+ All Categories
Home > Documents > PMP Forum - Template

PMP Forum - Template

Date post: 20-Dec-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
232
1
Transcript

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45

46

47

48

49

50

51

50

51

52

53

54

Can you read the question?

LCS International, Inc.

PMP Review

Chapter 1

What is a Project?

Presented by

David J. Lanners, MBA, PMP

These slides are intended to be used only in settings where each

viewer has an original copy of the Sybex PMP Study Guide book.

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 2

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

What Is a Project?

• Is It a Project?

• What Is Project Management?

• Defining Skills Every Good

Project Manager Needs

• Understanding Organizational Structures

• Understanding Project Life Cycles and

Project Management Processes

• The Project Management Knowledge Areas

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 3

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

What Is a Project?

• Projects versus Operations

• Stakeholders

• Project Characteristics

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 4

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Project Stakeholders

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 5

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Is It a Project?

• Projects are unique.

• Projects are temporary in nature and have

a definite beginning and ending date.

• Projects are completed when the project

goals are achieved.

• A successful project is one that meets or

exceeds the expectations of stakeholders.

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 6

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

What Is a Project?

• Is It a Project?

• What Is Project Management?

• Defining Skills Every Good

Project Manager Needs

• Understanding Organizational Structures

• Understanding Project Life Cycles and

Project Management Processes

• The Project Management Knowledge Areas

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 7

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

What Is Project Management?

• Programs

• Groups of related projects that benefit from

being managed in a coordinated way.

• Portfolios

• Collections of programs and projects that meet

a specific business goal or objective.

• Project Management Offices

• Also called Project Offices or Program Offices

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 8

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

What Is a Project?

• Is It a Project?

• What Is Project Management?

• Defining Skills Every Good

Project Manager Needs

• Understanding Organizational Structures

• Understanding Project Life Cycles and

Project Management Processes

• The Project Management Knowledge Areas

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 9

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Defining Skills Every Good

Project Manager Needs

• Communication

• Organization and Planning

• Budgeting

• Conflict Management

• Negotiation and Influencing

• Leadership

• Team Building and Motivating

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 10

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

What Is a Project?

• Is It a Project?

• What Is Project Management?

• Defining Skills Every Good

Project Manager Needs

• Understanding Organizational Structures

• Understanding Project Life Cycles and

Project Management Processes

• The Project Management Knowledge Areas

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 11

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Understanding Organizational

Structures

• Functional Organizations

• Projectized Organizations

• Matrix Organizations

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 12

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Functional Org Chart

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 13

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Functional Organizations

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 14

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Projectized Org Chart

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 15

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Projectized Organizations

• Project managers have ultimate authority over the project.

• The focus of the organization is the project.

• The organization’s resources are focused on projects and project work.

• Team members are collocated.

• Loyalties are formed to the project, not to a functional manager.

• Project teams are dissolved at conclusion of the project.

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 16

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Strong Matrix Org Chart

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 17

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Weak Matrix Org Chart

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 18

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Balanced Matrix Org Chart

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 19

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Comparing Matrix Structures

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 20

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

What Is a Project?

• Is It a Project?

• What Is Project Management?

• Defining Skills Every Good

Project Manager Needs

• Understanding Organizational Structures

• Understanding Project Life Cycles and

Project Management Processes

• The Project Management Knowledge Areas

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 21

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Understanding Project Life

Cycles and Project Management

Processes

• Project Life Cycles and Phases

• A series of handoffs or technical transfers

• Phases have specific deliverables

• Project Management Process Groups • Initiating

• Planning

• Executing

• Monitoring & Controlling

• Closing

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 22

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Characteristics of the Initiating

and Planning Processes

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 23

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Characteristics of the Monitoring &

Controlling and Closing Processes

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 24

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Project Management

Process Groups

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 25

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Process Interactions

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 26

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

What Is a Project?

• Is It a Project?

• What Is Project Management?

• Defining Skills Every Good

Project Manager Needs

• Understanding Organizational Structures

• Understanding Project Life Cycles and

Project Management Processes

• The Project Management Knowledge Areas

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 27

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

The Project Management

Knowledge Areas

• Integration

• Scope

• Time

• Cost

• Quality

• Human Resources

• Communications

• Risk

• Procurement

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 1 - Slide 28

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Knowledge Area Process Group Map

LCS International, Inc.

PMP Review

Chapter 2

Creating the Project Charter and

Preliminary Scope Statement Presented by

David J. Lanners, MBA, PMP

These slides are intended to be used only in settings where each

viewer has an original copy of the Sybex PMP Study Guide book.

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 2 - Slide 2

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Initiating the Project

• How Projects Come About

• Kicking Off the Project Charter

• Using Tools & Techniques for

Charter Development

• Formalizing and Publishing the

Project Charter

• Developing a Preliminary Project

Scope Statement

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 2 - Slide 3

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

How Projects Come About

• Needs and Demands

• Market demand

• Business need

• Customer request

• Technological Advance

• Legal requirement

• Social need

• Feasibility Studies

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 2 - Slide 4

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Using Project Selection Methods

• Selecting and Prioritizing Projects • Mathematical Models

• Benefit Measurement Methods

• Cost-Benefit Analysis

• Scoring Models

• Cash Flow Analysis Techniques • Payback Period

• Discounted Cash Flows

• Net Present Value

• Internal Rate of Return

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 2 - Slide 5

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Cash Flow Analysis Techniques

• Payback Period

• Measured in time

• Discounted Cash Flows

• Future value vs. Present value

• Net Present Value

• Measured in dollars ($$$)

• Internal Rate of Return

• Measured in percentage (%)

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 2 - Slide 6

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Enterprise Environmental Factors

• Organizational culture and structure

• Governmental or industry standards

• Infrastructure

• Human resources

• Personnel administration

• Organization’s work authorization system

• Marketplace conditions

• Stakeholder risk tolerance

• Commercial databases

• Project management information systems

Develop Project Charter Develop Project Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes

initial requirements that satisfy stakeholder needs and expectations. In multi-phase projects, this process is used to validate or refine decisions

made during the previous iteration of this process. The project charter is the document that formally authorizes a project. The project charter

also provides the project manager with authority to apply resources to project activities.

4.1 Project

Management

Integration

Tools & Techniques .1 Expert judgment

Inputs .1 Project statement of work

.2 Business case

.3 Contract

.4 Enterprise environmental factors

.5 Organizational process assets

To Develop Project Management Plan

From Project Initiator or Sponsor Request

Outputs .1 Project charter

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 2 - Slide 8

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Pulling the Project Charter Together

• Purpose or justification for the project

• Business need for the project

• Business justification including ROI analysis

• High-level project description or product description

• Stakeholder, sponsor, customer requirements

• Stakeholder influences

• Involvement of other departments needed

• Constraints and Assumptions

• Summary milestone schedule (preliminary)

• Summary budget (preliminary)

• Name of the project manager and authority level

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 2 - Slide 9

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Formalizing and Publishing

the Project Charter

• Key Stakeholders

• Project Manager

• Project Sponsor

• Project Champion

• Functional Managers

• Pulling the Project Charter Together

• Project Charter Sign-off

Identify Stakeholders Identify Stakeholders is the process of identifying all people or organizations impacted by the project and documenting the relevant information

regarding their interests, involvement, and impact on project success. Project stakeholders are persons and organizations such as customers,

sponsors, the performing organization, and the public that are actively involved in the project or whose interests may be positively or negatively

affected by the execution or completion of the project. Stakeholders may also exert influence over the project and its deliverables.

