GeohazardsGeohazards in Transportationin TransportationAppalachian Region Technical ForumAppalachian Region Technical Forum
August 1August 1--2, 20072, 2007
““Drilled Shafts for Bridge Foundation Drilled Shafts for Bridge Foundation Stability ImprovementStability Improvement
Ohio 833 Bridge over the Ohio RiverOhio 833 Bridge over the Ohio River””An UpdateAn Update
Meigs County, OhioMeigs County, OhioMason County, West VirginiaMason County, West Virginia
ByByStan Harris, P.E. and Eric Kistner, P.E.Stan Harris, P.E. and Eric Kistner, P.E.
FMSM EngineersFMSM Engineers
AgendaAgendaI.I. Introduction/BackgroundIntroduction/Background
A.A. GeneralGeneralB.B. Initial Slope MovementInitial Slope MovementC.C. Remediation SchemeRemediation SchemeD.D. Instrumentation PlanInstrumentation Plan
II.II. Instrumentation Results/Recent Slope Instrumentation Results/Recent Slope MovementMovement
III.III. New Instrumentation on Existing BridgeNew Instrumentation on Existing BridgeIV.IV. Lessons LearnedLessons LearnedV.V. Question/AnswerQuestion/Answer
I. Introduction/BackgroundI. Introduction/Background
Project LocationProject Location
Pomeroy, Ohio
Project TeamProject Team
Owner: ODOT/WVDOHOwner: ODOT/WVDOHDesigner: URS CorporationDesigner: URS CorporationContractor: Mahan/National Joint Contractor: Mahan/National Joint
VentureVentureGeotechnical Consultant Geotechnical Consultant –– FMSM FMSM
Existing StructureExisting StructureOHIO
WEST VIRGINIA
Proposed StructureProposed Structure
WEST VIRGINIA
OHIO
Project TimelineProject Timeline2000 2001 2002 2003 2004 2005
FMSM Geotechnical Exploration
Bridge DesignBridge Construction
Slope MonitoringSlope Movement Detected
Construction of Protective Measures
Monitoring of Protective Measures
20072006
Monitoring of Existing Bridge
Current State of ConstructionCurrent State of Construction
Stability Issues/Slope Movement/ReactionStability Issues/Slope Movement/Reaction
New Main Street EmbankmentNew Main Street EmbankmentShortShort--Term Stability ConcernsTerm Stability ConcernsControlled RateControlled Rate--ofof--FillFill–– Slope InclinometersSlope Inclinometers–– PiezometersPiezometers
Initial Detection of MovementInitial Detection of MovementAdditional InstrumentationAdditional Instrumentation
Original Extents of Slope MovementOriginal Extents of Slope Movement
Approximate Limits of Slope
Movement
Probable Causes of Slope Probable Causes of Slope MovementMovement
Weak slickensided clay shale Weak slickensided clay shale (mudstone)(mudstone)Possible ancient movementPossible ancient movementConstruction activity/embankmentConstruction activity/embankmentRapid drawdown cycles of Ohio RiverRapid drawdown cycles of Ohio River
Slope Geology/GeometrySlope Geology/Geometry
Shale/Clay Shale/Mudstone Bedrock
Alluvial Silt and ClayExisting Fill
New Fill
Ohio River
Apparent Failure Surface
Residual Clay
Siltstone
Ohio River
Potential Failure Surface
Siltstone
ODOTODOT’’s Preferred Option s Preferred Option and Related Decisionsand Related Decisions
One Row of Nine Drilled Shafts Between the Land Pier and the Water Pier
Realign Main Street to Reduce Fill Height
Touch Down PierAbutment
Ohio Tower
NEW BRIDGE
Change Abutment and Land Pier Foundations to Drilled Shafts
Plan View of Stabilization ShaftsPlan View of Stabilization Shafts
8’ Diameter Drilled Shafts on 12’ c/c
Spacing
Revised Roadway PlanRevised Roadway Plan
Instrumentation PlanInstrumentation Plan
