+ All Categories
Home > Documents > Preliminary Ventilation and Cooling during the ...tunnel2016/images/... · In order to specify and...

Preliminary Ventilation and Cooling during the ...tunnel2016/images/... · In order to specify and...

Date post: 21-Apr-2020
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
12
HBI Haerter www.hbi.ch 8 th International Conference “Tunnel Safety and Ventilation” 2016, Graz 1 / 12 Preliminary Ventilation and Cooling during the Construction of the Brenner Base Tunnel Andreas Busslinger (*), Romed Insam (**) (*) HBI Haerter AG, Switzerland (**) BBT SE, Austria
Transcript
Page 1: Preliminary Ventilation and Cooling during the ...tunnel2016/images/... · In order to specify and verify preliminary ventilation/cooling adequate simulation tools must be used (e.g.

HBI Haerter

www.hbi.ch 8th International Conference “Tunnel Safety and Ventilation” 2016, Graz 1 / 12

Preliminary Ventilation and Cooling

during the Construction of the

Brenner Base Tunnel

Andreas Busslinger (*), Romed Insam (**)

(*) HBI Haerter AG, Switzerland

(**) BBT SE, Austria

Page 2: Preliminary Ventilation and Cooling during the ...tunnel2016/images/... · In order to specify and verify preliminary ventilation/cooling adequate simulation tools must be used (e.g.

HBI Haerter

www.hbi.ch 8th International Conference “Tunnel Safety and Ventilation” 2016, Graz 2 / 12

Content

1. Introduction Brenner Base Tunnel

2. Design objectives preliminary ventilation / cooling

3. Base data

4. Methodology ventilation / cooling design

5. Concepts preliminary ventilation / cooling

6. Specification / performance data

7. Conclusions

Page 3: Preliminary Ventilation and Cooling during the ...tunnel2016/images/... · In order to specify and verify preliminary ventilation/cooling adequate simulation tools must be used (e.g.

HBI Haerter

www.hbi.ch 8th International Conference “Tunnel Safety and Ventilation” 2016, Graz 3 / 12

1. Introduction Brenner Base Tunnel

emergency stop station Trens

emergency stop station St. Jodok

emergency stop station Innsbruck

south portal Fortezza

north portal Innsbruck

rescue tunnel

exploratory tunnel

cross passage

Brenner Base Tunnel:

key element of European

high performance railway

network

amongst world’s longest

traffic tunnels (64 km)

construction (5 main

construction lots)

underway

increased rock

temperatures expected

Page 4: Preliminary Ventilation and Cooling during the ...tunnel2016/images/... · In order to specify and verify preliminary ventilation/cooling adequate simulation tools must be used (e.g.

HBI Haerter

www.hbi.ch 8th International Conference “Tunnel Safety and Ventilation” 2016, Graz 4 / 12

2. Design objectives ventilation / cooling

General objectives:

provision of decent tunnel

climate during normal

operation

support of rescue and

intervention in case of

emergency

smallest possible

restriction of construction

progress

high flexibility regarding

changes of construction

Page 5: Preliminary Ventilation and Cooling during the ...tunnel2016/images/... · In order to specify and verify preliminary ventilation/cooling adequate simulation tools must be used (e.g.

HBI Haerter

www.hbi.ch 8th International Conference “Tunnel Safety and Ventilation” 2016, Graz 5 / 12

3. Base data

Essential base

data of

ventilation /

cooling design:

construction

schedule (interaction

of activities)

construction method

(TBM, drill & blast)

logistics (transport

properties, mucking)

Page 6: Preliminary Ventilation and Cooling during the ...tunnel2016/images/... · In order to specify and verify preliminary ventilation/cooling adequate simulation tools must be used (e.g.

HBI Haerter

www.hbi.ch 8th International Conference “Tunnel Safety and Ventilation” 2016, Graz 6 / 12

4. Methodology ventilation / cooling design

PRESETTINGS

TUNNEL LOGISTICS

(construction schedule,

required staff/machinery,

available space, etc.)

THRESHOLDS

OCCUPATIONAL MEDICINE

(fresh air requirements,

max. temperatures, etc.)