10.1 Project

Communications

Management

To Plan Communications

From Develop Project Charter, Plan Procurements

Tools & Techniques .1 Stakeholder analysis

.2 Expert judgment

Inputs .1 Project charter

.2 Procurement documents

.3 Enterprise environmental factors

.4 Organizational process assets

Outputs .1 Stakeholder register

.2 Stakeholder management strategy

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 2 - Slide 11

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Project Constraints

Scope

Time Cost

“Triple Constraints” (cheaper, faster, OR better . . . rank them)

(Must be identified and documented)

LCS International, Inc.

PMP Review

Chapter 3

Developing the Project

Scope Statement Presented by

David J. Lanners, MBA, PMP

These slides are intended to be used only in settings where each

viewer has an original copy of the Sybex PMP Study Guide book.

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 3 - Slide 2

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Developing the Project

Scope Statement

• Develop Project Management Plan

• Collect Requirements

• Define Scope

• Create WBS

Develop Project Management Plan Develop Project Management Plan is the process of documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary

plans. The project management plan defines how the project is executed, monitored, controlled, and closed. The project management plan can be

summary level or detailed, and it can be composed of one or more subsidiary plans and other components. The project management plan evolves

through progressive elaboration and updates authorized through the integrated change control process until project closure.

4.2 Project

Management

Integration

To Direct and Manage Project Execution

From Develop Project Charter

Tools & Techniques .1 Expert judgment

Inputs .1 Project charter

.2 Outputs from planning processes

.3 Enterprise environmental factors

.4 Organizational process assets

Outputs .1 Project management plan

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 3 - Slide 4

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Documenting the

Project Management Plan

• Processes you’ll use to perform the project

• Degrees of execution of each of the processes selected for the project

• Tools and techniques to use from each process

• Dependencies and interactions of the processes used to manage the project

• Methods for executing the work of the project to fulfill the objectives

• Methods for monitoring and controlling changes

• Methods to perform configuration management

• Methods for determining & maintaining the validity of performance baselines

• Communication needs of the stakeholders & techniques to fulfill those needs

• Project life cycle

• Project phases for multi-phased projects

• Management reviews of issues and pending decisions

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 3 - Slide 5

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Documenting the

Project Management Plan

• Subsidiary Plans

• Project scope management plan

• Schedule management plan

• Cost management plan

• Quality management plan

• Process improvement plan

• Staffing management plan

• Communications management plan

• Risk management plan

• Procurement management plan

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 3 - Slide 6

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Documenting the

Project Management Plan

• Process components to be considered:

• Milestone list

• Resource calendar

• Schedule baseline

• Cost baseline

• Quality baseline

• Risk register

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 4 - Slide 7

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

• Develop Project Management Plan

• Collect Requirements

• Define Scope

• Create WBS

Developing the Project

Scope Statement

Collect Requirements Collect Requirements is the process of defining and documenting stakeholders’ needs to meet the project objectives. The project’s success is

directly influenced by the care taken in capturing and managing project and product requirements. Requirements include the quantified and

documented needs and expectations of the sponsor, customer, and other stakeholders. These requirements need to be elicited, analyzed, and

recorded in enough detail to be measured during project execution. Requirements become the foundation of the Work Breakdown Structure.

5.1 Project

Scope

Management

To Define Scope, Control Scope

Tools & Techniques .1 Interviews

.2 Focus groups

.3 Facilitated workshops

.4 Group creativity techniques

.5 Group decision making techniques

.6 Questionnaires and surveys

.7 Observations

.8 Prototypes

Inputs .1 Project charter

.2 Stakeholder register

From Develop Project Charter, Identify Stakeholders

Outputs .1 Requirements documentation

.2 Requirements management plan

.3 Requirements traceability matrix

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 4 - Slide 9

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

• Develop Project Management Plan

• Collect Requirements

• Define Scope

• Create WBS

Developing the Project

Scope Statement

Define Scope Define Scope is the process of developing a detailed description of the project and product. Preparation of a detailed project scope statement is

critical to project success and builds upon the major deliverables, assumptions, and constraints that were documented during project initiation.

During planning, project scope is defined and described with greater specificity as more information about the project is known. Existing risks,

assumptions, and constraints are analyzed for completeness. Additional risks, assumptions, and constraints are documented as necessary.

5.2 Project

Scope

Management

To Create WBS (Work Breakdown Structure)

From Collect Requirements

Tools & Techniques .1 Expert judgment

.2 Product analysis

.3 Alternatives identification

.4 Facilitated workshops

Inputs .1 Project charter

.2 Requirements documentation

.3 Organizational process assets

Outputs .1 Project scope statement

.2 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 3 - Slide 11

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Writing the Project

Scope Statement

• Scope Statement Components

• Project objectives

• Product scope description

• Project deliverables

• Project requirements

• Project boundaries

• Product acceptance criteria

• Project constraints

• Project assumptions

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 3 - Slide 12

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Project Objectives

• Objectives are quantifiable criteria used to

measure project success . . .

• Objectives should follow the SMART rule:

• S – Specific

• M – Measurable

• A – Achievable, Attainable or Accurate

• R – Relevant, Realistic, or Result-Oriented

• T – Time-bound, Time-limited, or Tangible

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 3 - Slide 13

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Project Constraints

• Constraints are anything that either restrict

actions or dictate actions of the team.

• Time constraints

• Budget constraints

• Quality constraints

• Schedule constraints

• Technology constraints

• Directive constraints

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 3 - Slide 14

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Documenting the Scope

Management Plan

• The process you’ll use to prepare the project

scope statement

• A process for creating the WBS

• A definition of how the deliverables will be

verified for accuracy and accepted

• A description of the process for controlling

scope change requests

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 4 - Slide 15

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

• Develop Project Management Plan

• Collect Requirements

• Define Scope

• Create WBS

Developing the Project

Scope Statement

Create WBS Create WBS (Work Breakdown Structure) is the process of subdividing the project deliverables and project work into smaller, more manageable

components. The WBS is a deliverable-oriented hierarchical decomposition of all the work to be executed by the project team to accomplish the

project objectives and create the required deliverables. Planned work is contained within the lowest-level WBS components, which are called

work packages. A work package can be scheduled, cost estimated, monitored, and controlled. The WBS serves as the basis for the activity list.

5.3 Project

Scope

Management

To Define Activities, Verify Scope

From Collect Requirements, Define Scope

Tools & Techniques .1 Decomposition

Inputs .1 Project scope statement

.2 Requirements documentation

.3 Organizational process assets

Outputs .1 WBS

.2 WBS dictionary

.3 Scope baseline

.4 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 4 - Slide 17

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Constructing the WBS

(First 2 levels)

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 4 - Slide 18

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Constructing the WBS

(First 3 levels)

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 4 - Slide 19

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Constructing the WBS

(Bottom 2 levels)

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 4 - Slide 20

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Unique WBS Identifiers

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 4 - Slide 21

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

WBS Dictionary

• Code of accounts identifier

• Statement of work

• Organization responsible for completion

• List of schedule milestones

• Contract information

• Quality requirements for the component

• Relevant technical references

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 4 - Slide 22

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Other Breakdown Structures

• Organizational Breakdown Structure (OBS)

• Bill of Materials (BOM)

• Risk Breakdown Structure (RBS)

• Resource Breakdown Structure (RBS)

LCS International, Inc.

