+ All Categories
Home > Documents > Primavera Tutorial - P3

Primavera Tutorial - P3

Date post: 07-Apr-2018
Category:
Upload: perwaiz
View: 224 times
Download: 1 times
Share this document with a friend

of 226

Transcript
  • 8/6/2019 Primavera Tutorial - P3

    1/226

    PLANNING USINGPRIMAVERA PROJECTPLANNER (ver. 3.1)

    It is easy itis simple

    . . t r yi t

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    2/226

    Module 1

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    3/226

    Module 1:Introduction to Primavera Project PlannerVer. 3.1

    This module contains: What is Primavera Project Planner (P3)? How to deal with P3 file commands? P3 screens

    Method of working How to create a new project

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    4/226

    What is Primavera Project Planner?

    Primavera Project Planner is the flagship product of PrimaveraSystems, Inc. the leader in the management software since 1982

    Primavera Project Planner is abbreviated P3 P3 is specialized in managing all types of projects: small,medium, and large

    Big projects throughout the world were planned and controlledusing P3 P3 is used in almost all countries of the world

    Mainly there are two stages in Project Management to manageany project:

    Planning stage Monitoring stage (also Control stage)

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    5/226

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    6/226

    In Planning stage, which takes place before the practical start ofthe project, the management team will plan for the following factors:

    TimeResources

    Cost

    What takes place in the Planning stage:

    Calculating activity duration

    Understanding the logic sequence of the projectAssigning Resources and Costs to activity

    In the Monitoring stage, the management team will:

    Collect actual data from the field, in daily basis

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    7/226

    How to start P3?

    You have two ways to start P3:

    Double-click shortcut in the desktop, or

    From Windows taskbar, click

    Start >Programs > Primavera >Primavera Project Planner

    P3 will start with no projects open

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    8/226

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    9/226

    From the toolbar clickOpen , or frommenus selectFile>Open

    The following dialoguebox will appear:

    Opening a project in P3

    1. Specify the Drive youwant to open theproject from

    2. Specify the Folders3. In the Projects table

    your project should bedisplayed in the list,click on it

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    10/226

    4. If you want to make surethat the selected project, isyour desired project, simplyclick Overview button, andthe following dialogue box

    will be displayed:

    5. If this is the file, click Open,otherwise click Cancel, and

    select another file

    In this dialogue box youcan see almost all the neededinformation including: Projecttitle, Company name, Planning

    unit, Project Start date, andData date, Activity count, EarlyFinish of the project

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    11/226

    P3 Bar Chart Screen

    P3 Displays to work with

    Toolbar Menu Bar Title Bar

    ActivityTable

    Bar Area

    Status Bar

    Edit Bar

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    12/226

    P3 PERT Screen

    P3 Displays to work with

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    13/226

    Method of Working

    P3 is using Critical Path Method(CPM) in calculating thedates and floats of the activities

    P3 is using Precedence Diagramming Method(PDM) inpresenting the network

    P3 will calculate the schedule reference to the Data Date(DD), which is defined as Time Now:

    If you are in the Planning phase DD is the StartDate of the Project If you are in Monitoring phase, it will be the date ofthe day you will run the Schedule command in

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    14/226

    Creating a New project

    From the toolbar: Click New button, orFrom menus: File>New

    The following dialogue box will appear:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    15/226

    Input the Project nameInput Number/VersionInput the Project title, and Company nameInput the Planning unit (Hour, Day, Week, and Month)Input Workdays/week, which is the number of working daysper a given weekInput Week starts onInput the Project start date

    Input when the Project must finish by date (optional)

    Click Add and a new empty project will be opening

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    16/226

    Module 2

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    17/226

    Module 2:Classification Using Activity Codes and IDs

    This module contains: The importance of Classification in projects The difference between Activity Codes and Activity IDs Steps to create Activity Code Dictionary Printing and Sharing Activity Code Dictionary

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    18/226

    Classification of Activities can be done using:

    Activity Codes (Code or ID) WBS (Work Breakdown Structure)

    Note: We will discuss in this course the ActivityCodes

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    19/226

    Before You Start

    Before you start inputting data to P3, go through thefollowing steps:

    1. Draw diagram (or diagrams, depends on your

    case) to show the types of classifications andtheir expected values, like the diagram below:

    Phase

    Construction Internal Finishing External Finishing

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    20/226

    2.Then type a code for each classification and itsvalues:

    PhasePHAS

    ConstructionCN

    Internal FinishingIF

    External FinishingEF

    From the diagram above, we can see the following:

    The classification (we will call it Activity Code) is Phase, and itsabbreviation is PHASThe expected values for this Activity Code are: Construction CN,Internal Finishing IF, and External Finishing EFThe number of characters for each value is 2

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    21/226

    Activity Code CommandFrom menus select Data>Activity Codes, the following dialogue boxwill appear:

    In the Activity Code tab you will find activitycodes defined in your project (these are thedefault activity codes, and they will be copied

    to any new project automatically) so the firststep will be to delete the existing codes

    Input the Activity Codes taking intoconsideration the following:

    The Nameof the code shouldnt exceed

    4 charactersThe Length, which is the number of

    characters for the values of thiscode (i.e. in our previous example itwas 2). Sum of all lengths shouldntexceed 64 characters

    The Description, which is a briefdescription of the code

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    22/226

    You will get something like the dialogue box shown below:

    Now input the values for each Activity Code, like below:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    23/226

    Activity ID tab in Activity Code

    In the Activity Code dialogue box there is a tab titled Activity ID:

    What is the significance of Activity ID in P3? To answer this question,we have to know that each and every activity in P3 should

    have an Activity ID (which is the Activity Name), which may beanything you wish, like:

    AA1, AA2, AA3, etc.123, 124, 125, etc.AAA, AAB, AAC, etc.

    But as you can see the above IDs dont reflect any meaning or anytype of information. P3 suggests to utilize the Activity ID part to dotwo things:

    Name our activities intelligentlyClassify our activities just like we did in Activity Codes

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    24/226

    You can have up to four classifications as Activity ID

    Click on the Activity ID tab, and do as you did in the Activity Code tab: The Nameof the ID shouldnt exceed 4 characters The Length, which is the number of characters for the values of

    this ID. The sum of all lengths shouldnt exceed 10 characters The Description, which is a brief description of the ID

    You will get something like the below:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    25/226

    Set the Order for Codes and IDs

    One of most important reasons we useActivity Codes, and Activity IDs is toorganize and group activities, like inthe picture on the right:

    In Order field you will specify whichgroup will appear first

    If you didnt interfere in the order, P3will order them alphabetically

    Check the dialogue box on the right :

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    26/226

    Validate Against Dictionary and Refresh

    If the planner, while linking Activity Codes (or Activity ID) to an

    Activity, input a value that doesnt exist in the dictionary, how would P3react?It depends on your project settings. There are two methods:

    Automatic method Manual method

    Automatic methodFrom menus select Data>Activity CodesIn the bottom portion of dialogue box, there is a checkbox says:When new code values occurs in project, validate againstdictionary

    Click this checkbox on

    From now on, whenever the user input any value that doesnt exist inthe dictionary, P3 will add this value to the dictionary

