+ All Categories
Home > Documents > PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… ·...

PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… ·...

Date post: 05-Jun-2020
Category:
Upload: others
View: 21 times
Download: 1 times
Share this document with a friend
44
[1] PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI, TEHSIL-RENGALI, DISTRICT SAMBALPUR, ODISHA Aryan Ispat & Power Private Limited APRIL 2015
Transcript
Page 1: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[1]

PRE-FEASIBILITY REPORT

EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA

AT VILLAGE-BOMALOI, TEHSIL-RENGALI,

DISTRICT SAMBALPUR, ODISHA

Aryan Ispat & Power Private Limited

APRIL 2015

Page 2: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[2]

CONTENTS

Sr.No. Title Page no.

1 EXECUTIVE SUMMARY

3

2 INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION

4

3 PROJECT DESCRIPTION

10

4 SITE ANALYSIS

28

5 PLANNING BRIEF

31

6 PROPOSED INFRASTRUCTURE

33

7 REHABILITATION AND RESETTLEMENT (R & R) PLAN

35

8 PROJECT SCHEDULE & COST ESTIMATES

36

9 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)

39

Annexure – I : Process Flow Sheet

Annexure - II : Water Balance

Annexure - III : ETP flow Diagram

Annexure - IV : Plant Layout

Page 3: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[3]

1. EXECUTIVE SUMMARY

S .No Description Details

1. Name of the Project Expansion of coal washery from 0.70 MTPA to 5.70 MTPA within the Integrated Steel Plant at village-Bomaloi, Tehsil-Rengali, District Sambalpur, Odisha by M/s Aryan Ispat & Power Private Limited [AIPPL].

2. Location of the Plant Village Bomaloi, Tehsil -Rengali, District Sambalpur, Odisha

3. Coal Washery Capacity (Total) 5.70 MTPA [Throughput]

4. Total project area

Expansion proposed within the existing project area of 204.65 acres. No additional land is needed.

5. Washing Technology Heavy Media Cyclone

6. Additional Water requirement & Source Process Plantation, dust suppression etc. Domestic

55 m3/hr 4.41 cusecs water from Hirkud Reservoir approved for the entire plant is adequate to meet the additional demand for the proposed washery addition. 44 m3 / hr 8 m3 / hr 3 m3 / hr Existing washery water consumption is 8 m3/hr

7. Power requirement [Total] & Source 5 MVA – Own Power Plant connected with the Grid Corporation of Odisha.

8. Working hours 3 shifts daily of 8 hr each 330 days a year [Effective working 18 hrs a day]

9. Rehabilitation and Resettlement No R & R issue involved

10. Manpower [Operation] 70 persons

11. Estimated Cost of the Project Rs. 60.07 crores

Page 4: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[4]

2. INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION

(i) Identification of project and project proponent

Coal is the most abundant fossil fuel. India is blessed with huge coal

reserves. 85% of these reserves are non coking coal, which caters to the

need of power, cement and sponge iron plants. However, most of these

reserves are of very low grade coal. The reserves of good quality coal are

fast depleting. On one hand, the demand for coal is increasing due to

higher demand from steel, power and cement sectors. On the other hand,

extensive mechanization of mines is resulting in more inferior coal

generation. Burning of such coal produces huge quantity of ash, disposal

of which is a real problem. The Ministry of Environment & Forests (MoEF)

made it mandatory for the coal based thermal power plants located

beyond 1000 km from the pit-head and also those located in urban or

sensitive or critically polluted areas to use beneficiated coal with an ash

content not exceeding 34% w. e. f. 01.06.2001. As a result, demand for

beneficiated coal has increased substantially. MoEF vide its Notification no.

02(E) dated 02.01.2014 has made certain rules further to amend the

Environment (Protection) Rules, 2014 making it mandatory for the

following coal based thermal power plants to use, raw or blended or

beneficiated coal with ash content not exceeding 34%, on quarterly

average basis, namely, (a) a stand-alone thermal power plant (of any

capacity), or a captive thermal power plant of installed capacity of 100

MW or above, located beyond 1000 km from the pit-head or, in an urban

area or an ecologically sensitive area or a critically polluted industrial

area, irrespective of its distance from the pit-head, except a pit-head

power plant, with immediate effect; (b) a stand-alone thermal power plant

(of any capacity), or a captive thermal power plant of installed capacity of

100 MW or above, located between 750 – 1000 km from the pit-head,

with effect from the 1st day of January, 2015; and (c) a stand-alone

thermal power plant (of any capacity), or a captive thermal power plant of

installed capacity of 100 MW or above, located between 500-749 km from

the pit-head, with effect from the 5th day of June, 2016. These new

Page 5: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[5]

provisions are not applicable to a thermal power plant using CFBC or AFBC

or PFBC or IGCC technologies or any other clean technologies as may be

notified by the Central Government.

As a result, demand for beneficiated coal with ash content not exceeding

34% would significantly increase.

M/S Aryan Ispat & Power Private Limited (AIPPL) intends to expand its

coal washery capacity from 0.7 MTPA to 5.70 MTPA. The expansion is

envisaged based on Heavy Media Cyclone process. The washery will

produce washed coal of an average ash around 34% (GCV 4350 Kcal /

kg.), middling (ash content about 58%) of GCV around 2350 Kcal per Kg

useable as fuel in FBC boilers. In the washing process, waste in the form

of rejects (ash content about 86.5%) with no useful heat value (3-4%

Carbon) will also be generated.

The proposed expansion will be the State-of-the-art with close circuit

water system, classifying cyclone, high frequency screens, thickener and

multi roll belt press filters.

Brief description of nature of the project

Need for the Project

The coal India Limited and its subsidiaries are the major domestic

producers and suppliers of coal in India. The annual requirement of non-

coking coal for various industrial sectors like power, steel and cement is

increasing day by day. The reserves of low ash good coal are depleting.

To meet demand, huge reserves of inferior grade coal are being mined.

The average ash in coal now being supplied is around 45 to 50%.

AIPPL’s decision to expand its washery capacity is based on projections

made by the Working Groups on Power and Coal & Lignite for XII Plan.

Coal washing is an important area both from economic and environment

Page 6: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[6]

points of view.