PMP Review

Chapter 4

Creating the Project Schedule

Presented by

David J. Lanners, MBA, PMP

These slides are intended to be used only in settings where each

viewer has an original copy of the Sybex PMP Study Guide book.

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 6 - Slide 2

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Creating the Project Schedule

• Define Activities

• Sequence Activities

• Estimate Activity Resources

• Estimate Activity Durations

• Develop Schedule

Define Activities Define Activities is the process of identifying the specific actions to be performed to produce the project deliverables. The Create WBS process

identifies deliverables at the lowest level in the Work Breakdown Structure. Project work packages typically are further decomposed into smaller

components called activities that represent work necessary to complete that work package. Activities provide a basis for estimating, scheduling,

executing, and monitoring and controlling work. Implicit in the process is defining and planning activities to achieve the project’s objectives.

6.1 Project

Time

Management

To Sequence Activities , Estimate Durations

From Create WBS (Scope baseline)

Tools & Techniques .1 Decomposition

.2 Rolling wave planning

.3 Templates

.4 Expert judgment

Inputs .1 Scope baseline

.2 Enterprise environmental factors

.3 Organizational process assets

Outputs .1 Activity list

.2 Activity attributes

.3 Milestone list

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 6 - Slide 4

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Creating the Project Schedule

• Define Activities

• Sequence Activities

• Estimate Activity Resources

• Estimate Activity Durations

• Develop Schedule

Sequence Activities Sequence Activities is the process of identifying and documenting relationships among the project activities. Activities are sequenced using

logical relationships. Every activity and milestone except the first and last are connected to at least one predecessor and one successor. It may

be necessary to use lead or lag time between activities to support a realistic and achievable project schedule. Sequencing can be performed by

using project management software or by using manual or automated techniques. Most software uses Precedence Diagraming Method (PDM).

6.2 Project

Time

Management

To Develop Schedule

From Define Activities

Tools & Techniques .1 Precedence Diagramming Method (PDM)

.2 Dependency determination

.3 Applying leads and lags

.4 Schedule network templates

Inputs .1 Activity list

.2 Activity attributes

.3 Milestone list

.4 Project scope statement

.5 Organizational process assets

Outputs .1 Project schedule network diagrams

.2 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 6 - Slide 6

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Creating the Project Schedule

• Define Activities

• Sequence Activities

• Estimate Activity Resources

• Estimate Activity Durations

• Develop Schedule

Estimate Activity Resources Estimate Activity Resources is the process of estimating the type and quantities of material, people, equipment, or supplies required to perform

each activity. Among the challenges is finding out when each resource will be available. The resource estimating process is closely coordinated

with the Estimate Costs process. Activities may have dependencies between them that can affect application and use of resources. Resource

requirements may depend upon when an activity is scheduled, and estimates may vary significantly when based on different assumptions.

6.3 Project

Time

Management

To Estimate Durations, Develop Schedule

From Define Activities

Tools & Techniques .1 Expert Judgment

.2 Alternatives analysis

.3 Published estimating data

.4 Bottom-up estimating

.5 Project management software

Inputs .1 Activity list

.2 Activity attributes

.3 Resource calendars

.4 Enterprise environmental factors

.5 Organizational process assets

Outputs .1 Activity resource requirements

.2 Resource breakdown structure

.3 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 6 - Slide 8

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Creating the Project Schedule

• Define Activities

• Sequence Activities

• Estimate Activity Resources

• Estimate Activity Durations

• Develop Schedule

Estimate Activity Durations Estimate Activity Durations is the process of approximating the number of work periods needed to complete individual activities with estimated

resources. Estimating activity durations uses information on activity scope of work, required resource types, estimated resource quantities, and

recourse calendars. Inputs originate from the person or group on the project team who is most familiar with the nature of the work in the specific

activity. Activity duration estimates are progressively elaborated, and the process considers the quality and availability of input data.

6.4 Project

Time

Management

To Develop Schedule

From Define Activities, Estimate Activity Resources

Tools & Techniques .1 Expert judgment

.2 Analogous estimating

.3 Parametric estimating

.4 Three-point estimates

.5 Reserve analysis

Inputs .1 Activity list

.2 Activity attributes

.3 Activity resource requirements

.4 Resource calendars

.5 Project scope statement

.6 Enterprise environmental factors

.7 Organizational process assets

Outputs .1 Activity duration estimates

.2 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 6 - Slide 10

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Creating the Project Schedule

• Define Activities

• Sequence Activities

• Estimate Activity Resources

• Estimate Activity Durations

• Develop Schedule

Develop Schedule Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create a project

schedule. Often an iterative process, it determines planned start and finish dates for project activities and milestones. The process can require

review and revision of the duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to track

project progress. Schedule development continues throughout the project as work progresses and environmental factors change.

6.5 Project

Time

Management

To Control Schedule

From Estimate Activity Duration, Risk Management

Tools & Techniques .1 Schedule network analysis

.2 Critical path method

.3 Critical chain method

.4 Resource leveling

.5 What-if scenario analysis

.6 Applying leads and lags

.7 Schedule compression

.8 Scheduling tool

Inputs .1 Activity list

.2 Activity attributes

.3 Project schedule network diagrams

.4 Activity resource requirements

.5 Resource calendars

.6 Activity duration estimates

.7 Project scope statement

.8 Enterprise environmental factors

.9 Organizational process assets

Outputs .1 Project schedule

.2 Schedule baseline

.3 Schedule data

.4 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 6 - Slide 12

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

The Activity Sequencing Process

• Activity Sequencing Tools and Techniques

• Precedence diagramming method (PDM or AON)

• Arrow diagramming method (ADM or AOA)

• Schedule network templates

• Dependency determination

• Mandatory (Hard limitations)

• Discretionary (Soft or preferential logic)

• External

• Applying leads and lags

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 6 - Slide 13

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Precedence Diagramming Method

PDM = AON (Activity On Node)

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 6 - Slide 14

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Arrow Diagramming Method

ADM = AOA (Activity On Arrow)

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 6 - Slide 15

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Logical Relationships

• Finish to Start (FS)

• Start to Finish (SF)

• Finish to Finish (FF)

• Start to Start (SS)

LCS International, Inc.

PMP Review

Chapter 7

Planning Project Resources

Presented by

David J. Lanners, MBA, PMP

These slides are intended to be used only in settings where each

viewer has an original copy of the Sybex PMP Study Guide book.

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 7 - Slide 2

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Resource Planning and Estimating

• Plan Procurements

• Develop Human Resource Plan

• Plan Quality

Plan Procurements Plan Procurements is the process of documenting project purchasing decisions, specifying the approach, and identifying potential sellers. It

identifies project needs which can best be, or must be, met by acquiring products, services, or results from outside of the project organization

versus those project needs which can be accomplished by the project team. This process involves consideration of whether, how, what, how

much, when to acquire, and potential sellers (suppliers), particularly if the buyer wishes to exercise influence over acquisition decisions.

