PIP Update Aug 6 th 2012
Transcript
Page 1: PIP Update

PIP Update

Aug 6th 2012

Page 2: PIP Update

Agenda

• Summary Update– Current Activities

• Bill Pellico – • N Eddy - Linac BPMs

Page 3: PIP Update

UpdateGeneral Info• Current Work

– Booster RF cavity 5 now being refurbished (putting on tuners)– Linac Transformer – Plant visit today by EE support, still working out details of install– Booster temp transformer installed – new one in 8 – 9 months– LCW – Work Continues – looks to be on schedule– RFQ – beam tests continue – next slide– REPORT for High Power – Preparing for submission to Directorate for approval– High Power Ferrite Testing - 5KW amp test done on old ferrite – still no notable lose?– Booster Absorber – absorber on aisle and parts being machined – – Linac Modulator – Testing at 7 for DTI – Modulator – SLAC will be in on Aug 27 to discuss their work– Booster Modulators – Aug. schedule says we should see have of Mods completed?

Shutdown - comments (Fernanda, Todd, Mary)?PIP PMG August 2nd – Went well – a lot of details

– TOPIC Presenter Time Description– Introduction/Management Pellico 20 Minutes History, goals and guidelines– Linac Fernanda 20 Minutes Linac (tasks, milestones/goals)– Booster Keith 20 Minutes Booster (tasks, milestones/ goals)– RLS/Project Controls Elmie 15 Minutes RLS schedule – base line/update(s) – Budget Constraints Bob 15 Minutes Budget and targeted goals issues

Page 4: PIP Update

FY12 Budget (~84% of FY)

Look at Task funds – make sure youas managers know what the balance is!!

Page 5: PIP Update

Testing of RFQ – Schedule

•Emittance Measurements• This week•RF Bunching Measurements• Maybe end of week – or early next•Run at operational level for a week•Review Schedule•Declare Start Date

Work still needs to be done on:Vacuum TestingSecond SourceLEBT Stand mechanics – slideEinzel Lens triggingMEBT stand – not yet receivedVacuum – Argonne GasSimulations – flatness questionExtractor second supplyExtractor Safety Switch

Page 6: PIP Update

Absorber Pics

Page 7: PIP Update

Talks

• N. Eddy - Linac BPMs• D. Barak - High Power Testing

Page 8: PIP Update

8

Linac/400 MeV BPM System Status

Nathan Eddy

PIP Meeting8/8/12

Page 9: PIP Update

9

Production Board Status (6/6/12)

• Received first fully stuffed production board before shutdown for checkout

• Found error in PCB– Require remaking 80 PCBs– Delay Assembly– $5k additional cost– $10k additional cost due to parts• 10 Additional boards + Prototypes

• New PCBs in production• Assembled boards ~1 month

Page 10: PIP Update

10

Production Board Status

• PCB manufacturer had issues with first run, boards failed testing– Lost their production line manager

• They had to re-run the boards – 6 week delay• PCB boards are now complete & tested and

were all delivered to the assembly house• Expect first golden sample from assembly

house by next week

Page 11: PIP Update

11

Production Board Status Cont’d

• Plan thorough checkout of the golden sample before releasing– Will include installing in LE Linac

• Once released assembly of all boards will be complete in 4 weeks– Expect all boards delivered by mid September

• Boards will be bench tested then can be installed– Will start with LE Linac– If feasible, all boards could be beam tested in LE

Linac before installation elsewhere

Page 12: PIP Update

12

LE Linac Beam Tests

• Work underway to instrument bpms (2H, 2V) from tank 3 with new electronics– Electronics installed last week (prototype)– ACNET device conversion underway

• Will install golden sample when available• Expand to include all LE bpms which see beam

during NTF running

Page 13: PIP Update

13

Software Status• Provide average Position, Intensity, & Relative

Phase over each beam pulse for every BPM @15Hz – in ACNET via linac controls

• Have an OAC to perform setup and control– Read/Write all control registers– Synchronized waveform readback• Position, Intensity, Phase @3MHz

– Calibration control– Basic functionality tested

Page 14: PIP Update

14

400 MeV Line Software

• Current 400 MeV Line bpms use different electronics, readout, and application software

• Had several meetings to discuss options• Plan is to extend Linac Controls readout to

these bpms– Existing front-end vme processors will be used– Readout structure will be tweaked to support

existing 400 MeV BPM applications

Page 15: PIP Update

15

Plan

• Complete conversion of LE Linac bpms to new system– Network connections done– Need to provide 805MHz– Replace these boards with Production boards once

available

• Will replace the rest of the crates as Production boards become available– Driven by board checkout – May rotate them through LE section for beam checkout– Expect all new boards installed early next year