assessments (C.4.3.4)

• Formalised RA’s for substandard structures (C5.10.2)

• Review of structural review processes to ensure compliance (C.5.6.3)

• Collated list of processes - Maintenance Manual

• “Fully Functioning” Bridge Management System

Page 72: Performance networks - apse

To facilitate the Asset Management Aspects of a risk based approach it is essential to have • Good data • Easily accessibly and readily available • The ability to prioritise and manage works In GCC we have questioned whether our existing system of an non-bespoke structures system and excel spreadsheets is really adequate in 2018.

Procurement exercise underway to allow us to achieve • Asset valuation • Performance data • Deterioration modelling & life cycle planning

Page 73: Performance networks - apse

Next Steps for GCC Structures

• Procurement of ‘Best of Breed’ BMS

• Review processes

• Create Structures Maintenance Manual

• Revision of Inspection policy based on hierarchy

• Identify method for identifying/locating highway retaining walls

Page 74: Performance networks - apse

Next steps for GCC Highways

• Complete Governance processes

• Complete review of risks for assets and processes

Page 75: Performance networks - apse

Monitoring/Evaluating Progress

• Item on Highways Management Team Agenda

• Quarterly progress meetings

• One of our reported KPIs (number of recommendations we are compliant with)

• Barriers….

Page 76: Performance networks - apse

Questions/Discussion