Dulles Corridor Metrorail Project
PHASE 2
COST AND SCHEDULE UPDATE
AS OF MARCH 31, 2021
MAY 2021
Meeting the COVID-19 Challenge
Protecting health and safety of employees,
contractors and subcontractors
COVID-19 Update• While vaccinations increase and some guidelines ease, the Silver Line Project
team continues to abide by all current local, state and Center for Disease Control
and Prevention guidelines, including social distancing, wearing masks, hand and
surface cleaning, and limiting the size of any in-person meetings.
• The project wide effort to follow the Metropolitan Washington Airports Authority
(Airports Authority) COVID-19 protocols resulted in very few confirmed project
cases.
• The cooperation on the part of the Airports Authority, the Washington Metropolitan
Area Transit Authority (WMATA), contractors and stakeholders to telework or when
required to work on site with adherence to all protocols resulted in minimal impact
to the ongoing construction and testing effort.3
Package A
March Expenditures $ 9.4 Million
Total Expenditures $ 2.443 Billion
Total Budget $ 2.778 Billion
Total Forecast $ 2.778 Billion
Phase 2 Cost Summary
5
Phase 2 Contingency Allocation
Total Contingency $ 551.5 Million
Contingency Allocated through February
2021
$ 385.5 Million
Contingency Allocated in March 2021 $ 20.4 Million
Total Contingency Allocated through March
2021
$ 405.9 Million
Remaining Contingency $ 145.6 Million
6
March Contingency Allocation
7
Total Contingency Allocated in March 2021 $20.4 Million
Package A – Capital Rail Constructors (CRC) $0.1 Million
• Miscellaneous Changes (changes less than $100,000) $61,600
Package B – Hensel Phelps (HP) $0 Million
• Tree Clearing within Field of Views of Cameras 2 and 3 $20,800
March Contingency Allocation
8
Package M $20.3 Million
• Program Management Support Services Additional Funding thru June
2021$17,015,464
• Airports Authority’s cost allocation to the Project for 2020 $3,109,304
• Additional Funding for IBTS Government Solutions LLC Contract thru
June 3, 2021$222,791
Package A Update• The N06 Tie-in work will be completed after one final weekend shutdown, which is
now scheduled for the weekend of June 26-27, 2021, to incorporate revised
turnback logic, complete Level F testing and install the final configuration. Hitachi
has started working on turnback logic and should be complete in about five weeks.
CRC is working on responding to WMATA comments on Hazard Analyses from
B&C and Hitachi but should be completed within the week.
• CRC has completed the installation for Negative Cross Bonds (NCB). Static and
dynamic regression testing are complete everywhere except the far west end of the
project.
• For dynamic testing, a second shift of testing began May 10. This will be followed
by Level F testing for the remaining Phase 2 Automatic Train Control (ATC)
System.
9
Overall Testing Progress
Excluding NCB Regression Testing
ATC Static — 99% complete
ATC Dynamic — 87% complete (excludes Final Level F)
Traction Power — 98% complete (punchlist work remaining)
Communications — 99% complete (punchlist work remaining)
Supervisory Control and Data Acquisition (SCADA) — 95% complete
NCB Regression Testing
ATC Static — 98% complete
ATC Dynamic — 40% complete (to get to Final Level F)
SCADA — 0% complete
System Testing and Integration Update
10
System Testing and Integration Update
8/2/19
10/6/19
ATC Dynamic Testing Progress by Testing Area
Base System
NCB Regression Testing
Test Area
Base System
Area 1 Area 2 Area 3 Area 4 Area 5 Total
% Complete 85 89 82 87 100 87
Test Area
NCBs
Area 1 Area 2 Area 3 Area 4 Area 5 Total
% Complete 85 50 N/A 10 N/A 50
Level F
Testing has
not started
Package A Safety and Security Certification
a. Design Criteria Conformance Checklist – 100% Accepted
b. Construction Specification Conformance Checklist – 79% Accepted
c. Systems Integration Testing Conformance Checklist – 42% Accepted
d. Open Issue Identification Forms – 5
e. Unresolved Hazards (Safety) – 0
f. Unresolved Vulnerabilities (Security) – 0
g. Final Safety and Security Certification Report and Certificate – To be
issued at Substantial Completion when everything above is complete.
This is one of the contractual requirements for Substantial Completion.