12.1 Project

Procurement

Management

To Conduct Procurements

From Collect Requirements, Identify Risks, etc.

Tools & Techniques .1 Make-or-buy analysis

.2 Expert judgment

.3 Contract types

Inputs .1 Scope baseline

.2 Requirements documentation

.3 Teaming agreements

.4 Risk register

.5 Risk-related contract decisions

.6 Activity resource requirements

.7 Project schedule

.8 Activity cost estimates

.9 Cost performance baseline

.10 Enterprise environmental factors

.11 Organizational process assets

Outputs .1 Procurement management plan

.2 Procurement statements of work

.3 Make-or-buy decisions

.4 Procurement documents

.5 Source selection criteria

.6 Change requests

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 7 - Slide 4

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Resource Planning and Estimating

• Plan Procurements

• Develop Human Resource Plan

• Plan Quality

Develop Human Resource Plan Develop Human Resource Plan is the process of identifying project roles, responsibilities, required skills and reporting relationships, and creating

a staffing management plan. Human resource planning is used to determine and identify human resources with the necessary skills required for

project success. The human resource plan documents project roles and responsibilities, project organization charts, and a staffing management

plan with a timetable for staff acquisition and release. Consideration should be given to the availability of, and competition for, scarce resources.

9.1 Project

Human Resource

Management

To Develop Project Management Plan

From Estimate Activity Resources

Tools & Techniques .1 Organization charts and position descriptions

.2 Networking

.3 Organizational theory

Inputs .1 Activity resource requirements

.2 Enterprise environmental factors

.3 Organizational process assets

Outputs .1 Human resource plan

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 7 - Slide 6

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Human Resource Planning

• Key Environmental Factors • Organizational factors

• Technical factors

• Interpersonal factors

• Location and logistics

• Political factors

• Organization structures (constraints)

• Collective bargaining agreements

• Economic conditions

• Organizational Process Assets

• Project Management Plan

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 7 - Slide 7

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Human Resource Planning

• Human Resource Planning Tools & Techniques

• Organization Charts and Position Descriptions

• Hierarchical Charts

• Matrix-Based Charts (RAM or RACI Charts)

• R = Responsible

• A = Accountable

• C = Consulted

• I = Informed (as needed)

• Text-Oriented Formats

• Networking

• Organizational Theory

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 7 - Slide 8

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Responsibility Assignment Matrix

(RAM)

Sample RACI Chart

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 7 - Slide 9

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Human Resource Planning

• Roles and Responsibilities

• Role = accountability

• Authority = legal power

• Responsibility = work to be done

• Competency = skills & abilities

• Staffing Management Plan

• Timetable (Histograms)

• Release criteria

• Training needs

• Recognition and rewards

• Compliance and Safety

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 7 - Slide 10

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Resource Histogram

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 7 - Slide 11

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Resource Planning and Estimating

• Plan Procurements

• Develop Human Resource Plan

• Plan Quality

Plan Quality Plan Quality is the process of identifying quality requirements and/or standards for the project and deliverables and documenting how the project

will demonstrate compliance. Quality planning should be performed in parallel with the other project planning processes. For example, proposed

changes in the product to meet identified quality standards may require cost or schedule adjustments and a detailed risk analysis of the impact to

plans. Quality should be planned, designed, and built into the final product or service - not inspected into it.

8.1 Project

Quality

Management

To Perform Quality Assurance & Control

From Create WBS, Identify Stakeholders

Tools & Techniques .1 Cost-benefit analysis

.2 Cost of quality

.3 Control charts

.4 Benchmarking

.5 Design of experiments

.6 Statistical sampling

.7 Flowcharting

.8 Proprietary quality management methodologies

.9 Additional quality planning tools

Inputs .1 Scope baseline

.2 Stakeholder register

.3 Cost performance baseline

.4 Schedule baseline

.5 Risk register

.6 Enterprise environmental factors

.7 Organizational process assets

Outputs .1 Quality management plan

.2 Quality metrics

.3 Quality checklists

.4 Process improvement plan

.5 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 7 - Slide 13

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Cost of Quality

• Prevention costs (Training)

• Appraisal costs (Inspection)

• Failure costs (Returns)

• Internal failure

• External failure

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 7- Slide 14

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Quality Gurus & Concepts

• Philip B. Crosby (Zero Defects)

• Joseph M Juran (Fitness for Use)

• W. Edwards Deming (85% Mgmt Problem)

• Kaizen (Continuous Improvement)

• TQM (Quality must be managed in)

• Six Sigma (3.4 defects per million)

LCS International, Inc.

PMP Review

Chapter 8

Developing the Project Team

Presented by

David J. Lanners, MBA, PMP

These slides are intended to be used only in settings where each

viewer has an original copy of the Sybex PMP Study Guide book.

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 8 - Slide 2

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Developing the Project Team

• Directing and Managing Project Execution

• Acquiring the Project Team

• Developing the Project Team

• Managing the Project Team

Direct and Manage Project Execution Direct and Manage Project Execution is the process of performing all of the work defined in the project management plan to achieve the project’s

objectives as defined in the project’s scope statement. The project manager acquires and manages team members, and directs use of resources

including materials, tools, equipment, and facilities. The activities generate project data for tracking cost, schedule, quality, progress, and status

to facilitate forecasting. The process generates change requests, adapts to approved changes, and implements approved responses to risks.

4.3 Project

Management

Integration

To Monitor and Control Project Work

From Develop Project Management Plan

Tools & Techniques .1 Expert judgment

.2 Project management information system

Inputs .1 Project management plan

.2 Approved change requests

.3 Enterprise environmental factors

.4 Organizational process assets

Outputs .1 Deliverables

.2 Work performance information

.3 Change requests

.4 Project management plan updates

.5 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 8 - Slide 4

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Work Performance Information

• Schedule status and progress

• Status of deliverable completion

• Progress and status of schedule activities

• Adherence to quality standards

• Status of costs (authorized and incurred)

• Schedule activity completion estimates

• Schedule activities percent complete

• Lessons learned

• Resource consumption and utilization

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 8 - Slide 5

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Developing the Project Team

• Directing and Managing Project Execution

• Acquiring the Project Team

• Developing the Project Team

• Managing the Project Team

Acquire Project Team Acquire Project Team is the process of confirming human resource availability and obtaining teams necessary to complete project assignments.

The project management team may or may not have direct control over team member selection because of collective bargaining agreements, use

of subcontractor personnel, matrix project environments, internal or external reporting relationships or other reasons. The project manager or

project management team should effectively negotiate and influence others who are in a position to provide the required human resources.

9.2 Project

Human Resource

Management

To Develop and Manage Project Team

From Develop Human Resource Plan

Tools & Techniques .1 Pre-assignment

.2 Negotiation

.3 Acquisition

.4 Virtual teams

Inputs .1 Project management plan

.2 Enterprise environmental factors

.3 Organizational process assets

Outputs .1 Project staff assignments

.2 Resource calendars

.3 Project management plan updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 8 - Slide 7

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Developing the Project Team

• Directing and Managing Project Execution

• Acquiring the Project Team

• Developing the Project Team

• Managing the Project Team

Develop Project Team Develop Project Team is the process of improving team competencies, team interaction, and the project team’s environment to enhance project

performance. Project managers should acquire skills to identify, build, maintain, motivate, lead, and inspire project teams to achieve high team

performance and to meet project objectives. Teamwork is a critical factor for project success, and developing effective project teams is one of

the primary responsibilities of the project manager. Project managers should create an environment that facilitates teamwork.

