+ All Categories
Home > Documents > PMP Lecture 8

PMP Lecture 8

Date post: 25-Feb-2018
Category:
Upload: zakhanisb
View: 227 times
Download: 1 times
Share this document with a friend

of 46

Transcript
  • 7/25/2019 PMP Lecture 8

    1/46

    AUC TechnologiesConsulting | Development | Mentoring | Training

    Project Management With PMP Exam Preparation

  • 7/25/2019 PMP Lecture 8

    2/46

    Agenda

    Plan Risk Management

    Identify Risk

    Perform Qualitative Risk Analysis

    Perform Quantitative Risk Analysis

    Plan Risk Response

  • 7/25/2019 PMP Lecture 8

    3/46

    Project Risk Management

    Project risk management is the art and science of identifying,

    analyzing, and responding to risk throughout the life of a project

    and in the best interests of meeting project objectives

    Risk management is often overlooked on projects, but it can

    help improve project success by helping select good projects,

    determining project scope, and developing realistic estimates

  • 7/25/2019 PMP Lecture 8

    4/46

    Why Take Risks? Because of Opportunities!

    OpportunitiesRisks

    Try to balance risks and opportunities

  • 7/25/2019 PMP Lecture 8

    5/46

    Negative Risk

    A dictionary definition of risk is the possibility of loss or injury

    Negative risk involves understanding potential problems that

    might occur on the project and how they might impede project

    success

    Negative risk management is like a form of insurance; it is an

    investment

  • 7/25/2019 PMP Lecture 8

    6/46

    Risk Can Be Positive

    Positive risks are risks that result in good things happening;

    sometimes called opportunities

    A more general definition of project risk is an uncertainty that

    can have a negative or positive effect on meeting project

    objectives

    The goal of project risk management is to minimize potential

    negative risks while maximizing potential positive risks

  • 7/25/2019 PMP Lecture 8

    7/46

    Risk Utility Risk Tolerance

    Risk toleranceaddresses the level of risk a project manager

    or key stakeholder is willing to take when money at stake is

    compared to the potential payoff. Its measured in terms of

    the amount of satisfaction or pleasure the individual

    receives from a payoff.

  • 7/25/2019 PMP Lecture 8

    8/46

    Risk Utility Risk Tolerance- Classifications

    Classification Description

    Risk-averter Not likely to take a risk that is considered a

    high risk.

    Risk-seeker Prefers an uncertain outcome and may be

    willing to pay a penalty to take a high risk.

    Risk-neutral Tolerance to risk is proportional to the

    amount of money at stake.

  • 7/25/2019 PMP Lecture 8

    9/46

    Plan Risk Management

    A plan that documents the procedures for managing risk

    throughout a project

    The project team should review project documents and

    understand the organizations and the sponsors approach to

    risk

    The level of detail will vary with the needs of the project

    Descr ib ing how to approach, plan, and execu te the risk

    management act iv i t ies for a pro ject

  • 7/25/2019 PMP Lecture 8

    10/46

    Plan Risk Management

    1. Enterprise

    Environmental

    Factor

    2. Organizational

    Process Asset

    3. Scope statement

    4. Project Mgmt Plan

    1. Planning Meeting

    and analysis

    1. Risk ManagementPlan

    Input

    Output

    Tools

  • 7/25/2019 PMP Lecture 8

    11/46

    Risk Management Plan Components

    Component Description

    Methodology Defines the tools, approaches, and data

    sources that may be used to perform risk

    management on the project.

    Budgeting A budget for project risk management

    should be established and included in

    the risk management plan.

    Role & Defines the lead, support, and riskResponsibility management team membership for

    each type of action in the risk

    management plan.

  • 7/25/2019 PMP Lecture 8

    12/46

    Risk Management Plan Components

    Component Description

    Timing Defines how often the risk management

    activities will be performed throughout

    the project life cycle.

    Risk categories Documentation such as risk breakdown

    structures (RBSes) or categories from

    previous projects will help identify and

    organize risks.

    Definitions of risk Risks and their probabilities are

    probability & impact defined for use in

    Qalitative Risk Analysis using a scale of very Unlikely to almost

    certain.

