+ All Categories

Prefab

Date post: 15-Oct-2015
Category:
Upload: satish-pandey
View: 39 times
Download: 0 times
Share this document with a friend
Description:
prefabrication
Popular Tags:

of 40

Transcript
  • Page 1

    PRE-FABRICATION

    SUBMITTED BY- RAJAT SINGH MOHAK JAIN SIDDHARTH ATREYA MEHJABEEN SULTHANA MOHIT RAJ NITESH KANNAUJIA RISHABH KAUSHIK

  • Page 2

    Pre-FabricationIt is the practice of assembling components of a structure in

    a factory or other manufacturing site,

    and transporting complete assemblies or sub-assemblies to

    the construction site where the structure is to be located.

    Definitions

    Pre-Fabricated ConstructionA construction method relying primarily on the use of standardized

    manufactured components; consists largely of assembling these

    parts rather than fabricating them at the site.

    Pre-Fabricated House A house assembled from components cut to size at a factory,

    or assembled from building modules shipped to the

    construction site.

    Pre-Fabricated Masonry Panel A wall panel fabricated of masonry units which are bonded

    together at a manufacturing plant and then transported to the

    job site as a construction unit, ready for erection.

  • Page 3

    HISTORY

    Buildings have been built in one place and reassembled in another throughout history. the first advertised prefab house was

    the Manning Portable Cottage.

    A London carpenter, Henry Manning, constructed a house that was built in components, then shipped and assembled by British

    emigrants.

    In Barbados the Chattel house was a form of prefabricated building which

    was developed by emancipated

    slaves who had limited rights to build

    upon land they did not own.

    As the buildings were

    moveable they were

    legally regarded aschattels.

  • Page 4

    In 1855 during the Crimean War, after Florence Nightingale wrote a letter to The Times, Isambard Kingdom Brunel was commissioned to design a prefabricated modular hospital.

    In five months he designed a 1,000 patient hospital, with innovations in sanitation, ventilation and a flushing toilet.

    Prefabricated housing was popular during World War II due to the need for mass accommodation for military personnel. The United States used Quonset huts as military buildings, and in the United Kingdom prefabricated buildings used included Nissen huts and Bellman Hangars.

    HISTORY

  • Page 5

    McDonalds uses prefabricated structures for their buildings, and set a

    record of constructing a building and

    opening for business within 13 hours on

    pre-prepared ground.

    In the UK, the major supermarkets have each developed a modular unit system

    to shop building, based on the systems

    developed by German cost retailers Aldi

    and Netto.

    HISTORY

  • Page 6

    Fabricated UnitFabricated are typically made of extruded or

    poured metal (aluminum or steel) The units

    range in scale from a small fasteners to steel

    bridge trusses. For the consideration of

    construction and design logics, metal

    fabricated components from the single stud to

    the 300-0 bridge truss are in this category.

    Panel SystemPanel systems contain integrated systems

    within one component. Often included are

    structural, thermal/waterproofing, electrical,

    mechanical systems. Made up of a sandwich of

    complementary materials. How the panels are

    handled on site is dependent on the weight and

    size of each piece.

    Precast ConcretePrecast concrete is fabricated in a multitude

    of sizes. Precast components are comprised

    of an internal steel rebar framework and high

    tolerance concrete. Concrete is meant to

    withstand transport to and movement on site.

    Units are limited in weight and dimensions

    based on the smallest unit of transportation

    Definitions

  • Page 7

    Steel Frame Construction

    Fabricated Units compose the structural framing.

    Fabricated Unit Logic

  • Page 8

    Panelized construction minimizes on-site

    construction. Construction materials typically

    fastened on-site are compiled into a component

    constructed in the controlled factory environment.

    Most common type of panel system is SIPs,

    structural insulated panels.

    SIPs are comprised of a thick layer of insulation

    between two layers of OSB, oriented strand board. A

    basic SIPs panel is composed of both structure and

    insulation layer.

    Panel systems may increase material cost by up to

    50% but on-site labor cost can potentially decrease

    by 50%. The benefit exists in the precision of factory

    controlled construction with isolation from problems

    that exist at the site.

    Installation of the panels is based on methodology

    developed for the specific system.

    Panel Installation Sequence

    Different systems will have

    different advantages: whether the

    panel is lightweight or resistant to

    weather, earthquakes, winds,

    insects, debris.

