    PIPING COSTING

    Presented By

    Rajendra M. Bharate (CEO & Managing Director)

    CONCEPTS CLEARANCE COMPANY PVT. LTD., 18/B3, Bandal Complex, Near PMTDepot, Paud Road, Pune38

  • 8/11/2019 Piping Cost

    2/33

    BUSINESS PERFORMANCE PARAMETERS

    1) Minimum Cost 2) Quality 3) On time Delivery 4) ProfitsReturn On Investment ( ROI )

    5) Meeting Customer Expectation & Satisfaction 6) Competitive Advantage 7) Information (All Right Factors ) 8) BenchmarkingAdherence World Standards

  • 8/11/2019 Piping Cost

    3/33

    PARTIES INVOLVED IN PROJECT 1) Owner (Client) 2) Shareholders 3) Financer 4)

    Licensor 5) Government (Statutory) 6) EPC Contractor (Equipment Vendor) 7) Various

    Contractors 8) Consultants 9) Detailed Design & Engineering etc..

  • 8/11/2019 Piping Cost

    4/33

    PROCEDURE FOR TENDERING

    1) Advertisement @ Intention 2) Submission of PQs 3) Evaluation of PQs 4) Issue of Tender

    to Pre-qualified Bidders (Techno-Com) 5) Submission of Technical Bids 6) Evaluation ofTechnical Bids 7) Submission of Commercial Bids 8) Evaluation of Commercial Bids 9)

    Finalization of Contractor & Issue of LOI 10) Contract Agreement

  • 8/11/2019 Piping Cost

    5/33

    PRE-QUALIFICATION

    1) Company Information 2) List of Directors, Management & Organization Chart 3) List of

    Clientele 4) Types of Work Done & Same Type of Experience 5) Work CompletionCertificates 6) Details of Staff & Workforce 7) Details of Construction Equipments 8)

    Financial Capabilities from the Bankers 9) Memorandum & Articles of Association (Limited

    Co.) 10) Balance Sheet for Last 3 Years

  • 8/11/2019 Piping Cost

    6/33

    TENDER / BID / PROPOSAL / QUOTATION

    Technical Part 1) Technical Terms & Conditions with Deviations 2) Work Methods & Detail

    Technical Specifications 3) Equipment & Organizational Deployment 4) QA Plans, Planning,Control & Reporting Systems 5) Overall Schedule (Bar Chart) 6) Original Bidding

    Documents Stamped & Signed Commercial Part 1) Price Schedule (Schedule of Rates) 2)

    Commercial Terms & Conditions 3) Rates for Extra Work

  • 8/11/2019 Piping Cost

    7/33

    TYPES OF GUARANTEES

    1) EMD (Alongwith Tender) (% or Fixed Amount) 2) Advance Payment (10 %) 3) Security

    Deposit (10 %) 4) Retention Money (5%) 5) Performance Guarantee (10%)

  • 8/11/2019 Piping Cost

    8/33

    TURNKEY ASPECT ( LSTK / EPC / EPIC CONTRACTS )

    Concept to Commissioning : Single Point Responsibility 1) Project Management 2)

    Engineering 3) Procurement 4) Quality Assurance 5) Construction 6) Commissioning

  • 8/11/2019 Piping Cost

    9/33

    FEW BASIC REQUIREMENTS

    1) Types of Projects (Fertilizers, ..) 2) Types of Disciplines (Civil, ..) 3) Types of Works

    Involved (Piping, ..) 4) Types of Piping (Offsite, ..) 5) Piping Materials (CS, ) 6) PipingSchedules & Weights 7) Pipe Fittings & Valves 8) Fabrication of Pipes from Plates 9)

    Painting Works (Primer, ..) 10) Insulation Works (Hot, ..) 11) NDT Works (Radiography ..)

    12) Testing & Commissioning

  • 8/11/2019 Piping Cost

    10/33

    Inch-Mtr (IM) & Inch-Dia (ID) Inch-MtrWhen a Pipe of 1 Inch Dia having a length of 1

    Mtr is installed, it is termed as 1 Inch-Mtr. (Ex. 6 Inch Pipe, Length 5 Mtr = 6 x 5 = 30 IM)

    Inch-DiaWhen a Pipe of 1 Inch Dia Size is welded having 1 joint, it is termed as 1 Inch-

    Dia. (Ex. 10 Inch Pipe, 4 Joints = 10 x 4 = 40 ID)