  • 7/25/2019 PMP Lecture 8

    13/46

    Risk Breakdown Structure

    A risk breakdown structure (RBS) organizes potential

    sources of risk to the project. Functioning much like a work

    breakdown structure, an RBS arranges categories into a

    hierarchy. This approach allows the project team to define

    risk at very detailed levels.

  • 7/25/2019 PMP Lecture 8

    14/46

    Risk Breakdown Structure Template

    IT Project

    Business Technical OrganizationalProject

    Management

    Competitors

    Suppliers

    Cash flow

    Hardware

    Software

    Network

    Executive

    support

    User support

    Team support

    Estimates

    Communication

    Resources

  • 7/25/2019 PMP Lecture 8

    15/46

    Identify Risk

    Risk identification is the process to figure out every

    possible risk that might affect your project.

    Its not about how unlikely the risk is, or how bad the

    impact would beit will be figure out later process

    Determ in ing wh ich r isks m ight af fect the pro ject and

    document ing their character is t ics

  • 7/25/2019 PMP Lecture 8

    16/46

    1. Risk management plan

    2. Activity cost estimates

    3. Activity duration

    estimates

    4. Scope baseline

    5. Stakeholder register6. Cost management

    plan

    7. Schedule management

    plan

    8. Quality management

    plan

    9. Project documents

    10. Enterprise

    environmental factors

    11. Organizational

    process assets

    1. Documentati

    on reviews

    2. Informationgathering

    techniques

    3. Checklist

    analysis

    4. Diagramming

    techniques5. SWOT

    analysis

    6. Expert

    judgment

    Input

    Tools

    1. Risk register

    updates

    Output

    Identify Risk

  • 7/25/2019 PMP Lecture 8

    17/46

    Identify Risk - Inputs

    1.Enterprise Environmental Factors

    Published Information

    Commercial databases

    Academic studies

    Benchmarking and other Industry studies

    2.Organizational Process Assets

    Historical experiences

  • 7/25/2019 PMP Lecture 8

    18/46

    Identify Risk Identification - Inputs

    3.Project Scope Statement

    Uncertainty in project assumptions

    4.Risk Management Plan

    Assignment of roles and responsibilities

    Provision for Risk Management activities in Schedule and

    Budget

    Categorizing Risks5.Project Management Plan

  • 7/25/2019 PMP Lecture 8

    19/46

    Identify Risk Tools & Techniques

    1.Documentation Reviews

    Performing structured reviews of Project artifacts

    2.Information Gathering Techniques

    Brainstorming

    Delphi Technique

    Interviewing

    Root Cause Identification

    SWOT Analysis

  • 7/25/2019 PMP Lecture 8

    20/46

    Identify Risk Tools & Techniques

    Checklist Analysis

    Developing Risk identification checklist based on historical

    precedence's

    Assumptions Analysis

    Diagramming Techniques

    Cause-and-effect diagram

    System or process flow charts

    Influence diagrams

  • 7/25/2019 PMP Lecture 8

    21/46

    Identify Risk - Output Risk Register

    The output of the risk identification process is risk register

    is a document that contains results of various risk

    management processes, often displayed in a table or

    spreadsheet format

    is a tool for documenting potential risk events and related

    information

    Risk events refer to specific, uncertain events that may occur

    to the detriment or enhancement of the project

  • 7/25/2019 PMP Lecture 8

    22/46

    Sample Risk Register

    Identified Risks Potential

    Responses

    Root Causes

    Each risk that you