9.3 Project

Human Resource

Management

To Manage Project Team

From Acquire Project Team

Tools & Techniques .1 Interpersonal skills

.2 Training

.3 Team-building activities

.4 Ground rules

.5 Co-location

.6 Recognition and rewards

Inputs .1 Project staff assignments

.2 Project management plan

.3 Resource calendars

Outputs .1 Team performance assessments

.2 Enterprise environmental factors updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 8 - Slide 9

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Develop the Project Team

• Team-building Activities

• Forming

• Storming

• Norming

• Performing

• Effective Team Characteristics

• Better conflict resolution

• Commitment to the project, team, and PM

• High job satisfaction

• Enhanced communications

• A sense of belonging and purpose

• A successful project

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 8 - Slide 10

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Developing the Project Team

• Negatives to watch out for

• Lack of motivation or “don’t care” attitudes

• Project work that isn’t satisfying

• Status meetings that turn into whining sessions

• Poor communication

• Lack of respect and lack of trust for the project

manager

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 8 - Slide 11

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Developing the Project Team

• Directing and Managing Project Execution

• Acquiring the Project Team

• Developing the Project Team

• Managing the Project Team

Manage Project Team Manage Project Team is the process of tracking team member performance, providing feedback, resolving issues, and managing changes to

optimize project performance. The project management team observes team behavior, manages conflict, resolves issues, and appraises team

member performance. Managing the project team requires a variety of management skills for fostering teamwork and integrating the efforts of

team members to create high-performance teams. Project managers should provide challenging assignments and recognize top performers.

9.4 Project

Human Resource

Management

To Perform Integrated Change Control

From Acquire & Develop Project Team

Tools & Techniques .1 Observation and conversation

.2 Project performance appraisals

.3 Conflict management

.4 Issue log

.5 Interpersonal skills

Inputs .1 Project staff assignments

.2 Project management plan

.3 Team performance assessments

.4 Performance reports

.5 Organizational process assets

Outputs .1 Enterprise environmental factors updates

.2 Organization process assets updates

.3 Change requests

.4 Project management plan updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 8 - Slide 13

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Motivational Theories

• Maslow’s Hierarchy of Needs

• Self-actualization (performing at peak potential)

• Self-esteem needs (accomplishment self-respect)

• Social needs (acceptance, belonging, friendship)

• Safety and security needs (physical welfare)

• Basic physical needs (food, clothing, shelter)

• Herzberg’s Hygiene (Two-factor) Theory

• Hygiene addresses dissatisfaction (retention)

• Motivation addresses satisfaction (performance)

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 8 - Slide 14

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Motivational Theories

• Expectancy Theory

• Probability of success

• Likelihood of reward for success

• Desirability of the reward

• “Self-fulfilling expectations”

• Achievement Theory

• Achievement

• Power

• Affiliation

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 8 - Slide 15

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Motivational Theories

• Leadership vs. Management

• Leadership imparts vision and inspiration

• Management maintains momentum

• McGregor’s Theory X and Theory Y

• Theory X managers are like dictators

• Theory Y managers are like coaches

• Contingency Theory

• Combines Theory Y and Hygiene Theory

• Professionals are motivated by competency

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 8 - Slide 16

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Motivational Theories

• Types of Power

• Punishment Power

• Expert Power

• Legitimate Power

• Referent Power

• Conflict Resolution

Forcing, Collaboration, Confrontation,

Withdrawal, Compromise, Smoothing

LCS International, Inc.

PMP Review

Chapter 9

Conducting Procurements

and Sharing Information Presented by

David J. Lanners, MBA, PMP

These slides are intended to be used only in settings where each

viewer has an original copy of the Sybex PMP Study Guide book.

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 9 - Slide 2

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Procurements and Sharing Info

• Conduct Procurements

• Perform Quality Assurance

• Distribute Information

• Managing Stakeholder Expectations

Conduct Procurements Conduct Procurements is the process of obtaining seller (supplier) responses, selecting a seller, and awarding a contract. In this process, the

team will receive bids or proposals and will apply previously defined selection criteria to select one or more sellers who are qualified to perform

the work and acceptable as a seller. On major procurement items, the overall process of requesting responses from sellers and evaluating the

responses can be repeated. A short list of qualified sellers can be established based on a preliminary proposal.

12.2 Project

Procurement

Management

To Administer Procurements

From Plan Procurements

Tools & Techniques .1 Bidder conferences

.2 Proposal evaluation techniques

.3 Independent estimates

.4 Expert judgment

.5 Advertising

.6 Internet search

.7 Procurement negotiations

Inputs .1 Project management plan

.2 Procurement documents

.3 Source selection criteria

.4 Qualified seller list

.5 Seller proposals

.6 Project documents

.7 Make-or-buy decisions

.8 Teaming agreements

.9 Organizational process assets

Outputs .1 Selected sellers

.2 Procurement contract award

.3 Resource calendars

.4 Change requests

.5 Project management plan updates

.6 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 9 - Slide 4

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Example: Weighted Scoring Model

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 9 - Slide 5

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Conduct Procurements

• Contract Life Cycles

• Requirement

• Requisition

• Solicitation

• Award

• Project Management Processes

• Plan Purchases and Acquisitions

• Plan Contracting

• Request Seller Responses

• Select Sellers

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 9 - Slide 6

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Procurements and Sharing Info

• Conduct Procurements

• Perform Quality Assurance

• Distribute Information

• Managing Stakeholder Expectations

Perform Quality Assurance Perform Quality Assurance (QA) is the process of auditing the quality requirements and the results from quality control measurements to ensure

that appropriate quality standards and operational definitions are used. Perform Quality Assurance is a project execution process that uses data

created during Perform Quality Control. A quality assurance department, or similar organization, often oversees the quality assurance activities.

Quality assurance also provides an umbrella for continuous process improvement, which is an iterative means for improving overall quality.

8.2 Project

Quality

Management

To Perform Integrated Change Control

From Plan Quality, Perform Quality Control

Tools & Techniques .1 Plan Quality and Perform Quality Control

tools and techniques

.2 Quality audits

.3 Process analysis

Inputs .1 Project management plan

.2 Quality metrics

.3 Work performance information

.4 Quality control measurements

Outputs .1 Organization process assets updates

.2 Change requests

.3 Project management plan updates

.4 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 9 - Slide 8

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Procurements and Sharing Info

• Conduct Procurements

• Perform Quality Assurance

• Distribute Information

• Managing Stakeholder Expectations

Distribute Information Distribute Information is the process of making relevant information available to project stakeholders as planned. It is performed throughout the

entire project life cycle and in all project management processes. The focus is mainly in the execution process, which includes implementing the

communications management plan as well as responding to unexpected requests for information. Effective information distribution includes an

appropriate sender-receiver model, media, writing style, meeting management techniques, presentation techniques, and facilitation techniques.

