Construction Management by Rahul Agrawal, Sanket Singi, Kishor Sondge, Ashutosh Pawar, Nikhil Kulkarni.... Dr Regulwar Sir GECA
Popular Tags:
7
5/1/2013 1 1 May 2013 1 Guided by Dr. D. G. Regulwar Presentated by Nikhil kulkarni BE09 F01 F001 Rahul Agrawal BE09 F01 F017 Sanket Singi BE09 F01 F059 Ashutosh Pawar BE09 F01 F060 Kishor Sondge BE09 F01 F063 Planning, Scheduling, Monitoring and Tracking of Construction Project GOVT. COLLEGE OF ENGINEERING, AURANGABAD Introduction 1 May 2013 2 To study and use primavera P3 for planning, scheduling, monitoring and tracking of construction project. Planning and scheduling aims at timely execution of work. Monitoring and tracking is important to find the deviation from the planned schedule. Construction Project Management 1 May 2013 3 Construction project is a high value time bound with predetermined performance objectives. Human and non human resources (completion). Function of Project Management 1 May 2013 4 Planning : course of action to guide Project completion Organizing : arrangement of resources Staffing : selection of expertise Directing : guiding of work Controlling : creation of system to measure report and forecast deviation. Time Planning Process 1 May 2013 5 Project Work Breakdown : breaking down into sub project Modeling & Analyzing Network : developing a logic diagram Scheduling Work Programs : putting time plan on calendar basis Resources Planning Process 1 May 2013 6 Manpower Material Equipment Standard Cost Budget
Transcript
Page 1: Primavera p3 [compatibility mode]

5/1/2013

1

1 May 2013 1

Guided by Dr. D. G. Regulwar

Presentated by

Nikhil kulkarni BE09 F01 F001

Rahul Agrawal BE09 F01 F017

Sanket Singi BE09 F01 F059

Ashutosh Pawar BE09 F01 F060

Kishor Sondge BE09 F01 F063

Planning, Scheduling, Monitoring and Tracking of

Construction Project

GOVT. COLLEGE OF ENGINEERING, AURANGABAD

Introduction

1 May 2013 2

• To study and use primavera P3 for planning,

scheduling, monitoring and tracking of

construction project.

• Planning and scheduling aims at timely

execution of work.

• Monitoring and tracking is important to find

the deviation from the planned schedule.

Construction Project Management

1 May 2013 3

• Construction project is a high value time

bound with predetermined performance

objectives.

• Human and non human resources

(completion).

Function of Project Management

1 May 2013 4

• Planning : course of action to guide Project

completion

• Organizing : arrangement of resources

• Staffing : selection of expertise

• Directing : guiding of work

• Controlling : creation of system to measure

report and forecast deviation.

Time Planning Process

1 May 2013 5

• Project Work Breakdown : breaking down into

sub project

• Modeling & Analyzing Network : developing a

logic diagram

• Scheduling Work Programs : putting time plan

on calendar basis

Resources Planning Process

1 May 2013 6

• Manpower

• Material

• Equipment

• Standard Cost

• Budget

Page 2: Primavera p3 [compatibility mode]

5/1/2013

2

Objective of Project

1 May 2013 7

• To prepare CPM (critical path method), Chart

for a building being built.

• To acquire good Knowledge of primavera P3

software which is globally used.

Desired results of Planning and

scheduling

1 May 2013 8

• To have un-interrupted flow of work

• To reduce amount of re-work

• To minimize confusion and misunderstanding

• To get the understanding of amount of work done

by each labour

• To integrate all work and ensure a quality project.

Factors affecting work Scheduling

1 May 2013 9

• Time

• Manpower

• Materials

• Machinery

• Capital

Techniques for planning and

scheduling

1 May 2013 10

• Bar Chart

• Network Technique

– Critical Path Method

– Program Evaluation and Review Technique

Introduction to Primavera Project

Planner

1 May 2013 11

• It is product of Primavera systems Inc., USA.

• It is a multi-user product that operate on LAN Local Area

Network.

• Can manage up to one lakh activities.

