+ All Categories
Home > Documents > Prioritizing Boiler and Piping Inspections - structint.com · Prioritizing Boiler and Piping...

Prioritizing Boiler and Piping Inspections - structint.com · Prioritizing Boiler and Piping...

Date post: 29-Apr-2018
Category:
Upload: dinhtuyen
View: 222 times
Download: 5 times
Share this document with a friend
4
District Energy / First Quarter 2011 29 Prioritizing Boiler and Piping Inspections: Risk-based approach enhances system reliability Joe Maciejczyk, PE, Associate, Structural Integrity Associates F or the first time in 60 years of U.S. Energy Information Administration recordkeeping, electrical consump- tion in the United States decreased for two consecutive years, in 2008 and 2009. The recession certainly played a part in this, as did Americans’ increased aware- ness of their energy use and the need for conservation. Suppliers of all types of energy have had to accommodate this reduced demand. As district heating customers have used less energy, boiler operators have seen curtailed operation, more hot stand- by and cyclic operations. This type of operation poses unique challenges to cap- ital equipment and infrastructure piping – creating the potential for problems that, if left unaddressed, could lead to unplanned outages, unbudgeted expenditures and disruptions of service to customers. Typical inspections of boilers and piping are not designed to identify these types of problems. They generally focus on baseloaded operation, such as the yearly inspection of the boiler and relief valves by an authorized inspector. Distribution piping inspections are most often handled on an exception basis: When leaks and failures create a forced outage, they are repaired, and the system is put back into operation. Cyclic opera- tion exacerbates these issues. Failures and forced outages can be avoided, however, with a program of pro- active boiler and piping inspections and repairs that are prioritized on the basis of system risk factors. Conducted during a normal scheduled outage, this type of targeted inspection program is crucial to keeping district heating systems opera- tional and safe until the next scheduled inspection. Boiler Inspections Boilers are typically not designed to handle cyclic operations. Startups and shutdowns, even though they are within operating parameters for pressure and temperature, generate metal temperature gradients and set the stage for cracking and through-wall defects – resulting Courtesy Structural Integrity Associates. Failures and unplanned outages of critical infrastructure piping and boilers can be avoided with a proactive, risk-based inspection program. © 2011 International District Energy Association. ALL RIGHTS RESERVED. For more information or a quote, call Structural Integrity Associates, Inc. at 877-4SI-POWER
Transcript

District Energy / First Quarter 2011 29

Prioritizing Boiler and Piping Inspections:Risk-based approach enhances system reliabilityJoe Maciejczyk, PE, Associate, Structural Integrity Associates

For the first time in 60 years of U.S.

Energy Information Administration

recordkeeping, electrical consump-

tion in the United States decreased for

two consecutive years, in 2008 and 2009.

The recession certainly played a part in

this, as did Americans’ increased aware-

ness of their energy use and the need

for conservation. Suppliers of all types

of energy have had to accommodate this

reduced demand.

As district heating customers have

used less energy, boiler operators have

seen curtailed operation, more hot stand-

by and cyclic operations. This type of

operation poses unique challenges to cap-

ital equipment and infrastructure piping –

creating the potential for problems that, if

left unaddressed, could lead to unplanned

outages, unbudgeted expenditures and

disruptions of service to customers.

Typical inspections of boilers

and piping are not designed to identify

these types of problems. They generally

focus on baseloaded operation, such as

the yearly inspection of the boiler and

relief valves by an authorized inspector.

Distribution piping inspections are most

often handled on an exception basis:

When leaks and failures create a forced

outage, they are repaired, and the system

is put back into operation. Cyclic opera-

tion exacerbates these issues.

Failures and forced outages can be

avoided, however, with a program of pro-

active boiler and piping inspections and

repairs that are prioritized on the basis

of system risk factors. Conducted during

a normal scheduled outage, this type of

targeted inspection program is crucial to

keeping district heating systems opera-

tional and safe until the next scheduled

inspection.

Boiler Inspections Boilers are typically not designed to

handle cyclic operations. Startups and

shutdowns, even though they are within

operating parameters for pressure and

temperature, generate metal temperature

gradients and set the stage for cracking

and through-wall defects – resulting

Feature Story

Co

urt

esy

Stru

ctu

ral I

nte

gri

ty A

sso

ciat

es.

Failures and unplanned outages of critical infrastructure piping and boilers can be avoided with a proactive, risk-based inspection program.