10.3 Project

Communications

Management

To Update Organizational Process Assets

From Report Performance

Tools & Techniques .1 Communications methods

.2 Information distribution tools

Inputs .1 Project management plan

.2 Performance reports

.3 Organizational process assets

Outputs .1 Organization process assets updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 9 - Slide 10

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Procurements and Sharing Info

• Conduct Procurements

• Perform Quality Assurance

• Distribute Information

• Managing Stakeholder Expectations

Manage Stakeholder Expectations Manage Stakeholder Expectations is the process of communicating and working with stakeholders to meet their needs and addressing issues as

they occur. The process involves communication activities directed toward project stakeholders to influence their expectations, to address their

concerns, and to resolve issues. Actively managing stakeholder expectations increases the likelihood of project acceptance by negotiating and

influencing their desires to achieve and maintain the project goals. Addressing concerns that have not become issues yet can reduce conflict.

10.4 Project

Communications

Management

To Perform Integrated Change Control

From Identify Stakeholders

Tools & Techniques .1 Communications methods

.2 Interpersonal skills

.3 Management skills

Inputs .1 Stakeholder register

.2 Stakeholder management strategy

.3 Project management plan

.4 Issue log

.5 Change log

.6 Organizational process assets

Outputs .1 Organization process assets updates

.2 Change requests

.3 Project management plan updates

.4 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 9 - Slide 12

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Monitor and Control Project Work

• Communication, Information Distribution and Scope

Verification help to manage and control progress

• Scope Verification = Accepting work results.

(Formal Acceptance)

• Quality Assurance = Evaluating project performance

on an ongoing basis to increase confidence

• Quality Control = Monitoring specific project results

to measure compliance with relevant standards

LCS International, Inc.

PMP Review

Chapter 10

Measuring and Controlling

Project Performance Presented by

David J. Lanners, MBA, PMP

These slides are intended to be used only in settings where each

viewer has an original copy of the Sybex PMP Study Guide book.

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 10 - Slide 2

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Measuring Project Performance

• Monitor and Control Project Work

• Administer Procurements

• Report Performance

• Perform Integrated Change Control

Monitor and Control Project Work Monitor and Control Project Work is the process of tracking, reviewing, and regulating the progress to meet the performance objectives defined

in the project management plan. Monitoring is performed throughout the life of the project. It includes collecting, measuring, and distributing

performance information, and assessing measurements and trends to effect process improvements. Control includes determining corrective or

preventive actions or replanning and following up on action plans to determine if the actions taken resolved the performance issues.

4.4 Project

Management

Integration

To Perform Integrated Change Control

From Develop Project Management Plan

Tools & Techniques .1 Expert judgment

Inputs .1 Project management plan

.2 Performance reports

.3 Enterprise environmental factors

.4 Organizational process assets

Outputs .1 Change requests

.2 Project management plan updates

.3 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 10 - Slide 4

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Measuring Project Performance

• Monitor and Control Project Work

• Administer Procurements

• Report Performance

• Perform Integrated Change Control

Administer Procurements Administer Procurements is the process of managing procurement relationships, monitoring contract performance, and making changes and

corrections as needed. Both the buyer and the seller will administer the procurement contract for similar purposes. Each must ensure that both

parties meet their contractual obligations and that their own legal rights are protected. The Administer Procurements process ensures that the

seller’s performance meets procurement requirements and that the buyer performs according to the terms of the contract.

12.3 Project

Procurement

Management

To Close Procurements

From Conduct Procurements

Tools & Techniques .1 Contract change control system

.2 Procurement performance reviews

.3 Inspections and audits

.4 Performance reporting

.5 Payment systems

.6 Claims administration

.7 Records management system

Inputs .1 Procurement documents

.2 Project management plan

.3 Contract

.4 Performance reports

.5 Approved change requests

.6 Work performance information

Outputs .1 Procurement documentation

.2 Organization process assets updates

.3 Change requests

.4 Project management plan updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 10 - Slide 6

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Measuring Project Performance

• Monitor and Control Project Work

• Administer Procurements

• Report Performance

• Perform Integrated Change Control

Report Performance Report Performance is the process of collecting and distributing performance information, including status reports, progress measurements, and

forecasts. Performance reporting involves periodic collection and timely analysis of baseline versus actual data to understand and communicate

the project progress and performance information as well as to forecast the project results. Performance reports need to provide information at

an appropriate level for each audience. The format may range from a simple summary or dashboard status report to more elaborate reports.

10.5 Project

Communications

Management

To Distribute Information

From Direct and Manage Project Execution

Tools & Techniques .1 Variance analysis

.2 Forecasting methods

.3 Communication methods

.4 Reporting systems

Inputs .1 Project management plan

.2 Work performance information

.3 Work performance measurements

.4 Budget forecasts

.5 Organizational process assets

Outputs .1 Performance reports

.2 Organization process assets updates

.3 Change requests

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 10 - Slide 8

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Measuring Project Performance

• Monitor and Control Project Work

• Administer Procurements

• Report Performance

• Perform Integrated Change Control

Perform Integrated Change Control Perform Integrated Change Control is the process of reviewing change requests, approving changes, and managing changes to the deliverables,

organizational process assets, project documents and the project management plan. It is performed from project inception through completion.

The project management plan, project scope statement, and other deliverables are maintained by carefully and continuously managing changes,

either by rejecting changes or by approving changes, thereby assuring that only approved changes are incorporated into the revised baseline.

4.5 Project

Management

Integration

To Develop Project Management Plan

From Monitor and Control Project Work

Tools & Techniques .1 Expert judgment

.2 Change control meetings

Inputs .1 Project management plan

.2 Work performance information

.3 Change requests

.4 Enterprise environmental factors

.5 Organizational process assets

Outputs .1 Change request status updates

.2 Project management plan updates

.3 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 10 - Slide 10

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Perform Integrated Change Control

• Project management methodology

• Change Control System • Change Control Board (CCB)

• Project management information system

• Configuration Management System • Configuration identification

• Configuration status accounting

• Configuration verification & auditing

LCS International, Inc.

PMP Review

Chapter 11

Controlling Work Results

Presented by

David J. Lanners, MBA, PMP

These slides are intended to be used only in settings where each

viewer has an original copy of the Sybex PMP Study Guide book.

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 2

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Monitor and Control Risk

• Control Costs

• Control Schedule

• Perform Quality Control

• Verify Scope

• Control Scope

Monitor and Control Risks Monitor and Control Risks is the process of tracking identified risks, implementing risk response plans, monitoring residual risks, identifying new

(secondary) risks, and evaluating risk process effectiveness throughout the project. Project work should be continuously monitored for changing

and outdated risks. The process applies techniques such as variance and trend analysis to determine if project assumptions are still valid and/or

analysis shows that an assessed risk has changed or can be retired. The process should keep contingency reserves aligned with project risks.