12
Measuring 34.5 kV Transition Boxes at Transmission Power
Substation (TPSS) #12 for Code Compliance
13
Testing Emergency Trip System at TPSS #12
14
Replacing Cracked Third Rail Supports
15
Completion Items Update
Package A Items• Traction Power Surge Arrestors — Original surge arrestors were activating unpredictably and
were replaced with another surge arrestor model with a higher surge capacity. The contractor’s
root cause analysis indicates that the surge arrestors were undersized. The Airports Authority
has engaged an expert who concurs that the original arrestors were marginally sized; there has
been no evidence of excessive voltage surges. WMATA is in agreement that there is no
evidence of a system wide issue with the traction power system. CLOSED.
• Malfunctioning Uninterruptible Power Supply (UPS) Fans in TPSS, Tie Breaker Station (TBS)
and AC Rooms — Several of these fans have been running constantly at high speed and have
burned out. The manufacturer believes this is caused by not pushing a reset panel after
accessing the unit. A field test seemed to support the manufacturer’s position. Letter received
from manufacturer. CLOSED. (Same item as Package B)
17
Package A Items• Cracked Impedance Bonds — All 11 cracked bonds have been replaced by CRC. The
cracking was caused by incorrect installation of the cables which has been resolved.
WMATA has identified other imperfections of concern. An extended warranty or provision of
additional spares to close this issue is being discussed.
• Cracked Third Rail Insulators and Coverboard Brackets — The contractor has proactively
replaced insulators that were exhibiting cracks. The root cause analysis of the failure from
the contractor indicates cracks are due to over-tightening of bolts. CRC has responded to
WMATA’s comments regarding Root Cause explanation. More replacement parts are being
ordered as CRC is re-torqueing all the bolts.
18
Package A Items• Damaged Direct Fixation (DF) Track Fasteners — These have been identified on all direct
fixation tracks. The contractor claims that the damage is caused by installation issues. The
Rail Office and WMATA are engaging independent engineering firms to do assessments.
The Rail Office completed surveying all pads in the field to document locations of damage
and has sent 10 new DF Pads and 5 damaged pads to the Transportation Test Center lab in
Colorado for them to perform independent testing. The field survey did not show any
patterns that would indicate excessive movement in the structures or the rail.
• Deficient Paver Installation at Station Platforms — Systemic problems experienced with the
concrete paver system on Phase 1 station platforms have not been adequately addressed
by the contractor on Phase 2. Extensive paver joint issues have occurred allowing water to
penetrate the platform and significant efflorescent deposits are present at the platform
edges, including at the platform edge light fixtures. WMATA is considering allowing the
current system to remain in place subject to an acceptable escrow to cover future
maintenance.
19
Package B
Rail Yard Design-Build ActivitiesConstruction:
• WMATA has begun inspecting the yard facilities and buildings to develop the final
punchlist. The lists will be organized by building or rail area. Meanwhile HP
continues to work on its internal work list.
• WMATA’s Chief Mechanical Officer and staff visited the yard on April 28 to observe
overspeed testing of the train wash, turntable installation in the Service and
Inspection Building (SIB) and typical hoist operation using the hoist central control
panel. Their comments will be the subject of resolution meetings as soon as they
are received.
• HP continues to work on correcting discrepancies on the computerized yard train
control machine and reports these corrections are taking longer than anticipated.
This work must be completed before the Systems Performance Demonstration can
be accomplished.
21
Rail Yard Design-Build Activities
Systems Testing (Percentage Complete)
• Traction Power 98%
• Yard Train Control 95%
• Communications 95%
• Building Electrical 95%
• SCADA 90% (HP working on deficiencies to prepare for retesting)
• Fire – Life Safety 95%
22
Package B Safety and Security Certificationa. Design Requirements Conformance Checklist – 100%
b. Construction Specification Conformance Checklist – 43%
c. Systems Integration Testing Conformance Checklist – 10%
d. Open Issue Identification Forms – 8
e. Unresolved Hazards (Safety) – 3
f. Unresolved Vulnerabilities (Security) – 0
g. Final Safety and Security Certification Report and Certificate – To be issued at Substantial
Completion if everything above is complete. This is one of the contractual requirements for
Substantial Completion.
23
Train Wash Testing
April 28
24
Hoist
Demonstration
April 28
25
Completion Items Update
Package B Items• Precast Concrete Wall Panel Cracks at Dulles Yard Buildings — The Project Team has
developed Life Cycle maintenance estimate as first step in developing escrow estimate.