Site Site –– Slope Inclinometers, PiezometersSlope Inclinometers, PiezometersExisting Bridge Existing Bridge –– Tiltmeters, Survey Tiltmeters, Survey TargetsTargetsTouch Down Pier Touch Down Pier –– Strain Gauges, InStrain Gauges, In--Place and Manually Read InclinometerPlace and Manually Read InclinometerStabilization Shafts Stabilization Shafts –– Tiltmeters, Strain Tiltmeters, Strain Gauges, InGauges, In--Place and Manually Read Place and Manually Read InclinometersInclinometers
Stabilization Shaft Instrumentation PlanStabilization Shaft Instrumentation Plan
II.II. Recent Slope Movement/ Recent Slope Movement/ Instrumentation ResultsInstrumentation Results
Recent Movement (Oct Recent Movement (Oct ’’06 06 -- Feb Feb ’’07)07)
DetectionDetection–– Instrumentation Activity (late October)Instrumentation Activity (late October)–– Tension Cracks (early December)Tension Cracks (early December)–– Water Main Break (early December)Water Main Break (early December)
CausesCauses–– Construction ActivityConstruction Activity–– River FluctuationRiver Fluctuation
Tension Cracks Tension Cracks –– 12/11/0612/11/06
Construction Activity Construction Activity –– 11/30/0611/30/06
Ohio River FluctuationsOhio River FluctuationsRiver Elevation (feet)
520.0
530.0
540.0
550.0
560.0
570.0
580.0
10/1
/04
12/1
/04
2/1/
05
4/1/
05
6/1/
05
8/1/
05
10/1
/05
12/1
/05
2/1/
06
4/1/
06
6/1/
06
8/1/
06
10/1
/06
12/1
/06
2/1/
07
Slope Movement
Tied Back Retaining WallTied Back Retaining Wall
Results of InstrumentationResults of InstrumentationSiteSite–– 4 Years of Data4 Years of Data–– Numerous Inclinometers Sheared Due to Slope Numerous Inclinometers Sheared Due to Slope
MovementMovementExisting BridgeExisting Bridge–– 3 Years of Data3 Years of Data–– Abutment Tilt Due to Recent MovementAbutment Tilt Due to Recent MovementNew Bridge Touch Down PierNew Bridge Touch Down Pier–– 3 Years of Data3 Years of Data–– Top Deflection Due to Lateral LoadingTop Deflection Due to Lateral LoadingStabilization Shafts Stabilization Shafts –– 2 Years of Data2 Years of Data–– Northernmost Shaft Being LoadedNorthernmost Shaft Being Loaded
Current Extents of Slope MovementCurrent Extents of Slope Movement
Limits of Movement
Existing Bridge Tiltmeter ResultsExisting Bridge Tiltmeter Results
11/01/2004
12/01/2004
01/01/2005
02/01/2005
03/01/2005
04/01/2005
05/01/2005
06/01/2005
07/01/2005
08/01/2005
09/01/2005
10/01/2005
11/01/2005
12/01/2005
01/01/2006
02/01/2006
03/01/2006
04/01/2006
05/01/2006
06/01/2006
07/01/2006
08/01/2006
09/01/2006
10/01/2006
11/01/2006
12/01/2006
01/01/2007
02/01/2007
03/01/2007
04/01/2007
05/01/2007
06/01/2007
07/01/2007
08/01/2007
09/01/2007
Time
-0.15
-0.10
-0.05
0.00
0.05
0.10
0.15
Tilt
(deg
)AbutmentLand Pier TopLand Pier BottomWater Pier Top
Zeroed Y-Tilt ReadingsPositive → Top Moving Downslope
Abutment
Land Pier Top
Land Pier Bottom
Water Pier Top
Instrument Malfunction Instrument Malfunction
Existing Bridge Tiltmeter ResultsExisting Bridge Tiltmeter Results
-30 -20 -10 0 10 20 30 40 50 60Temperature (C)
-0.15
-0.10
-0.05
0.00
0.05
0.10
0.15
-20
-10 0 10 20 30 40 50 60 70 80 90
100
110
120
130
140
Temperature (F)Temperature Influence on Y-Tilt Readings
-30 -20 -10 0 10 20 30 40 50 60Temperature (C)
-0.15
-0.10
-0.05
0.00
0.05
0.10
0.15
Tilt
(deg
)
-20
-10 0 10 20 30 40 50 60 70 80 90
100
110
120
130
140
Temperature (F)Temperature Influence on X-Tilt Readings
Land Pier Top Tiltmeters
Looking Upslope, P
ositive → C
lockwise Tilt
Positive → Top M
oving Dow
nslope
First Track:Oct-2004 – Mar-2005
Second Track:Aug-2005 – Oct-2006