11.6 Project

Risk

Management

To Perform Integrated Change Control

From Identify Risks, Work Performance Information

Tools & Techniques .1 Risk reassessment

.2 Risk audits

.3 Variance and trend analysis

.4 Technical performance measurement

.5 Reserve analysis

.6 Status meetings

Inputs .1 Risk register

.2 Project management plan

.3 Work performance information

.4 Performance reports

Outputs .1 Risk register updates

.2 Organization process assets updates

.3 Change requests

.4 Project management plan updates

.5 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 4

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Monitor and Control Risk

• Control Costs

• Control Schedule

• Perform Quality Control

• Verify Scope

• Control Scope

Control Costs Control Costs is the process of monitoring the status of the project to update the project budget and managing changes to the cost baseline.

Updating the budget involves recording actual costs incurred to date. Any increase to the authorized budget can be approved only through the

Perform Integrated Change Control process. Monitoring the expenditure of funds without regard to the value of work being accomplished has

little value to the project other than to allow the project team to stay within the authorized funding.

7.3 Project

Cost

Management

To Perform Integrated Change Control

From Determine Budget, Direct Project Execution

Tools & Techniques .1 Earned value management

.2 Forecasting

.3 To-complete performance index (TCPI)

.4 Performance reviews

.5 Variance analysis

.6 Project management software

Inputs .1 Project management plan

.2 Project funding requirements

.3 Work performance information

.4 Organizational process assets

Outputs .1 Work performance measurements

.2 Budget forecasts

.3 Organization process assets updates

.4 Change requests

.5 Project management plan updates

.6 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 6

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Earned Value Technique

• Planned Value (PV) = Budgeted Cost of

Work Scheduled (BCWS)

• Actual Cost (AC) = Actual Cost of

Work Performed (ACWP)

• Earned Value (EV) = Budgeted Cost of

Work Performed (BCWP)

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 7

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Earned Value Chart

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 8

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Earned Value Performance

• Cost Variance

(CV) = EV – AC

• Schedule Variance

(SV) = EV – PV

• Performance Indices

• Cost Performance Index (CPI ) = EV ÷ AC

• Schedule Performance Index (SPI) = EV ÷ PV

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 9

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Earned Value Forecasting

• Budget at Completion = [Sum of All Project Budgets]

• Estimate at Completion EAC = AC + ETC [Assumptions Changed]

EAC = (AC + BAC) – EV [Variances will STOP]

EAC = [AC + (BAC – EV) ÷ CPI] [Variances will Continue]

• Estimate to Complete (ETC) = EAC – AC [See 1st Formula Above]

(ETC) = (BAC - EV) / CPI [Variances will Continue]

• Variance at Completion * (VAC) = BAC – EAC * [Not in Guide to PMBOK]

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 10

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Hint: All abbreviations in rows and colums are in alphabetical order.

ACWP BCWP BCWS

AC EV PV

cpi ÷ ÷ spi

CV - - SV

Hint: Start with EV and then follow the arrows to create each formula

Earned Value Memory Aid

This chart is copyrighted by David J. Lanners, MBA, PMP

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 11

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Monitor and Control Risk

• Control Costs

• Control Schedule

• Perform Quality Control

• Verify Scope

• Control Scope

Control Schedule Control Schedule is the process of monitoring the status of the project to update project progress and manage changes to the schedule baseline.

It is concerned with determining the current status of the project schedule, influencing the factors that create schedule changes, determining that

the project schedule has changed, and managing the actual changes as they occur. Progress reporting and current schedule status includes

information such as actual start and finish dates for schedule activities and the remaining durations for unfinished schedule activities.

6.6 Project

Time

Management

To Perform Integrated Change Control

From Develop Schedule, Direct Project Execution

Tools & Techniques .1 Performance reviews

.2 Variance analysis

.3 Project management software

.4 Resource leveling

.5 What-if scenario analysis

.6 Adjusting leads and lags

.7 Schedule compression

.8 Scheduling tool

Inputs .1 Project management plan

.2 Project schedule

.3 Work performance information

.4 Organizational process assets

Outputs .1 Work performance measurements

.2 Organization process assets updates

.3 Change requests

.4 Project management plan updates

.5 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 13

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Monitor and Control Risk

• Control Costs

• Control Schedule

• Perform Quality Control

• Verify Scope

• Control Scope

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 14

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Schedule Compression

• Crashing

• Adding resources (always adds cost)

• Fast tracking

• Overlapping tasks (always adds risk)

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 15

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Perform Quality Control

• Verifying Project Scope

• Controlling Scope Changes

• Formulating Project Closeout

• Close Project or Phase

• Close Procurements

• Releasing Project Team Members

Perform Quality Control

Tools & Techniques .1 Cause and effect diagrams

.2 Control charts

.3 Flowcharting

.4 Histogram

.5 Pareto chart

.6 Run chart

.7 Scatter diagram

.8 Statistical sampling

.9 Inspection

.10 Approved change requests review

Outputs .1 Quality control measurements

.2 Validated changes

.3 Validated deliverables

.4 Organization process assets updates

.5 Change requests

.6 Project management plan updates

.7 Project document updates

Perform Quality Control (QC) is the process of monitoring and recording results of executing the quality activities to assess performance and

recommend necessary changes. Quality control is performed throughout the project. Quality standards include project processes and product

goals. Project results include deliverables and project management results, such as cost and schedule performance. The project management

team should have a working knowledge of statistical quality control, especially sampling and probability, to evaluate quality control outputs.

Inputs .1 Project management plan

.2 Quality metrics

.3 Quality checklists

.4 Work performance measurements

.5 Approved change requests

.6 Deliverables

.7 Organizational process assets 8.3 Project

Quality

Management

To Perform Quality Assurance

From Plan Quality

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 17

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Control Chart

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 18

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Process Capability

Process capability is measured by comparing the customer’s specification

width to the process’s “normal” output (which is calculated by monitoring

the process output and calculating ± 3 std deviations from the mean).

Cp >1 is needed to meet specs without waste.

Acceptable Specification Width

Process Output Width Cp =

Upper Spec – Lower Spec

6 Standard Deviations Cp =

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 19

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Process Capability Example

Upper Spec – Lower Spec

6 Standard Deviations Cp =

Process requires metal rods to be 5.000 inches long +- 0.050 inches.

The production process has a standard deviation of 0.006 inches.

(+ 0.050) – (- 0.050)

6 x (0.006) =

( 0.100 )

(0.036) = = 2.77

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 20

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Frequency of Failures

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 21

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Pareto Diagram

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 22

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Scatter Diagram

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 23

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Normal distribution (Bell-shaped curve)

| 68% |

| 95% |

| 99% |

Mean

2

3

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 24

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Measures of Central Tendency

Mean = Average

n

x...xxx n21

n

1i

i

80 + 10 + 10 + 50 + 70 + 90 ________________________

6

= 310 ____

6

= 51.67

52 (Rounded)

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 25

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Measures of Central Tendency

• Median – (Middle) as in Highway Median

• Data: 80 10 10 50 70 90

• First put in order: 10 10 50 70 80 90

• If an even number of data points, calculate the

midpoint between the two “middle” numbers.