The Working Group on Coal & Lignite for XI Plan had assessed that in the

terminal year 2011-12 of XI Plan, about 96% of total coal production of

the country would be non-coking coal and around 2/3rd of this non-coking

coal produced, would be of E to G grade (i.e. high ash content).

The washed non-coking coal production for 2012-2017 from existing and

proposed washeries has been projected in the Working Group report on

Coal & Lignite for XII Plan. At present [November 2011], 32 non-coking

coal washeries with a total throughput capacity of 95.96 Mty are in

operation in the country. CIL operates 5 non - coking coal washery with a

total throughput capacity of 17.22 Mty and others operate 27 non-coking

coal washeries with a total throughput capacity of 78.74 Mty.

The anticipated total capacity of beneficiation of non-coking coal in India,

by the end of XII Plan, has been estimated as 199 Mty and projected low

grade coal production [other than pithead linked coal] as 360 Mt, thus

there will be a huge gap of 161 Mt for capacity addition requirement of

washing the entire low grade coal to be produced.

At present, Coal India Ltd. (CIL) operates 17 coal washeries with a total

capacity of 39.4 Mty. Of which, 5 are non-coking washeries with a total

capacity of 17.22 Mty and 12 coking coal washeries with 22.18 Mty.

Contracts have been finalized for three more washeries. Besides, action to

finalize to more washeries is in the advance stage. Further, 12 more

washeries have been identified by CIL to be taken up during the XIIth Five

Year Plan.

The wide gap assessed between the projected requirement of beneficiated

non-coking coal and the existing total capacity, clearly indicates that there

is enough scope for building up of capacity to beneficiate non-coking coal

in the private sector. Further, it may not be consistently feasible to

Page 7: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[7]

operate washeries at their 100% capacity. Therefore, provision for

another 40-50 Mt capacity addition may have to be considered in

subsequent phase.

As the major availability of coal during the XII Plan is expected from the

Karanpura, Korba, Mand – Raigarh, & Ib Valley coalfields, AIPPL proposal

for expansion of Bomaloi washery by 5 MTPA is justified. Supply of sized

quality coal from the washery to the client is important for AIPPL.

At AIPPL’s washery, raw coal of around 45 - 50% ash will be washed to

produce washed coal having around 34% ash. The primary discards will

be subjected to secondary washing to produce middling at around 58%

ash and rejects at around 86.5% ash. The use of washed coal has the

following advantages:

1. Supply of consistent quality coal can be ensured thereby avoiding

frequent adjustments in input to boiler and minimizing operators’

error

2. Higher thermal efficiency of boiler and higher steam rate

3. Less wear and tear of the coal grinding mills

4. Lower capital and operating cost for installing smaller ESP

5. Higher productivity and campaign life of DRI kiln

The total capacity of the coal washery after expansion will become 5.70

Million TPA of raw coal throughput. The existing plant capacity is 0.70

MTPA. Additional 5 MTPA capacity will have the following parameters:

Capacity : 1000 TPH

No. of operating days in a year : 330 days

No. of effective operating hours in a day: 18 hours, three shifts

operation

Page 8: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[8]

Plant utilization : 85%

Annual throughput : 100 X 18 X 330 X 0.85

= 5049000 tonnes

Say 5 million tonnes

The project will have the following outputs:

Raw Coal - Ash - 45 - 50%, Moisture 5.5%, GCV 3000 K

cal / Kg, FC 26%, VM 24%.

Washed Coal - Ash - 34%, Moist 12%, FC - 36%, VM 28%,

Yield 44%, GCV - 4350 K cal / Kg.

Middling - Ash - 58%, Moist – 8.5%, FC 22%, VM 20%,

Yield 47% , GCV - 2350 K cal / Kg.

Rejects - Ash - 86.5%, Yield 9% (No useful heat value)

All the yield figures indicated are tentative and are meant for estimation

purposes only.

(ii) Demand-Supply Gap

The demand for washed non-coking coal has significantly increased in

view of the Ministry of Environment and Forests Notification on use of coal

with ash content not more than 34% in power plants located beyond 1000

km from the pithead and in urban area or sensitive area or critically

polluted area. The demand for use of washed coal for power generation

would further increase as the distance threshold limit has been reduced to

500 km. The Government has also laid thrust on adoption of Clean Coal

Technologies (CCTs) to mitigate adverse impact of coal usage on the

environment.

Page 9: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[9]

Total established non-coking coal washing capacity [November 2011] of

CIL & others is 95.96 MTY. The coal requirement for power generation in

2016-17 has been estimated by CEA as 842 MT. The requirement of

washed coal will be 361 MTPA. This does not include demand from the

other sectors like sponge iron and cement.

By the end of XII Plan, low grade coal production, other than pithead

linked coal, has been estimated as 360 MT and total capacity of

beneficiation of non-coking coal as 199 MTY. Thus there is a huge gap of

161 MT for washery capacity addition in the XII Plan.

(iii) Imports vs Indigenous production

Raw coal will be obtained from the Mahanadi Coalfields Ltd. mines on

behalf of the clients. Cost-wise indigenous production is much cheaper

than the imported equivalent quality coal.

(iv) Export Possibility

No coal will be exported.

(v) Domestic / export Markets

Coal washeries established in India are not able to meet the domestic

requirement of washed coal at present.

(vi) Employment Generation (Direct &Indirect) due to the

Project

During construction period, the requirement of man power will be about

200. In the operation phase, 70 persons will get direct employment in

various services. About 250 persons will get indirect employment.

Page 10: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[10]

The plant management will be responsible for overall performance of the

unit. The management will be supported by a team of highly skilled

persons having varied expertise and experience, which will function

individually as well as collectively for overall performance of the plant.

The following set up is recommended to look after the various activities in

the washery:

S. No. Position Number

1. Manager Production 1

2. Engineer (Mech. & Process, Electrical &

Instrumentation)

4

3. Foreman cum control room operator 8

4. Fitter cum Operator 10

5. Helper 10

6. Electrician 8

7. Helper for Electrician 8

8. Instrument mechanic 4

9. Chemist 4

10. Helper for chemist 4

11. Office and Weighbridge staff 5

12. Horticulturist 1

13. Watchman 3

TOTAL 70

Besides, unskilled workforce (10 heads per shift), mostly from the nearby

villages, required for cleaning & other day to day jobs like magnetite

charging etc. will be hired through contractor.

1. PROJECT DESCRIPTION

(i) Type of project including interlinked and interdependent

projects, if any.

