PRE-FEASIBILITY REPORT
ON
MODERNISATION OF EXISTING STAINLESS STEEL PLANT BY INSTALLATION OF NEW 148 m2 SINTER PLANT AND 680 m3 BLAST
FURNACE ALONG WITH ASSOCIATED FACILITIES AT KALINGA NAGAR INDUSTRIAL
COMPLEX JAJPUR, ODISHA
FOR
JINDAL STAINLESS LIMITED
MARCH 2020
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report
TABLE OF CONTENTS
Page
- i -
1 - EXECUTIVE SUMMARY...................................................1-1
1.1 Identification of the Project and Project Proponent .............. 1-1 1.2 Brief Description of Nature of the Project............................ 1-2 1.3 Employment Generation (Direct and Indirect) due to the
Project ............................................................................ 1-2 1.4 Location with Co-ordinates ............................................... 1-2 1.5 Size or Magnitude of Operation.......................................... 1-2 1.6 Project Description with Process Details ............................. 1-3 1.6.1 Blast Furnace ............................................................... 1-3 1.6.2 Sinter Plant .................................................................. 1-5 1.7 Raw Material ................................................................... 1-6 1.8 Availability of Water and Power ......................................... 1-7 1.8.1 Water ........................................................................... 1-7 1.8.2 Power ........................................................................... 1-7 1.9 Waste Generation and Management ................................... 1-7 1.9.1 Waste Water Management .............................................. 1-7 1.9.2 Solid Waste Management ............................................... 1-7 1.10 Land Form, Land Use and Land Ownership ........................ 1-7 1.11 Existing Land Use of Project site........................................ 1-8 1.12 Drinking Water Management ............................................. 1-8 1.13 R&R................................................................................ 1-8 1.14 Schedule ......................................................................... 1-8 1.15 Capital Cost Estimate ....................................................... 1-8 1.16 Financial and Social Benefits of the Project ........................ 1-9
2 - INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION ...............................................................2-1
2.1 Identification of the Project and Project Proponent .............. 2-1 2.1.1 Project.......................................................................... 2-1 2.1.2 Project Proponent .......................................................... 2-1 2.2 Brief Description of Nature of the Project............................ 2-2 2.3 Need for the Project and Its Importance to the Country
and/ or Region................................................................. 2-3 2.4 Demand-Supply Gap ........................................................ 2-3 2.5 Imports vs. Indigenous production..................................... 2-3 2.6 Export Possibility ............................................................. 2-4 2.7 Domestic/ Export Markets ................................................ 2-4 2.8 Employment Generation (Direct and Indirect) due to the
Project ............................................................................ 2-4
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report
TABLE OF CONTENTS (Continued)
Page
- ii -
3 - PROJECT DESCRIPTION.................................................3-1
3.1 Type of Project including interlinked and interdependent projects, if any ................................................................. 3-1
3.2 Location with Co-ordinates ............................................... 3-1 3.3 Details of Alternate Sites and the Basis of Selecting the
Proposed Site................................................................... 3-3 3.4 Size or Magnitude of Operation.......................................... 3-4 3.5 Project Description with Process Details ............................. 3-4 3.5.1 Blast Furnace ............................................................... 3-4 3.5.2 Sinter Plant .................................................................. 3-9 3.5.3 Auxiliary Facilities........................................................3-11 3.6 Raw Material ..................................................................3-11 3.7 Resource Optimization/Recycle & Reuse envisaged in the
project ...........................................................................3-12 3.8 Availability of Water and Power ........................................3-12 3.8.1 Water ..........................................................................3-12 3.8.2 Power ..........................................................................3-12 3.9 Waste Generation and Management ..................................3-13 3.9.1 Waste Water Management .............................................3-13 3.9.2 Solid Waste Management ..............................................3-13 3.10 Schematic representations of the feasibility drawing
which give information of EIA purpose ..............................3-13
4 - SITE ANALYSIS..............................................................4-1
4.1 Connectivity .................................................................... 4-1 4.2 Land Form, Land Use and Land Ownership ........................ 4-1 4.3 Topography ..................................................................... 4-2 4.4 Existing Land Use of Project site........................................ 4-2 4.5 Existing Infrastructure ..................................................... 4-2 4.6 Soil Classification ............................................................ 4-2 4.7 Climatic Conditions.......................................................... 4-4 4.8 Social Infrastructure Available .......................................... 4-4
5 - PLANNING BRIEF ...........................................................5-1
5.1 Planning Concept ............................................................. 5-1 5.2 Population Projection ....................................................... 5-1 5.3 Land use planning ........................................................... 5-1 5.4 Assessment of Infrastructure Demand................................ 5-2 5.5 Amenities/Facilities ......................................................... 5-2
6 - PROPOSED INFRASTRUCTURE .......................................6-1
6.1 Industrial Area (Processing Area) ....................................... 6-1
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report
TABLE OF CONTENTS (Continued)
Page
- iii -
6.2 Residential Area (Non Processing Area)............................... 6-1 6.3 Greenbelt ........................................................................ 6-1 6.4 Social Infrastructure ........................................................ 6-2 6.5 Connectivity .................................................................... 6-2 6.6 Drinking Water Management ............................................. 6-3 6.7 Industrial Waste Management ........................................... 6-3 6.8 Solid Waste Management .................................................. 6-3 6.9 Power Requirement and Supply/Source.............................. 6-3
7 - REHABILITATION AND RESETTLEMENT..........................7-1
8 - PROJECT SCHEDULE AND COST ESTIMATE ....................8-1
8.1 Schedule ......................................................................... 8-1 8.2 Capital Cost Estimate ....................................................... 8-2
9 - ANALYSIS OF PROPOSAL...................................................1
9.1 Financial and Social Benefits of the Project ........................... 1
TABLES
Table 1-1 - Main Technical and Economical Indices ............................ 1-3 Table 1-2 - Basic Design and Operating Parameter ............................. 1-5 Table 1-3 - Raw Materials for SP & BF............................................... 1-6 Table 3-1 - Main Technical and Economical Indices ............................ 3-6 Table 3-2 - Blast Furnace Production Capacity................................... 3-8 Table 3-3 - Basic Design and Operating Parameter ............................. 3-9 Table 3-4 - Raw Materials for SP & BF..............................................3-11
FIGURES
Fig. 3-1 - General Location of Site ..................................................... 3-2 Fig. 3-2 - Specefic Location of Site .................................................... 3-3 Fig. 3-3 - Schematic Diagram for purpose of EIA ...............................3-14 Fig. 4-1 - Topographic Map of the Steel Plant Site ............................. 4-3 Fig. 8-1 - Implementation Schedule For Preordering Activities ............ 8-1
DRAWINGS
Drg 11555-97A-000-ENV-0001 - Plant General Layout Drg 11555-97A-000-ENV-0002 - Process Flow Diagram
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report
1-1
1 - EXECUTIVE SUMMARY
1.1 IDENTIFICATION OF THE PROJECT AND PROJECT PROPONENT
M/s Jindal Stainless Limited (JSL) has proposed to
modernize their existing stainless steel plant by installation of a new 148
m2 Sinter plant and a Blast Furnace of 680 m3 capacity (reduced from
capacity of 180 m² Sinter Plant and 1600 m³ Blast Furnace as per EC
dated 1st November, 2007) along with their auxiliary facilities in existing
steel plant at Kalinga Nagar Industrial Complex (KNIC) in Jajpur District
of Odisha to replace the use of scrap with hot metal in existing EAF.
However, there will not be any increase in overall plant
production capacity w.r.t crude steel and saleable steel. No additional
land would be required for the proposed project.