  • 8/11/2019 Piping Cost

    11/33

    ManHour, ManDay & ManMonthManHourWhen 1 Worker works for 1 Hour, it is said 1 MH of work. (Ex. 2 Workers

    worked 8 Hrs = 2 x 8 = 16 MH) ManDayWhen 1 Worker works for 1 Day, it is said 1 MD

    of work (Ex. 3 Workers worked 7 Days = 3 x 7 = 21 MD) ManMonthWhen 1 Workerworks for 1 Mth, it is said 1 MM of work (Ex. 8 Workers worked for 5 Mths = 8 x 5 = 40

    MM)

  • 8/11/2019 Piping Cost

    12/33

    Piping Rates Quotation Basis

    1) Per Mtr 2) Per Inch-Mtr 3) Per Inch-Dia 4) Per MT 5) Lumpsum

  • 8/11/2019 Piping Cost

    13/33

    Piping Welding Productivity Normal Figures as per the Average working of any Company,

    certain Norms are as belowa) Shop Floor50 - 60 ID / Day / Welder (Marking, Cutting,

    Grinding, Tacking etc..) b) Erection at Site25 - 30 ID / Day / Welder (Laying, Fit-up,

    Welding, Testing etc..)

  • 8/11/2019 Piping Cost

    14/33

    Piping Fabrication from Plates

    Normally, above 30 Inch Size Pipes are Prefabricated out of Plates by Rolling & Welding.

    Plate Bending Machine is very much important aspect in this Fabrication. It is Specified asThk (mm) x Width (Mtr)

  • 8/11/2019 Piping Cost

    15/33

    Related Piping Works

    Pipe Supports Fabrication & Erection Mitres Fabrication (Tee, Reducer, Elbow ..) Insulation

    (Hot & Cold) Sand Blasting (SA 2 ) Painting (Primer, Intermediate, Final) Hydro Testing

    Chemical Cleaning etc..

  • 8/11/2019 Piping Cost

    16/33

    Various NDT Requirements

    Visual Inspection Radiography (X Ray, Gamma Ray) DP / MP Testing Vacuum Box Testing

    Ultrasonic testing (UT) etc..

  • 8/11/2019 Piping Cost

    17/33

    Various Piping Materials CS API 5L, A 106 Gr B (IBR, Non IBR) LTCS

    A333 Gr 6 ASA335 Gr P1, P11, P22 SS304, 304 L, 316, 316 L, 347 H GIIS 1239

    HDPE / Plastic C.I. / Cement Pipes Cement Lined

  • 8/11/2019 Piping Cost

    18/33

    PIPING ERECTION TYPES

    a) Unit PipingInvolved within the plant mostly coming on Equipments & has more number

    of welding joints is referred as Unit Piping. b) Offsite / Rack / Yard Piping Involved withinthe plant mostly on Racks & across the plant, but has less number of welding joints is

    referred as Offsite Piping. c) Cross country PipingOut of plant mostly coming across the

    cities & has naturally less number of welding joints is referred as Cross-country Piping. (Oil,

    Gas, Water) d) Under Ground PipingInvolved under the ground / buried may be within or

    outside the plant & has less number of welding joints is referred as Underground Piping

  • 8/11/2019 Piping Cost

    19/33

    Ratio of Inch-Mtr to Inch-Dia (Appr.) Unit Piping 1.5 to 2.0 Offsite / Rack / Yard Piping

    3.5 to 4.0 Cross-Country Piping10.0 to 12.0 Under-Ground Piping4.0 to 6.0

  • 8/11/2019 Piping Cost

    20/33

    IM & ID Calculations from Isometrics Piping Material wise Grouping Sizewize Grouping

    Number of Fittings Valves (Welded / Bolted)

  • 8/11/2019 Piping Cost

    21/33

    Piping Gangs a) Piping PrefabricationPipe Fabricator, Gas Cutter, Tack Welder, Grinder,

    Helper b) Piping ErectionPipe Fitter, Tack Welder, Rigger, Helper c) Piping Welding

    Qualified Welder, Rigger, Helper

  • 8/11/2019 Piping Cost

    22/33

    Weighted Inch-DiaPiping involves various types of Schedules. To estimate Man-hours, Consumables etc.. for

    each Schedule, it is really a tough task. Hence, all welding Inch-Dia are converted to a 40

    Schedule as a base. On this basis costing is done, which becomes easier. This is calledWeighed Inch-Dia.