Page 11: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[11]

It is envisaged to create additional 5 Million TPA capacity to wash coal using

Heavy Media Cyclone technology.

(ii) Location

The proposed expansion is within the existing integrated steel plant site at

Bomaloi Village, Tehsil Rengali, Distt. Sambalpur, Odisha. Total project area

is 204.65 acres. The project span between Latitude: 22°08’02.39”-

22°08’19.41” North and Longitude: 83°14’ 30.21”-83°14’ 50.01” East. The

entire project area falls in Survey of India Toposheet No. 73C/2, (1A

Quadrant).

The index map of the project site is shown in Figure-1 and a map showing

area 10 km around the project site is shown in Figure-2.

Page 12: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[12]

FIGURE-1 INDEX MAP SHOWING THE PROJECT SITE

Page 13: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[13]

FIGURE-2 MAP OF THE AREA 10 KM AROUND THE PROJECT SITE

Page 14: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[14]

(iii) Details of alternate sites considered and the basis of selecting

the proposed site, particularly the environmental considerations

gone into should be highlighted.

Alternate sites have not been considered as the proposal is for expansion

of the coal washery within the project premises. The requisite logistic

support is available at the existing plant.

(iii) Size or magnitude of operation.

5.70 MTPA (Total Throughput) capacity

(v) Project description with process details

The entire raw coal for beneficiation will be brought from the mines of MCL

by rail. The own railway siding is about 700m from the project site.

Modular concept of designing the washery is envisaged. Two identical

additional modules of 2.50 MTPA each will beneficiate 1000 TPH coal.

Washed coal, middling and rejects will be transported by rail-cum-road

mode.

RAW COAL CHARACTERISTICS & SELECTION OF PROCESS

Coal Characteristics

Selection of process is based on the study of the available washability test

results of coal from MCL mines in the region. It was found that in average

raw coal, ash content varies from 45 % to 50 %.

Technology & Process

Scope of The Project

The scope of the project is to enhance the capacity of the coal

beneficiation plant to 5.70 MTPA to produce sized and quality coal to suit

Page 15: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[15]

the captive requirement as well as that of the other clients.

Coal Washing Processes

There are several processes for coal washing which may be categorized

under two broad headings as follows:

Dry Process

Pneumatic tables or Jig Rotary Breaker

Wet Process

Natural media barrel Natural media cyclone Jig Chance cone separator Heavy media Bath Heavy media drum Heavy media cyclone Larcodem Triflow separators Dyna Whirlpool separator Vorsyl Separator Froth floatation Column floatation Spirals

Brief description of some of the processes

Principles and techniques of different coal cleaning methods are outlined

below:

Jigging

The separation of coal from shale is accomplished in a form of fluidised

bed created by a pulsing column of water which produces a stratifying

effect on the raw coal. This is quite different in its effect from dense-

medium separation. This stratifying effect results in a definite order of

deposition of all fragments contained in the bed. The main purpose of the

rising and falling column is to create what is known as ‘dilation’ or opening

Page 16: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[16]

up of the bed, and it is the extent to which this dilation may be controlled

which governs the effectiveness of the separation.

During the pulsion, or rising part of the cycle, the bed is elevated en

masse. But as the velocity decreases towards the end of the pulsion

stroke, the bed begins to dilate, with the bottom ceasing motion first and

the lowermost fragments commencing their descent. This produces an

element of freedom of movement for all fragments signalling the

commencement of the various principal effects leading to stratification.

The most influential effects occurring during jigging are, in order of

occurrence:

o Dilation;

o Differential acceleration;

o Hindered settling; and

o Consolidated tracking.

The Jig is divided into two compartments lengthwise, one completely

sealed from the atmosphere - called the air chamber - and one open

section, which receives the material to be separated and accommodates it

during the stratification process. The water valve allows admission of ‘

back water’ at a level below that of the bed plate. The longitudinal section

is further divided into several sections or compartments along the

direction of flow. The purpose of this is to provide control over the

separation as the material moves along the box; hence each of these

sections has its own individual air and water controls. Two-elevator

arrangement is the most common. In the first, moving along the direction

of flow, the heavier shale are separated. In the second, lighter stones and

any middling are extracted.

The plate which supports the coal and shale bed, usually referred to as the

bed plate or screen plate, allows the water current to rise and fall and is

usually perforated. Fine material inevitably percolates through the

perforations to the hutch compartment and this is removed by screen

Page 17: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[17]

conveyor which delivers it to the bucket elevators.

Efficient collection of the product is of paramount importance. Clean coal

overflows the end of the box together with the majority of the flowing

water.

Merits

Water is used in this process instead of magnetite.

This process gives fairly good efficiency if the coal is easy to wash (low

NGM like European coal) at cut point gravity above 1.7 (deshaling

application).

Large size coal up to ( - ) 100 mm can be fed to Jigs.

Demerits

Not a suitable process for washing Indian Coal which is “Exceedingly

Difficult” to wash due to high Near Gravity Material (NGM).

Mediocar efficiency.

Sensitive to variations in feed rate and / or characteristics.

Electronic adjustment system is complex and requires optimizing.

Efficiency becomes extremely low for gravities below 1.60.

The process misplacement is very high.

High EP (Ecart Probable) around 0.14.

Difficulties in maintaining good product quality.

Heavy Media Coarse Coal Bath

Static dense-medium bath behave in a similar way to laboratory float-sink

apparatus. Two categories of dense-medium baths, deep baths and

shallow bath, have many common features. Float products are removed

from the top of the baths, usually by paddles or by the natural flow of the

medium. Discard removal varies from one type to another. Dense medium

baths usually treat coal in the 100 mm X 6 mm size range.

Page 18: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[18]

Merits

The process has good efficiency of separation for coal above 10/13 mm

size.

Insensitive to variations in feed rate and / or characteristics.

Easy to adjust the separating gravity.

Wide range of separating gravity (1.30 – 1.90).

Fairly good EP of around 0.06 can be achieved.

Demerits

Coal below 10/13 mm size shall have to be separately washed in H.M.

Cyclone or small Coal Jig which have lower efficiency.

If lower size coal is fed, the efficiency will fall drastically and also

create other problems in the bath.

Efficiency lower than HM cyclone process treating sized coal.