Jindal Stainless is one of the largest stainless steel
conglomerates in India. It was founded by Shri O.P Jindal in 1970. It
ranks amongst the top ten stainless steel conglomerates in the world.
Jindal Stainless Group has an annual crude steel capacity of 1.9 MTPA
and the group has an annual turnover of US $ 3.2 billion (as on
March'19). The group consists of five companies.
JSL is one of the largest integrated manufacturers of
stainless steel in India with existing capacity of
0.8 MTPA and received EC for capacity expansion of crude steel from
1.1 MTPA to 2.2 MTPA and cold rolling mill from 0.8 MTPA to 1.6 MTPA.
For more details, visit the website https://www.jslstainless.com/.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 1 - Executive Summary (cont’d)
1-2
1.2 BRIEF DESCRIPTION OF NATURE OF THE PROJECT
The proposed Brownfield project would fall under Category
‘A’ of item 3(a) “Metallurgical Industries (ferrous & non-ferrous)” of the
Schedule to the EIA Notification 2006 and amendments thereof.
1.3 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT
It is estimated that about 500 to 600 casual/contractor
workers will be required during construction phase. Subsequently in the
operation phase, approximately 97 personnel would be directly employed
(57 executives and 40 non executives) and 258 personnel would be
indirectly employed.
1.4 LOCATION WITH CO-ORDINATES
The proposed sinter plant and blast furnace along with their
auxiliary facilities would be installed in the existing Steel plant of JSL at
KNIC, Danagadi near Duburi in Jajpur district of Odisha state. No
additional land is required for the proposed project. The project site is
located within 20º56’23” to 20º58’10” North latitude and 86º01’53” to
86º03’43” East longitude.
1.5 SIZE OR MAGNITUDE OF OPERATION
The proposed project would include production of the
following for captive use of JSL:
Sinter .. 1.34 MTPA
Hot metal .. 0.84 MTPA
Gran Shot/Pig casting .. 0.15 MTPA
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 1 - Executive Summary (cont’d)
1-3
1.6 PROJECT DESCRIPTION WITH PROCESS DETAILS
1.6.1 Blast Furnace
One no. of 680 m³ BF is proposed with annual operating
days of 350 days(8400h) and output of 0.84 MTPA hot metal for steel
making.
Product Mix: Major product and by-product are the hot
metal for steel making, BF gas and slag.
Out Put of Hot Metal .. 840,140 TPA
Normal output of BF gas .. 17×104 Nm3/h
Maximum output of BF gas .. 19×104 Nm3/h.
TABLE 1-1 - MAIN TECHNICAL AND ECONOMICAL INDICES
Sl. No. Description Unit Index Remarks
1 Working volume of Blast Furnace
m³ 680 --
2 Nos. of Blast Furnace -- 1 -- 3 Annual working days D 350 -- 4 Agglomerate rate % 80 Sinter ore 80%,
Lump ore 20% 5 Comprehensive grade of
charged ore to BF % > 56.5
--
6 PCI rate Kg/THM 150 -- 7 Top Pressure Bar (g) 1.5 Equipment capacity:
0.2 8 Furnace Top Temperature OC 120 - 250 -- 9 Hot Blast temp OC 1250 Preheating by
combustion air 10 Average daily production TPD 2400 11 Maximum daily
production
TPD 2600
12 Gas generating volume 104 Nm³/h 17 Max. 19
The blast furnace is envisaged to operate with sized iron ore,
sinter, coke, coal dust, fluxes and additives. The furnace will produce
840,140 TPA of gross hot metal. Coke will be supplied from existing
recovery type coke oven battery complex. The Blast Furnace will be
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 1 - Executive Summary (cont’d)
1-4
provided with coal dust injection facility to reduce the requirement of
coke. It will also be supplied with humidified and oxygen enriched air
blast. The hot metal produced will be generally sent to the steel melting
shop. Surplus hot metal will be converted in Gran Shot/pig. The
liquid slag will be granulated at the cast house slag granulation unit.
The BF top gas will be cleaned in the dust catcher and gas cleaning
system and distributed for further consumption to the stoves, runner
drying, Reheating furnaces in Mills, sinter plant etc. the balance BF gas
will be utilized for generation of power in existing 13 MW WHRB Power
Plant.
Gas Cleaning System: BF produces raw gas as a by-product
of the iron making process. The raw gas has a calorific value, which
allows it to be used as fuel. However BFG must be suitably cleaned prior
to further use. The gas cleaning plant consists of dry gas cleaning
system through bag filters, which has an advantage of elimination of
effluent treatment plant and no slurry is generated. The dry dust is
recycled back to Sinter plant. The clean gas is supplied to various users.
The normal gas composition % by volume as follows:
Pulverized Coal Injection System: The system will
comprise of coal storage, raw coal handling, drying unit and pulverizer,
conveying facility, coal dust collection unit, storage bunker and
pulverized coal injection system.
Gran shot/Pig Casting machine: For casting the hot metal
into cold pigs two numbers of Gran Shot/Pig casting machine of capacity
1,800 TPD each has been envisaged for the BF. The machine will be
equipped with lime milk spray system, water spray for pigs/shots
cooling, etc. The pigs/shots will be discharged into the pig storage yard
and thereafter handled by a magnet gantry crane. Each machine will be
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 1 - Executive Summary (cont’d)
1-5
provided with hoists at the discharge end and lime milk preparation
building. An under slung crane has been envisaged in the pouring end
for maintenance and shot disposal.
1.6.2 Sinter Plant
To satisfy the requirement of 680 m³ Blast Furnace annual
outputs of 0.84 MT towards sinter production capacity, JSL planning to
set up 1 x 148 m² sintering machine. The annual output of qualified/net
sinter is 1.34 MT. The operating parameters of the Sinter Plant are
indicated in Table 1-2.
TABLE 1-2 - BASIC DESIGN AND OPERATING PARAMETER
Sl. No. Description Unit Value 1 Number of Sintering Machine Set 1 2 Effective area of sintering machine m2 148 3 Productivity (rated) T/m2/h 1.37 4 Availability of sintering machine % 90.4 5 Annual working regime days/annum 340 6 Annual sinter production MTPA 1.34 7 Quality of sinter
7.1 Grade TFe 54~55% 7.2 Basicity CaO/SiO2 1.8~2.1 7.3 Sized of the finished sinter mm 5-50 7.4 Temperature 0C <120 7.5 Drum index (+6.35) % 74 8 Dust content in exhaust gas at stack mg/Nm3 Below 50
Dry type electrostatic precipitators of total 1,250,000 m3/h
capacity at 160 OC - 250 OC shall be envisaged for de-dusting of waste
gases before entering the main exhausters. The unit will have high
efficiency to ensure less than 50 mg/Nm3 of dust in the outgoing gases
from the stack. Double cone dust valves and drag link chain conveyors
will be provided for discharge of dust from ESP hoppers. The dust from
ESP will be moistened in a moistening drum and will be recycled in the
sintering process. The waste gases coming out of the exhauster will be
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 1 - Executive Summary (cont’d)
1-6
let out to the atmosphere through a RCC stack of height 100 m
after de-dusting in ESP.
The main exhaust fan unit is envisaged for suction of air
through sinter mix bed on the sintering machine. The capacity of
exhauster is 18,000 m³/min at 160 OC and 1,600 mm WC suction at fan
inlet. The exhauster will be housed in a separate building. Adequate
handling facilities shall be provided in the main exhaust fan unit. The
suitable dedusting system has been envisaged at dust generation points
in the sinter plant complex.
1.7 RAW MATERIAL
The raw material required for the existing project is given in
Table 1-3.