    PANEL System

  • Page 9

    Precast concrete construction is most readily

    seen within the city as infrastructure. It is a

    versatile construction type.

    Composition of Precast

    Materials and Accessories

    Rebar concrete: portland cement, water,

    air, aggregate

    Formwork:

    positive/negative connection keys

    Epoxy cementitious grout:

    between precast segments/ components.

    Structural Components

    Slabs

    length factor by function of service

    width by transportation restriction

    Beams

    depth is dependent on length

    length is function of capacity load

    Columns

    height is dependent on the width1. Solid

    2. Hollow Core

    3. Single Tee

    4. Double Tee

    5. Rectangular

    6. Inverted Tee

    7. L-shaped

    8. Round|Rectangle

    9. Square

    10. Double Height

    PRECAST CONCRETE

  • Page 10

    Process

  • Page 11

    Advantages of Prefabrication High capacity- enabling the realization of important projects

    Factory made products

    Shorter construction time- less than half of conventional cast in situ construction

    Independent of adverse weather conditions during construction

    Continuing erection in winter time until -20 C

    Quality surveillance system

    Opportunities for good architecture

    Healthy buildings

    Reduced energy consumption

    Environmentally friendly way of building with optimum use of materials, recycling of waste products, less noise and dust etc.

    Cost effective solutions

  • Page 12

    Disadvantages of Prefabrication Leaks can form at joints in prefabricated components.

    Transportation costs may be higher for voluminous prefabricated sections than for the materials of which they are made, which can often be packed

    more efficiently.

    Large prefabricated sections require heavy-duty cranes and precision measurement and handling to place in position.

    Larger groups of buildings from the same type of prefabricated elements tend to look drab and monotonous.

    Local jobs may be lost, if the work done to fabricate the components being located in a place far away from the place of construction. This means that

    there are less locals working on any construction project at any time,

    because fabrication is outsourced

  • Page 13

    EXAMPLES of Prefabrication

    NAKAGIN CAPSULE TOWER

    T30A HOTEL TOWER

    GFRG Demo Building at IIT Madras

  • Page 14

    NAKAGIN CAPSULE TOWER LOCATION: TOKYO, JAPAN

    BUILDING STATISTICS-

    SITE AREA: 442 SQUARE METRES BUILDING AREA: 430 SQUARE METRES TOTAL FLOOR

    AREA: 3,091 SQUARE METRES.

    STRUCTURE DETAILS: STRUCTURAL STEEL FRAME PARTLY ENCASED IN CONCRETE MAX

    OF 140 CAPSULE UNITS (PREFABRICATED) 11-

    13 STORIES INCLUDING 1 BASEMENT

    MATERIAL DETAILS: CAPSULE EXTERIOR: STEEL WITH SPRAYED PAINT FINISH CAPSULE

    INTERIOR: STEEL CAPSULE WITH CLOTH

    CEILING AND FLOOR CARPET TOWERS:

    CORTEN STRUCTURAL STEEL FRAME LOWER

    LEVELS: FAIR-FACED REINFORCED CONCRETE

    .

  • Page 15

    Methodology: Japanese Metabolism,

    physical objects are never eternal,

    celebrates individualism, response to

    long commutes.

    Units of Prefabrication: Capsules

    arrive from factory completely

    prefabricated, ready to be lifted by

    crane and bolted onto the

    superstructure.

    Structure: Steel frame with light-

    weight concrete shaft which houses

    vertical circulation, mechanical shafts.

    Delivery: Dense urban surroundings

    meant that capsules were delivered

    from factory to site on the same day it

    was attached to the superstructure

    NAKAGIN CAPSULE TOWER

  • Page 16

    THE STRUCTURE :

    REPUTED TO BE THE WORLDS FIRST STRUCTURE THAT IMPLEMENTED THE INNOVATIVE IDEA OF

    CAPSULE ARCHITECTURE, KISHO KUROKAWA

    DESIGNED THE NAKAGIN CAPSULE TOWER BASED

    OFF OF HIS SUSTAINABILITY CONCEPT CALLED

    METABOLISM.

