+ All Categories
Home > Documents > Produced Water for Cooling – A Case...

Produced Water for Cooling – A Case...

Date post: 14-Apr-2018
Category:
Upload: dinhkhuong
View: 218 times
Download: 2 times
Share this document with a friend
36
Presented by Michael N DiFilippo, Consultant July 08, 2008 Produced Water for Cooling – A Case Study San Juan Generating Station Advanced Cooling Technologies EPRI Workshop
Transcript

Presented byMichael N DiFilippo, Consultant

July 08, 2008

Produced Water for Cooling – A Case StudySan Juan Generating Station

Advanced Cooling TechnologiesEPRI Workshop

Produced Water for Cooling – A Case StudySan Juan Generating Station

San Juan generating Station’s Water Issues…..San Juan Generating Station (SJGS) consumes 22,000 acre-feet of water per year (467,600 BPD or 13,640 gpm) from the San Juan River.SJGS is a base-loaded plant and needs a reliable source(s) of water to operate.Researchers at the University of Arizona predict an extended drought for the region – possibly lasting 40 to 50 years.SJGS is a long-term energy production site and will be there 25 years or more.PNM has negotiated short-term and long-term water contracts to ensure supply, however if a severe a drought develops water contracts are irrelevant.If SJGS uses less water through conservation and obtains alternative supplies (e.g. produced water), more water will be available for other beneficial uses.

One drought scenario…..

SJGS has to reduce power by 10% for an entire year.SJGS has a long-term take-or-pay fuel contract, i.e. PNM must pay for fuel whether it uses it or not.SJGS will have to purchase power from other generators (most likely gas-fired combined cycle plants).The financial impact for this scenario could be in excess of $45million per year.PNM has looked at scenarios where water reductions approach 30%.

The basis for this project was to provide supplemental water to avoid or minimize the financial impact of such a scenario.....

Produced Water

For every barrel of oil, 8 to 10 barrels of water are brought to the surface.....

0 gpm

0-700 gpm

700-7,000 gpm

7,000-70,000 gpm

70,000-420,000 gpm

0 AF/yr

0-1,120 AF/yr

1,120-11,200 AF/yr

11,200-112,000 AF/yr

112,000-672,000 AF/yr

mgd

mgd

mgd

mgd

mgd

Onshore Produced Water Generation

DOE – US-Russia Energy Working Group, April 2003

Project Setting

San Juan Geologic Basin

UtahArizona

ColoradoNew Mexico

San Juan Basin

FruitlandPetroleumSystem

Farmington

New Mexico

Albuquerque

Santa Fe

Farmington

San Juan Basin

SJGS

Fruitland PetroleumSystem Boundary

13W 7W 6W 5W 4W12W 11W 10W 9W 8W 3W14W15W16W

32N

31N

30N

29N

27N

28N

ColoradoNew Mexico

Base Map of Study Area (~2,200 sq miles)20 miles 510 0

64

550

550

64

N

San Juan River

San Juan Rive

r

Animas

Rive

r

Navajo Reservoir

San Juan C

ounty

Rio A

rriba County

Farmington

Kirtland

Bloomfield

AztecSan Juan Generating Station

Township Grid

13W 7W 6W 5W 4W12W 11W 10W 9W 8W 3W14W15W16W

32N

31N

30N

29N

27N

28N

ColoradoNew Mexico

64 64

550

550

Farmington

Kirtland

Bloomfield

Aztec

SJGS

Produced Water Project –Extent of ProductionNew Mexico Oil Conservation Division, 2002

20 miles 510 0

Each circle represents a production well or well cluster

Fruitland Petroleum System

Total Produced Water = 61,775 BPD

N

San Juan River

San Juan Rive

r

Animas

Rive

r

Navajo Reservoir

San Juan C

ounty

Rio A

rriba County

In the Four Corners area almost all of the produced water is trucked to disposal.....