TABLE 1-3 - RAW MATERIALS FOR SP & BF
Sl. No. Raw Material
Quantity, MTPA
Source Mode of Transportation
1 Coke 0.34 From JCL In plant 2 PCI coal 0.13 Import Rail/Road 3 Coke Breeze 0.06 From JCL In plant 4 Lump iron ore 0.26 Barbil/Joda/open market Rail/Road 5 Iron ore fines 0.99 Barbil/Joda/open market Rail/Road 6 Lime stone 0.04 - In plant 7 Dolomite 0.006 Jharkhand/ Chattisgarh Rail/Road 8 Pyroxenite 0.006 Sukinda Rail/Road 9 Quartz 0.014 Andhra Pradesh/
Chattishgarh Rail/Road
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 1 - Executive Summary (cont’d)
1-7
1.8 AVAILABILITY OF WATER AND POWER
1.8.1 Water
The estimated raw water requirement for the proposed
project is around 144 m3/hr (SP - 28 m3/hr and BF - 116 m3/hr). This
requirement will be met by existing source of water i.e. Brahmani river
and internal recycling.
1.8.2 Power
The estimated total average load of power requirement of the
proposed project is envisaged as 31 MW.
1.9 WASTE GENERATION AND MANAGEMENT
1.9.1 Waste Water Management
Waste waters from the various units i.e. Cooling Tower blow-
down, Boiler blow-down and part of the blow-down from the BF Circuit
would be utilised for slag granulation. Balance blow-down from the Blast
Furnace Circuit will be used in the Pig Casting Machine. Hence, the
proposed project is planned on “Zero Liquid Discharge” concept.
1.9.2 Solid Waste Management
The main solid waste generated in the proposed project
would be BF slag which will be granulated and sold to the cement
manufacturers. Other solid wastes like ESP/Bag Filter dust, refractory
debris, flue dust of existing steel plant etc. generated would be reused in
the sinter plant.
1.10 LAND FORM, LAND USE AND LAND OWNERSHIP
The proposed project will be installed within the complex of
existing Steel plant, hence the entire land belongs to JSL and the present
status of the land is industrial land. The proposed site primarily consists
of barren land.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 1 - Executive Summary (cont’d)
1-8
1.11 EXISTING LAND USE OF PROJECT SITE
Approx 18.12 Ha of land would be required for the proposed
project. The proposed site primarily consists of barren land & bushes
and the present status of the land is industrial land as designated by
IDCO, Bhubaneswar.
1.12 DRINKING WATER MANAGEMENT
The total water requirement for drinking & sanitation would
be 1 KLD which is proposed to be drawn from the existing plant water
system.
1.13 R&R
The proposed project does not require additional land and
would be housed within the available plant boundary. Hence, there
would not be displacement of any human settlement. Hence there are no
issues relating to ‘Rehabilitation and Resettlement’.
1.14 SCHEDULE
The project is envisaged to be implemented within a period of
twenty four (24) months from the receipt of EC. Pre-ordering activities
are envisaged to be completed within 6 months from the date of receipt
of EC.
1.15 CAPITAL COST ESTIMATE
The capital cost of the project is estimated at
Rs. 805 cr. including IDC of Rs. 70 cr.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 1 - Executive Summary (cont’d)
1-9
1.16 FINANCIAL AND SOCIAL BENEFITS OF THE PROJECT
The proposed project of installation of Sinter plant and Blast
Furnace would
i) generate local direct & indirect employment opportunities and improve local income
ii) improve and build road network in the adjoining
villages iii) strengthen school buildings with playgrounds iv) provide the drinking water facilities v) promote diversification in skill set amongst young
adults vi) provide & conduct the free eye & health check up
programmes vii) further improve social awareness programme such as
sanitation and hygiene viii) augment the development of ancillary small-medium
scale industries, trade & commercial establishments and local entrepreneurship
ix) contribute to the Central and State Govt. revenue
through road tax, income by registration of trucks & trailers, income tax, corporate tax, GST etc
The peripheral development activities that would be
undertaken by the proposed project under Corporate Environment
Responsibility (CER) will focus on marginal communities and attempt to
bring forward an overall social development with emphasis in the areas
of education, training, health and social & physical infrastructure.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report
2-1
2 - INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION
2.1 IDENTIFICATION OF THE PROJECT AND PROJECT PROPONENT
2.1.1 Project
M/s Jindal Stainless Limited (JSL) has proposed to
modernize their existing stainless steel plant by installation of a new 148
m2 Sinter plant and a Blast Furnace of 680 m3 capacity (reduced from
capacity of 180 m² Sinter Plant and 1600 m³ Blast Furnace as per EC
dated 1st November, 2007) along with their auxiliary facilities in existing
steel plant at Kalinga Nagar Industrial Complex (KNIC) in Jajpur District
of Odisha to replace the use of scrap with hot metal in existing EAF.
However, there will not be any increase in overall plant
production capacity w.r.t crude steel and saleable steel. No additional
land would be required for the proposed project.
2.1.2 Project Proponent
Jindal Stainless is one of the largest stainless steel
conglomerates in India. It was founded by Shri O.P Jindal in 1970. It
ranks amongst the top ten stainless steel conglomerates in the world.
Jindal Stainless Group has an annual crude steel capacity of 1.9 MTPA
and the group has an annual turnover of US $ 3.2 billion (as on
March'19). The group consists of following five companies :
i) Jindal Stainless Corp Mgt Services Pvt. Ltd.
ii) Jindal Stainless Ltd.
iii) Jindal Stainless (Hisar) Ltd.
iv) Jindal Coke Ltd.
v) Jindal United Steel Ltd.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 2 - Introduction of the Project/Background Information (cont’d)
2-2
Jindal Stainless Limited (JSL) is one of the largest integrated
manufacturers of stainless steel in India with existing capacity of
0.8 MTPA and received EC for capacity expansion of crude steel from
1.1 MTPA to 2.2 MTPA and cold rolling mill from 0.8 MTPA to 1.6 MTPA
vide letter no J-11011/281/2007-IA II(I) dated 18th September, 2019. A
leader and a name synonymous with Enterprise, Excellence and Success,
the company’s ethos mirrors most characteristics similar to the metal it
produces; Akin to stainless steel Jindal Stainless Limited is innovative
and versatile in its thought process; strong and unrelenting in its
operations. For more details, visit the website
https://www.jslstainless.com/.
Associate Vice President (Env) of JSL is the responsible
authority for this EIA Report. The contact information is given below:
Shri Tushar Kanti Misra
Associate Vice President (Env),
Jindal Stainless Limited
Jajpur – 755026 (Odisha)
2.2 BRIEF DESCRIPTION OF NATURE OF THE PROJECT
JSL has proposed to modernize their existing steel plant by
installation of a new 148 m2 Sinter plant and a Blast Furnace of 680 m3
capacity (reduced from capacity of 180 m² Sinter Plant and 1600 m³
Blast Furnace as per EC dated 1st November, 2007) along with their
auxiliary facilities in existing steel plant at KNIC in Jajpur District of
Odisha to replace the scrap with hot metal in existing EAF.
The proposed Brownfield project would fall under Category
‘A’ of item 3(a) “Metallurgical Industries (ferrous & non-ferrous)” of the
Schedule to the EIA Notification 2006 and amendments thereof.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 2 - Introduction of the Project/Background Information (cont’d)
2-3
2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND/ OR REGION
JSL intends to replace the scrap with hot metal in the
existing EAF to maximize the utilization of heat energy. This will also
reduce the dependency of availability of scrap and facilitate in producing
the consistent quality of product. This project would also generate
employment and other benefits which would be discussed in Section 9.1.