• 50 + 70 = 120 / 2 = 60 is the median

• Mode - the most common (a la mode)

• 10 is the number that appears most frequently

• 10 is the mode

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 26

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Population

• Mean

• Variance

• Standard Deviation

Terms and symbols

Sample

• Mean

• Variance

• Standard

Deviation

2

_x

2s

s

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 27

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Variance & Standard Deviation

Population

2N

1i

i

2

N

x

Variance

2 Standard

Deviation

Sample

1

)( 2

12

n

xx

s

n

i

i

Sample

Variance

2ss Standard

Deviation

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 28

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Calculate the standard deviation () of this data:

80 10 10 50 70 90

1. Compute the mean, 310/6 = 51.67 52

2. Subtract the mean from the data point and square the result:

80 - 52 = 28, 28 x 28 = 784

10 - 52 = -42, -42 x -42 = 1,764

10 - 52 = -42, -42 x -42 = 1,764

50 - 52 = -2, -2 x -2 = 4

70 - 52 = 18, 18 x 18 = 324

90 - 52 = 38, 38 x 38 = 1,444

total = 6,084

3. Calculate variance (2) = 6,084 / 6 = 1,014

4. Calculate standard deviation () = 1014 = 31.84

Example

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 29

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Using Perform Quality Control Techniques

• Verifying Project Scope

• Controlling Scope Changes

• Formulating Project Closeout

• Close Project or Phase

• Contract Closure

• Releasing Project Team Members

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 30

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Monitor and Control Risk

• Control Costs

• Control Schedule

• Perform Quality Control

• Verify Scope

• Control Scope

Verify Scope Verify Scope is the process of formalizing acceptance of the completed project deliverables. Verifying scope includes reviewing the deliverables

with the customer or sponsor to ensure that they are completed satisfactorily and obtaining formal acceptance of deliverables by the customer

or sponsor. Scope verification differs from quality control in that scope verification is primarily concerned with acceptance of the deliverables,

while quality control is primarily concerned with conformance to specifications and meeting quality requirements specified for the deliverables.

5.4 Project

Scope

Management

To Control Scope, Close Project or Phase

From Collect Requirements, Perform Quality Control

Tools & Techniques .1 Inspection

Inputs .1 Project management plan

.2 Requirements documentation

.3 Requirements traceability matrix

.4 Validated deliverables

Outputs .1 Accepted deliverables

.2 Change requests

.3 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 32

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Monitor and Control Risk

• Control Costs

• Control Schedule

• Perform Quality Control

• Verify Scope

• Control Scope

Control Scope Control Scope is the process of monitoring the status of the project and product scope and managing changes to the scope baseline. Controlling

project scope ensures that requested changes and recommended corrective or preventive actions are processed through the Perform Integrated

Change Control process. Project scope control is also used to manage actual changes when they occur and is integrated with the other control

processes. Uncontrolled changes often are referred to as scope creep. Because change is inevitable, some kind of change control is mandated.

5.5 Project

Scope

Management

To Perform Integrated Change Control

From Collect Requirements

Tools & Techniques .1 Variance analysis

Inputs .1 Project management plan

.2 Work performance information

.3 Requirements documentation

.4 Requirements traceability matrix

.5 Organizational process assets

Outputs .1 Work performance measurements

.2 Organizational process assets updates

.3 Change requests

.4 Project management plan updates

.5 Project document updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 34

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Formulating Project Closeout

• Addition - (evolve into operations)

• Starvation - (resources are cut off)

• Integration - (resources distributed)

• Extinction - (natural completion)

LCS International, Inc.

PMP Review

Chapter 12

Professional Responsibility

Presented by

David J. Lanners, MBA, PMP

These slides are intended to be used only in settings where each

viewer has an original copy of the Sybex PMP Study Guide book.

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 12 - Slide 2

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Professional Responsibility

• Close Project or Phase

• Close Procurements

• Balancing Stakeholders’ Interests

• Applying Professional Knowledge

• Respecting Differences in Diverse Cultures

• Ensuring Integrity

Close Project or Phase Close Project or Phase is the process of finalizing all activities across all of the Project Management Process Groups to complete the project or

phase. Completion of the project scope is measured against the project management plan, and the project manager reviews project documents

ensure that they are completed before considering the project closed. The process establishes procedures to investigate and document reasons

for action taken if a project is terminated before completion. The process also transfers lessons learned to the organization’s knowledge base.

4.6 Project

Management

Integration

To Final Product, Service, or Result Transition

From Develop Project Management Plan

Tools & Techniques .1 Expert judgment

Inputs .1 Project management plan

.2 Accepted deliverables

.3 Organizational process assets

Outputs .1 Final product, service, or result transition

.2 Organizational process assets updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 12 - Slide 4

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Professional Responsibility

• Close Project or Phase

• Close Procurements

• Balancing Stakeholders’ Interests

• Applying Professional Knowledge

• Respecting Differences in Diverse Cultures

• Ensuring Integrity

Close Procurements Close Procurements is the process of completing each project procurement. Closing procurements supports the Close Project or Phase process

since it involves verification that all work and deliverables were acceptable. The Close Procurements process involves administrative activities

such as finalizing open claims, updating project records to reflect final results, and archiving information for future use. Unresolved claims may

be subject to litigation after closure. The contract terms and conditions can prescribe specific procedures for contract closure.

12.4 Project

Procurement

Management

To Close Project or Phase

From Administer Procurements

Tools & Techniques .1 Procurement audits

.2 Negotiated settlements

.3 Records management system

Inputs .1 Procurement management plan

.2 Procurement documentation

Outputs .1 Closed procurements

.2 Organization process assets updates

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 12 - Slide 6

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Professional Responsibility

• Close Project or Phase

• Close Procurements

• Balancing Stakeholders’ Interests

• Applying Professional Knowledge

• Respecting Differences in Diverse Cultures

• Ensuring Integrity

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 12 - Slide 7

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Balancing Stakeholders’ Interests

• Competing Needs

• Dealing with Issues and Problems

• Balancing Constraints

• Scope, Time, Cost

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 12 - Slide 8

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Professional Responsibility

• Close Project or Phase

• Close Procurements

• Balancing Stakeholders’ Interests

• Applying Professional Knowledge

• Respecting Differences in Diverse Cultures

• Ensuring Integrity

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 12 - Slide 9

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Applying Professional Knowledge

• Project Management Knowledge

• Professional Conduct

• Industry Knowledge

• Truthful Reporting

• Laws and Regulations Compliance

• Respect for Confidential Information

• Company Data

• Intellectual Property

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 12 - Slide 10

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Professional Responsibility

• Close Project or Phase

• Close Procurements

• Balancing Stakeholders’ Interests

• Applying Professional Knowledge

• Respecting Differences in Diverse Cultures

• Ensuring Integrity

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 12 - Slide 11

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Respecting Differences in

Diverse Cultures

• Global Competition

• Culture Shock

• Respecting Your Neighbors

• Training

• Perceiving Experiences

• Appreciating Diversity

• Required by Law

• Good for Business

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 12 - Slide 12

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Professional Responsibility

• Close Project or Phase

• Close Procurements

• Balancing Stakeholders’ Interests

• Applying Professional Knowledge

• Respecting Differences in Diverse Cultures

• Ensuring Integrity

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 12 - Slide 13

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Ensuring Integrity

• Personal Integrity

• Conflict of Interest

• Associations and Affiliations

• Vendor Gifts

• Stakeholder Influence

• Professionally Demeanor

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 12 - Slide 14

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Professional Responsibility

• Current PMP certification information . . .

www.pmi.org


Recommended