The sealer utilized requires less frequent applications than originally anticipated, resulting
in lower overall life cycle costs.
• Tight Gauge at Switches in Dulles Rail Yard — Railcars arrived in the yard the last part of
April, however the contractor is still updating the Yard Train control Machine. Until that is
operational, movement of trains through the yard is limited. Once general movement is
possible, trains will be run through all switches, which will be followed by rechecking the
gauge issue.
• Hoists and Turntables at Dulles Yard — On April 28, the WMATA Chief Mechanical Officer
and staff visited the Train Wash for overspeed testing and the SIB for HP’s
demonstrations of the turntables and hoist operation using the hoist central control
panels. Comments are pending.
27
Package B Items• Non-Compliant Crib Heaters — HP proposed and WMATA has accepted receiving longer
(72”) heaters for future retrofit through ongoing maintenance. Currently 54” crib heaters are
installed. HP is providing the longer heaters, waiting delivery. CLOSED.
• Fuel Center Deficiencies (Slab Thickness over Fuel Tanks) at the Yard — HP has provided a
Design Standard Change Proposal (DSCP). WMATA SAFE continues to have concerns over
a ‘hazard’ from the slab thickness. Engineering shows equivalent strength of provided slab
which is the tank manufacturer’s recommendation. The slab exceeds American Association
of State Highway and Transportation Officials HS 20 loading that WMATA generally accepts
elsewhere.
• Malfunctioning UPS Fans in TPSS, and AC Rooms — WMATA is reviewing information from
the Manufacturer from tests on Package A. Once accepted, Package B will apply the same
corrections. CLOSED.
28
Package B Items• HP was directed to correct track indication deficiencies in the Computerized Yard Train
Control Machine, MC Dean is working to correct but is experiencing longer than
expected times to complete rework in preparation for testing. Late May is now the
target date.
• Distance between Insulated Joints and Signals at Dulles Rail Yard — The Project Team
has surveyed actual conditions in the Yard and is preparing a White paper with findings
and recommendations. The Airports Authority is still awaiting the requested Hazard
Analyses from WMATA to better understand the Safety concerns.
• Turntable Deficiencies at Dulles Rail Yard SIB — The Airports Authority is consolidating
comments from the April 28 demonstration and will schedule resolution meetings with
HP.
• Embedded Track Deficiencies Dulles Rail Yard Maintenance Buildings — The
contractor has agreed to correct deteriorated asphalt embedment. Recheck of rail to
floor elevations found rail within tolerance. Asphalt rework to be scheduled.29
Package B Items• Non-Compliant Clearance in Elevator Machine Room at Dulles Yard — The room has
passed third party inspection from a certified elevator inspector. WMATA
independently inspected the room and provided informal comments. The Airports
Authority is working with the WMATA Project team to conduct a formal inspection with
all concerned parties to develop a resolution.
• Systems Performance Demonstration (SPD) — HP is completing a number of
prerequisites prior to initiating the SPD, including completing corrective action on the
Yard Train Control workstation. HP has been requested to schedule demonstrations of
facilities and equipment that does not require railcars in the interim.
30
Package K
Package KThe Package K Design-Build Task Order contract is required to support the closeout of
Phase 2. Package K will resolve items that are associated with the original design-build
contracts but are beyond the scope of those contracts. Certain post-construction
requests by Project Partners to meet their specific needs are being addressed. Package
K was developed to preclude delay claims for changes by the Package A and Package B
contractors. Two task order contracts were awarded on June 12, 2020, to W.M.
Schlosser Company, Inc. (Schlosser) and Balfour Beatty Construction. To maintain
competitive pricing for the Project, the two companies provide separate bids on each
individual task orders.
The following slides identify existing and planned task orders based on the source of the
request.
32
• 02 - Blast Resistant Trash Receptacles — Notice to Proceed (NTP) issued to Schlosser.
Procurement underway. Submittal comments received.
• 04 - Railings Around Piping at Ashburn Station
Water Service — NTP issued to Schlosser.
Submittals approved as noted.
Task Orders — Requested by WMATA
33
• 05 - Changes to Bookcases and Lockers — add
additional bookcases and move Americans with
Disabilities Act-compliant lockers to allow greater
wheelchair access in the station locker rooms.