2.4 DEMAND-SUPPLY GAP
According to Steel Minister of India, India's shortage of
domestic scrap supply in the April 2017-March 2018 was at 6.85 MT
which will increase to 9.11 MT in 2021-22. The country imported
5.42 MT of steel scrap in 2017-18 compared with 5.71 MT in 2016-17.
Total demand for scrap in the April 2019-March 2020 is expected at
48.1 MT, while domestic supply is expected to reach 40.19 MT. Major
scrap suppliers to India are the UAE, the US, UK and South Africa
(source: https://www.argusmedia.com/en/news/1825052-indias-
domestic-steel-scrap-shortage-to-deepen).
The proposed project is the replacement of scrap with hot
metal in existing EAF. Replacement of scrap with hot metal would
maximize the utilization of heat energy. In addition, this will increase the
productivity, reduce the power consumption, reduce the electrode
consumption and increase the quality of steel.
2.5 IMPORTS VS. INDIGENOUS PRODUCTION
The proposed project is the replacement of scrap with hot
metal in existing EAF. Hence, this will replace import of scrap resulting
in lowering the dependency on Interaction supplies, savings for
foreign exchequer and would promote Make in India with utilization of
domestic raw material in Iron & Steel making process.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 2 - Introduction of the Project/Background Information (cont’d)
2-4
2.6 EXPORT POSSIBILITY
Products from Sinter Plant and Blast Furnace of the
proposed project are purely for captive use of JSL, hence, export
possibilities for the proposed project has not been envisaged. However,
the final product i.e. Stainless steel is being exported.
2.7 DOMESTIC/ EXPORT MARKETS
There is no proposal to sell the sinter and hot metal as the
production is purely for captive use of JSL.
2.8 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT
During the construction & operation phases of the proposed
projects, both direct & indirect workers would be required.
It is estimated that about 500 to 600 casual/contractor
workers will be required during construction phase. Subsequently in the
operation phase, approximately 97 personnel would be directly employed
(57 executives and 40 non executives) and 258 personnel would be
indirectly employed.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report
3-1
3 - PROJECT DESCRIPTION
3.1 TYPE OF PROJECT INCLUDING INTERLINKED AND INTERDEPENDENT PROJECTS, IF ANY
The proposed project is envisaged for installation of a new
Sinter plant and Blast furnace along with their auxiliary facilities in the
existing Steel complex at Odisha to meet the hot metal requirement in
existing EAF for replacement of scrap. However, there will not be any
increase in overall plant production capacity w.r.t. crude steel and
saleable steel.
3.2 LOCATION WITH CO-ORDINATES
The proposed sinter plant and blast furnace along with their
auxiliary facilities would be installed in the existing Steel plant of JSL at
KNIC, Danagadi near Duburi in Jajpur district of Odisha state. No
additional land is required for the proposed project. The project site is
located within 20º56’23” to 20º58’10” North latitude and 86º01’53” to
86º03’43” East longitude. General location of the project site is shown in
Fig. 3-1. Specific location of the project along with the coordinates of the
corner points is shown in Fig. 3-2. Project site layout is shown in Drg.
11555-97A-000-ENV-0001.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 3 - Project Description (cont’d)
3-2
FIG. 3-1 - GENERAL LOCATION OF SITE
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 3 - Project Description (cont’d)
3-3
FIG. 3-2 - SPECEFIC LOCATION OF SITE
3.3 DETAILS OF ALTERNATE SITES AND THE BASIS OF SELECTING THE PROPOSED SITE
The area within the existing works boundary of JSL would be
able to accommodate the new sinter plant and blast furnace. Hence, no
additional land would be required for the proposed project and no
alternative sites have been considered for the proposed project. The
existing site has also the following advantages:
i) Availability of adequate land for installation of sinter plant and blast furnace along with their auxiliary facilities
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 3 - Project Description (cont’d)
3-4
ii) Availability of suitable infrastructure in terms of connectivity, availability of water & power
iii) Suitability of the land from topographical and
geological considerations. iv) Availability of skilled labour force v) The site does not require any Rehabilitation &
Resettlement (R&R) issues
3.4 SIZE OR MAGNITUDE OF OPERATION
The proposed project would include production of the
following for captive use of JSL:
Sinter .. 1.34 MTPA
Hot metal .. 0.84 MTPA
Gran Shot/Pig casting .. 0.15 MTPA
Process Flow Diagram is shown in Drg. 11555-97A-000-ENV-0002.
3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS
3.5.1 Blast Furnace
One no. of 680 m³ BF is proposed with annual operating
days of 350 days(8400h) and output of 0.84 MTPA hot metal for steel
making.
Product Mix: Major product and by-product are the hot
metal for steel making, BF gas and slag.
Out Put of Hot Metal .. 840,140 TPA
Normal output of BF gas .. 17×104 Nm3/h
Maximum output of BF gas .. 19×104 Nm3/h.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 3 - Project Description (cont’d)
3-5
Main Technical feature and level of equipment:
1. Technique for long BF campaign: dumpy BF profile and optimized refractory configuration. 2. BF proper: fully-covered cooling stave; bosh, belly and proper upper area use SG iron cooling stave with dual industrial cooling water pipelines, and furnace bottom is water-cooled. 3. Energy friendly for BF: higher blast temperature –oxygen enrichment& PCI.
4. The stock house system 5. BF charging is by belt conveyors.
6. The top charging is by BLT.
7. The BF is equipped with 1 no. of tapping hole without slag hole. The main iron runner is hot-metal storage type with air-cooling facility. It dopts fully-hydraulic mud gun and fully hydraulic tapping machine.
8. The cast house is a flat platform without sand-filled level, which is featured in less investment, good-looking and practical.
9. Granulating process: Open filter bed type, Featured by high quality of granulation and environment-friendliness.
10. Three Nos. of improved top-combustion HBS, which is
featured in less investment, air and gas preheating, 1200OC of hot blast temp which is helpful for longer service life.
11. The BF Gas Cleaning Plant is under fully dry-type process.
12. The energy from BF gas pressure and temperature shall be recycled.
13. The design of automation control system shall be in principle of EIC. The process control for major BF process production line shall be by Level 2 automation system.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 3 - Project Description (cont’d)
3-6
TABLE 3-1 - MAIN TECHNICAL AND ECONOMICAL INDICES
Sl. No. Description Unit Index Remarks
1 Working volume of Blast Furnace
m³ 680 --
2 Nos. of Blast Furnace -- 1 -- 3 Annual working days D 350 -- 4 Agglomerate rate % 80 Sinter ore 80%,
Lump ore 20% 5 Comprehensive grade of
charged ore to BF % > 56.5
--
6 PCI rate Kg/THM 150 -- 7 Top Pressure Bar (g) 1.5 Equipment capacity:
0.2 8 Furnace Top Temperature OC 120 - 250 -- 9 Hot Blast temp OC 1250 Preheating by
combustion air 10 Average daily production TPD 2400 11 Maximum daily
production
TPD 2600
12 Gas generating volume 104 Nm³/h 17 Max. 19
The blast furnace is envisaged to operate with sized iron ore,
sinter, coke, coal dust, fluxes and additives. The furnace will produce
840,140 TPA of gross hot metal. Coke will be supplied from existing
recovery type coke oven battery complex. The Blast Furnace will be
provided with coal dust injection facility to reduce the requirement of
coke. It will also be supplied with humidified and oxygen enriched air
blast. The hot metal produced will be generally sent to the steel melting
shop. Surplus hot metal will be converted in Gran Shot/pig. The
liquid slag will be granulated at the cast house slag granulation unit.