McGrath SWD (Salt Water Disposal) Facility

McGrath is a large SWD near Farmington, New Mexico. Produced water generated at the wellhead is transported by tanker trucks to SWDs. At the SWD, oil is separated from the produced water. The water is then filtered and injected into a non-producing formation at depths that sometimes reach 5,000 feet. In some locations, injection pressures exceed 1,500 psi. There are 53 SWDs in the San Juan Basin.

Fairway

13W 7W 6W 5W 4W12W 11W 10W 9W 8W 3W

32N

31N

30N

29N

27N

28N

ColoradoNew Mexico

Township Grid

San Juan RiverSan Ju

an River

Animas

Rive

r

Navajo Reservoir

San Juan C

ounty

Rio A

rriba County N

Produced Water Generation – High-Volume AreasNew Mexico Oil Conservation Division, 2003

20 miles 510 0

Produced WaterCollection Center

Farmington

Kirtl andBloomfield

Aztec

San Juan Generating Station

64

550

64

CO2 Gas LineHart Canyon LineExtension (new)Produced WaterPipeline (new)

High Volume Area

SWD Injection Well

Tri-CityClose-in

High-Volume Production AreasFairwayClose-inTri-CityTotal

20,680 BPD12,520 BPD

2,760 BPD39,560 BPD

39,560 BPD = 1,154 gpm

Likely Recoverable WaterPNM - Produced Water Project - SJGS

1,000

1,500

2,000

2,500

3,000

2005 2010 2015 2020 2025 2030

Project Year

Like

ly R

ecov

erab

le W

ater

, AF/

yr

Likely Recovery Range

Water Recovery CasesTotal Resource90% – Case 580% – Case 470% – Case 3

Scenario 36% Declination

Life-of-project recoverable water.....

Project Implementation

Cost sharing with the oil & gas producers reduced overall costs.....

The project would be implemented in two phases.....

Phase 1An 11-mile pipeline would be build to collect water from Close-in producers (exclusively CBM production).Producers would inject filtered water into the line.Producer disposal costs would be reduced by $0.25/bbl.

Phase 2PNM would extend the pipeline an additional 17.5 miles to Bloomfield.Burlington resources would refurbish two existing pipelines and install satellite collection stations to gather theirs and other producer’s water in areas of heavy tanker-truck traffic.PNM would build a collection Center in Bloomfield to accept and pretreat water gathered by Burlington Resources.Producer disposal costs would be reduced by up to $1.00/bbl.Some SWDs could be put on stand-by and the life of costly injection wells ($1.5 to $2.5 million per well) would be extended.

Produced Water Collection & Conveyance SchematicPNM – Produced Water Project - SJGS

Lift Station

PipelineCharge Pumps

Produced WaterCollection &Pretreatment

SJG

S

ProducedWater

TreatmentSystem

17.5 miles

Produced Water Pipeline

Tri-CityProduced

Water

Hart

Cany

on L

ine

CO2

Gas L

ine

Close-in ProducedWater New Intertie & Extention

SatelliteCollection

Stations

SWD DirectInjection

FairwayProduced

Water

(Bloomfield)

Burlington Resources

Dugan ProductionRichardson OperatingPrax AirBHP Billiton

11 miles

Phase 2Phase 1

Produced Water Treatment

Produced Water SalinityBurlington Resources, McGrath SWD

5,000

10,000

15,000

20,000

25,000

4/4/03 4/9/03 4/14/03 4/19/03 4/24/03 4/29/03 5/4/03 5/9/03

Sample Date

TDS,

mg/

l

Bloomfield Collection CenterPNM – Produced Water Project - SJGS

Produced WaterReceiving Tanks (2)

Gravity-CoalescingO/W Separators

(2-100%)

Skimmed Oil

Grit

Gas Floatation Units(2-100%)

Float

2-Day Equalization Basin

PipelineCharge Pumps

(4-33%)

Off-spec

40,000 BPDProducedWater

AETurb

AECond

DP

Walnut Shell Filters(2-100%)

Rinse

Backwash

Bloomfield Collection CenterPNM – Produced Water Project - SJGS

Produced WaterReceiving Tanks (2)

Gravity-CoalescingO/W Separators

(2-100%)

Skimmed Oil

Grit

Gas Floatation Units(2-100%)