Heavy Media Cyclone Cleaning

Where only gravitational forces are involved in providing the downward or

high density separating force, the type of dense-medium separators

employed treat only relatively coarse solids i.e., + 6 mm. They cannot

separate out particles smaller than 6 mm effectively, as for such small

particles, gravity is overridden by viscosity forces. What is required is a

separating force surpassing gravity. As a cyclone utilizes the centrifugal

force (e.g., 100 X gravity) for the separation of fractions, it became

possible also to treat fine-grained coal (sized, e.g. 0.5 mm to 6 mm).

Because the force potential of cyclone separator is great, it is possible to

treat relatively large quantities of raw coal in a unit of small physical size

when compared to dense-medium baths. The corresponding relationship

to this form of separation is:

Settling Velocity, S = [S2/r X v(d – D) – R]

Page 19: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[19]

Where, v is the volume of coal sphere, d is the density of coal, D is the

relative density of the fluid, R is the resistance factor and r is the radius of

the path of the grain.

The feed comprising raw coal and medium is introduced at a precise

pressure into the tangential inlet. The ensuing flow is rapid and spiralling

towards the apex of the unit, and in the core of the cyclone a very fast

flow-rate creates centrifugal classification causing shale to move outwards

towards the inner wall of the conical shell. As a result shale is discharged

from the spigot or nozzle and coal is carried by the rising internal spiral

towards the vortex finder to be discharged from the overflow.

Merits

Due to higher efficiency of separation more yield of cleans.

The process can handle wide variation in capacity.

Specific gravity of separation can be adjusted very easily, if coal

characteristics change.

Quantity of water handled much less compared to Jig Process.

Operation and maintenance is very easy.

Most suitable for coal having difficult washability characteristics.

Insensitive to variations in feed rate and / or characteristics.

Wide range of separating gravity ( 1.30 – 1.90).

Low EP (0.025 to 0.035).

Demerits

As finely ground magnetite will be used there will be higher erosion in

the pipe lines. Basalt lining or extra thick pipe will reduce the problem.

In case of power failure there will be a chance of jamming. The

contents of slurry lines are drained out to overcome this problem. The

drained material is pumped back to the system after the plant

restarted.

Page 20: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[20]

Selection of Suitable Process

Selection of coal washing process depends mainly upon the following criterion:

Washability characteristic of input coal.

Size and quality (ash & moisture) requirement of products.

Indian coal is of “drift” origin (unlike European, Australian Or American

coal which are of “In situ” origin), hence, have very high Near Gravity

Material (NGM). Presence of high NGM (more than 20 units) in ROM coal

makes the washing of coal very difficult. Hence, selection of suitable

washing process is of paramount importance for Indian coal. Bird’s

classification of NGM Vis-à-Vis suitable washing process is indicated

below :

NGM Type of Coal Process

0 – 7 Simple Coal Jig 7 – 10 Moderately difficult Baths, tables, spirals 10 – 15 Difficult to wash 15 – 20 Very difficult HM Cyclone 20 – 25 Exceedingly difficult > 25 Formidable

From the above table, it is clear that the HM Cyclone process is the only

suitable process for treating high NGM Indian coal.

Moreover, from process efficiency point also the HM Cyclone process is most

suitable process which gives lowest EP (Ecart Probable – means Error

Probable) i.e. lowest misplacement. A comparison of EP achievable in

various processes is given below:

1) HM Cyclone : 0.025 to 0.035.

2) Jig : 0.10 to 0.12

3) Barrel : 0.09 to 0.10

Page 21: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[21]

The process misplacement which is depicted by the partition curve (Fig 8.3

attached) also shows minimum misplacement in case of HM Cyclone

process.

Considering all the above mentioned factors, Heavy Media Cyclone process

is recommended for both primary & secondary separation. This will

contribute to higher yield by HM cyclone process, which is about 10 to 15%

more than Jig or Bath.

Process Know how

Complete process knowhow will be provided by M/s A. Mukherjee &

Associates, a company incorporated in 2003 with a totally futuristic

perception about the needs of the industry.

Plant and Machineries for the washing plant will be procured from various

reputed manufacturers in India and abroad as per the specifications laid

down. Detail engineering, design and drawings for civil, structural,

mechanical, electrical, control system and instrumentation will be provided

by M/s. A. Mukherjee & Associates. Civil works and site construction and

erection jobs will be executed through reputed parties in the field.

Brief Description of the Process

Pre-treatment section

Coal [ROM] from MCL mines will be transported to the washing plant by rail.

Own railway siding is 700m away from the project site. Trucks will either

dump coal into the ground hopper or on to the nearby ground dump from

where the same will be fed in the ground hopper.

From the ground hopper the raw coal will be subjected to two stage close

circuit crushing and screening and finally sized to minus 50 mm. The sized

coal will be taken to a series of storage bunker

Page 22: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[22]

Washing Section

Sized raw coal, (-) 50 mm, from bunker will be transported to the washing

plant building through covered belt conveyors where the same will be fed

into coal wetting launder where water will be added with coal. Coal water

slurry then will flow through launder to a set of Desliming Sieve Bend and

Screen to remove (-) 1 mm coal fines from the slurryl. Coal slurry collected

from Desliming Sieve Bend and Screen under pan will gravitate through

pipes to a Fine Coal Sump.

De-slimed coal coarser fraction of (+) 1 mm will go from screen discharge

chute to the launder. Magnetite media of required specific gravity will be

added at the back of the launder to get mixed with the coal and

simultaneously to push the mixture of magnetite & coal slurry into the

central column provided in the centre of the Primary HM Cyclone tank.

Coal & magnetite mixture from the centre column will be pumped by

Primary Cyclone Feed Pump to feed to Primary Heavy Media Cyclones.

Cyclones are lined with high alumna ceramic tiles. Cyclone will have

overflow and underflow. Clean coal along with magnetite media will be

received as over flow from the cyclone and be fed to a set of Clean Coal

Sieve Bend and Clean Coal Draining & Rinsing Screen. Magnetite media will

be drained through Sieve Bend and first part of the Screen and be collected

in the screen’s dense catch pan. The same will be re-circulated back to the

primary washing system.

The carried away magnetite with the coal particles will be removed by water

spraying in the discharge part of the screen. Magnetite removed from coal

by water spraying will be collected in the dilute catch pan of screen as dilute

media, and be taken to dilute media tank

Underflow of primary cyclone treated as primary discard will be fed to a set

of double sieve bend. Magnetite media drained through sieve bend will be

Page 23: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[23]

re-circulated back to the primary system.