The BF top gas will be cleaned in the dust catcher and gas cleaning
system and distributed for further consumption to the stoves, runner
drying, Reheating furnaces in Mills, sinter plant etc. the balance BF gas
will be utilized for generation of power in existing 13 MW WHRB Power
Plant. Following facilities are envisaged in the project:
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 3 - Project Description (cont’d)
3-7
i) Raw material storage yard, stock house, fines handling and main blast furnace charging conveyor
ii) Blast furnace proper
iii) Cast house with tilting runners and dedusting system
iv) Stoves and waste gas chimney
v) Hot blast supply system including hot blast main, expansion joints, bustle main and tuyere stock assembly
vi) Dust catcher and dust discharge equipment
vii) Gas cleaning plant including water system and sludge tanks and flare stack system
viii) Cast house slag granulation plant with its water system Dry slag pit
ix) Water cooling system for blast furnace proper, blast furnace under hearth and stove valves
x) Stock house dedusting system, ventilation and air- conditioning system
xi) Ladle repair shop
xii) Gran shot/Pig casting machine
xiii) Railway tracks for transportation of hot metal and rolling stock, locomotives
xiv) Instrumentation, automation and process control system
xv) Blower house and cold blast supply system
xvi) Compressor and compressed air piping
xvii) Shop electrics and illumination
xviii) Hoisting and handling facilities
xix) Effluent, waste handling, drainage and sewerage
xx) Interplant and inter shop pipelines for steam, BF gas, compressed air and oxygen & Nitrogen
xxi) BF control room
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 3 - Project Description (cont’d)
3-8
TABLE 3-2 - BLAST FURNACE PRODUCTION CAPACITY
Sl. No. Name Quantity 1 Main product:
Hot Metal
840,140 TPA 2 By-product:
Granulated Slag BF Gas
268,845 TPA
17 x 104 Nm3/hr (avg) 19 x 104 Nm3/hr (max)
Molten slag will be granulated in the cast house slag
granulation plant under normal operation and 95% yield has been
assumed in the system. However, if slag granulation is not done due to
slag quality variation or non-availability of slag granulation plant, then
the slag will be discharged in the dry slag pits.
Gas Cleaning System: BF produces raw gas as a by-product
of the iron making process. The raw gas has a calorific value, which
allows it to be used as fuel. However BFG must be suitably cleaned prior
to further use. The gas cleaning plant consists of dry gas cleaning
system through bag filters, which has an advantage of elimination of
effluent treatment plant and no slurry is generated. The dry dust is
recycled back to Sinter plant. The clean gas is supplied to various users.
The normal gas composition % by volume as follows:
Pulverized Coal Injection System: The system will
comprise of coal storage, raw coal handling, drying unit and pulverizer,
conveying facility, coal dust collection unit, storage bunker and
pulverized coal injection system.
Gran shot/Pig Casting machine: For casting the hot metal
into cold pigs two numbers of Gran Shot/Pig casting machine of capacity
1,800 TPD each has been envisaged for the BF. The machine will be
equipped with lime milk spray system, water spray for pigs/shots
cooling, etc. The pigs/shots will be discharged into the pig storage yard
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 3 - Project Description (cont’d)
3-9
and thereafter handled by a magnet gantry crane. Each machine will be
provided with hoists at the discharge end and lime milk preparation
building. An under slung crane has been envisaged in the pouring end
for maintenance and shot disposal.
3.5.2 Sinter Plant
To satisfy the requirement of 680 m³ Blast Furnace annual
outputs of 0.84 MT towards sinter production capacity, JSL planning to
set up 1 x 148 m² sintering machine. The annual output of qualified/net
sinter is 1.34 MT. The operating parameters of the Sinter Plant are
indicated in Table 3-3.
TABLE 3-3 - BASIC DESIGN AND OPERATING PARAMETER
Sl. No. Description Unit Value 1 Number of Sintering Machine Set 1 2 Effective area of sintering machine m2 148 3 Productivity (rated) T/m2/h 1.37 4 Availability of sintering machine % 90.4 5 Annual working regime days/annum 340 6 Annual sinter production MTPA 1.34 7 Quality of sinter
7.1 Grade TFe 54~55% 7.2 Basicity CaO/SiO2 1.8~2.1 7.3 Sized of the finished sinter mm 5-50 7.4 Temperature 0C <120 7.5 Drum index (+6.35) % 74 8 Dust content in exhaust gas at stack mg/Nm3 Below 50
The following advanced features have been envisaged for the
proposed sinter plant complex.
i) Electronic weighing and proportioning system ii) Circular sinter cooler iii) Energy efficient ignition furnace
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 3 - Project Description (cont’d)
3-10
iv) Process gas and plant de-dusting system using high efficiency ESP’s
v) Process control and automation using PLC vi) Waste Heat Recovery System in Sinter Cooler to
generate steam.
The sinter plant complex envisaged receipt of crushed fuel &
flux, iron ore fines, BF returns fines flue dust and RMP and
proportioning unit. The sinter plant will consist of the following main
technological units:
i) Fuel and flux crushing unit ii) Flux screen unit iii) Proportioning unit iv) Primary mixing room v) Secondary mixing room vi) Sintering and cooling unit vii) Waste gas de-dusting unit viii) Main exhaust fan unit ix) Cold sinter screening unit x) Plant de-dusting units
The above units will be inter connected by conveyor
galleries and junction houses for conveying sinter mix, finished sinter,
hearth layer and sinter return fines.
Dry type electrostatic precipitators of total 1,250,000 m3/h
capacity at 160 OC - 250 OC shall be envisaged for de-dusting of waste
gases before entering the main exhausters. The unit will have high
efficiency to ensure less than 50 mg/Nm3 of dust in the outgoing gases
from the stack. Double cone dust valves and drag link chain conveyors
will be provided for discharge of dust from ESP hoppers. The dust from
ESP will be moistened in a moistening drum and will be recycled in the
sintering process. The waste gases coming out of the exhauster will be
let out to the atmosphere through a RCC stack of height 100 m
after de-dusting in ESP.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 3 - Project Description (cont’d)
3-11
The main exhaust fan unit is envisaged for suction of air
through sinter mix bed on the sintering machine. The capacity of
exhauster is 18,000 m³/min at 160 OC and 1,600 mm WC suction at fan
inlet. The exhauster will be housed in a separate building. Adequate
handling facilities shall be provided in the main exhaust fan unit. The
suitable dedusting system has been envisaged at dust generation points
in the sinter plant complex.
2.3.5 Laboratory
A well equipped laboratory for testing of raw materials, fuel,
products, & water Facilities for environment monitoring is also a part of
laboratory.
3.5.3 Auxiliary Facilities
Various services facilities like repair and maintenance shop,
central stores, administrative building, canteen, guesthouse, time office,
water supply & laboratory etc. are provided.
3.6 RAW MATERIAL
The raw material required for the existing project is given in
Table 3-4.
TABLE 3-4 - RAW MATERIALS FOR SP & BF
Sl. No. Raw Material
Quantity, MTPA
Source Mode of Transportation
1 Coke 0.34 From JCL In plant 2 PCI coal 0.13 Import Rail/Road 3 Coke Breeze 0.06 From JCL In plant 4 Lump iron ore 0.26 Barbil/Joda/open market Rail/Road 5 Iron ore fines 0.99 Barbil/Joda/open market Rail/Road 6 Lime stone 0.04 - In plant 7 Dolomite 0.006 Jharkhand/ Chattisgarh Rail/Road 8 Pyroxenite 0.006 Sukinda Rail/Road 9 Quartz 0.014 Andhra Pradesh/
Chattishgarh Rail/Road
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 3 - Project Description (cont’d)
3-12
3.7 RESOURCE OPTIMIZATION/RECYCLE & REUSE ENVISAGED IN THE PROJECT
The proposed plant would be designed with state-of-art
technology for optimum consumption of energy & other resources.