    User should later input the description, and order

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    27/226

    Manual method

    From menus select Data>Activity Codes

    Click off the checkbox says: When new code values occurs in

    project, validate against dictionary

    From now on, whenever the user input any value that doesntexist in the dictionary, P3 will not add this value to the dictionary,but rather will wait for the user to do that manually

    To do that manually, click Refresh button

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    28/226

    Printing Activity Code Dictionary

    In order to include the classification hierarchy with your project papers, soother users would understand the coding structure of your project, you can

    print a report and save it

    Click the Print button, P3 will give you the following warningmessage:

    Click OK, the following dialogue box will appear:

    A report will be produced, just like the one on the next page

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    29/226

    This is a sample of a report:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    30/226

    Transferring Activity Code Dictionary

    You can transfer Activity Code Dictionary between projectsGo to the new project you want to transfer to

    From menus select Data>Activity CodesClick the Transfer button, the following warning message willappear:

    Click OK. The following dialogue box will appear:

    Specify the Drive and Folder whichthe desired project you want to copy

    from resides in, then at the top portionof the dialogue box specify theproject. Now click Transfer

    The dictionary will be copied to yourproject

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    31/226

    Module 3

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    32/226

    Module 3:Inputting Basic Activity Data

    This module contains:

    What is activity?The basic activity data needed to input an activityPreparation before you input an activity

    Adding/Deleting/Editing ActivitiesCopying activitiesLinking activities with Activity Codes

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    33/226

    What is an Activity?

    1. Activity is the basic component of any project2. We can define activity as any work you want to accomplish. Work

    is a very loose word, each one of us can look at it from differentangle. For instance, one will consider Constructing First FloorSlab as a single activity, Another will consider:

    Formwork for First Floor Slab as an activity Re-baring for First Floor Slab as an activity Concrete Placement for First Floor Slab as an activity

    It is a common knowledge that if two planners were given thesame project, the activity list will be very different. This will highlight thefact that Activity List writing is not an exact science

    We can input lots of information pieces for an activity, but initially weneed only need four:

    1. Activity ID2. Activity Description3. Activity Original Duration (abbreviated as OD)4. Activity Type

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    34/226

    Activity ID

    Activity ID is the Activity NameIt is the only compulsory piece of information P3 asks for, other data

    either can be left empty, or there is a default value for itIn Module 2, we selected the Building to be our Activity ID, with expectedvalues Classrooms CR, Gym GM, and Lab LBNow, each activity ID in our project will start with either CR, GM, or LB,example would be CR100, GM205, and LB303. The numbers after the twocharacters would be sequential number, which would be left to the user

    Activity ID could be as long as 10 characters (spaces are allowedand counted)

    Activity Description

    This piece of information is devoted for the user to write a short

    description about the activityYou can leave it empty if you wish (P3 will not generate any errormessages)You can type up to 48 characters (including spaces)

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    35/226

    Activity Original Duration (OD)

    Activity Original Duration can be either input by the user, orcalculated by P3

    It depends on the type of resources which will be assigned to it:If the resources were Non-Driving, the user will assign the durationIf the resources were Driving, P3 will calculate the duration

    (In this course, we will tackle only the first type of activities, hence we needto calculate the OD manually then input the value to P3)

    Some guidelines to help calculating OD would be:Prepare for each activity a worksheet (this can be a piece of paper orMS Excel sheet)List the resources which will work on the activityList the amount of work in which each resource can accomplishSpecify the productivity, and estimated count of each resource to beassigned

    With the above information available the user can produce correctOD which is based on real calculation

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    36/226

    Activity Type

    In P3, there are 9 types of activities, each one would suit a certain case, the default type isTask activityIn this courseware, we will discuss only five of them, they are:

    Task activityStart Milestone activity (SM)Finish Milestone activity (FM)Start Flag activity (SF)Finish Flag activity (FF)

    Task Activity >The default type of activities>Task activity is any activity that has a duration, the start and finish of it

    will be calculated according to the activity base calendar>Duration should be input by the user if no resources or Non-Drivingresources were assigned to the activity. In case of Driving Resources P3will calculate the duration

    Start and Finish >Zero-Duration activitiesMilestone >Start Milestone used to signify the beginning of an activity or

    group of related activities. Finish Milestone used to signify the

    ending of an activity or group of related activities>Start Milestone considered to be a Constraint, as all of the activitiesrelated to it directly cant start before it, but rather with it, or after it>Finish Milestone considered to be a Constraint, as all of theactivities related to it directly cant finish after it, but rather with it,or before it>Start Milestone should be updated, and will have Actual Start

    >Finish Milestone should be updated, and will have Actual Finish

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    37/226

    >Zero-Duration activities

    >Start Flag used to signify the beginning of an activity or group ofactivities. Finish Flag used to signify the ending of an activity orgroup of activities

    >Start Flag considered to be a Constraint, as all of the activitiesrelated to it directly cant start before it, but rather with it, or afterit

    >Finish Flag considered to be a Constraint, as all of the activities

    related to it directly cant finish after it, but with it, or before it

    >Start Flag, and Finish Flag are always Successorsto otherActivities and never considered as Predecessors to otherActivities. Accordingly, SF will accept neither Start-To-Finish, norFinish-To-Finish relationships. In addition, FF will accept neitherFinish-To-Start, nor Start-To-Start relationships.

    >Start Flag, and Finish Flag will not be updated by the user, butP3will update them according to the activities linked to them

    Start and FinishFlag

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    38/226

    Example ofMilestones

    Activity CActivity A

    Activity D

    Activity B

    Activity E

    Activity F

    FinishMilestone

    StartMilestone

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    39/226

    Example ofFlags

    Activity CActivity A

    Activity D

    Activity B

    Activity E

    Activity F

    FinishFlag

    StartFlag

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    40/226

    Before You Start

    Before you start inputting basic activity data,from menus select Tools>Options>Activity Inserting, the following dialogue box

    will appear:

    You have three choices to select from:

    To Automatically number activities without showing the Activity FormTo Automatically number activities and showing the Activity FormTo show the Activity Form only

    Using the Activity Form only will give you more control over the process ofinputting activities. Consequently, do the following:

    Click off Automatically number activities

    Click on Use activity form when inserting an activity

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    41/226

    Adding Activities

    From the Edit Bar, click the button with plus signThe Activity Form will appear automatically:

    You will find the cursor blinking in the ID part, type in the

    Activity ID, then press Tabkey, or click the next field (dontpress Enter, as this means that you are done with inputting)Next field is Activity Description, type in the activitydescription, press TabkeyThe cursor will go directly to the OD field, input theestimated original duration of your activitySpecify the Activity Type, you have two choices:

    If your activity is Task, click OK, or press EnterIf your activity is SM, FM, SF, or FF, right-click on the Typefield, the following menu will appear:

    Select the desired activity typeClick OK, or press Enter, the Activity Form will disappearTo add another activity click below the last activity in theactivity table, or click plus sign again

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    42/226

    Deleting Activities

    Select the activity (or activities) to be deletedFrom Edit bar, click minus sign , or from menus click Edit>Delete

    The following dialogue box will appear:

    Editing Activities

    There are two methods to edit the activity data: Editing all types of data Editing single data