© 2011 International District Energy Association. ALL RIGHTS RESERVED.

F o r m o r e i n f o r m a t i o n o r a q u o t e , c a l l S t r u c t u r a l I n t e g r i t y A s s o c i a t e s , I n c . a t 8 7 7 - 4 S I - P O W E R

30 District Energy / First Quarter 2011

most likely from either thermal fatigue,

an external phenomenon, or corrosion

fatigue, an internal actor. Undetected

cracking that is allowed to grow unchecked

can result in forced shutdowns and safety

concerns for operating personnel. Plan-

ning a program of risk-based inspec-

tions to prevent such issues is fairly

straightforward for boilers, given that

boilers tend to be quite standard in

design (as compared with the unique

nature of most piping installations). The

areas presenting the greatest potential

for problems typically include welds,

boiler tubing and exhaust ducting, and

internal boiler water wall tubing.

Thermal fatigue cracking is most

likely to occur at or near welds. Inspecting

every weld in a boiler may be possible, but

it is impractical in terms of time and cost.

Thermal transients in boilers will flex

components that are the farthest away

from rigid anchors. This flexing causes

fatigue cracks to form and grow. Suspect

areas include welded rigid anchors and

boiler-tube-to-header connections.

Corrosion fatigue cracking, an inter-

nally generated attack of cold-side water

wall tubing, most often shows up as a

pinhole leak at the base of a weld.

Nondestructive examination of

the main anchors is the basis

of a sound boiler inspection

program.

Review of the boiler construction

drawings can locate the main anchors

and supports in the system for inspec-

tion planning. In lieu of drawings, a visu-

al inspection of the boiler internals can

also locate these anchors. Nondestructive

examination (NDE) of these anchors to

verify their integrity and look at the high-

flex connections associated with them

forms the basis of a sound inspection

program. NDE, also called “nondestruc-

tive testing,” refers to the analysis of

system components or materials without

causing damage, using any of a number

of methods such as magnetic particle

testing, radiography, dye checks or vari-

ous forms of ultrasonic testing (linear

phased array, time of flight diffraction,

A and B scans, etc.).

The type of NDE typically done

for welds in boilers to detect external

cracking is magnetic particle testing.

Components to be examined are placed

under a magnetic field by a handheld

electromagnetic yoke, and magnetic

field-sensitive particles are sprayed or

dusted on the area to be inspected. The

particles align with any defect on the

metal’s surface. Internal tubing issues

are found through such NDE techniques

as fiber optic visual inspection, radiog-

raphy or linear phased array ultrasonic

scanning. Depending on the particular

defect, it may either be removed by weld

repair, tracked for followup or analyzed

more rigorously if it appears to indi-

cate a larger, more systemic problem.

Technologies for more in-depth analysis

include field metallography and finite

element modeling with software such

as ANSYS.

Cyclic boiler operation can create

other issues that, if unchecked, can also

result in forced outages and loss of

revenue. Some of these include external

corrosion of boiler tubing and exhaust

ducting, and internal boiler water wall

tubing failure. Cyclic operation can put

boiler components in the dew point

temperature range that will promote the

condensation of acids, which can rapidly

destroy tubing exterior or ducting, and

other components. Loss of cycle chem-

istry during downtime, startups or load

changes can lead to deposit formations

in water walls, which can initiate under-

deposit corrosion and oxygen pitting.

Review of operational logs and targeted

followup inspections can locate these

issues and result in procedural refine-

ments to mitigate their occurrence.

Piping Inspections Over the past 20 years, significant

advancement has been made by indus-

try and professional organizations in

the area of risk-based inspections of

equipment and piping. Some notable

examples of guidelines they have pro-

duced include the American Petroleum

Institute’s standard API 581 (Risk-Based

Inspection) and the American Society of

Mechanical Engineer’s standard PCC-3

(Inspection Planning Using Risk-Based

Methods). API 581 takes a quantitative

Co

urt

esy

Stru

ctu

ral I

nte

gri

ty A

sso

ciat

es.

Typically, boiler tubes are inspected using a single-point probe to take readings at stochastically selected points in an attempt to locate tube wall loss. Thanks to recent advances in ultrasonic NDE technology, however, a guided wave inspection, shown here, can scan an entire tube from one location to find areas of wall loss or leaks.

Co

urt

esy

Stru

ctu

ral I

nte

gri

ty A

sso

ciat

es.