Replacement of scrap with hot metal would maximize the utilization of
heat energy. In addition, this will increase the plant productivity, reduce
power and electrode consumption and increase the quality of steel. Also,
adoption of compact layout for the Plant would enable to optimise the
utilisation of land, which is another critical resource. Water consumption
would also be optimised by recycle of treated water as plant make-up
water.
3.8 AVAILABILITY OF WATER AND POWER
3.8.1 Water
The estimated raw water requirement for the proposed
project is around 144 m3/hr (SP - 28 m3/hr and BF - 116 m3/hr). This
requirement will be met by existing source of water i.e. Brahmani river
and internal recycling.
3.8.2 Power
The tentative power requirement of the proposed system is given below:
Area Power requirement, MW Blast Furnace 16.5 Sinter Plant 9.5 Utilities 5
Total 31.0
The required power will be sourced from existing captive power plant.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 3 - Project Description (cont’d)
3-13
3.9 WASTE GENERATION AND MANAGEMENT
3.9.1 Waste Water Management
Waste waters from the various units i.e. Cooling Tower blow-
down, Boiler blow-down and part of the blow-down from the BF Circuit
would be utilised for slag granulation. Balance blow-down from the Blast
Furnace Circuit will be used in the Pig Casting Machine. Hence, the
proposed project is planned on “Zero Liquid Discharge” concept.
3.9.2 Solid Waste Management
The main solid waste generated in the proposed project
would be BF slag which will be granulated and sold to the cement
manufacturers. Other solid wastes like ESP/Bag Filter dust, refractory
debris, flue dust of existing steel plant etc. generated would be reused in
the sinter plant.
3.10 SCHEMATIC REPRESENTATIONS OF THE FEASIBILITY
DRAWING WHICH GIVE INFORMATION OF EIA PURPOSE
As per the Environment Impact Assessment (EIA)
notification dated 14th September 2006 and subsequent amendments,
this project falls under category A. It would be required to prepare
EIA/EMP report to obtain the Environmental Clearance (EC) for the
project from the MoEFCC. The schematic diagram given in Fig. 3-3
represents the purpose of EIA report.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 3 - Project Description (cont’d)
3-14
FIG. 3-3 - SCHEMATIC DIAGRAM FOR PURPOSE OF EIA
Project Concept
Land requirement
Water requirement
Power requirement
Raw material requirement
TOR received from the concerned Authority
Baseline Data Generation for
Air, Water, Noise, Soil, Ecology and Sociology
Impact Assessment
Mitigation/Management Plan Suggested
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report
4-1
4 - SITE ANALYSIS
4.1 CONNECTIVITY
The Plant is situated in Kalinga Nagar Industrial Complex
(KNIC), Jajpur in the state of Odisha. State Highway (SH-20) runs on the
northern side of the plant. East Coast railway line connecting Jakhpura
and Daitari stations runs parallel to the plant boundary on the eastern
side. Tata Steel and Visa Steel are located on the western and southern
part of the plant repectively. SH-20 connects the plant to Jajpur Road.
The site is also well connected by roads, including National highways, to
Bhubaneswar/Cuttack and Paradeep Port. NH-53 (old NH-200) runs
parallel to the site in western direction at an aerial distance of about
4.5 km. The Jajpur Keonjhar road railway station on Howrah-
Kharagpur- Bhubaneswar- Vishakhapatnam line is about 12 km towards
East of the project site. The nearest international airport is at
Bhubaneswar, about 110 km by road from the plant site. Paradeep port
and Dhamra Port are about 120 km and 140 km respectively by road
from the plant site.
4.2 LAND FORM, LAND USE AND LAND OWNERSHIP
The proposed project will be installed within the complex of
existing Steel plant in KNIC, hence the entire land belongs to JSL and
the present status of the land is industrial land as designated by IDCO,
Bhubaneswar. The proposed site primarily consists of barren land &
bushes.
The total land required for proposed expansion is estimated
around 18.12 Ha within the existing plant premises of 452.61 Ha of JSL.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 4 - Site Analysis (cont’d)
4-2
4.3 TOPOGRAPHY
The study area is characterized by moderately undulating
topography with presence of moderate to low lying hillocks and mounds
at places. The elevation of plain area is upto 120 m above mean sea level.
The topographic features of the project area may be seen
from Survey of India OSM Sheet No. F45U1. The Topographic map is
shown in Fig 4-1. The study area is mainly drained by the river
Brahmani along with its tributaries. The river is having south-easterly
flow direction. The meandering of rivers gives rise to formation of ox-bow
lakes along their course. The drainage pattern is anastomosing and
braided in the alluvial plain while it is dendritic in nature near the
foothills. There are no streams or river passing through and no visible
drainage course spread in the existing plant premises.
4.4 EXISTING LAND USE OF PROJECT SITE
Approx 18.12 Ha of land would be required for the proposed
project. The proposed site primarily consists of barren land & bushes
and the present status of the land is industrial land as designated by
IDCO, Bhubaneswar.
4.5 EXISTING INFRASTRUCTURE
The proposed project will be installed within the complex of
existing Steel plant which is already well connected by road & rail.
Existing water, power and land infrastructures are adequate for the
proposed expansion.
4.6 SOIL CLASSIFICATION
To assess the soil quality of study area, Physico-chemical
data on soil samples were collected from secondary data. The soil pH is
in the range of 6.9 to 7.4. Electrical conductivity ranged from 0.32 – 0.42
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 4 - Site Analysis (cont’d)
4-3
dS/cm. SAR value in the range of 4.41 to 4.82 indicate moderate level of
sodium present in the soil of the study area. The soil is very rich in iron
content.
FIG. 4-1 - TOPOGRAPHIC MAP OF THE STEEL PLANT SITE
210 00
860 00’ 860 05’
OSM No – F45N16
JSL Plant
200 55’
OSM No – F45O4
SH 20
NH 53
Brahmani River
OSM No – F45T13 OSM No – F45U1
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 4 - Site Analysis (cont’d)
4-4
4.7 CLIMATIC CONDITIONS
The study area lies in the humid tropical region. Climate of
the region is characterized by aggressive summer and a seasonal rainfall.
The summer season (March-May) is very hot and the temperature is in
the range of 45°C to 46 °C followed by South-west monsoon which starts
from the first week of June to the end of September. The annual rainfall
is about 1475 mm. The wind direction is predominantly from S and SW.
4.8 SOCIAL INFRASTRUCTURE AVAILABLE
i) The project area falls under ‘Kalinganagar Industrial Complex’. With the development of several large and medium scale industries, the study area has witnessed speedy development of infrastructure with regard to road linkages, black top roads, communication facilities, trade and commerce. The State Highway (SH-2) connects Jajpur and Talcher and the Expressway that runs from Daitari and Paradeep Port are in the study area
ii) The General Hospital in Jajpur Town is the main
health care centre in the study area, equipped with modern facilities. There are few villages having Primary Health Centres as well.
iii) Socio-economic infrastructure facilities like that of
schools (both primary & secondary), parks, banks, post offices and shopping centres are available in the study area.
iv) With regard to education, the district of Jajpur is
characterized by several educational and professional institutes namely B.B. High School, Dasarathpur High School, N.C.College, V.N. College, N.C College, Biraja Women’s College, Biraja Law College, B.S.College, Sukinda College and A.P.College etc.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report
5-1
5 - PLANNING BRIEF
5.1 PLANNING CONCEPT
The proposed project is the installation of sinter plant and
blast furnace along with their auxiliary facilities. The proposed project
would fall under Category ‘A’ of item 3(a) “Metallurgical Industries
(ferrous & non-ferrous)” of the Schedule to the EIA Notification 2006 and
amendments thereof. Following facilities have also been considered in
the proposed project:
� Augmentation of existing EAF material handling syatem to meet the requirement
� Augmentation of existing water and power supply
network
5.2 POPULATION PROJECTION
The total population of Study area (earlier EIA Report
November 2018) for the years 2001 and 2011 are 3,01,593 and 3,57,475
respectively. The computed decadal growth is that of 18.53 %. Hence the
projected population of study area as per the computed decadal growth
for the year 2020 is estimated at 417,100.