    Editing all activity dataDouble-Click on any activity, the Activity Form will appear, then you can edit whatever data youwould likeThe same can happen if you select from menus Edit>Edit Activity

    Editing single activity dataSelect the cellwhich contains the data you want to edit (the cell selector is a bold frameappears around the cell required), just like the below example:

    The contents of the cell will appear in the Edit barClick the Edit bar, or press F2 to edit the contents

    If you are sure of what you are doing click Yes, theactivity will be deletedIf not click No, the deleting process will stop

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    43/226

    Notes:

    Other ways to show the Activity Form permanentlyare:

    From menus select View>Activity Form

    Press F7From toolbar click Activity Form icon

    These 3 ways are ON/OFF functions, which means they will show or hide the Activity Form.Using the above methods of editing activities is applicable to all types of data except twotypes:

    All the data calculated by P3 (like ES, EF, LS, LF, TF, etc.) which we will discuss later

    Activity ID, unless you opened your project as Exclusive (which is a checkbox in theOpen dialogue box)

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    44/226

    Copying Activities

    Copying activities means copying the whole data of single activity or activitiesCopying can be done from a project to the same project, or across projects

    Select the desired activity (or activities)From menus select Edit>Copy, Ctrl+C, or right-click and select Copy

    Go to the desired place (the same project, or open another project)

    From menus select Edit>Paste, Ctrl+V, or right-click and select Paste

    In order for P3 to make sure that no duplication of the same activity ID will takeplace, the following dialogue box will appear:

    You can select one of the four choices available:

    Rename duplicates only

    Rename all

    Prefix or suffix

    Auto-increment

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    45/226

    Rename P3 will select the coming activities with matching IDs only to be renamed, the rest willduplicates only be pasted without any change

    Rename All P3 will show all activities to be renamed

    Prefix or suffix It is a fast way to rename activities, by suggesting a character (or characters) to appear

    to the left of the coming activities IDs (this is prefix) or appear to the right of the comingactivities IDs (this is suffix)

    Auto-increment It is another fast way to rename activities, by suggesting a base name (for instanceGM100) and then an increment number (for instance 10) this will allow P3 to rename allthe coming activities easily

    Also you can make sure that the coming activities are the desired ones, by clickingContents button which will display the names of the coming activities

    Linking Activities with CodesIn Module 2 we created Activity Code Dictionaryin this Module we will link each activity with the proper code valueThe lower left part Activity Form contains the Activity Codes defined and its value

    Right-click on the desired code, a list of the available values will be displayed, select thedesired value

    Do the same for the other codes

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    46/226

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    47/226

    Module 4:Inputting Logic Relationships

    This module contains:What is logic relationship?Predecessor and SuccessorTypes of relationshipInputting relationships using Bar Chart viewInputting relationships using PERT view

    Editing relationshipsTracing relationshipsLink and unlink activitiesUsing Autolink function

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    48/226

    What is Logic Relationship?

    In Module 1 it was mentioned that P3 uses PDM

    (Precedence Diagramming Method) in representing thenetwork. There are mainly two methods to represent anetwork:

    Activity-On-ArrowActivity-On-Node

    Activity-On-ArrowAlso known ADM (Arrow Diagramming Method)The old method of representing the networkTo go from event A to event B, you will do certain thing:

    Almost none of the software in the current market is offering thismethod for representing the network

    CBA Excavation Foundation

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    49/226

    Activity-On-NodeAlso known as PDM

    The activities are at the two nodes of a logic relationship.Logic relationship is a link which ties two activities in asequence manner, for instance:

    Excavation Foundation Filling

    The name Logicindicates that the relationship is not compulsorybut rather it represents how the planner is viewing the sequenceof the project, hence any delay in start or end, is acceptable

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    50/226

    Predecessor and Successor

    Based on the latter each activity will have:

    Predecessor (or Predecessors)

    Successor (or Successors)

    PredecessorIs any activity takes place in time before a given activityThere could be more than one predecessor for a given activity

    SuccessorIs any activity takes place in time after a given activityThere could be more than one successor for a given activity

    One of the common practices is to prepare a table called either the Successor tableor Predecessor table, depends on the way you want to take it:

    If you want to start with the first activity and go all the way to the right,you should produce a Successor table

    If you want to start with the last activity and go all the way to the left, youshould produce a Predecessor table

    A successor table may look something like the following:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    51/226

    Types of Relationships

    P3 supports four types of relationships:

    Finish-To-Start (known as FS)Start-To-Start (known as SS)Finish-To-Finish (known as FF)Start-To-Finish (known as SF)

    Note: When we say Start, that means the start of a working

    day, when we say Finish, that means the finish of workingday

    Finish-To-StartThe most commonly used relationship, and the defaultrelationship in P3

    When A finishes B starts the next day:

    AOD=7

    BOD=10

    S=1 F=7 S=8 F=17

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    52/226

    Start-To-StartOne of two relationships which allows parallel activitiesWhen A starts B starts at the same day:

    A

    OD=7

    B

    OD=10

    S=1 F=7

    S=1 F=10

    Note: In the above case A is considered to be a Predecessor ofB although A and B starts at the same day

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    53/226

    Finish-To-FinishThe second relationship which allows parallel activitiesWhen A finishes B finishes at the same day:

    A

    OD=7

    BOD=10

    F=7

    F=7

    Note: In this case A is considered tobe a Predecessor of B although A andB finishes at the same day

    Start-To-FinishThis relationship is seldom used by planners

    It can be used effectively with flagsIf you want to link a start of an activity with aFinish Flag you can use Start-To-FinishrelationshipWhen A starts B finishes

    A

    B

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    54/226

    Relationships with LagNormally the following applies to relationship:In FS relationship if the predecessor finishes in day 5 (forinstance) the successor will start at day 6In SS relationship if the predecessor starts at day 5, thesuccessor will start at day 5

    In FF relationship if the predecessor finishes at day 11, thesuccessor will finish at day 11The above shows that relationships dictate immediatestart orfinish for the successor. If you dont want immediate start or finishfor the relationship, you have to use the Lagtime

    Lagtime is the number of time-periods (days in our case) whichyou delay the successor from its predecessor. Lag time can bepositive, or negative, check the following examples in the nextpage:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    55/226

    A

    B

    SS 6

    A BFS 7

    A

    B

    FF 4

    A

    B

    FS -3

    Start-To-Start with (+) Lag

    Finish-To-Start with (+) Lag

    Finish-To-Finish with (+) Lag

    Finish-To-Start with (-) Lag

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    56/226

    Inputting Relationships Using Bar Chart View: Step 1

    Draw your network on paper first:The biggest mistake a planner can do is to start inputtingrelationships without preparing it on paper first

    The management team should have more than one meetingdiscussing the logic of the network

    Drawing the network and the logic sequence is not an easy job, itneeds:

    Huge field experienceTeam work and discussion (even sometimes needs BrainStorming)

    Deciding which is more important to the planner (it differs from

    owner point-of-view, to contractor point-of-view) the completiontime, or the expenditure of money and resources. Hencecreating more serial fashion relationships, or parallel (oroverlapping) fashion relationships