Primary discard collected from discharge end of double sieve bend will be

fed to the central column of secondary heavy media tank along with

magnetite media of required specific gravity.

Coal and magnetite mixture from the central column will be pumped by

secondary cyclones feed pump to feed secondary heavy media cyclones.

Middling along with magnetite media will be received as overflow from the

cyclone and will be fed to a set of sieve bend and draining & rinsing screen.

Underflows of cyclone along with magnetite are also fed to a sieve bend &

screen. Magnetite media will be drained through sieve bend and first part of

the screen and be collected in the screen’s dense catch pan. The same will

be re-circulated back to the secondary system.

Carried away magnetite with the coal particles will be removed by water

spraying and be collected in the dilute catch pan of the screen and the same

will be taken to dilute media tank.

Clean coal collected from discharge end of clean coal screen will be dried in

centrifuge and transported to clean coal storage shed through belt conveyor

/ or directly to clean coal storage bunker.

Middling collected from overflow of the screen will be dried in a centrifuge.

Dried middling along with dewatered fine coal will either be transported

directly to FBC Power Plant through belt conveyor or to middling storage

bunker.

Reject collected will be transported to a reject bunker and from there to

reject disposal area.

Fine coal slurry collected in the fine coal tank will be pumped into a set of

classifying cyclone. The underflow of classifying cyclone will be dewatered

Page 24: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[24]

in Hi Frequency screen while the overflow from cyclone will be fed to a Hi-

rate Thickener. Thickened slurry from thickener will be dewatered in a Multi

Roll Belt Press filter. Anionic and Cationic Flocculants will be used in

thickener and Belt Press to facilitate settling and dewatering process. The

discharge from Hi Frequency screen and belt press will be mixed with

middling for dispatch to the end users.

Media Preparation & Regeneration Circuit

Dilute media as collected in the Dilute Media Tank will be pumped by a

Dilute Media Pump to a Magnetic Separator Feed box. From there, the dilute

media will be feed to a Wet Drum Magnetic Separator. The Separators will

separate out magnetite from water and the dense media gets dislodged

from the magnetic drum to the dense media launders and from there to the

Primary Heavy Media Tank and Secondary Heavy Media tank.

Effluent from the magnetic separator goes to fine coal tank through wetting

launder.

During the process of operation, some amount of magnetite gets lost which

will be made up by adding fresh magnetite to the system. For this purpose,

a magnetite addition RCC sump will be provided where ground magnetite

will be charged and diluted with water. The dilute magnetite media then will

be pumped through a vertical sump pump to the Dilute Media Tank.

Process Control Philosophy

There will be a control room with a centralized PLC based control system to

enable operator(s) to start-up, monitor, control and shut down all main

equipment and process functions like feed input to the plant, product

transfer to conveyors etc. A hot standby back-up will be provided to take

care of power tripping and fluctuations.

Page 25: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[25]

All major items of equipment will be interlocked in an automatic stopping

sequence within the PLC in such a manner that both material and liquid

flows will always be fail safe. Stop push buttons will be located adjacent to

each drive and will be operable at all times.

An emergency stop button will be located either in the control room or in the

operating computer to enable the whole plant to be stopped.

The density of the magnetite media will be controlled to ensure the required

quality of the washed products. The specific gravity control will be achieved

automatically by respective modulating splitter actuators. The density

measurement will be done by a nucleonic density gauge. Indication and

recording of the density levels will be done in the control room computer.

(vii) Raw material required along with estimated quantity likely

source, marketing area of final products, mode of transport of raw

material and finished product.

Additional 1000 MTPA raw coal will be brought to the washery site by rail

from the MCL mines which are linked to the rail network otherwise by road.

The washery will produce clean coal, middling, fines and rejects. After captive

consumption [100TPD], washed coal and middling including rejects will be

transported to the clients. Clean coal, middling mixed with fines and rejects

will be transported to the end users by rail-cum-road. The railway siding is

700m from the project site. Lapanga railway station is about 1 km from the

project site.

(vii) Resource optimization / recycling and reuse envisaged in the

project, if any, should be given.

Plant will have close circuit water circulation system so that no effluent is

discharged in the open outside the plant boundary. All the process effluent

will be collected in the thickener. Settled slurry of the thickener will be

Page 26: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[26]

dewatered in a multi roll belt press filter. The dewatered filter cake will be

mixed with the middling. The clarified water from the thickener overflow will

be re-circulated in the washing circuit as process water. Only make-up water

requirement will be added in the clarified water tank.

Since the plant will be designed with close circuit water system as described

above, no tailing dam will be required for treating the process effluents /

tailings. However, a set of cascading type emergency settling ponds will be

constructed within the plant boundary to take care of any unforeseen

situation like pipe line jamming or break down of thickener. The clarified

water from these emergency settling ponds will also be pumped back to the

plant for use as process water. These emergency settling ponds will also be

used for harvesting rain water, which can be used as process water.

Expensive imported equipment like centrifuge, belt press filter, high

frequency screen as well as thickener will be installed to ensure close circuit

water system; minimize loss of water through products; and evaporation

losses.

(vi) Availability of water its source, Energy / power

requirement and source should be given.

Water Supply & Sewerage

Water supply arrangement for the proposed expansion will basically cover

the industrial and potable water demand. Washery will operate on closed

water circuit, therefore, only make-up water is required. Requirement of

additional water for pollution control measures will be 8 m3/hr for dust

suppression, floor washing and plantation. In accordance with the

technology adopted, process and other features, the additional process

Page 27: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[27]

water [make-up] requirement of the washing circuit will be 44 m³/hr. An

additional RCC water reservoir of around 1500 m3 storage capacity will be

constructed.

Additional 55 m3/hr of water is required for the proposed washery.

4.41 cusecs water approved for the integrated steel plant from the

Hirakud Reservoir is adequate to meet the additional water demand.

There will be no industrial waste water discharge as the plant will be

designed on zero effluent discharge principle. Septic tanks and soak pits

will be provided for sewage treatment and disposal.