NTP issued to Balfour Beatty on April 22.
Task Orders — Requested by WMATA
34
• 07 and 08 - Fiberglass Reinforced
Plastic Cable Tray Crossovers below
Station Platforms in Utility Spaces — to
replace metal access panels with plastic
ones below the platforms. NTP for Task
Order 07 - Pre-Solicitation Inspection
issued to both contractors.
• 10 - Station Platform Edge Lights — to
change the platform edge lights from
red to white to meet current WMATA
standards. Proposals received and are
under review.
Task Orders — WMATA Requested
35
• Cathode Breaker Enclosures — to provide breaker enclosures at the wayside
facilities. Under development.
• Package A and Package B Fall Protection and Ladder Modifications — to provide
additional safety provisions for maintenance personnel at certain flat roof roofs.
Request for Proposal (RFP) issued.
Task Orders — WMATA Requested
36
• 01 - Landscaping at Herndon Garage — Project
utility relocation work along Sunrise Valley Drive
delayed completion of Fairfax County’s garage site
work. The Project agreed to assume this work so
as not to create a delay claim by the County’s
contractor. Work is completed.
• Wiehle Avenue Bus Stop Removal – An original part of the Project in Phase 2. It cannot
be started until six months after WMATA begins Phase 2 revenue service to allow for
orderly changes to the WMATA and Fairfax Connector bus services.
• Sunrise Valley Drive Sidewalk at Reston Station (funded by Fairfax County) — Scope is
under development.
Task Orders — Fairfax County Requested
37
• 09 - Additional Project Signage at
Numerous Locations — to provide
additional safety signs throughout the
Project. The RFP is under final review
before issuing.
• 06 - Third Rail Coverboard and
Disconnect Switch Decals — to provide
additional location decals in the Rail Yard.
Proposals are under review.
• 13 - Public Address Speakers at the
Station Areas of Refuge — RFP issued.
Task Order — Washington Metrorail Safety
Commission Requested
38
• Dulles Airport Historical Landscaping
(originated with preliminary engineering, but full
scope was not determined before the Package
A bid) — RFP issued. Responding to bidder’s
questions.
• 12 - Dulles Airport Station Lighting for the
Pedestrian Tunnel Exit Sidewalk — to provide
lighting for the sidewalk from the Airport
Terminal Walkback Tunnel Exit to Garage 1.
RFP issued.
Task Orders — Airports Authority Requested
39
Add Video Slide Here
DULLESMETRO.COM
Dulles Rail
Description Budget Total Contract Contract
Amount Forecast Amount Total NTP Substantial
Percent
b c c/b
DULLES CORRIDOR METRORAIL PROJECT - PHASE 2
DESIGN-BUILD Package A 1,193,777,000$ 1,442,639,877$ 1,383,853,296$ 96% 8-Jul-13 7-Aug-19
DESIGN-BUILD Package G -$ 7,133,991$ 6,782,546$ 95% 22-Aug-18 7-Oct-20
DESIGN-BUILD Package P* -$ 25,099,181$ 23,509,411$ 94% 14-Jun-18 11-Jun-21
DESIGN-BUILD Package B + S 273,280,530$ 311,828,543$ 288,912,994$ 93% 18-Nov-13 23-Dec-18
PROJECT CLOSEOUT Package K -$ 11,868,163$ 185,166$ 2% 12-Jun-20 12-Jun-23
ROW 58,600,000$ 56,284,200$ 27,944,307$ 50% 8-Jul-13 30-Sep-17
WMATA 305,324,718$ 280,759,119$ 242,104,215$ 86% N/A 3-Feb-20
PRELIMINARY ENGINEERING 75,000,000$ 75,000,000$ 73,266,056$ 98% 15-Jul-09 30-Dec-13
PROJECT MANAGEMENT 320,802,137$ 422,048,286$ 396,675,664$ 94% N/A 2-Jan-19
CONTINGENCY 551,451,179$ 145,574,204$