    THE NAKAGIN CAPSULE TOWER IS A MIXED-SYSTEM STRUCTURE, UTILIZING BOTH TRADITIONAL ARCHITECTURE WITH MODERN

    TECHNOLOGY WITHIN ONE ENTITY. IT IS MADE OF

    TWO REINFORCED CONCRETE AND STEEL FRAME

    PILLARS OF ASYMMETRIC HEIGHTS, BOTH HOUSING

    PUBLIC UTILITIES SUCH AS STAIRS, ELEVATORS,

    PLUMBING, AND ELECTRICAL SYSTEMS .

    THE 14-STORY HIGH TOWER HAS 140 CAPSULES

    STACKED AT ANGLES AROUND THE CENTRAL CORE.

    KUROKAWA DEVELOPED THE TECHNOLOGY TO

    INSTALL THE CAPSULE UNITS INTO THE CONCRETE

    CORE WITH ONLY 4 HIGH-TENSION BOLTS, AS WELL

    AS MAKING THE UNITS DETACHABLE AND

    REPLACEABLE.

    NAKAGIN CAPSULE TOWER

  • Page 17

    THE CAPSULE :

    THE STEEL FRAME CAPSULES (WHICH

    HAVE BEEN DESIGNED TO BE

    REPLACEABLE, REMOVABLE, AND

    TRANSPORTABLE) WERE PREFABRICATED

    IN SPECIALIST FACTORIES AND

    ASSEMBLED AT A PLANT BEFORE BEING

    DELIVERED TO THE SITE. EACH ONE WAS

    LIFTED BY MECHANICAL CRANES AND

    WERE ATTACHED TO THE TOWER SHAFTS

    USING 4 HIGH-TENSION BOLTS

    THE CAPSULE INTERIOR WAS PRE-

    ASSEMBLED IN A FACTORY THEN HOISTED

    BY CRANE AND FASTENED TO THE

    CONCRETE CORE SHAFT.

    DETAIL OF SYSTEM OF CAPSULE JOINING TO SHAFT

    NAKAGIN CAPSULE TOWER

  • Page 18

    THE CAPSULE :

    Capsule Axonometric

    1. Plumbing, Electrical, & Waste Lines

    2. Vertical Plug-In Service Fin

    3. Air Conditioning Duct

    4. Air Conditioning Register

    5. Prefabricated Bathroom

    6. Built-In Desk

    7. Moveable Chair

    8. Built-In Bed

    NAKAGIN CAPSULE TOWER

  • Page 19

    Typical Capsule Plan 1. Capsule Entrance

    2. Prefabricated Bathroom

    3. Air Conditioning Chase

    4. Interior Finish Surface

    5. Welded Light-Weight Steel Truss Member A6. Welded Light-Weight Steel Truss Member B7. Built-In Bed

    8. Circular Window

    NAKAGIN CAPSULE TOWER

    The capsules contained a built-in bed and

    drop-in bathroom unit. They were outfitted off

    site and hoisted into place by crane, latching

    onto the fourteen-story superstructure and its

    concrete shaft of vertical circulation. All

    capsules were driven in by truck the same

    day they were to be plugged-in. A stop-over happened on the outskirts of Tokyo where

    the capsules got transferred to smaller

    trucks.

  • Page 20

    HE BORROWED THE CAPSULE TERMINOLOGY FROM THE AEROSPACE INDUSTRY (ALREADY AWARE THAT

    MANY SPACESHIPS HAVE IMPLEMENTED THE IDEA OF

    EFFICIENT AREA-USAGE) AND RETROFITTED A

    RECTANGULAR CABIN OF 8 FEET BY 12 FEET FLOOR

    SPACE WITH A BUILT-IN BATHROOM, DOUBLE BED,

    DESK, STORAGE SPACES, TV, TAPEDECK,

    TYPEWRITER, CALCULATOR, CLOCK RADIO, AND A 2-

    BURNER STOVE. IT WAS PLANNED AS A FUTURISTIC

    NICHE FOR MODERN BUSINESSMEN IN TOKYO.

    NAKAGIN CAPSULE TOWER

    KUROKAWAS DESIGN CONCEPT FOCUSES ON HOW TO MAKE

    THE MOST EFFICIENT USE OF

    LIVING SPACE TO

    ACCOMMODATE THE EVERYDAY

    ESSENTIALS OF A PERSON.