    and team come upshould go here

    Your Risk

    Identificationmeetings should

    always include a

    discussion of how

    to respond to the

    risk

    This is where the

    result of rootcause analysis

    lists

  • 7/25/2019 PMP Lecture 8

    23/46

    Perform Qualitative Risk Analysis

    Some risks will cause a whole lot of damage to your project

    if they happen, while others will barely make a scratch

    and you care much more about the risks that will have a big

    impact

    Prior i t izing Risks for subs equent fu r ther analys is or act ion

    by assessing and combin ing their probabi l i ty or occurrence

    and impact

  • 7/25/2019 PMP Lecture 8

    24/46

    1. Risk register

    2. Risk management plan

    3. Project scopestatement

    4. Organizational process

    assets

    1. Risk probability

    and impact

    assessment2. Probability and

    impact matrix

    3. Risk data quality

    assessment

    4. Risk

    categorization

    5. Risk urgencyassessment

    6. Expert judgment

    Input

    Tools

    1. Risk registerupdates

    Output

    Perform Qualitative Risk Analysis

  • 7/25/2019 PMP Lecture 8

    25/46

    Perform Qualitative Risk Analysis - Inputs

    1.Organizational Process Assets

    Data about risks on past projects

    Lessons learned knowledge base

    Project Scope Statement

    Projects of common or recurring type

    Projects using first-of-its-type technology

  • 7/25/2019 PMP Lecture 8

    26/46

    Perform Qualitative Risk Analysis - Inputs

    3.Risk Management Plan

    Roles and responsibilities

    Budget, and schedule activities for risk management

    Risk Categories

    Definition of probability and impact

    Probability and impact matrix

    Revised stakeholders tolerance

    4.Risk Register

  • 7/25/2019 PMP Lecture 8

    27/46

    Qualitative Analysis Tools & Techniques

    1.Risk Probability and Impact Assessment

    Risk assessment by interviews

    Meetings with participants

    2.Probability and Impact Matrix

    Risk ratings

    Classification of risks as high, moderate and low

    Risk Score Card

  • 7/25/2019 PMP Lecture 8

    28/46

    Qualitative Analysis Tools & Techniques

    3.Risk data Quality Assessment

    Accuracy

    Quality

    Integrity of data about risk

    4.Risk categorization

    By sources of risk

    By area of project affected

    5.Risk Urgency Assessment

  • 7/25/2019 PMP Lecture 8

    29/46

    Probability/Impact Matrix Template

  • 7/25/2019 PMP Lecture 8

    30/46

    Probability/Impact Matrix Template

    Risk Score for a Specific Risk Chart Threshold Limits

    Probability Risk Score = P x I Moderate High

    0.9 0.05 0.09 0.18 0.36 0.72 0.05 0.18

    0.7 0.04 0.07 0.14 0.28 0.56

    Set Chart Threshold Limitshere by

    changing Moderateand Highlimits

    to desired values.

    0.5 0.03 0.05 0.10 0.20 0.40

    0.3 0.02 0.03 0.06 0.12 0.24

    0.1 0.01 0.01 0.02 0.04 0.08

    0.05 0.10 0.20 0.40 0.80

    Impact on an Objective (e.g., cost, time, or

    scope)(Ratio Scale)

  • 7/25/2019 PMP Lecture 8

    31/46

    Qualitative Risk Analysis - Output

    Identified

    Risks

    PotentialResponses

    RootCauses

    Category Priority Urgency

    Each

    risk

    that

    you

    and

    team

    comeup

    should

    go

    here

    Your Risk

    Identificati

    on

    meetings

    should

    always

    include adiscussio

    n of how

    to

    respond

    to the risk

    This is

    where

    the

    result

    of root

    cause

    analysis lists

    Source

    of Risk

    Project

    Phase

    How

    Import

    ant a

    risk is.