Third Track:Oct-2006 – Dec-2006 Fourth Track:
Dec-2006 – Feb-2007
Fifth Track:Feb-2007 – July-2007
Stabilization Shaft Strain Gage ResultsStabilization Shaft Strain Gage Results
-6000 -5000 -4000 -3000 -2000 -1000 0 1000 2000 3000 4000 5000 6000Moment (kip-ft)
460
470
480
490
500
510
520
530
540
550
Ele
vatio
n (ft
)
LPILE 0.2"21-Oct-200604-Nov-200618-Nov-200602-Dec-200616-Dec-200630-Dec-200614-Jan-200728-Jan-200711-Feb-200725-Feb-200711-Mar-200725-Mar-200708-Apr-200722-Apr-200706-May-200720-May-200703-Jun-200717-Jun-200701-Jul-200715-Jul-2007
SS9: Moment Diagram
Cra
ckin
g M
omen
t
Cra
ckin
g M
omen
t
Bottom of Shaft
Top of Rock
Top of Shaft
With Linear RegressionDarker =
More Recent
Positive Moment ⇒ Tension on Upslope Face
Stabilization Shaft 9 Stabilization Shaft 9 –– IPI PlotIPI Plot
Touch Down Pier Strain Gage ResultsTouch Down Pier Strain Gage Results
09/01/0410/01/0411/01/0412/01/0401/01/0502/01/0503/01/0504/01/0505/01/0506/01/0507/01/0508/01/0509/01/0510/01/0511/01/0512/01/0501/01/0602/01/0603/01/0604/01/0605/01/0606/01/0607/01/0608/01/0609/01/0610/01/0611/01/0612/01/0601/01/0702/01/0703/01/0704/01/0705/01/0706/01/0707/01/0708/01/0709/01/07
Time
-6000
-5000
-4000
-3000
-2000
-1000
0
1000
2000
3000
4000
5000
6000
Ben
ding
Mom
ent (
kip-
ft)
El. 530 ftEl. 534 ftEl. 542 ftEl. 566 ftEl. 576 ft
DS-54: Bending Moment History
Cracking Moment (approx. 30% of Moment Capacity)
Cracking Moment (approx. 30% of Moment Capacity)
III. New Instrumentation on III. New Instrumentation on Existing BridgeExisting Bridge
–– Jointmeters Jointmeters (3 Joints on (3 Joints on Ohio Side)Ohio Side)
–– Tiltmeters on Tiltmeters on Linkage Linkage AssembliesAssemblies
–– Strain Gages Strain Gages on Truss on Truss MembersMembers
IV. Lessons LearnedIV. Lessons LearnedDifficulty with Instrumentation Durability in Difficulty with Instrumentation Durability in Construction/River EnvironmentConstruction/River EnvironmentSoleSole--Source Instrumentation ConsultantsSource Instrumentation ConsultantsCommunication Between Contractor and Communication Between Contractor and Engineer KeyEngineer KeyBetter Results from Tiltmeters/Strain Gages Better Results from Tiltmeters/Strain Gages than than IPIIPI’’ssLook for Agreement Between InstrumentsLook for Agreement Between InstrumentsHuman Intervention with Instruments Human Intervention with Instruments Necessary At TimesNecessary At TimesInstallation and Access Can Be DifficultInstallation and Access Can Be Difficult
V. Questions/AnswersV. Questions/Answers
“Drilled Shafts for Bridge Foundation Stability Improvement�Ohio 833 Bridge over the Ohio River”�An Update��Meigs County, OhAgendaI. Introduction/BackgroundProject LocationProject TeamExisting StructureProposed StructureProject TimelineCurrent State of ConstructionStability Issues/Slope Movement/ReactionOriginal Extents of Slope MovementProbable Causes of Slope MovementSlope Geology/GeometryPlan View of Stabilization ShaftsRevised Roadway PlanInstrumentation PlanStabilization Shaft Instrumentation PlanRecent Slope Movement/ Instrumentation ResultsRecent Movement (Oct ’06 - Feb ’07)Tension Cracks – 12/11/06Construction Activity – 11/30/06Ohio River FluctuationsTied Back Retaining WallResults of InstrumentationCurrent Extents of Slope MovementExisting Bridge Tiltmeter ResultsExisting Bridge Tiltmeter ResultsStabilization Shaft Strain Gage ResultsStabilization Shaft 9 – IPI PlotTouch Down Pier Strain Gage ResultsIII. New Instrumentation on Existing BridgeIV. Lessons LearnedV. Questions/Answers