The focused-beam ultrasonic NDE technique shown here targets the inside of the boiler water tube to look for under-deposit corrosion. Corrosion deposits can form in boilers that are cycling and have water chemistry control difficulties. These deposits can lead to through-wall oxygen pitting.

© 2011 International District Energy Association. ALL RIGHTS RESERVED.

F o r m o r e i n f o r m a t i o n o r a q u o t e , c a l l S t r u c t u r a l I n t e g r i t y A s s o c i a t e s , I n c . a t 8 7 7 - 4 S I - P O W E R

District Energy / First Quarter 2011 31

look at specific equipment and lets own-

ers calculate a risk factor that can be

applied to their equipment as a ranking

input to an inspection program. ASME’s

standard takes a broad approach and

recommends reviewing both quantita-

tive and qualitative factors as a basis

for an inspection program.

There are multiple interrelated

factors that affect the overall risk

of an individual piping component.

These include

• fluid service,

• component location and

• potential damage mechanisms.

Multiple interrelated factors

affect the overall risk of an

individual piping component,

including fluid service,

location and potential damage

mechanisms.

The type of fluid being conveyed in

the piping system is a critical factor in

prioritizing piping inspections. The flu-

ids utilized by an energy supplier range

from natural gas and fuel oil to steam

and chilled water. The relative hazard

posed by each of these fluids needs

to be considered together with other

facility-specific factors to determine the

risk of an individual piping system com-

ponent. For example, chilled water is

generally treated as a low-hazard fluid;

but a chilled-water line rupture in a tun-

nel distribution system can potentially

expose personnel to an inundation risk

– thus elevating the hazard rating of the

piping component in the affected areas.

The location of the piping drives its

relative risk factor. Components located

in vaults or manholes, or near a build-

ing or tunnel egress, all garner a higher

risk factor, but for different reasons.

Vaults or manholes are typically permit-

confined spaces with single-point egress.

Failure of a piping component while these

spaces are occupied by personnel would

obviously have major consequences, thus

elevating the relative risk factor.

Buildings or tunnels have multiple

egress points, which would seem to

suggest they are safer; but piping com-

ponents located near any routine-use

egress point have a high ‘man-pass’

frequency and, consequently, a higher

relative risk.

Other location-specific risk factors

for piping components include their

proximity to vehicular traffic, whether

they are buried or above ground, and

their relative accessibility. It is self-

evident, for example, that an exposed,

unprotected piping system is at greater

risk of a catastrophic impact by a vehicle

than piping components that are remote

to roadways. The same is true for pip-

ing located above ground versus com-

ponents below ground. An inaccessible

component, however, can create risks

that are easy to underestimate and

that can even obscure multiple other

attendant risks. For example, a piping

component installed in a location with

inadequate clearances to walls, floors

or other obstructions may not allow for

proper fitup and welding; and the initial

construction inspection of this com-

ponent’s welded joint could have been

subpar or even overlooked. Because of

this piping component’s inaccessibility,

it has an increased risk of failure and

would therefore rank high in priority in

a risk-based inspection program.

In addition to fluid service and

component location, the potential dam-

age mechanisms that may affect piping

systems also need close scrutiny. One

common issue faced by energy suppliers

is the myriad causes of piping corrosion,

Engineer Solutionor Modify Operating

Procedures

Can FailurePotential BeDetected?

ComponentFailure

Document andAnalyze Failure

Piping Bill ofMaterial

Document

Identify SystemRisk Factors

RankRisk Factors

Risk Rank PipingComponents

Defect Found?

Perform SystemAs-Built Walkdowns

Determine Scope ofNDE Inspections

Inspect HighestRanking Components

Analyze andDetermine Cause of

Defect

YES

NO

REFINE

NO

YES, REFINE

Figure 1. Example of a Risk-Based Piping Inspection Program.

Source: Structural Integrity Associates.

© 2011 International District Energy Association. ALL RIGHTS RESERVED.

F o r m o r e i n f o r m a t i o n o r a q u o t e , c a l l S t r u c t u r a l I n t e g r i t y A s s o c i a t e s , I n c . a t 8 7 7 - 4 S I - P O W E R

32 District Energy / First Quarter 2011 © 2010 International District Energy Association. ALL RIGHTS RESERVED.

which range from microbes, poor water

chemistry control and underinsulation to

flow-accelerated corrosion and cathodic

protection failure in buried piping. This

corrosion can manifest itself as either

systemwide or highly localized issues –

all with varying degrees of detectability.