DEFINITION

REQUIRED

FRESH AIR AMOUNT

AT WORK SITES

DEFINITION

REQUIRED

COOLING POWER

AT WORK SITES

CONCEPT

PRELIMINARY

COOLING

CONCEPT

PRELIMINARY

VENTILATION

SPECIFICATION

PRELIMINARY

COOLING SYSTEM

SPECIFICATION

PRELIMINARY

VENTILATION SYSTEM

Page 7: Preliminary Ventilation and Cooling during the ...tunnel2016/images/... · In order to specify and verify preliminary ventilation/cooling adequate simulation tools must be used (e.g.

HBI Haerter

www.hbi.ch 8th International Conference “Tunnel Safety and Ventilation” 2016, Graz 7 / 12

5. Concepts preliminary ventilation

General

characteristics:

individual concept for

each construction phase

focus on peak

construction performance

every portal used for air

supply / removal.

fresh air requirements

achieved

no substantial obstruction

of tunnel construction

Page 8: Preliminary Ventilation and Cooling during the ...tunnel2016/images/... · In order to specify and verify preliminary ventilation/cooling adequate simulation tools must be used (e.g.

HBI Haerter

www.hbi.ch 8th International Conference “Tunnel Safety and Ventilation” 2016, Graz 8 / 12

5. Concepts preliminary cooling

Main principles:

local heat removal with

air cooling machines at

work sites

heat transport via cooling

water in pipes

heat disposal to the

ambient with cooling

towers

low impact on the

ambient

flexible / nearly fail safe

operation

Page 9: Preliminary Ventilation and Cooling during the ...tunnel2016/images/... · In order to specify and verify preliminary ventilation/cooling adequate simulation tools must be used (e.g.

HBI Haerter

www.hbi.ch 8th International Conference “Tunnel Safety and Ventilation” 2016, Graz 9 / 12

6. Specification / performance data

Preliminary ventilation:

specification of fans and

air ducts based on concept

and calculations

outline: 56 main fans, 16

auxiliary fans, 200 km air

duct, 172 air barriers, 8 air

locks

performance: total power

demand 25 MW, fresh air

supply 2’100 m3/s

to be verified in execution

Page 10: Preliminary Ventilation and Cooling during the ...tunnel2016/images/... · In order to specify and verify preliminary ventilation/cooling adequate simulation tools must be used (e.g.

HBI Haerter

www.hbi.ch 8th International Conference “Tunnel Safety and Ventilation” 2016, Graz 10 / 12

6. Specification / performance data

Preliminary cooling:

specification of air cooling

machines, pipes, water

pumps and cooling towers

based on tunnel climate

simulations (BAUKLIMA)

outline: 6 cooling towers,

94 pumps, 300 km pipe,

228 air cooling machines

performance: demand

50 MW, cooling 70 MW

to be verified in execution

Page 11: Preliminary Ventilation and Cooling during the ...tunnel2016/images/... · In order to specify and verify preliminary ventilation/cooling adequate simulation tools must be used (e.g.

HBI Haerter

www.hbi.ch 8th International Conference “Tunnel Safety and Ventilation” 2016, Graz 11 / 12

7. Conclusions Intense tunnelling requires a great deal of fresh air challenged by

limited accessibility.

Concepts only call for minor additional excavation (no additional shafts

and tunnels).

Diligent analysis of construction phases ensures uninterrupted

ventilation/cooling.

Ventilation/cooling design are mainly based on occupational medicine

and tunnel logistics.

In order to specify and verify preliminary ventilation/cooling adequate

simulation tools must be used (e.g. the code BAUKLIMA) particularly

considering interaction of ventilation and cooling.

A module based design of ventilation and cooling rather allows for

changes in construction schedule (e.g. can be adapted easier) than a

fixed or centralised solution.

Changes of tunnel logistics relating to preliminary ventilation and

cooling must be continuously checked.

Page 12: Preliminary Ventilation and Cooling during the ...tunnel2016/images/... · In order to specify and verify preliminary ventilation/cooling adequate simulation tools must be used (e.g.

HBI Haerter

www.hbi.ch 8th International Conference “Tunnel Safety and Ventilation” 2016, Graz 12 / 12

Thank you for your attention!


Recommended