    When you

    Need to deal

    with it

  • 7/25/2019 PMP Lecture 8

    32/46

    Risk Register Assignment

    Create a Risk Register of given Case Study use qualitative

    risk analysis tools and list the items

  • 7/25/2019 PMP Lecture 8

    33/46

    Quantitative Risk Analysis

    Often follows qualitative risk analysis, but both can be done

    together or separately

    Large, complex project involving leading edge technologies

    often require extensive quantitative risk analysis

    Numerical ly assignin g the effect on overal l pro ject object ive

    of ident i f ied r isks

  • 7/25/2019 PMP Lecture 8

    34/46

    1. Risk register

    2. Risk management

    plan

    3. Cost managementplan

    4. Schedule

    management plan

    5. Organizational

    process assets

    1. Data

    gathering andrepresentatio

    n techniques

    2. Quantitative

    risk analysis

    and modeling

    techniques

    3. Expertjudgment

    Input

    Tools

    1. Risk register

    updates

    Output

    Perform Quantitative Risk Analysis

  • 7/25/2019 PMP Lecture 8

    35/46

    Quantitative Risk Analysis - Inputs

    Organizational Process Asset

    Information on similar risk in other projects, Risk

    database and study of similar risk by specialist

    Project Scope Statement

    Initial Risk identification

    Risk Management Plan

    Roles and Responsibilities, risk categories, revised

    stakeholders

  • 7/25/2019 PMP Lecture 8

    36/46

    Quantitative Risk Analysis - Inputs

    Risk Register

    List of identified risks, Risk ranking and Risk

    Categorization

    Project Management Plan Project Schedule Mgt Plan

    Controls Project schedule

    Project Cost Mgt Plan

    Controls Project budget

  • 7/25/2019 PMP Lecture 8

    37/46

    Quantitative Risk AnalysisTools & Techniques

    Data gathering and representation

    Interviewing: Taking subjective probability and representing

    that data objectively.

    Probability distributions: Visually represents risk probability.

    Expert judgment: Utilizes subject matter experts to validate

    a particular risk.

  • 7/25/2019 PMP Lecture 8

    38/46

    Quantitative Risk AnalysisTools & Techniques

    Quantitative risk analysis and modeling

    Sensitivity analysis: Examines how the uncertainty of a project

    element affects the objective in question if the other uncertain

    elements remain unchanged.

    Expected monetary value analysis: Calculates the average

    outcome under uncertainty.

    Decision tree analysis: Evaluates possible outcomes to help the

    decision-maker select the decision that provides the greatest

    expected value.

    Modeling and simulation: Includes cost risk analysis, which is

    most commonly performed using the Monte Carlo method.

  • 7/25/2019 PMP Lecture 8

    39/46

    Decision Trees and Expected Monetary Value

    Decision tree is a diagramming analysis technique used to

    help select the best course of action in situations in which

    future outcomes are uncertain

    Expected monetary value (EMV) analysisis a method of

    calculating the average outcome when the future is uncertain.

    (Opportunities will have positive values and risks will have

    negative values.)

    You can draw a decision tree to help find the EMV

  • 7/25/2019 PMP Lecture 8

    40/46

    Expected Monetary Value (EMV) Example

  • 7/25/2019 PMP Lecture 8

    41/46

    Decision Tree Example

    90%

    60%

    100,000 PKR

    Airline A Fare

    10,000PKR

    Airline B Fare

    8000PKR

    100,000 PKR

    PIA 10000 + (90% * 0=0) + (100,000 *

    10%=10000)=20,000

    Air

    Blue

    8000 + (60% * 0=0) + (100,000 *

    40%=40,000)=48,000

  • 7/25/2019 PMP Lecture 8

    42/46

    Plan Risk Response

    After identifying and quantifying risk, you must decide how to

    respond to them

    How to approach and conduct Risk Response Planning

    Prepare Risk response Plan

    Developing opt ions and act ions to enhance oppo rtuni t ies,

    and to reduce threats to project object ives

  • 7/25/2019 PMP Lecture 8

    43/46

    1. Risk register

    2. Risk management

    plan

    1. Strategies

    for negative

    risks orthreats

    2. Strategies

    for positive

    risks or

    opportunities

    3. Contingentresponse

    Strategies

    4. Expert

    judgment

    Input

    Tools1. Risk Register

    updates

    2. Risk-related

    contractdecisions

    3. Project

    management

    plan updates

    4. Project

    document

    updates

    Output

    Plan Risk Response

  • 7/25/2019 PMP Lecture 8

    44/46

    Response Strategies for Negative Risks

    Risk Avoidance Eliminate the threat by eliminating the cause

    Risk Mitigation

    Reduce the probability or the impact of a threat

    Risk Transference

    Make another party responsible for the risk throughpurchasing of insurance, performance bonds,

    warranties, guaranteed or outsourcing the work

  • 7/25/2019 PMP Lecture 8

    45/46

    Response Strategies for Positive Risks

    Risk exploitation (the reverse of avoid) Add work or change the project to make sure the

    opportunity occurs

    Risk sharing

    Allocate ownership of the opportunity to a third party

    ( forming a partnership, team or joint venture)

    Risk enhancement (the reverse of mitigate)

    Increase the likelihood, probability and positive impactsof the risk event

  • 7/25/2019 PMP Lecture 8

    46/46

    Questions


Recommended