Particulars Water Quantity m3 / hour Remarks

Additional

Requirement

Consumption

/ loss

Waste

water

generation

Process [Make-up]

44 44 - Close Circuit System

Domestic & others 3 1 2 Septic tank & soak pit

Dust suppression & plantation

8 8 -

Total 55 53 2 Zero Effluent

Power

The total connected load for the coal washing plant including crushing &

screening will be around 5 MVA. Specific power consumption for washing

including crushing & screening will be around 2 units per tonne of raw coal

throughput.

Power for the proposed expansion will be met from the own the Power Plant

/ received through the State Grid. The electrical equipment like

Transformers, MCC distribution centers, cables, lighting etc will be suitably

selected as per requirements. Proper earthing is envisaged as per the

Indian Electrical rules and relevant Indian standards.

Page 28: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[28]

Proper illumination of the plant, conveyor gantries, and transfer points and

general illumination etc. is envisaged. Proper PLC based automation system

is envisaged for the automatic control of all the equipment including

instrumentation like level transmitters, flow meters, pressure gauges, fire

alarms system.

Two DG sets of 1250 KVA each are available at the project.

(vii) Quantity of wastes to be generated and scheme for their

Management/disposal.

The washery will generate additional 90 TPH rejects. Efforts will be made to

supply rejects to the brick kiln owners in the region.

4. SITE ANALYSIS

Infrastructure

For establishment and successful operation of coal washing plant, it is

imperative to ensure availability of the following infrastructure:

o Availability of additional raw coal [1000 TPH] and its proximity to

the plant to reduce cost of transportation

o Road / Rail head connection so that raw materials and products can be easily and economically transported

o Availability of water

o Permanent and reliable source of power

o Adequate land for the plant, storage of raw coal and products and

disposal of waste material

Coal from MCL mines, namely, Basundra, Samleswari, Belpahar,

Lakhanpur etc., located within about 100km, will be transported by rail.

Own railway siding is 700m from the project site. The nearest Railway

Page 29: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[29]

station is Lapanga about 1 km from the project site. Power supply can be

easily met from 33 KVA line connected with the Grid Corporation of

Odisha. Sufficient land for expansion of coal washing plant is available.

(i) Connectivity

District Headquarter Sambalpur, nearest township Jharsuguda and rail

head at Lapanga are about 24 km, 22 km and 1 km respectively from the

project site. The nearest Airport is at Raipur, 292 km by road from the

project site. The nearest State Highway is SH-10.

(ii) Land details

No additional land for the proposed expansion is required. The existing

204.65 acres land acquired through IDCO is adequate to meet the

functional needs, green belt development, essential staff accommodation

etc.

It is proposed to bring coal to the plant site by rail-cum-road mode.

Washed coal, middling and rejects will be dispatch from the existing

railway siding.

Sr. No. Particulars Area (in Acres) Existing Additional

1. Washery Plant 4.47 9.85

2. Raw Coal Stockyard 5.00 7.00

3. Clean coal, middling & Rejects 5.00 4.47

4. Plantation - 9.15

Total 14.47 30.47

** Includes bins (iii) Topography and drainage

The topography of the site is fairly flat and requires minimum filling. No

filling material from outside is envisaged for the plant construction.

Page 30: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[30]

The drainage pattern in the buffer zone is dendritic to sub-parallel. The

drainage density is medium to high.

(iv) Existing land use pattern, shortest distances from the periphery

of the project to periphery of the forests, water bodies.

The land use of the project site is industrial. There is no water body in the

project area. Information on forests and water bodies falling within 10 km

from the project site is given below:

Water bodies

10 km around the project site forms the part of Mahanadi river basin. The

river Mahanadi and its tributaries control the drainage of the area. The

main tributaries of Mahanadi, within 10 km, are Bheden river [6.6 km,

NW] and Ib river [10.5 km, WNW]. The minor tributaries are Matwali nadi

[2.6 km, S]. The river Mahanadi has been dammed at Hirakud. The

Hirakud Reservoir is about 1 km W of the project site.

Forests

Ghichaimura RF, Maulabhanja RF Patrapalli RF, Baighara RF and Katikela

RF are 4.3 km E, 5.2 km SW, 8.2 km NW, 8.6 km S and 8.6 km NNE

respectively from the project site.

There is no notified Sanctuary, National Park, Tiger reserve or Biosphere

reserve within 15 km around the project site. Elephant corridor is about

36.5 km SE from project site. Elephants movement starts from Badrama

Sanctuary located within the Sambalpur Elephant Reserve [SER] and

enters the adjoining Mahanadi Elephant Reserve [MER]. Nearest fringe of

SER is 0.1km E. MER is about 89.5 km SE from project site.

Page 31: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[31]

(v) Infrastructure facility The plant site is well connected through the State and National highways. The nearest railway station is at Lapanga about 1 km of the project site.

5. PLANNING BRIEF (i) Planning concept (type of industries, facilities transportation

etc). Town and country planning/development authority classification

The following large scale industries / PSUs [2010-11] are located in

Sambalpur and in its surroundings:

1. Maa Samaleshwari Sponoge Iron Ltd., Katrabag, Sambalpur

2. T.R Chemicals Pvt. Ltd., Belpada Bamra

3. M/s. Hindalco Industries Ltd., Hirakud

4. Samaleswari Ferro Metal Pvt. Ltd., Dishalkhinda, Dhankuda

5. Bhushan Steel & Power, Thelkuli, Rengali, Sambalpur

6. Aryan Ispat & Power Pvt. Ltd., Bomaloi, Rengali, Sambalpur

7. Rathi Steel & Power Projects Ltd., Sikridi, Pitapali, Rengali

8. R.B Sponge Iron Ltd. Kenghati, Jujumara,

9. Vedanata Smelter Plant & CPP

10. Jay Jagannath Steel & Power Ltd., Belpada, Bamra

11. Shyam DRI, Power Ltd., Rengali

12. Viraj Steel & Energy Ltd., Gurupali

13. Maa Samaleshwari Industries Pvt. Ltd., Lapanga

14. Aditya Aluminium Ltd., Lapanga

15. Mahanadi Coal Fields Ltd., Jagruti Vihar, Burla

16. Hindalco Talabira Coal Mine

Besides, there are 5990 micro and small enterprises and other units in the

Sambalpur District. The project area falls in the region which is well

connected by road and rail to the District Headquarters Sambalpur.