5.3 LAND USE PLANNING
The total steel plant area of undivided JSL is
502.02 hectares (1240 acre). The total area is divided among three Group
companies with areas given below:
JSL – 318.02 Ha (785.52 acre)
JUSL – 154.66 Ha (382.02 acre)
JCL – 29.34 Ha ( 72.46 acre)
Total – 502.02 Ha (1240.00 acre)
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 5 - Planning Brief (cont’d)
5-2
Now JUSL will surrender part of their allocated land
(332.43 acre) to JSL. Land area allocation after surrender will be as
follows:
JSL – 452.61 Ha (1117.95 acre)
JUSL – 20.07 Ha ( 49.59 acre)
JCL – 29.34 Ha ( 72.46 acre)
Total – 502.02 Ha (1240.00 acre)
5.4 ASSESSMENT OF INFRASTRUCTURE DEMAND
i) Toilet facility will be provided at all new control rooms, pump houses, substations, offices and all manned units.
ii) Workers rest rooms with drinking water facility.
5.5 AMENITIES/FACILITIES
Workers will be provided with safety equipments, rest rooms,
drinking water and first aid facilities.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report
6-1
6 - PROPOSED INFRASTRUCTURE
6.1 INDUSTRIAL AREA (PROCESSING AREA)
The proposed Sinter plant and Blast furnace along with their
auxiliary facilities would be sited in the existing Steel plant of JSL at
Kalinga Nagar Industrial Complex in Odisha state. No additional land is
required for the present project.
The proposed project would be carried out within the existing
plant area (452.61 Ha) of JSL. 18.12 Ha of vacant land would be utilized
for the proposed plant.
6.2 RESIDENTIAL AREA (NON PROCESSING AREA)
No new residential facilities have been considered for the
proposed project. Only temporary rest shed has been provided for the
labour.
6.3 GREENBELT
It is obligatory to develop dense greenbelt area in proposed
project plant as per CPCB guidelines. Green belt is proposed to be
developed in compliance with the regulatory norms. This would not only
prevent the fugitive dust emissions but also improve the peripheral
appearance of the plant from aesthetics point of view. Unpaved areas, if
any, within the plant boundary would be provided with grass/tree cover.
Depending on the type of soil suitable for growth, higher
survival rate in the region, large leaf index area, nativity of the species
and pollution load, following are the proposed species of trees which may
be planted as greenbelt at the steel plant site:
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 6 - Proposed Infrastructure (cont’d)
6-2
List of selected tree species for greenbelt development: 1. Amaltas - Cassia fistula 2. Cassia - Cassia siamea 3. Jamun - Syzygium cumini 4. Neem - Azadirachta indica 5. Siris - Albizzia lebbek 6. Sisoo - Dalbergia sisso
6.4 SOCIAL INFRASTRUCTURE
i) Support and augmentation of existing government initiatives related to sanitation
ii) Support towards industrial and vocational training for youth of marginal communities
iii) Support towards strengthening of existing medical facilities & allied camps/awareness programmes to cater to the local population
iv) Support towards repairing of local approach and link roads for better communication
v) Awareness and promotion for use of renewable energy
vi) Supply of potable water in the surrounding villages
6.5 CONNECTIVITY
State Highway (SH-20) runs on the northern side of the plant
which connects the plant to Jajpur Road. East Coast railway line
connecting Jakhpura and Daitari stations runs parallel to the plant
boundary on the eastern side. The site is also well connected by roads,
including National highways, to Bhubaneswar/Cuttack and Paradeep
Port. NH-53 (old NH-200) runs parallel to the site in western direction at
an aerial distance of about 4.5 km. The Jajpur Keonjhar road railway
station on Howrah- Kharagpur- Bhubaneswar- Vishakhapatnam line is
about 12 km towards East of the project site. The nearest international
airport is at Bhubaneswar, about 110 km by road from the plant site.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 6 - Proposed Infrastructure (cont’d)
6-3
Paradeep port and Dhamra Port are about 120 km and 140 km
respectively by road from the plant site. Nearest town is Jajpur. No new
external rail and road connectivity has been envisaged in this proposed
project.
6.6 DRINKING WATER MANAGEMENT
The total water requirement for drinking & sanitation would
be 1 KLD which is proposed to be drawn from the existing drinking water
system. The sewage water received from the toilets of office buildings
areas would be fed to the existing sewage treatment plant.
6.7 INDUSTRIAL WASTE MANAGEMENT
The proposed project would generate various types of wastes
which have been mentioned in Chapter-3.
6.8 SOLID WASTE MANAGEMENT
Major solid wastes produced in the proposed project would
be namely blast furnace slag. The solid waste management has been
discussed in details in Chapter-3.
6.9 POWER REQUIREMENT AND SUPPLY/SOURCE
The tentative power requirement of the proposed system is
given below:
Area Power requirement, MW
Blast Furnace 16.5
Sinter Plant 9.5
Utilities 5
Total 31.0
The required power will be sourced from existing captive power plant.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report
7-1
7 - REHABILITATION AND RESETTLEMENT
The proposed project does not require additional land and
would be housed within the available plant boundary. Hence, there
would not be displacement of any human settlement. Hence there are no
issues relating to ‘Rehabilitation and Resettlement’.
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report
8-1
8 - PROJECT SCHEDULE AND COST ESTIMATE
This chapter indicates the Project Schedule and the
estimated Capital Cost.
8.1 SCHEDULE
The project is envisaged to be implemented within a period of
twenty four (24) months from the receipt of EC. Pre-ordering activities
are envisaged to be completed within 6 months from the date of receipt
of EC. An implementation schedule, in the form of bar charts, for pre-
ordering activities is shown in Fig. 8-1.
Duration in Months Sl.
No.
Activities 1 2 3 4 5 6
1 Issue of Tender & receipt of offer
2 Tender discussion & Evaluation of bids
3 Price Bid evaluation & finalisation of L1 bid
FIG. 8-1 - IMPLEMENTATION SCHEDULE FOR PREORDERING ACTIVITIES
The preliminary overall implementation schedule for the
project, indicating the time period required for completing the major
activities like ordering of main process equipment, basic & detail
engineering for the project, manufacturing & supply to site, construction
(civil & structural work and erection including cold trials/testing).
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report 8 - Project Schedule and Cost Estimate (cont’d)
8-2
8.2 CAPITAL COST ESTIMATE
The capital cost of the project is estimated at
Rs. 805 cr. including IDC of Rs. 70 cr. The details are given below:
Blast Furnace .. 300 crore
Sinter Plant .. 210 crore
Gran Shot/Pig Casting .. 40 crore
Infrastructure .. 150 crore
Sub Total .. 700 crore
IDC .. 70 crore
Others .. 35 crore
Total .. 805 crore
JINDAL STAINLESS LIMITED Installation of 148 m2 Sinter Plant and 680 m3 Blast Furnace within the existing Plant at Kalinga Nagar Industrial Complex Pre-Feasibility Report
9-1
9 - ANALYSIS OF PROPOSAL
9.1 FINANCIAL AND SOCIAL BENEFITS OF THE PROJECT
The proposed project of installation of Sinter plant and Blast
Furnace would
i) generate local direct & indirect employment opportunities and improve local income
ii) improve and build road network in the adjoining
villages iii) strengthen school buildings with playgrounds iv) provide the drinking water facilities v) promote diversification in skill set amongst young
adults vi) provide & conduct the free eye & health check up
programmes vii) further improve social awareness programme such as
sanitation and hygiene viii) augment the development of ancillary small-medium
scale industries, trade & commercial establishments and local entrepreneurship
ix) contribute to the Central and State Govt. revenue
through road tax, income by registration of trucks & trailers, income tax, corporate tax, GST etc
The peripheral development activities that would be
undertaken by the proposed project under Corporate Environment
Responsibility (CER) will focus on marginal communities and attempt to
bring forward an overall social development with emphasis in the areas
of education, training, health and social & physical infrastructure.