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    57/226

    Inputting Relationships Using Bar Chart View: Step 2

    Prepare the layout so you can easily see the relationship lines. Thisinvolves three steps to do:1. Make sure that the relationship lines is shown

    2. Increase the Row Height3. Learn how to Find Activities

    1. Show Relationship linesThe relationships can be either displayed, or hidden. To make sure, do thefollowing:from menus choose View, the following menu will appear:

    If you see () beside Relationships, you will knowthat the relationship lines will be displayed, if not, doone of the following:

    From menus select View>RelationshipsPress F3, or

    From toolbar, click Relationship Lines tool

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    58/226

    2. Increase Row Height

    Increasing Row Height is to spread the activities vertically so you can view therelationship lines better, see the following examples:

    Without Increasing the row height: With Increasing the row height:

    a) Select one of the activities

    from menus select Format>Row Height,the following dialogue box will appear:

    b) Do the following steps:

    Turn off the check box Automatic

    Size Set the Row height in points value

    to the desired number Click on All Activities under Apply

    to part Click OK

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    59/226

    3. Find activityThis function is very important, as sometimes you need to locate an activity to startdefining its successor(s)

    Do one of the following:

    From menus select Edit>Find Activity

    Press Ctrl+F

    From toolbar, click Find Activity tool

    Using any of the above the following dialogue box will appear:

    Type in the Activity ID, select All activities, then click Find

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    60/226

    Inputting Relationships Using Bar Chart View: Step 3

    You can input the relationships using:Activity FormGraphically

    Using Activity Form

    Select (or Find) the activity you want to define either successor(s), orpredecessor(s) for

    Press F7

    Click either Pred, or Succ buttons

    The following dialogue box will appear>>>>>>>>>

    Click (+) sign, type in the predecessor (or successor) ID

    Specify the Rel (which is the relationship). The default is FS

    If there is any Lag, specify it

    You can define more than one predecessor, or successorSelect one of the predecessors, or successors, and click Jump , to go to it.Then continue defining relationships

    This what you may get>>>>>>>>>>

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    61/226

    Using Graphically method

    Specify the end (Start, or Finish) you want to start with for a certain activity

    Get closer to it, up until the cursor change to Relationship cursor

    Now click and hold. The relationship line will appear

    Go to the other desired end, and drop the relationship line

    The relationship line will be created

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    62/226

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    63/226

    Each activity is represented by a box, the left part of the box is the start, and theright part is the finish

    As you can see the boxes are very close to each other. To spread the boxeshorizontally and vertically, you can increase the spacingFrom menus select Format>Organize, the following dialogue box will appear,select the Spacing tab:

    Change to the new value for the spacing horizontally, and vertically

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    64/226

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    65/226

    Editing Relationships

    For both Bar chart view, and PERT view, the editing methods are the same.Available editing methods are:

    Using Activity FormGraphical method

    Using Activity Form

    Find the activity you want to edit the relationship for

    Press F7, The Activity Form will appear

    Click both Pred, or Succ buttonsThis what you will see:

    You can add new relationship, editan existing one, or delete arelationships according to your need

    Once you are done, close the twoforms, on the Activity Form clickOK. Now find another activity to editits relationships

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    66/226

    Graphical method

    It is better to do it in the PERT view, as the relationship lines appear clearer in thisviewGo to PERT viewFind the desired relationship to be editedClick the relationship line, the following dialogue box will appear:

    The dialogue box will show the following information:

    The current Predecessor (un-editable)

    The current Successor (un-editable)The relationship type

    The Lag

    Change either the relationship type, or the lagOr you can delete the relationship by clicking the Delete button

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    67/226

    Tracing Logic in PERT ViewOne of the greatest methods to check your logic:Go to PERT view

    Select an activityFrom menus View>Trace LogicThe screen will be cut into two halves. The lower half will show the currentactivity, its predecessor(s), and its successor(s):

    Check your work, then select another activity from the upper half, or from the lowerhalf

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    68/226

    Link and Unlink Activities

    This should be done only on Bar chart viewIf you have a series of activities and all of them are connectedwith FS relationship, you can link them fast and smoothly usingLink activity function, do the following steps:

    Select the desired activitiesFrom menus select Edit>Link ActivitiesThe activities will be linked with FS relationship

    You can unlink activities if they were linked with FS

    relationships:Select the desired activitiesFrom menus select Edit>Unlink ActivitiesThe activities will be unlinked

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    69/226

    Autolink ActivitiesThis facility is an automatic method of linking activities asyou input themFrom menus select Insert>AutolinkSelect an activity (this is a very important step) which will

    be the predecessor of the coming activitiesStart adding activitiesWhenever you are done, an FS relationship will beadded to the new activity

    To stop this facility, from menus select Insert>Autolinkagain

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    70/226

    Module 5

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    71/226

    Module 5:First Schedule Run

    This module contains:

    Automatic vs. Manual SchedulingSchedule PassesTotal and Free FloatThe Schedule command

    The view after SchedulingSchedule report

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    72/226

    Introduction

    Schedule is to calculate the start and finish datesfor each activity, hence will produce the finish date ofthe project

    Normally in Planning phase, the planner willperform scheduling several times, and the first oneshould be after finishing inputting activities and

    relationships. The purpose of the first run, is to getthe initial dates, so it can be used in the comingmeetings

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    73/226

    Automatic Schedule vs. Manual ScheduleIn P3 there are two types of scheduling:

    AutomaticManual

    Automatic Schedule

    From menus select Tools>Schedule, the following dialogue box willappear:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    74/226

    Click the Options button, the following dialogue box will appear:

    Under Automatic scheduling and leveling, make sure that Scheduleautomatically is selected, then click OK

    If you turn the automatic schedule on, that means, P3 will always recalculatethe dates if any new data and/or editing took place in your project. This methodwill not produce any schedule reports, which will deprive the user from knowingand documenting the changes that happened on the dates through out thedevelopment of the plan

    Note: This method is not recommended

    S

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    75/226

    Manual Schedule

    Under Automatic scheduling and leveling, make sure that Scheduleautomatically is NOTselected, instead select Off, then click OK

    This method means you have to issue the command of Tools>Schedule eachand every time your perform any changes on your project which will affect the startand finish dates.It will produce a scheduling report (will be shown later in this Module) whichcontains great information to the planner, also, it is considered a documenting toolto show the development of the planNote: This method is highly recommended

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    76/226

    The Schedule Passes

    When the user issue the Schedule command, P3 will perform two passes:Forward Pass, which will start from the first activity with no predecessor, all the

    way to the last activity with no successorBackward Pass, which will start from the last activity with no successor, all theway to the first activity with no predecessor

    Forward Pass

    This is done to calculate the Early Start (ES), and the Early Finish (EF), which wecall them Early dates. Early dates are the earliest dates an activity can start and

    finish after the finish of its predecessor(s).