Page 32: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[32]

Due to setting up of increasing number of large and medium industries in

Sambalpur and nearby region, there is positive growth in the large and

medium enterprises in the area. The industrial growth and development in

the surroundings is being organized by the District Industrial Centre under

the Department of Industries, Govt. of Odisha.

(ii) Land use planning

Expansion is within the 204.65 acres of integrated steel plant. 30.47

acres of land is available for the washery plant expansion. Out of 204.65

acres, 73 acres area is under plantation.

(iii) Assessment of infrastructure demand (physical & social)

Amenities / Facilities.

Facilities available for the existing project will be upgraded for -

Routine maintenance of all equipment.

Incidental minor repair / replacement of sub-assemblies and

components of CHP equipment, coal washery equipment and

accessories, water pumps and pumping installations.

Day-to-day repair and maintenance of plant and machinery.

Inspection and scheduling of major repairs from outside agencies.

Service Buildings

Existing office building, sub-station, other buildings areas such as first

aid centre, rest shelter, canteen etc. of appropriate size will be upgraded,

if needed.

Residential Buildings

The Bachelor’s accommodation and staff quarters will be located in the

project area.

Page 33: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[33]

Roads

No new approach road is required. 6. PROPOSED INFRASTRUCTURE

(i) Industrial area (processing area)

The entire 204.65 acres of project land is under industrial use.

(ii) Residential Area

Improvement of bachelor’s accommodation and staff quarters in the

project area.

(iii) Green belt

Approx. 73 acres of the project area is under plantation.

(iv) Social infrastructure

The existing canteen, rest shelter / room, recreation room will be upgraded,

if needed.

(v) Connectivity

The existing road and rail network is adequate and does not require any

up-gradation. Already coal from the MCL mines is being transported via

these routes.

vi) Drinking Water Management (Source & Supply of water) Domestic and other purposes water demand of the existing integrated

steel plant including the washery for is 35 m3/hr. The additional

Page 34: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[34]

requirement of 3 m3 / hour water for domestic purpose will be met from

ground water resource. The project area on ground water resource

considerations falls in “Safe Zone” category.

(vii) Sewerage System.

Domestic sewage will be treated and disposed of through Septic Tanks &

Soak Pits.

(ii) Industrial Waste Management.

a) Washery effluent:

Zero effluent discharge will be practiced. Waste water will be collected in

slime ponds and circulated back in the process.

b) Domestic effluent:

Septic Tanks & Soak Pits have been provided. Sludge after digestion is

used as manure.

(iii) Solid Waste Management. a. Rejects Additional 90 TPH rejects will be generated from the proposed expansion.

Efforts will be made to utilize this waste material in backfilling of de-

coaled pits in MCL opencast mines and supply to the brick kilns

manufacturers in the nearby region and / or other buyer(s).

b. Municipal waste

Additional 600kg per month municipal waste will be generated, which

after composting will be used as manure.

Page 35: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[35]

(iv) Power Requirement & Supply / source.

Power requirement of 5 MVA will be met from the own power plant

connected with the Grid Corporation of Odisha. A standby DG set of 125

KVA will be provided.

7. REHABILITATION AND RESETTLEMENT (R & R) PLAN

The entire 204.65 acres of project land is already under possession

through IDCO. There is no R & R issue involved.

PROJECT SCHEDULE & COST ESTIMATES (i) Likely date of start of construction and likely date of Completion It is planned to award EPC contract within 3 - 4 months of issuance of

“Environmental Clearance” and ‘Consent to Establish” and complete the

project in 24 months period.

(ii) Estimated project cost along with analysis in terms of economic viability of the project. Total project cost has been estimated as Rs. 60.07 crores. Broad break-up of investment is given below

1) Land : Rs.190.00 Lakhs 2) Land Development : Rs. 50.00 lakhs 3) Know How : Rs. 150.00 Lakhs TOTAL : Rs. 390.00 Lakhs

TABLE-8 : COST ESTIMATE FOR 800 TPH THROUGHPUT CAPACITY

Page 36: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[36]

COAL WASHING PLANT

Sr. No.

Item Description Make Quantity Amount (Rs. in Lakhs)

Total A. Know How

A.1

Design and Engineering

L.S. 55.00

B. Building & Structural B.1 Civil Work (RCC

work including) 3000 Cu

M3 230.00

B.2 Structural Steel work

3000 MT 1650.00

Sub Total B 1880.00 C. Plant & Machinery C.1 Unbalance Motor

Feeder IC /

ELECTROMAG/TRF

Lot 35.00

C.2 Over Band Magnetic Separator & Metal Detector

ELECTROMAG 2 Sets 25.00

C.3 Rotary Breaker L&T/TRF/MBE 1 No. 165.00 C.4 Crusher TRF/MBE/MECH

TECH 4 Nos. 175.00

C.5 Dry Screen MECHTECH / TRF / IC

4 Nos. 63.00

C.6 Wet Screens : Desliming D&R Screen

TRF/IC

12 Nos.

160.00

C.7 Sieve Bend MMH 16 Nos. 45.00 C.8 Pumps (Slurry) Metso/Warman /

MBE Lot. 90.00

C.9 H M Cyclone 710 Carborundum 12 Nos.

55.00

C10 Classifying Cyclone Carborundum 12 Nos.

20.00

C.11 Hi Rate Thickener HDO/MBE/Delkor 2 Nos. 65.00 C.12 Horizontal Basket

Centrifuge Don Valley, UK

6 Nos. 330.00

C.13 Wet Drum Magnetic Separator

Eriez/Ing. Mineral

4 Nos. 66.00

C.14 High Frequency Screen

Linatex, S.A / Parnaby, UK

3 No. 66.00

C.15 Multi Roll Belt Press Filter

Parnaby 2 Nos. 245.00

Page 37: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[37]

Sr. No.