Float

2-Day Equalization Basin

PipelineCharge Pumps

(4-33%)

Off-spec

40,000 BPDProducedWater

AETurb

AECond

DP

Walnut Shell Filters(2-100%)

Rinse

Backwash

Produced WaterReceiving Tanks (2)

Gravity-CoalescingO/W Separators

(2-100%)

Skimmed Oil

Grit

Gas Floatation Units(2-100%)

Float

2-Day Equalization Basin

PipelineCharge Pumps

(4-33%)

Off-spec

40,000 BPDProducedWater

AETurb

AECond

DP

Walnut Shell Filters(2-100%)

Rinse

Backwash

AETurb

AECond

DP

Walnut Shell Filters(2-100%)

Rinse

Backwash

HERO System – Process SchematicSan Juan Generating Station

Degassifier

Ca(OH)2

Na2 CO3

Coagulant Aide

H2 SO4 NaOCl

Vent

Air

Reactor-Clarifier& Thickener

Weak-Acid CationExchanger (WAC)

Backwash & Spent Regenerant

ThickenedSludge toScrubbers

NaOH

Reverse Osmosis

Permeate to Reuse

Reject to Evaporators

NaHSO3

ProducedWater

Permeate to FilterBW & WAC Regen

Ove

rflow

Recirculation PumpSeed Tank

FeedwaterDeaerator

FeedwaterHeat Exchanger

Waste Brine

Distillate

RO RejectFeedwater

Rec

ircul

atin

g B

rine

Vapor

Gas ReleaseDemisters

Packing

Vapor Compressor

Acid

Antiscalant

Vapor

Tube

RecirculatingBrine

Film Flow &Vapor Release

Detail

Brine Concentrator – Process Schematic

Condenser

Simplified Water BalanceSan Juan Generating Station

Cooling Towers(4 units)

Ash System(4 units)

ProcessWastewater

Ponds

BrineConcentrators (2)

Demins

FGDs(4 units)

Evaporation Ponds (75 acres)

Limestone Prep

Slurry Dewatering

San Juan River

Water Lostto Disposal

Water Lostto Disposal

Boiler Make-up

Brin

e

FGD Purge Water

Boiler Cleaning(occasional)

Recycle to Limestone Prep

Evap & Drift

Blowdown

Boiler Blowdown

Plant Drains

Distillate

Water Lossto Flue Gas

Steam Losses

Plant ServiceWater

Coal Pile Runoff(occasional)

Overflow(occasional)

Spe

nt R

egen

Treated Produced Water Reuse PointsSan Juan Generating Station

Cooling Towers(4 units)

Ash System(4 units)

ProcessWastewater

Ponds

BrineConcentrators (2)

Demins

FGDs(4 units)

Evaporation Ponds (75 acres)

Limestone Prep

Slurry Dewatering

San Juan River

Water Lostto Disposal

Water Lostto Disposal

Boiler Make-up

Brin

e

Boiler Cleaning(occasional)

Recycle to Limestone Prep

Evap & Drift

Blowdown

Boiler Blowdown

Plant Drains

Distillate

Water Lossto Flue Gas

Steam Losses

Plant ServiceWater

Coal Pile Runoff(occasional)

Overflow(occasional)

Spe

nt R

egen

ProducedWater

Treatment

Rer

oute

d FG

D P

urge

Wat

er

FGD Purge Water

Prod

uced

Wat

er

Trea

tmen

t Was

tew

ater

Wastewater toEvap Ponds

Economic Analysis2004 Basis

Collection 14-inch HERO + TotalCenter Pipeline BC 3 Project

Capacity, BPD 34,000 60,000 53,000Peak Conditions, BPD 30,670 44,710 48,130Equipment & Installation $5,200,000 $12,900,000 $11,800,000 $29,900,000Contingency 15% $780,000 $1,940,000 $1,770,000 $4,490,000NMGRT (1) 6.125% $320,000 $790,000 $720,000 $1,830,000PNM G&A (2) 5.5% $290,000 $710,000 $650,000 $1,650,000Total Project $6,590,000 $16,340,000 $14,940,000 $37,870,000

Notes…..1. NMGRT is the New Mexico Gross Receipts Tax.2. G&A is a "general and admistrative" charge applied to all PNM projects.