    INSIDE THE CAPSULE

    (2.5M X 4.5 X 2.5M) :

  • Page 21

    Exploded Axonometric

    1. Precast Concrete Shell w/ Steel Frame

    2. Plug-In Service Fins

    3. Lightweight Precast Concrete Floor Plates

    4. Precast Concrete Lift Shaft

    5. Ground Level Podium - Office Space

    Armature: a framework to support the clay or other

    material used in modelling.

    The tower is comprised of two, interconnected towers

    which serve as the framework for the capsules to rest

    on. The on-site preparation work to create the armature

    is the first stage.

    The Armature Components

  • Page 22

    Components: Plan & Core

    1. Typical Capsule

    2. Lightweight Precast Concrete Floor Plate

    3. Prefabricated Interim Bridge

    4. Plug-In Service Fin

    5. Precast Concrete Shell w/ Steel Frame

    6. Prefabricated Lift Cage

    7. Typical Floor Entrance/Exit

    Aggregation: Type 1

    1. Typical Side-Entry Capsule w/ Side Window

    2. Typical Front-Entry Capsule w/ Side Window

    3. Side Window Capsule Aggregation

    Aggregation: Type 2

    1. Typical Side-Entry Capsule w/ End Window

    2. Typical Front-Entry Capsule w/ End Window

    3. End Window Capsule Aggregation

    The Aggregation & Capsule Delivery

    NAKAGIN CAPSULE TOWER

    Type 1

    Type 2

  • Page 23

    Capsule Delivery 1. Capsule Base Connections Dtail

    2. Capsule Bolting Process

    3. Capsule Bolting Connection Detail

    4. Prefabrication - 3 Hour Assembly

    5. Transportation - 500km

    6. Construction - 7-8 Months

    NAKAGIN CAPSULE TOWER

  • Page 24

    TIME LINEThe precast concrete floor slabs that were part of the

    cores structure were erected at a rate of one every two days, alternating with the construction of the steel frame,

    affording a full operational core to facilitate the periodic

    construction of the framework without an external

    scaffold. 144 capsules were attached to the building in

    less than a month. Interestingly, the podium, which is the

    most under-looked part of the project, had more

    traditional construction techniques and also responsible

    for much of the on-site construction time.

  • Page 25

    NAKAGIN CAPSULE TOWER

  • Page 26

    NAKAGIN CAPSULE TOWER

  • Page 27

    T30A HOTEL TOWER

    LOCATION- CHANGSHA, CHINA HEIGHT: 99.9 meter / 328 feet FLOORS- G+30 GROUND FLOOR AREA- 17,602 m / 189,466 ft OWNER/DEVELOPER- BSB GROUP

    (BROAD SUSTAINABLE BUILDING)

    BUILDING FUNCTION- HOTEL STRUCTURAL MATERIAL- STEEL

  • Page 28

    A 3.915.6m main board including flooring and ceiling, embedded shafts of ventilation,

    water supply & drainage, electricity and

    lighting. All needed pillars, diagonal bracings,

    doors, windows, walls and even sanitary &

    kitchen wares for the room installation are

    placed on main board for factory shipment.

    One truck can carry 120m2 main boards and

    then deliver them to the construction site to

    be hoisted in installation place. What all

    workers need to do is just screwing bolts,

    painting. Such a high-efficiency construction

    mode makes on-site installation only account

    for 7% of the total construction hours. This

    building is 93% factory-made.

    T30A HOTEL TOWER

  • Page 29

    T30A HOTEL TOWER

  • Page 30

    THE INSTANT SKYSCRAPER

  • Page 31

    THE INSTANT SKYSCRAPER

  • Page 32

    THE INSTANT SKYSCRAPER

  • Page 33

    THE INSTANT SKYSCRAPER

  • Page 34

    THE INSTANT SKYSCRAPER

  • Page 35

    T30A HOTEL TOWER

  • Page 36

    GFRG Demo Building at IIT Madras

  • Page 37

    GFRG Demo Building at IIT Madras

  • Page 38

    GFRG demo building at IIT Madras (1981 sq ft)

    GFRG Demo Building at IIT Madras

  • Page 39

    GFRG Demo Building at IIT Madras

    TYPICAL FLOOR PLAN

    BUILT UP AREA-1981.3 SQ. MT.

  • Page 40


Recommended