Item Description Make Quantity Amount (Rs. in Lakhs)

C.16 Air Compressor with drier

IR/Atlas

2 Sets. 34.00

C.17 Dust Suppression system

TPS / Kaveri Lot 55.00

C.18 Belt Conveyor MMH/TRF / Masyc

900 Mtr. 245.00

C.19 Travelling Tripper MMH 2 Nos. 27.00 C.20 EOT Crane with grab

bucket WMI / Federal / Asian / Jaypee

3 Nos. 84.00

C.21 Rock Breaker 1 No. 28.00 C.22 Miscellaneous Items

like gate etc. MMH Lot 28.00

C.23 Erection & Commissioning

LS 210.00

C.24 Taxes & duties 355.00 Sub Total C 2671.00

D. Misc. Fixed Assets D1 Pipes & Pipe fitting Steel Tube /

Vasuki Lot 50.00

D.2 Valves Vaas/ Audco/ Steam & Mining /

Vasuki

Lot 50.00

D.3 Tiles & tiling work VS Enterprise/ CUMI

Lot 66.00

D.4 Electricals Lot 220.00 D.5 Instrument & cable Lot 110.00 D.6 Plant Lighting etc. Lot 30.00 D.7 Public Address system Lot 30.00 D.8 Laboratory Eqpt.. Lot 55.00

Sub Total D 611.00 E. Substation and

125 KVA DG Set 125.00

F. Total A+B+C+D+E 5342.00 G. Contingency 5% 275.00

Grand Total 5617.00** ** Excludes cost of land and land development

OPERATING COST

The operating cost of the coal washery per tonne of raw coal

throughput will be Rs. 80.00, which does not include interest and

depreciation components. Its break-up is given below:

Page 38: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[38]

Manpower - Rs. 8.00 Magnétite - Rs. 5.00 Floculant - Rs. 10.00 Spares - Rs. 12.00 Lubricants etc. - Rs. 8.00 Electricity - Rs. 28.00 Misc. - Rs. 9.00 Total - Rs. 80.00 On the basis of capital investment envisaged for the project, this project

is economically viable.

9. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS) POLLUTION CONTROL

Design of washing plant expansion will include measures to ensure

effective compliance with environmental regulations. The following

measures are proposed:

Online Continuous Ambient Air Quality Monitoring system

(CAAQMS) and Continuous Stack Monitoring system CSMS have

been installed at the plant and real time data for PM, SO2, CO, NOX,

PM2.5 & PM10 is being transmitted to the State Pollution Control

Board server.

Dust extraction / dry fog type dust suppression system to control

dust from the material transfer points.

Regular Water Sprinkling on Roads Plant with close circuit water circulation system so that no effluent

is discharged in the open outside the plant boundary. All the

process effluent will be collected in the thickener. Settled slurry of

the thickener will be dewatered in a multi roll belt press filter. The

dewatered filter cake will be mixed with the middling. The clarified

Page 39: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[39]

water from thickener overflow will be re-circulated to the plant for

use as process water. Only make-up water requirement will be

added in the clarified water tank.

Since the plant will be designed with close circuit water system, no

treatment of the process waste water will be needed. Emergency

settling ponds, cascading type, will be constructed within the plant

boundary to take care of any unforeseen situation like pipe line

jamming or break down of thickener. The clarified water from these

ponds will be recycled as process water. These ponds will also be

used for harvesting rain water, which will eventually reduce ground

water abstraction.

Expensive imported equipment like centrifuge, belt press filter, high

frequency screen as well as thickener will be installed to maximize

water recovery from the washing circuit. This will ensure water

conservation, a precious natural resource.

Plantation in 33% of the project area is envisaged. Financial and social benefits The project will improve the socio-economic status of the society in the

region by generating direct and indirect employment opportunities. The

project will contribute additional revenue to the State & Central

exchequers in the form of taxes, cess, etc.

The anticipated impacts of the project are explained below:

Human settlement is expected to increase after this project gets

operational.

In the long term, the project will have impact on the population growth

due to migration of people from outside area. Indirect employment

opportunities will also add to this.

Page 40: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[40]

The literacy level of the project area is likely to increase as there will be

influx of many educated people taking up jobs in the project, which is

likely to result in establishment of better educational facilities.

The impact of the project on the civic amenities will be minimal. Various

additional initiatives to be planned by AIPPL in the project area will result

in improvement / up-gradation of civil amenities.

Health care facilities will be developed for the employees of the proposed

project. These medical facilities will be extended to surrounding villages.

Under the social- welfare measures and CSR initiatives AIPPL will also

take up various community health care programs in consultation with the

local Gram Panchayats.

The project related construction activities will benefit the local populace

in a number of ways such as supply of construction labourers – skilled,

semi-skilled and un-skilled, tertiary sector employment and provision of

goods and services for daily needs including transport. The proposed

project will provide employment to the skilled as well as un-skilled

persons. The local population will be given preference depending upon

their suitability to the job requirement. Besides direct employment,

indirect employment opportunities will also open up. The project will

have positive impact in the region. Quality of life of the people will

further improve, which in-turn will improve the socio-economic

conditions of the area.

Page 41: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[41]

ANNEXURE-I PROCESS FLOW SHEET

HEAVY MEDIA CYCLONES

DIVERTER

CLEAN COAL CONVEYOR

MAGNETITE SUMP CHARGING

TANK & PUMP FINE COAL

HEAVY MEDIA TANK & PUMP

TANK & PUMPDILUTE MEDIA

BOX

DESLIME SCREEN

SIEVE SCREEN

DIVERTER

BOX

SIEVE SCREEN

CLEAN COAL D & R SCREEN with

MAG. SEP.FEED BOX

PLANT FEED BELT

MAGNETIC SEPARATORSINGLE DRUM

MIDDLING CONVEYOR

TANK & PUMP SECONDARY WASHING

SUMP & PUMP

CLEAN UP

TOPUMP

PROCESS WASH DOWN

HI-RATE THICKENER

PUMPU'FLOW

MAKE-UPWATER

O'FLOWPUMP

D & R SCREEN with

CLEAN

COAL CENTRIFUGE

PRIMARY DISCARD

BOX

DIVERTER SIEVE SCREEN

WASHING CYCLONE

BELT PRESS FINE COAL

HI-FREQUENCY SCREENCLASSIFYING

CYCLONES

REJECT CONVEYOR

FINES DUMP

MIDDLING CENTRIFUGE

Page 42: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

WAANNE

ATER BALA

[42]

EXURE-II ANCE DIA

AGRAM

Page 43: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[43]

ANNEXURE-III EFFLUENT TREATMENT PLANT DIAGRAM

Page 44: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0_11_Jun_2… · PRE-FEASIBILITY REPORT EXPANSION OF COAL WASHERY FROM 0.70 MTPA TO 5.70 MTPA AT VILLAGE-BOMALOI,

[44]

ANNEXURE-IV PLANT LAYOUT


Recommended