LT S/S
roll shop
65.00FGL
46.00FGL
48.00FGL
48.00FGL
48.00FGL
52.00FGL
48.00FGL
45.00FGL
52.00FGL
65.00FGL
CAL = 711.124 m (FM TOPT)
CAL = 711.097 m (FM TOPT)
7.6 M
SPACE FOR CRANE MOVEMENT & UNLOADING PLATFORM ( 700 M x 30 M)
HIGH MAST LIGHT HIGH MAST LIGHT
46.00FGL
56.50FGL
65.00FGL
51.50
53.50
X 1200
X 1300
X 1900
X 1600
X 1700
X 1800
X 1500
X 1400
X 2000
X 2100
X 2200
X 2400
X 2300
X 4000
X 4200
X 3900
X 4400
X 4300
X 2900
X 2800
X 2700
X 2600
X 2500
X 3200
X 3300
X 3400
X 3100
X 3000
X 3700
X 3800
X 3600
X 3500
X 4100
Y 2500
Y 2400
Y 2300
Y 2900
Y 2800
Y 2700
Y 2600
Y 3200
Y 3100
Y 3000
Y 3600
Y 3500
Y 3400
Y 3300
Y 3900
Y 3800
Y 3700
Y 4200
Y 4100
Y 4000
Y 2200
Y 2100
Y 2000
Y 1900
Y 1800
Y 1700
Y 1600
Y 1500
Y 1400
Y 4300
Y 4400
Y 1805.072
SECURI
TY BAR
RACK
AIR
SMS AREA
JCL AREA
RAW MATERIAL STORAGE AREA
MRSS AREA
POWER PLANT
RAW MATERIAL STORAGE AREA
RAW MATERIAL STORAGE AREA
CRM AREA
JUSL TRANSFERED BOUNDARY (332.43 ACRE)
PROPOSED FACILITIES (44.74 ACRE)
CALCINING
SEPARATION
PLANT
AIR
SEPARATION
PLANT
PLANT
RESERVOIR AREA
FERRO ALLOY PLANT AREA
JUSL AREA
GREENBELT
ASSEMBLY POINT
RESERVOIR AREA
AREA
JUSL AREA
JUSL
AREA
GATE
MATERIAL ENTRY GATE
GATE
EMERGENCY
GATE
EMERGENCY
GATE
ENTRY & EXIT
GATE
EMERGENCY
MATERIAL
GATE
RAIL
GATE
CRM AREA
JUSL PLANT BOUNDARY
HSM AREA
JUSL PLANT BOUNDARY
PROPOSED BF & SINTER PLANT AREA
PROPOSED BF & SINTER PLANT AREA
SINTER PLANT AREA
BLAST FURNACE AREA
RAW MATERIAL
JSL EXISTING BOUNDARY (785.52 ACRE)
PROPOSED JUSL BOUNDARY (49.59 ACRE)
JCL AREA (72.46 ACRE)
LEGEND
JINDAL STAINLESS LIMITED
JAJPUR,ODISHA
PRE-FEASIBILITY REPORT FOR INSTALLATION OF
130 SQM SINTER PLANT & 680 CUM BLAST FURNACE
CONSULTING ENGINEERS, KOLKATA
M. N. DASTUR & COMPANY (P) LTD
PLANT GENERAL LAYOUT
11555-97A-000-ENV-0001 0
1. ALL QUANTITIES ARE IN TONS PER YEAR ON NET AND DRY BASIS,
UNLESS OTHERWISE SPECIFIED.
CALCINING PLANT
1 X 200TPD
LIME STONE
TO CALCINING PLANT
524,400
DOLOMITE 315,000
NOTES :
EAF
2X150 TON
59,000
CA
LC
IN
ED
LIM
E
25,050
CA
LC
IN
ED
D
OLO
39,095
MS
S
CR
AP
233,800
SLAG
CAPACITY OF PROPOSED FACILITIES
CALCINED DOLO
122,600
204,080
CALCINED LIME
TO CALCINING PLANT
SS
S
CR
AP
743,676
AOD
LF
408,700
2,200,000
LIQUID STEEL
2,200,000
LIQ
UID
S
TE
EL
SLAB CASTER
1X1 STRAND
SLABS
2,134,000
ASP
1 X 425 TPD
1 X 425 TPD
AIR
OXYGEN
NITROGEN
ARGON
1 X 150 T
1 X 150 T
1 X 150 T
1 X 150 T
SLAG
1X1 STRAND
OTHER ADDITIVES 68,100
OTHER FERRO ALLOYS 133,120
CAPACITY OF EXISTING FACILITIES
HAPL
0.8 MTPA
0.45 MTPA
805,000
789,880
HR PRODUCT
340,000
432,000
CR PRODUCT
CAPL
HYDRATED LIME PLANT
(BOO)
(BOO)
HAPL
0.8 MTPA
0.45 MTPA
805,000
789,880
HR PRODUCT
340,000
432,000
CR PRODUCT
CAPL
Fe Cr
1 X 13 MW
50 TPH AFBC BOILER
WHRB
LINES
FINISHING
LINES
FINISHING
Fe Alloy
0.25 MTPA
PLANT
METAL
50 TPH
PLANT
RECOVERY
80 TPH
SALE TO JUSL
1,610,000
HOT ROLLED COIL (ROLLED FROM JUSL)
(BOO)
1 X 450 TPD +1 X600 TPD
MS SCRAP 36,900
FeC
r
702,100
GRANULATED SLAG
268,845
151,730
GRANULATION PLANT
GRAN SHOT
RETURN FINES
SLAG
PRODUCT SINTER
BLAST FURNACE
840,140
HOT METAL
CH
AR
GE
C
OK
E
CH
AR
GE
S
IN
TE
R
QU
AR
TZ
IT
E
PC
I C
OA
L
LIM
E
LIM
E S
TO
NE
CO
KE
B
RE
EZ
E
CH
AR
GE
S
IN
TE
R
IR
ON
O
RE
F
IN
ES
DU
ST
, S
CA
LE
&
S
LU
DG
E
PY
RO
XE
NIT
E
CHARGE SINTER
DO
LO
MIT
E
339,900
1 x 680 cum
14,500
126,000
LIM
ES
TO
NE
58,000
148 SQM
SINTER PLANT
6,000
103,900
994,400
18,200
18,200
151,730
HOT METAL
134,000
1,206,000
1,206,000
1,340,000
688,410
HO
T M
ET
AL
1,206,000
151,730
GR
AN
S
HO
T
SIZ
ED
O
RE
263,800
4,000
6,000
MACHINE
GRAN SHOT
CONSULTING ENGINEERS, KOLKATA
M. N. DASTUR & COMPANY (P) LTD
PRE-FEASIBILITY REPORT FOR INSTALLATION OF
JINDAL STAINLESS LIMITED
JAJPUR, ODISHA
130 SQM SINTER PLANT & 680 CUM BLAST FURNACE
PROCESS FLOW DIAGRAM
11555-97A-000-ENV-0002 0