• It help to build project network quickly and graphically.

• We can impose up to ten restrictions.

Primavera File Structure

1 May 2013 12

• The project has mandatory four characters for

project name.

• All files will have P3 extension.

• All files are preferred with four characters file name.

• It works with one file type only. i.e. P3

Page 3: Primavera p3 [compatibility mode]

5/1/2013

3

Project Overview

1 May 2013 13

• A Building of configuration G+1 of an approximate area of 1100 Sq ft is

considered in this project.

• The building is being built for residential purposes in Shahnoorwadi.

• The actual work is started in December 2012.

• The software tool Primavera Project Planner is used for planning,

scheduling and controlling.

• The activities required to complete the building structure (excluding the

interiors) was identified and was fed as an input to Primavera along with

their durations.

• The critical activities and the project time which is represented by the

summation of critical path durations are obtained from the primavera

schedule.

1 May 2013 14

STEPS FOR PLANNING & SCHEDULING

i. Creating A Project

• Open a new project name & is given as ABCD.

• The client name & location is selected.

• The planning unit is selected in days.

• The project start date is entered.

ii. Defining Calendars

• Before the activity list is entered , the calendar are defined.

• Calendars are used to model the working time for each activity.

Planning and Scheduling in Primavera

Add New Project

1 May 2013 15

Assigning the Start and Finish

1 May 2013 16

Blank Page

1 May 2013 17 1 May 2013 18

Identification Of Project Activities• The activities required to complete the project is identified and

the activity list is entered

Sequencing the Activities• Finish to start relationship : Start of successor activity depends on

the completion of predecessor.

• Start to Start relationship : start of successor activity depends on

start of predecessor activity.

• Finish to Finish relationship : finish of successor activity depends

on finish of its predecessor activity.

• Start to Finish relationship : successor activity can’t complete until

its predecessor activity start.

Activity’s Description

Page 4: Primavera p3 [compatibility mode]

5/1/2013

4

Activity’s Description

1 May 2013 19

List of Activities

1 May 2013 20

Activity Form

1 May 2013 21 1 May 2013 22

Cost and Resources

1 May 2013 23

Editing Bar

1 May 2013 24

Page 5: Primavera p3 [compatibility mode]

5/1/2013

5

End Point of the Bar

1 May 2013 25

Time Scale

1 May 2013 26

Editing Bar

1 May 2013 27 1 May 2013 28

GENERATION OF REPORT SCHEDULE

•Schedule reports contain a tabular list schedule

data, including activity ID’s description, durations,

float early & late schedule dates.

•Additional data relating to this report shows the

activity ID, successors, predecessors & total float for

that particular activity.

Tabular Reports

1 May 2013 29

Tabular Reports

1 May 2013 30

Page 6: Primavera p3 [compatibility mode]

5/1/2013

6

Tabular Reports

1 May 2013 31

Time Scale Logic..

1 May 2013 32

Time Scale Logic..

1 May 2013 33

Time Scale Logic..

1 May 2013 34

PERT….

1 May 2013 35 1 May 2013 36

• CPM of the building G+1 is obtained using the planning and scheduling

software using primavera project planner P3.

• The activity required to complete the structure are identified and put

in to primavera project planner.

• The scheduled network was then analyzed & schedule report was

generated using Primavera.

• Obtaining optimum network diagram & minimizing the time and cost

is the major objective.

• It has helped us to understand fundamental principles & techniques of

construction project management.

• An important part of project was acquisition of knowledge about

Primavera Project Planner.

Conclusion

Page 7: Primavera p3 [compatibility mode]

5/1/2013

7

1 May 2013 37

1. Primavera Reference Guide (2004), CADD Centre Training Services Pvt.

Ltd.

2. Garold D. Oberlender (2000), Project Management for Engineering and

Construction, McGraw Hil

3. Chitkara K. K. (2001), “Construction Project Management” Tata

McGraw Hill Publishing, New Delhi

4. Sandeep Mantri, “ A to Z Practical Building Construction and its

Management”, 8th edition, Satya Prakashan, New Delhi.

References

1 May 2013 38