    P3 will first locate the first activity with no predecessor. It could be more than oneactivity. The ES of the first activity is the start date of the project (which youinput when you created the project)

    To calculate the EF, P3 will use the following EF=ES+Dur-1

    (Why the -1? Comparing to the text books in management, this formula isdifferent. The formula used there is EF=ES+Dur. The answer to thatquestion is; text books starts at day 0, which is not practical. Yet in P3 westart at day 1, and hence we have to deduct 1 from the duration)

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    77/226

    Activity A

    EF=4OD=4ES=1

    Activity B

    EF=8OD=8ES=1

    Activity C

    EF=24OD=16ES=9

    Note: Activity C, waited for all of its predecessors to finish, hence startedat day 9. The calculated finish date of this small project derived from the EFof the last activity is day 24

    See the following example:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    78/226

    Backward Pass

    This is to calculate the Late Start (LS), and the Late Finish (LF), whichwe call them Late dates. Late dates are the latest dates an activity canstart and finish without delaying the calculated finish date of the project.

    P3 will locate the last activity with no successor. It could be morethan one activity . The LF of the last activity is the calculated EF whichwas produced in the Forward PassTo calculate the LS, P3 will use the following LS=LF-Dur+1

    (As we deduct 1 in the Forward Pass, we have to add 1 in theBackward Pass, so we can finish with day 1)

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    79/226

    Note: LF of activity A, and B is the day before LS of activity C, hence the LF isday 8

    Activity A

    LF=8

    EF=4OD=4ES=1

    LS=5

    Activity B

    LF=8

    EF=8OD=8ES=1

    LS=1

    Activity C

    LF=24

    EF=24OD=16ES=9

    LS=9

    See the following example:

    Total Float

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    80/226

    Total Float

    As a result of the Forward Pass, and Backward Pass, four dates will be produced(namely; ES, EF, LS, and LF). In view of that, P3 will calculate the Total Float (TF)

    Total Float is the number of days you can delay the start of an activity

    without starting at ES, but without delaying the wholeprojectTF = LF EF

    Accordingly the Backward Pass will be:

    Activity ALF=8TF=4

    EF=4OD=4ES=1

    LS=5

    Activity B

    LF=8TF=0

    EF=8OD=8ES=1

    LS=1

    Activity C

    LF=24TF=0

    EF=24OD=16ES=9

    LS=9

    If there is no Imposed Finish Datediscussed in the next Module), or anytype of Constraintthe lowest TF for any

    activity would be (zero) (0)We call the activities with TF = 0CriticalactivitiesWe call the activities with TF > 0 Non-CriticalactivitiesWe call the path that links the Criticalactivities; the Critical PathCritical Pathis the longest path in thenetworkA given network may have more thanone Critical PathWe call the above method ofcalculation, the Critical Path Method(CPM)

    Free Float

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    81/226

    Free Float

    P3 also will calculate the Free Float (FF). Free Float is the number of days youcan delay the start of an activity without starting at ES, but without delaying thesuccessor

    TF = ES of the successor - EF of the activity 1FF can be equal to TF, and can be different

    Other Data Checked for While Scheduling

    As you can see from the previous discussion, when the user issues the Schedule

    command, P3 will calculate six types of data, which are:Two Early Dates (ES, EF)

    Two Late Dates (LS, LF)

    Two Floats (TF, FF)

    Other data checked for, while scheduling are:

    Circular Loops

    Constraints ActivitiesOpen Ends Activities

    Out-of-Sequence Activities

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    82/226

    Circular Loop

    The Circular Loop is the relationships that starts at an activity and return back tothe same activity. If P3 detect any loop, it will stop the Schedule calculation and

    produce a report stating the relationships which led to the loop

    Here is an example of the Circular Loop Report:

    A B C

    Constraints Activities

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    83/226

    Constraints Activities

    P3 will identify any activity with constraints imposed on it, and report it in theSchedule report. The four types of activities SM, FM, SF, FF, are all consideredConstraints, hence they will be reported in the Schedule report.

    Open Ends Activities

    P3 will assume that each activity will have at least one predecessor, and onesuccessor. Any activity with no predecessor, or with no successor, is considered anopen end. Planners as they are creating their network will consider therecommendation that network should start with one activity, and finish with one

    activity (although, neither networking methods, nor P3 will object if the networkstarted with 100 activities, and finished with 100 activities). If the Planners abide tothe above rule, they will have a prior knowledge that two activities will be mentionedin the report as Open Ends. So, if more than these were mentioned, planners willknow that they overlooked a relationship.

    Out-of-Sequence Activities

    If an activity started the actual work before the finish of its predecessor, this activityis considered to be out-of-sequence. This is evident when the actual work starts andnot while Planning phase.

    Schedule Command

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    84/226

    Schedule Command

    From menus select Tools>Schedule

    Or from toolbar, click Schedule button, the following dialogue box will

    appear:

    Specify Data Date, as mentioned in Module 1, Data Date definition is Time Now:

    In the Planning phase the Data Date is always the first day of the project asdefined when the project was created

    Once you start inputting actual data, Data Date will be the day of which you

    performed the schedule invIf you want to include in you report:

    Constraint listing, click this checkbox on

    Open Ends listing, click this checkbox on

    Out-of-Sequence activities listing, click this checkbox on

    Click Schedule Now button the following dialogue box will appear:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    85/226

    Click Schedule Now button, the following dialogue box will appear:

    Make sure that View on screen is selected, then click OKP3 will start performing the calculationP3 will then produce the Schedule report. The Schedule Report is avery valuable tool for planners, as it will help in the following points:

    It contains valuable information about the project and thenetwork It will work as a tool in the hand of the planner to document howthe project evolved through the Planning phase

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    86/226

    The following is an example of a Schedule report:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    87/226

    Note: If you press F9 the following dialogue box will appear:

    This is identical to the command above except it will not producethe report

    The View after Schedule

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    88/226

    The View after Schedule

    It is recommended, that immediately you close your project and reopenit again, so the sorting will take place. You will see two groups of

    activities:Red Activities, which means Critical activitiesGreen Activities, which means Non-Critical activities

    Activities will be sorted according to their ES, and then TF, therefore the list ofactivities will be different

    Schedule Report

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    89/226

    p

    P3 is equipped with lots of pre-defined tabular reports, One of these is theSchedule Report

    From menus select Tools>Tabular Reports>Schedule, the following

    dialogue box will appear:

    Click the Add button, the following dialogue box will appear:

    Each Schedule report will have an ID, starting with the letters SR, then a sequentialnumber (which is given by P3), click Add, to accept the number. The dialogue box inthe next page will be displayed

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    90/226

    Type in the Title of the report (highly recommended), so you can utilize itIn Content tab, and under Include the following data, the following applies:

    Leave Activity Code line there. This line shows the basic activity dataYou can add to this basic data other information like Predecessor, Successor,and lots of other types

    In Content tab, and under Show these codes on activity code line, you canspecify up to five different codes for each activity

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    91/226

    Click the Format tab, you will see the following:

    Set the Sort by criteriaSelect the information to be displayed

    O d li k R b tt di l th t ill b

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    92/226

    Once you are done, click Run button, accordingly the report will beproduced, hence you can print it, or save it

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    93/226

    Module 6

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    94/226

    Module 6:

    Inputting Activity Calendar

    This module contains:What is global calendar

    What is individual calendarAssigning calendars to activitiesImposing a Finish date on the projectDefining Holidays

    Printing calendarsTransferring calendars

    Introduction

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    95/226

    Introduction

    When we created the project, P3 asked two questions:

    Workdays/WeekWeeks starts on

    Let us assume that you answered the first question with 5, and thesecond question with Monday. Accordingly P3 will create anindividual calendar, and its ID is 1, which contains that the working

    days of the week are Monday, Tuesday, Wednesday, Thursday, andFriday, and the two weekends are Saturday and Sunday

    Activity calendar means calendar attached to an activity, affecting theSchedule calculation of this activity. Schedule will not calculate an ES

    (for instance) in a day that considered as holiday or weekend in thecalendar of an activity. So sometimes one of the techniques todecrease the total duration of projects is to assign the criticalactivities to calendars with more working days per week

    Global Calendar

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    96/226

    Global Calendar

    P3 has a uniquecalendar called Global calendar. This calendar containsinformation which will affect the whole project and the other individual calendarsGlobal Calendar cant be assigned to activities

    From menus select Data>Calendars, the following dialogue box will appear:

    From the upper list, click on Global Calendar

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    97/226

    o t e uppe st, c c o G oba Ca e daClick the Standard button, the following dialogue box will appear:

    You can change the following data:

    In which day the week will start

    When the calendar will start (P3 will always assume that calendar will start ayear before the starting date of the project)

    When the project will start

    When is the Data DateImposed Finish Date (will be discussed later in this Module)

    If a holiday occurs in a weekend, how should P3 treats it. It is either byturning this rule off, and hence you do it manually. Or turning this rule on, andlet P3 handles it, by making the nearest workday as a holiday

    Click the Holidays button, the following dialogue box will appear:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    98/226

    y g g pp

    The holidays that will be defined here will affect all individual calendars, for thatreason, we call it Global Holidays.In the table titled Nonworkperiods, specify the holidays. The following rules apply:

    If you have one day holiday, define it in the Start field

    If you have multiple uninterrupted holiday, define the Start field and the FinishfieldIf this holiday occurs at the same period every year, make this holidayRepeatingIf you have an interrupted holiday, simply specify the whole holiday in theNonworkperiods table, then specify the working days within the holiday in theExceptions table

    Individual Calendar

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    99/226

    P3 has up to 31 individual calendars. These calendars will be assigned to activitiesIndividual calendar contains information which will affect only the activities attachedto it

    Select an individual calendar, then click Standard button, the followingdialogue box will appear:

    In this dialogue box you can do two things:

    Type in a title for the calendar (highly recommended)

    Set the working days per weekAll the things discussed in Holidays of the Global calendar applies on theindividual calendars. Contrary to Global Calendar holidays, the defined holidays inindividual calendar will affect the activities attached to it only and not all activities

    How to create New Individual Calendar

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    100/226

    How to create New Individual Calendar

    From menus select Data>Calendars, the following dialogue box will appear:

    Click Add button, the following dialogue box will appear:

    P3 will give it a new ID,which you can change it

    Type in the desired title, andclick OK

    You can see that a new calendar is shown in the list

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    101/226

    Make sure it is selected, and click Standards, you will see the following dialoguebox:

    As you can see from above, when you create a new individual calendar, all of thedays will be considered workdays.Click off the desired weekends, and click OK

    How to delete an existing calendar

    From menus select Data>CalendarsSelect the desired calendarClick Delete button, the following warning message will appear:

    If you are sure of what you are doing clickYes, if not click No to stop the process ofdeletion

    Assigning Individual Calendar to an Activity

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    102/226

    g g y

    Either double-click on the desired activity,or select the activity and press F7, the Activity Form will appear:

    Imposing a Finish Date on theProject

    In Global calendar at the Standard

    dialogue box, we saw that we canimpose a finish date on the project.Most likely this will be the contractual

    finish date of the project

    We need to input it in our project, so wecan compare the calculated finish to theimposed finish. It will replace the LF ofthe last activity:

    Activity A6TF=2

    EF=4OD=4ES=1

    LS=3

    Activity BLF=6TF=-2

    EF=8OD=8ES=1

    LS=-1

    Activity CLF=22TF=-2

    EF=24OD=16ES=9

    LS=7

    The difference between the Imposed finish date and Calculated

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    103/226

    The difference between the Imposedfinish date and Calculatedfinish date may be:

    Zero, if they are equal (rare cases)Negative, if the Calculated > Imposed (most likely)Positive, if the Calculated < Imposed (rare cases)

    As you can see in the previous example, the TF of the critical pathequals to -2, and that is because Calculated > Imposed

    The negative TF tells us how many days we need to compress ourcritical path to meet the contractual finish date of the project

    By default negative TF, LS, or LF is not acceptable

  • 8/6/2019 Primavera Tutorial - P3

    104/226

    Using Nonwork button

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    105/226

    Select multiple days (consecutive by clicking and dragging, ornonconsecutive by using Ctrl key and clicking)

    Click Nonwork button, the selected days will become holidays

    Also, if you double-click the headingof a day, just like below:

    Then you click Nonwork button, this day in the current month will become a holiday

    At any moment select a holiday, and click Work button, you will turn it intoworkday

    Printing Calendars

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    106/226

    Unfortunately, you cant previewcalendars before printing them. This command will print allyour calendars. There are two modes:

    Summary printout

    Detailed printout

    Summary printoutThis will produce a table that contains:

    At the horizontal; list of the calendarsAt the vertical; list of days starting from the start of the projectAt the core of the table the holidays

    Detailed printout

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    107/226

    It will print a wall-likecalendar, indicating the holidays in each month, starting fromthe start date of the project

    Example of Detailed printout:

    From the Calendars dialogue box, click Print , the following dialoguebox will appear:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    108/226

    box will appear:

    Select the desired Style, whether Summary, or DetailsSelect the time Span, and click OK

    Transferring Activity CalendarsYou can transfer Activity Calendars between projects

    Go to the new project you want to transfer toFrom menus select Data/Calendars

    Click the Transfer button, the following dialogue box will appear:

    Transfer Individual calendar

    If t t i di id l l d t th l d ithi th j t

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    109/226

    If you want to copy an individual calendar to another calendar within the same project:

    Specify the source calendar and the target calendar, then click Transfer

    Transfer All calendars

    Click All calendars choice, the dialogue box will change to:

    Specify the Driver and Folder which the desired project you want to copy fromresides in, then specify the project. Now click Transfer

    The calendars will be copied to your project

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    110/226

    Module 7

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    111/226

    Module 7:Resources and Cost Assignment

    This module contains:How to create Resource dictionary?How to create Cost Account dictionary?

    Assigning resources and cost to activityViewing resources and cost profilesProducing tabular resources and cost reports

    Introduction

    Resources and cost assignment goes into two main steps:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    112/226

    Resources and cost assignment goes into two main steps:

    Creating the Resource Dictionary, and Cost Account Dictionary (or transferringthem from other projects)

    Assignment of resources

    Most likely you have to create the Resource Dictionary and Cost Account Dictionaryonce, and then you can transfer them from project to another

    For resources, the first step is to create a list of the resources available to completeany project taking into consideration the following:

    Resource name

    Resource unit of measureResource description

    Resource availability (Normal and Maximum)

    Resource unit cost

    For cost accounts, create a hierarchy showing the relationship between the differentcost accounts, taking into consideration the following:

    Cost account numberCost account description

    Cost Category

    How to Create Resource Dictionary?