Another damage mechanism, cyclic ther-

mal stress, can initiate localized fatigue

cracking. An as-built stress analysis of

the piping system can identify areas to

inspect for this.

Identifying the risk potential that

these damage mechanisms hold for a

piping system requires a failure analysis

program and recordkeeping methodology

that feeds and refines the inspection

program. Risk ratings for failure mecha-

nisms can be based on a number of

factors such as consequences of failure,

ease of detectability, rate of progression

or probability of occurrence. These fac-

tors can be considered individually or

combined with multiple factors to achieve

a relative risk rating for each affected

piping component.

Once risk factors have been identi-

fied and rated, they need to be applied

to individual piping components so an

overall ranking for each component can

be achieved. Routine walkdowns of the

piping system with as-built drawings

will help identify new exceptions such

as unreported, broken or missing hang-

ers and supports, incorrectly specified

piping components or previously unre-

ported hazards. NDEs are then planned

to inspect the highest-risk components.

Results are evaluated, documented and

fed back into component rankings to

continue to refine a system’s fitness for

service (fig.1).

Inspections alone will not eliminate

or mitigate all potential risks. Components

that have reached their end of life will

need capital investment to maintain

system integrity and safety. For exam-

ple, a pipe elbow that has corroded

past its minimum safe wall thickness

will need replacement instead of addi-

tional inspections. Human error is

another risk factor that cannot be

eliminated by inspections; it is best

handled instead by operational or

managerial procedures. But a proactive

program of boiler and piping inspec-

tions will reduce the risk of forced out-

ages, increase equipment availability,

increase the safety of personnel, help

eliminate service disruptions to cus-

tomers and provide knowledge for

making informed decisions.

Joe Maciejczyk, PE, is an asso-ciate with Structural Integrity Associates in the firm’s Annapolis, Md., office. A registered profes-sional engineer, Maciejczyk has more than 25 years of experience

in the design, fabrication, inspection, testing and operation of boilers, pressure vessels and piping systems. His experience spans multiple industries including utility power plants, district heating and chilled-water facilities, as well as cogenera-tion and industrial chemical processing facilities. Maciejczyk holds a bachelor of science degree in mechanical engineering from Louisiana State University and a master of business administra-tion degree from the University of Pittsburgh. He can be contacted at [email protected].

The potential for expansion joint failure is one of the risk factors to be considered in planning piping system inspections. Although expansion joints are designed to last 12 years or more in service, premature failures occur; and when they do, a systematic program approach to replacing them is needed. Start treating your expansion joints like an engineered asset versus a commodity. Make sure you have a data sheet for each joint containing all its design and fabrica-tion information; the Expansion Joint Manufacturer’s Association (EJMA), which publishes expansion joint standards, has such data sheets available for your use in documenting the parameters under which your expansion joints are operating. Then review each joint failure and make sure your findings are captured on the data sheet. Procure replacement joints from an EJMA member, which will ensure they adhere to industry quality and engineering requirements. New joint designs are continually introduced into the marketplace. If you are looking to adapt a new design, make sure the supplier of the new joint design can meet or exceed the data sheet requirements. If there is any doubt,

utilize the services of the vendor and a mechanical engineer to properly advise you on the purchase. Often misunderstood in the procurement of a new expansion joint is the joint’s design flexibility. Joints can be designed and built to expand, contract, translate, limit or allow movement in all planes and angles. All this information is an output from a piping stress analysis and needs to be recorded on the joint’s data sheet. If your improved vigilance on joint procurement is not solving your expansion joint problems, reviewing and updating the system stress analysis may be appropriate. Missing or broken hangers or supports, changes in operating conditions (pressure, temperature and cycles) can all have negative effects on expansion joints. In addition, changes or inadequacies in system water chemistry can also have adverse effects on your joints’ metallurgy, leading to premature failures. Make sure your expansion joint program investigates and resolves metallurgical issues. A program approach, and attention to detail with your expansion joints, pays dividends with improved joint life, reduced maintenance and reduced costs.

All Expansion Joints Are Not Created Equal

© 2011 International District Energy Association. ALL RIGHTS RESERVED.

F o r m o r e i n f o r m a t i o n o r a q u o t e , c a l l S t r u c t u r a l I n t e g r i t y A s s o c i a t e s , I n c . a t 8 7 7 - 4 S I - P O W E R

Reprinted with Permission from Combined Cycle Journal


Recommended