Capital Costs Incurred by PNMCapital Costs Incurred by PNM

Total Project Capital Costs BR Gathering system to Collection Center $5,000,000Dugan Inject into pipeline $100,000Richardson Inject into pipeline $100,000PNM Collection Center, pipeline & treatment $37,900,000Total Project $43,100,000

Notes..... 1. Installation costs for Dugan and Richardson are most likely high.

Infrastructure Costs Incurred by PNM & Oil Producers

PNM Operating CostsPNM - Produced Water Project - SJGS

$5.0

$5.5

$6.0

$6.5

$7.0

2005 2010 2015 2020 2025 2030

Mill

ions

Project Year

Esca

late

d A

nnua

l Op

Cos

t

Water Recovery Cases90% – Case 580% – Case 470% – Case 3

Scenario 36% Declination

Likely Recovery Range

Annual Tax CreditPNM - Produced Water Project - SJGS

$0.0

$0.5

$1.0

$1.5

$2.0

$2.5

2005 2010 2015 2020 2025 2030

Mill

ions

Project Year

Ann

ual T

ax C

redi

t

Likely Recovery Range

Water Recovery Cases90% – Case 580% – Case 470% – Case 3

Scenario 36% Declination

PNM was planning to qualify for a State of New Mexico for a tax credit of $1,000/AF for water- savings infrastructure. The tax credit would have an annual limit and life-time cap.....

Total Annual Project RevenuePNM - Produced Water Project - SJGS

$0

$2

$4

$6

$8

$10

$12

2005 2010 2015 2020 2025 2030

Mill

ions

Project Year

Esca

late

d A

nnua

l Rev

enue

Water Recovery Cases90% – Case 580% – Case 470% – Case 3

Scenario 36% Declination

Likely Recovery Range

Revenue to PNM would be generated by reducing producer disposal costs.....

Life-of-Project Cost of WaterPNM - Produced Water Project - SJGS

-$1,000

-$500

$0

$500

$1,000

$1,500

$2,000

$2,500

$3,000

$3,500

$4,000

40% 50% 60% 70% 80% 90% 100%

Water Recovery

Cos

t of W

ater

, $/A

FN

et

PNM Share of Producer Savings0%

25%50%75%

6% Compound Decline4%

2%

Likely Recovery Range

with Tax Credit

Producer participation significantly influenced the cost of this water resource.....

Project Economics.....

Produced water project economics are based on capital and operating costs as well as a revenue stream. PNM’s operating costs include treatment chemicals, power, labor, materials, maintenance and capital recovery costs.Revenue streams offset PNM operating costs.The first revenue stream would be a tax credit of $1,000/AF provided by the State of New Mexico (the tax credit would have an annual limit and life-time cap). The second revenue stream would be a share of the oil-producer savings derived from reduced disposal of produced water and deferred costs of injection wells.Depending on the revenue scenario, the 20-year, life-of-project costs would vary as follows:

50-50 Share of producers savingswith the New Mexico tax credit

$720 to $970/AF ($125 to $150/AF)* $1.3 to $1.7 million/year

50-50 Share of producers savingswithout the tax credit

$1,200 to $1,500/AF ($160 to $200/AF) $2.0 to $2.6 million/year

No revenue streams $2,500 to $3,000/AF ($260 to $330/AF) $4.3 to $5.1 million/year

*Blended water costs – San Juan River @ $75/AF plus treated produced water.

PNM Project Benefits…..

Conserve river water for other beneficial uses in New Mexico.Enable the San Juan Generating Station to be more drought resistant.Avoid costly fuel-delivery penalties and power purchase costs.

Oil & Gas Producer Benefits.....

Reduce the volume of produced water that must be handled and injected.Establish an infrastructure to minimize produced water injection in the San Juan Basin.Establish area-wide opportunities to reduce produced water handling and injection costs.


Recommended