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    113/226

    As a first step prepare your work on a paper, listing all the resources availableshowing the following information:

    The Resource name (code for the resource up to 8 characters, spaces areallowed)

    Unit of measure (P3 doesnt have any predefined unit of measure), forinstance you can type m, sq.m, cu.m, ton, mh (manhour), md (man-day), etc,up to four characters

    Resource description (up to 40 characters)

    Resource limits, which states the number of units of this resource availablefor the current project in Normal times, and the maximum number of units,which can be provided. If this resource limits change with time, record the dateof change

    Resource Price/Unit, which states the cost of the unit. If this price/unit

    change with time, record the date of change (P3 will not check for consistency,for instance you typed the unit of a certain resource is md, then you input thecost of mh)

    Once you are done with this list, now, go to the menus selecting Data>Resources,th f ll i di l b ill

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    114/226

    the following dialogue box will appear:

    It is preferable to do the inputting as follows:Input the resource name, the unit, and the description for all of the resourcesThen select the first resource, and specify the limits and price for it, now select thesecond one and so on

    To print the Resource Dictionary, click Print button, the following dialogue boxwill appear:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    115/226

    will appear:

    Click OK, and produce the report on the screen, you will get something like the

    following:

    To bring a Resource Dictionary from another project, click the Transfer button,the following dialogue box will appear:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    116/226

    the following dialogue box will appear:

    The message means, if the resources to come have an identical match in the host,they will update them, whereas, the resources with no matching they will beappended

    Click OK, the following dialogue box will appear

    Specify the Driver and Folder which thedesired project you want to copy fromresides in, then, at the top portion of thedialogue box specify the project. Now clickTransfer

    The dictionary will be copied to yourproject

    How to Create Cost Account Dictionary?

    Fi t d th C t A t t hi h h h th t ill b

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    117/226

    First draw the Cost Account tree, which shows how the cost will bebroken down, just like below tree:

    ExpansionProject

    EP

    ConstructionCostEP01

    FinishingCostEP02

    ConcreteEP0101

    Mech/ ElecEP0102

    SteelEP0103

    InternalEP0201

    ExternalEP0202

    Give for each level of your tree a code. Each code should not exceed 11 characters.

    Also, develop a one-character(alpha numeric) category code, which will categorize thecost, example may be:

    1 Labor2 Machine3 Material

    You can have up to 36 categories (0-9, and A-Z). The cost category is considered the 12thcharacter of the cost account, hence cost account can be 11 characters, and can be 12characters

    From menus select Data>Cost Accounts, the following dialoguebox will appear:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    118/226

    Input the Cost Categories, and the Category Title (up to 8 characters)Input the Account numbers, and the Account Title (up to 40 characters)To print the Cost Account Dictionary, click Print button, the following

    dialogue box will appear:

    Click OK, and accept to view on screen

    The following is an example of what you may get:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    119/226

    To bring Cost Account Dictionary from another project, click the Transferbutton, the following dialogue box will appear:

    Click OK, the dialogue box on the next page will appear

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    120/226

    Specify the Driver and Folder which the desired project you want to copy from

    resides in, then at the top portion of the dialogue box specify the project. Now clickTransfer

    The dictionary will be copied to your project

    Assigning Resources and Cost to Activities

    There are two methods to assign cost to activities:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    121/226

    gAssignment of defined resource to an activity with number of units per day, P3accordingly will multiply the number of days with the number of units with unit price, whichwill generate a cost assigned to this activity

    Assignment of cost right away without any resources in the middle

    When you assign a resource, P3 will need the following information:Resource nameResource UPT = Units Per Timeperiod (in our case Units Per Day)Cost Account numberCost Category

    CalculationThe first value will be calculated is BQ = Budgeted Quantity which will be based on the followingformula:

    BQ = OD * UPT (OD here is Original Duration)Other values can be calculated based on the following:

    The fist formula is QTC = RD * UPTThe second formula is QAC = QTC + ATD

    Where;QTC = Quantity of certain resource To Complete certain activityRD = Remaining DurationQAC = Quantity of certain resource At the Completion of certain activityATD = Actual quantity of certain resource from the beginning of certain activity To

    Date

    As for Cost the following formulas apply:

    BC = BQ * Unit Price

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    122/226

    BC BQ Unit PriceCTC = QTC * Unit PriceCAC = QAC * Unit Price

    Where;

    BC = Budgeted CostCTC = Cost To CompleteCAC = Cost At Completion

    ExampleAssume we have an activity with OD = 6 days, and you assign 2 units per day from a certainresource, which has Unit Price of 10, what are the resource and cost values P3 willcalculate:

    BQ = 6 * 2 = 12 unitsBC = 12 * 10 = 120QTC = 6 * 2 = 12 unitsCTC = 12 * 10 = 120QAC = 12 + 0 = 12 unitsCAC = 12 * 10 = 120

    As you can see BQ = QTC = QAC, this is true only in the Planning phase. Also, BC =

    CTC = CAC which is true only in the Planning phase.

    Another Way of calculationAnother way would be to input BQ right away without inputting UPT, hence P3 will calculatethe values as follows:

    UPT = BQ/OD

    The rest will be the same

  • 8/6/2019 Primavera Tutorial - P3

    123/226

    If you typed in a resource name that does not exist in the Resource Dictionary P3

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    124/226

    If you typed in a resource name that does not exist in the Resource Dictionary, P3will give you the ability to add it to the dictionary. It will show the following

    Type in the Title, and click OK

  • 8/6/2019 Primavera Tutorial - P3

    125/226

    As you can see from the upper dialogue box, there are two types of costs:

    Cost generated from resource assignment (the first two)

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    126/226

    g g ( )

    Cost NOT generated from resource assignment (the third)

    For the second type do the following:

    DONT input the Resource nameInput Cost Account and Cost Category

    Input BC

    Unit Price change after Resource Assignment

    What if you changed the resource unit price after resource Assignment:

    Go to Resource Dictionary command, and change any resource unit price

    Once you click Close, P3 will produce the following message:

    Click Yes, to recalculate the resource and cost values based on the new prices.