TOTAL FOR DCMP 2,778,235,564$ 2,778,235,564$ 2,443,233,655$
*Final Completion extends to 6/12/2023 due to additional 2 years of maintenance
DULLES CORRIDOR METRORAIL PROJECT - PHASE 2
MONTHLY COST SUMMARY
As of March 31, 2021
Expenditures to Date
Dulles Rail
ATTACHMENT 2
Description Amount
in million
($)
DULLES CORRIDOR METRORAIL PROJECT - PHASE 2
Total Contingency 551.5$
Contingency Allocated through February 2021 385.5$
Expended Contingency in March 2021* 20.4$
Total Contingency Allocated through March 2021 405.9$
Remaining Contingency 145.6$
Package A (CRC) $0.1 Million
Miscellaneous Changes (changes less than $100,000) 61,600$
Package B (HP) $0 Million
Tree Clearing within Field of Views of Cameras 2 and 3 20,800$
Package M $20.3 Million
PMSS Additional Funding thru June 2021 17,015,464$
Airports Authority’s cost allocation to the Project for 2020 3,109,304$
Additional Funding for IBTS Government Solutions Contract thru June 3, 2021 222,791$
*See table below for details
DULLES CORRIDOR METRORAIL PROJECT - PHASE 2
CONTINGENCY ALLOCATION
As of March 31, 2021
Dulles Rail
ATTACHMENT 1
Airport Project No DescriptionBudget
Amount
DULLES CORRIDOR METRORAIL PROJECT - PHASE 2
DESIGN-BUILD Package A
DCMP 5401 Package A - Mainline (CRC) 1,177,777,000$
DCMP 5406 Commodity Escalation 16,000,000$
DCMP 5408 Contingency amount
DCMP 5408 Secondary mitigation amount
SUBTOTAL - DESIGN-BUILD Package A 1,193,777,000$
DESIGN-BUILD Package B+S
DCMP 5402 Package B - Yard 269,280,530$
DCMP 5402 Package S - Yard Site Preparation incl above
DCMP 5406 Commodity Escalation 4,000,000$
DCMP 5408 Contingency amount
DCMP 5408 Secondary mitigation amount
SUBTOTAL - DESIGN-BUILD Package B+S 273,280,530$
ROW
DCMP 5404 Land & Relocation 47,225,000$
DCMP 5404 Support Services 11,375,000$
DCMP 5408 Contingency
SUBTOTAL - ROW 58,600,000$
WMATA
DCMP 5405 WMATA Vehicles 205,868,200$
DCMP 5405 WMATA other costs 90,205,767$
DCMP 5405 WMATA Non Revenue Vehicles 9,250,751$
DCMP 5408 Contingency
SUBTOTAL - WMATA 305,324,718$
PRELIMINARY ENGINEERING
DCMP 5406 PRELIMINARY ENGINEERING 75,000,000$
SUBTOTAL - PRELIMINARY ENGINEERING 75,000,000$
PROJECT MANAGEMENT
DCMP 5406 MWAA Staff 34,000,000$
DCMP 5406 MWAA Allocated Cost 13,560,000$
DCMP 5406 Rent 9,200,000$
DCMP 5406 Relocation, IT, Furniture 2,700,000$
DCMP 5406 MWAA ODCs 17,060,000$
Dulles Rail
ATTACHMENT 1
Airport Project No DescriptionBudget
Amount
DCMP 5406 Insurance (OCIP) 49,082,137$
DCMP 5406 PMSS 140,000,000$
DCMP 5406 VDOT 10,000,000$
DCMP 5406 DRC Prof Svcs 2,500,000$
DCMP 5406 PSI (Special Inspections) 14,000,000$
DCMP 5406 DGS 2,000,000$
DCMP 5406 TRIP II 2,000,000$
DCMP 5406 Dept of Conservation & Recreation (DCR) 2,000,000$
DCMP 5406 MWAA Permits/Inspection 4,000,000$
DCMP 5406 Power for System Testing 16,000,000$
DCMP 5406 Historical/Archaeologic 2,700,000$
DCMP 5408 Contingency
SUBTOTAL - PROJECT MANAGEMENT 320,802,137$
CONTINGENCY
DCMP 5408 Contingency - Package A 289,067,231$
DCMP 5408 Secondary mitigation amount - Package A -$
DCMP 5408 Contingency - Package B 109,006,387$
DCMP 5408 Secondary mitigation amount - Package B -$
DCMP 5408 Contingency - ROW 5,860,000$
DCMP 5408 Contingency - WMATA 30,532,472$
DCMP 5408 Contingency Project Management 116,985,089$
SUBTOTAL - CONTINGENCY 551,451,179$
TOTAL FOR DCMP - PHASE 2 2,778,235,564$