    Example

    Size 6 Dia 6 Dia Sch 40 120 Thk Actual ID 6 mm 100D 18 mm 100D Wighted ID

    100D 300D

  • 8/11/2019 Piping Cost

    23/33

    Material wise Piping Consumables (Sch 40 as a base) (Rs / Inch-Dia) C.S. 30

    CSLT35 AS80 SS125 G.I.10 PVC / HDPE5

  • 8/11/2019 Piping Cost

    24/33

    Material wise Piping Rates (Only Factors) (Considering CS as a base) C.S. 1.00

    CSLT1.25 AS2.50 SS3.50 G.I.0.60 PVC / HDPE0.40

  • 8/11/2019 Piping Cost

    25/33

    Direct Cost Direct Labor Direct Supervision Consumables R & M of Tools / Tackles &

    Vehicles Rental Charges of Equipments Power & Water consumption

  • 8/11/2019 Piping Cost

    26/33

    Indirect Cost Administrative Staff Indirect Labor Accommodation Tools / Tackles &

    Vehicles Depreciation Insurance Preparatory Expenses Travel Bank Guarantees General

    Expenses Guarantee Obligation

  • 8/11/2019 Piping Cost

    27/33

    Total Price Direct Expenses + Indirect Expenses + Material Supplies + Subcontracting

    Charges + Taxes & Duties + Agents Commission + Overheads + Profits

  • 8/11/2019 Piping Cost

    28/33

    Section A ( Fill in the Blanks) ( 5 Marks ) 1) 6 Inch Size pipe having 15 Mtr length laid on a

    rack will have how many total InchMtr of work -2) 12 Inch size pipe 5 Joints to welded will

    be having total -------- Inch dia of work. 3) For Unit piping installed to be in Plant will have

    Inh-mtr to Inch-dia ratio approximately -----4) Pipe Fabrication from Plates is done at sitenormally above ------- Inch Size Pipe. 5) Fabrication of Larger diameter Piping Fittings like

    Tees, Elbow, Mitre, Reducer etc.. is done on basis of Per -- rate. (Please mention unit)

  • 8/11/2019 Piping Cost

    29/33

    Section B ( State True or False ) ( 5 Marks ) 1) 6 Inch Sch 40 CS piping of 2000 Mtr is to be

    erected as Offsite Piping & the same quantity is to be erected as Unit Piping in one Refinery

    Plant. Then Offsite piping will have Less number of joints than Unit piping. 2) SS rate will be

    More than CS of the same schedule. 3) Various Schedules of Piping Inch-dia work isconverted to single unit of inch-dia of work for easy calculation purpose. This concept is

    called Weighted Inch-dia. 4) One welder gang in Erection Site will give an average of 25-

    30 ID Productivity in a working shift of 8 hours. 5) The Piping, which is involved across

    cities & has less number of welding joints, is referred Cross-country Piping

  • 8/11/2019 Piping Cost

    30/33

    Section C ( Write Answers in Short ) ( 5 Marks ) 1) 5 Welders work for one daily shift of 8

    hours per day for 10 days. Calculate total man-hours worked by them. 2) Total work done on

    one piping job was of 5,200 Manhours. Assuming one ManMonth (MM) of 208 Manhours,

    find total ManMonths spent on piping job. 3) One piping project has got total workersstrength of 100 during its peak period. Find out the total Direct Supervision strength

    (Engineers & Supervisors) as per the normal experience of few standard norms. 4) Write the

    Elements of Direct Cost. 5) Write the Elements of Indirect Cost.

  • 8/11/2019 Piping Cost

    31/33

    Section D ( Full Descriptive Question ) ( 10 Marks ) Shriniwas Constructions Limited,

    Lucknow (UP) In one of the Fertilizer Plant near Shahajanpur (UP) some Piping Work is to

    be done. Quantity is finalized by the Petroleum Company Design department & handed over

    to Contracts Section for Estimation to find out the Total Cost involved. They floated theTender & ultimately Shriniwas Construction Limited, Lucknow (UP) was Selected as a

    Final Contractor to Award the Contract being the Lowest Tender.

  • 8/11/2019 Piping Cost

    32/33

    Question1) Estimate the Total Cost in Rupees, which will be required to carry out the

    work, as the Contracts Department has to get Top Management Approval. 2) Shriniwas

    Construction Ltd., Lucknow has offered 10 % discount on Total Pricing. Hence, also

    calculate the Discount & Final Tender Price in Rupees Separately to inform to the TopManagement.

  • 8/11/2019 Piping Cost

    33/33

    Tender for Ammonia Fertilizer, Shahajanpur (UP)Sr 1 2 3 4 5 6 7 8 9 Item Piping Laying Piping Welding Pipe Support Insulation Painting

    Extra Labor Work Radiography (10%) Commissioning Labor 25 T Crane Supply Unit IM ID

    MT M2 M2 Mhrs --Mhrs Days Ltrs Qty 3,000 2,000 10 50 100 200 ? 100 5 10 Rate 50 1002,500 100 50 75 50 50 2000 200 Amount