    Some Results

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    127/226

    You can see direct results of what you are doing, if you go to the activity table,and check the Last two columns at the right, which they are Resource column,

    and Budgeted Cost column

    Resource and Cost Profiles (Histograms)After you assign resources, and costs you have to take a look at the Resource/Cost

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    128/226

    ProfilesFrom menus select View>Resource ProfileOr, from toolbar click Resource/Cost Profile button, the following view willappear:

    As you can see there are two scales:

    At the left, the scale is for the histogram

    At the right, the scale is for the cumulative curveThe yellow horizontal line stands for Normal limit, whereas the red line representsthe Maximum limit (from the above view you can see the changing limit through thetime)

    The histogram contains 3 colors:

    Green, which is within the Normal limit

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    129/226

    Yellow, which is between Normal and Maximum limit

    Red, which is above Maximum (overloaded)

    When the histogram appears, a small dialogue box appears also:

    By default P3 will sort the resources according to alphabetic order, hence thepop-up list will show them in this manner, click pop-up list to select the resourceyou want to display the histogram for:

    Or you can use the Previous and Next button to browse theresources one-by-one

    Display button

    Histogram contains lots of variables, so we need to control the view by knowing the

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    130/226

    Histogram contains lots of variables, so we need to control the view by knowing thethings we can changeClick Display button on the small dialogue box, the following dialogue box

    will appear:

    Under Display control:

    To show for Units (Qauntaties), orCosts

    To show according to Early dates

    or Late datesTo show for All activities, or theSelected activities only

    To show or hide Histogram

    To show or hide cumulativeCurves

    To show the view for Time

    Interval (Days, Weeks, Months,Quarters, and Years) if you selectDays then the histogram will showthe daily usage, else it will sum upthe usage for the time intervalselected

    Under Histogram control:Calculate options, whether Total, Peak, or Average

    C l l t d d th Ti I t l l t d i th i it ill k

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    131/226

    Calculate depends on the Time Interval selected in the previous page, it will workonly if the Time Interval is not DaysIf you selected to show the Time Interval of Weeks, then select to Calculate the

    Total usage of the week, or the Peak quantity of the week, or the Average usage ofthe weekTo show Bars or Area

    To show values for Current Estimate, Earned Value, or Planned Values (we willdiscuss this later in the Updating Module)To Draw Normal and Maximum limits as horizontal lines (yellow and red). This is

    important if you want to compare available to needed resourcesTo Emphasize overload with colors (to show green, yellow, and red areas)

    Curves will be discussed in the Module 11

    Clicking Bar in HistogramIf you select a Bar format for your display, clicking the bar will display its valueYou may get something like:

    Specially for Cost

    By default when you show the cost histogram of a resource, it will only show the cost

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    132/226

    y y g , yof that resource. In order to show the cost of all resources in a certain period, youneed to select from the list the option Total

    In the small dialogue box, and after the last resource in alphabetic order you will findthe option Total

    Total is the only way to see the direct cost you input on an activity on the histogram

    To see the total cost of whole project, see where the cumulative curve gets flat,right-click on the curve, you will see something like the following dialogue box:

    Resource and Cost Tabular Reports

    P3 has more than one pre-defined report for resources and costs. If you are

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    133/226

    working using a method that states resources are the primary cost generator,then the resources and costs reports will be look-alike

    Resource Loading ReportThis report will show how the resources were distributed over the time

    From menus select Tools>Tabular Reports>Resource>Loading, the followingdialogue box will appear:

    Click Add button, the following dialogue box will appear:

    Accept the default sequentialnumber, and click Add again

    The following dialogue box will appear:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    134/226

    Type a good title for your report

    Make sure that you are inResource Selection tab:

    Under Profile if, right-click,

    and select EQUnder Low Value Resourceright-click and select the desiredresource to generate report for

    Click Format tab:

    Select to Organize the report according to which criteriaSelect to Truncate activity description or notSelect to Repeat activity title on all horizontal sheets or not

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    135/226

    Select to Repeat activity title on all horizontal sheets or notSelect to Display row totals at the Left or at the Right of the pageClick the Timescale tab:

    Select the Date range you want to include in the report, by specifying the Startdate and the End dateSelect the Display Unit (Day, Week, Month, Quarter, Year, and 4 weeks period),accordingly select the Usage (Total, Peak or Average)Click Run, and select to see the report on the screen,

    The following is an example of Resource Loading report:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    136/226

    The Cost Loading report is identical to the above except it will display the cost of theresource and not the quantityFrom menus select Tools/Tabular Reports/Cost/Loading, andfollow the same procedure you did in the Resource Loading report

    The Cost Loading report is identical to the above except it will display the cost of theresource and not the quantityFrom menus select Tools>Tabular Reports>Cost>Loading and follow the same

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    137/226

    From menus select Tools>Tabular Reports>Cost>Loading, and follow the sameprocedure you did in the Resource Loading report

    The following is an example of Cost Loading report:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    138/226

    Module 8

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    139/226

    Module 8:Layouts and Formatting Options

    This module contains:What is layout in P3?Formatting columnsFormatting selected barsGlobal Bar formatting

    What is Layout in P3?Old (DOS) version depended on tabular and graphical reports to produce the output ofthe scheduling and resource/cost loading. These reports (in general) are poor quality

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    140/226

    the scheduling and resource/cost loading. These reports (in general) are poor qualityreports, and dont utilize the current technology of printing (laser, color laser, or inkjetprinters). From the starting of the Windows based versions, P3 adopted the concept of

    Layouts, which if utilized fully, can replace almost all of the tabular and graphicalreports

    Layout is What you see on your screen like:

    The list of activity shown on the screen

    Activity columns

    Bar Area

    Colors usedTimescale

    Date FormatTo save a new layout, do the following steps:

    Change all the desired changes on the layout

    From menus select View>Layout>Save As, the following dialogue box will

    appear:P3 will give you a sequential number as layout ID, whichstarts with LT-number, then type in a good title describing yourlayout, click Save

    To make changes on the current layout, and save it under the same ID, and name:From menus select View>Layout>SaveOr from toolbar, click Save Layout button

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    141/226

    , yTo open an existing layout:From menus select View>Layout>Open

    Or from toolbar, click Open Layout button, the following dialogue box willappear:

    Select the desired layout and click Open

    The name of the current layout will appear at the mid position of the status bar

    Formatting Columns

    T h hid l t th ti it t bl

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    142/226

    To show or hide columns at the activity tableFrom menus select Format>Columns, or press F11

    Or from toolbar, click Format Columns button, the following dialogue box willappear:

    Under Column information, you will find a table listing the current columns

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    143/226

    The listing of the columns from topto bottomin the table, is the same as thearrangement of columns in the layout from leftto right

    Use the plus sign to show a new column on the list. Right-click to show a pop-up list to select the type of information you would like to display in the new column

    If you want to show a new column at the top of the list, pick the first column of thecurrent list then click plus sign

    If you want to show a new column at the mid, pick an existing column, click plussign, the new column will push the existing down and will be at its place (the newcolumn will be at the left of the existing in the layout)

    If you want to show a new column at the end of the list, indicate the last column atthe list, then click beneath it

    To hide an existing column, simply select it, and click the minus sign

    While you are in the Columns dialogue box you can change:Title of the column (use | to wrap the text to two lines)The width of the column

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    144/226

    The width of the columnThe alignment of the text in the column (left, center, or right)The font which will be used to display the contents of the column

    The font for the titlesTo show or not the lines between rows and columns

    ExampleThis is the default column arrangement:

    And this is the new arrangement:

    http://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    145/226

    Formatting Selected Bars

    You can select one or more activities and format their barsThen you can copy the format and paste it on another activity bar

    http://www.abbyy.com/buyhttp://www.abbyy.com/buyhttp://www.abbyy.com/buy
  • 8/6/2019 Primavera Tutorial - P3

    146/226

    Then you can copy the format and paste it on another activity barAlso, you can get the bars back to their default format

    Modify Bar Format

    Select the desired activity

    From menus select Format>Selected Bars>Modify Bar Format, the followingdialogue box will appear:

    You can do the following changes (you can

    see the changes you are making on theSample):

    To Show or hide the bar

    To change the Bar style (Bar, Dashed line,Do


Recommended